Metro Area Express Light Rail Project. WASC 2013. Dave Thomas, Project Director 16 May 2013. Overview. Introductions Background - draft Public Transport Plan for Perth MAX project overview Current progress MAX planning context Discussion. Draft Public Transport Plan for Perth in 2031. - PowerPoint PPT Presentation
Citation preview
Metro Area Express Light Rail
Project
WASC 2013
Dave Thomas, Project Director
16 May 2013
Overview
• Introductions• Background - draft Public Transport Plan for Perth • MAX project overview• Current progress• MAX planning context• Discussion
Draft Public Transport Plan for Perth in 2031
Trains• Fast spines
On-road transit• Light Rail Transit• Bus Rapid Transit• Bus priority
Bus network• Urban coverage
Central Northern Corridor selection
Why light rail?
Project outcomesAn integrated public transport system that:
•Helps to mitigate against increasing traffic congestion and pollution through the provision of an additional, attractive mode of public transport•Links key activity centres including the CBD, hospitals, universities and major facilities•Coordinates with land-use planning, enabling revitalisation and new developments along the alignment – catalyst for city change
Proposed project timeline
MAX project scope
The Project
Mirrabooka in the north through the Perth CBD
before splitting into two branches to:
•QEII Medical Centre, and•The Causeway
Possible future extensions
•QEII to UWA•The Causeway to Curtin
University•The Causeway to the new
Perth Stadium•QEII to Glendalough and
Stirling stations
MAX vs Melbourne Trams
Proposed MAX Network
Mirrabooka
Dianella
QEII Medical CentreVictoria ParkTransfer Station
North PerthECU
Funding committed to planning phase
Whole-of-government approach
Project team has cross-portfolio expertise:
• Department of Transport (lead agency)• Public Transport Authority• Main Roads WA• Department of Planning• Treasury• Department of Housing and• Department of Lands
Stakeholder & community engagement
• Stakeholder Engagement Strategy and Plan• Individual meetings and briefings• Workshops, information sessions• Market research • Website• Project information sheets• Public information hotline and email enquiries• Social media and other online engagement tools
Planning & urban design context
• Not just a transport project• Land use and transport integration is a key component
of all Department of Transport plans• Key objective is activation of corridors and centres• Alignment with Directions 2031+ and spatial planning
activities• Department of Planning’s Strategic Project Implementation
Team is directly involved in MAX• Working closely with councils on integration with town
centre planning
Legislation• Legislation for project construction and operation
needs to be in place in 2014• Proposed legislative regime for light rail and bus
rapid transit will draw on existing powers within current WA Acts to build and operate public transport infrastructure such as railways
• Recommended policy proposals will go to Cabinet for endorsement as early as possible in 2013
• Total of 31km as well as 100m down all side streets surveyed to date
• Base survey carried out using a combination of theodolite & terrestrial and mobile laser scanning
• Fixed GPS used for some control points
• Heights from mobile GPS units deemed too inaccurate to be used for design purposes
Surveying
Chesterfield Road looking from Yirrigan Drive
3D Model – Fitzgerald Street• Initial traverse triangulated
to create existing surface model
• Street furniture modelled in place (light poles, pit lids, valves, hydrants etc.)
Key
Telstra pits
Western Power pits
WaterCorp valve locations
Light poles
Power poles
AlignmentFitzgerald Street with alignment overlayed (purple)
3D Model - Wellington Street• Digital DBYD information
draped onto existing surface and diameter (size) applied
• Depths applied as per Utility Providers code of practise
• Clash check performed between existing utility models and proposed rail alignment
Wellington Street (underneath)
Current progress• ‘Real Potential’ business case due for completion
in June 2013.• Final business case, including procurement
options, due in March 2014.• Northern section initial concept designs are largely
complete.• East – west section initial LRT concept designs
due for completion in the coming weeks.• Focus on the concept design west of Perth is on
confirming the alignment through the QEII site.
Current progress
• CBD alignment options being investigated.•Systems design for LRT, including scheduling, about to commence.•Depot location.•Cycle routes and access. •MAX Planning Framework.•Working closely with local government to integrate centre planning work (Dianella, Mirrabooka, North Perth) and other local planning processes.
Anticipated market interactionMarket sounding – late 2013•Update market on project•Advise on procurement approach, risk position, etc.
Procurement process – mid 2014 – end of 2015•Currently considering a PPP model, incorporating:
− Design− Finance− Construction− Rolling stock− Operations− Maintenance
•This approach to be endorsed as part of Business Case
Examples of light rail
Freiburg, Germany Mulhouse, France
Examples of light rail
Strasbourg, France Amsterdam, Holland
Discussion
Contact
Dave Thomas 6551 6639 [email protected]
MAX information line 1800 820 844Email enquiries [email protected] www.max.wa.gov.au