Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
MLK CONNECTOR LARGE DIAMETER PILE REPAIR
Presented by
Brad Hessing & Heather Shoup
Midwest Geotechnical Conference, September 17-19, 2019 1
PRESENTATION OVERVIEW
•Installation of Large Diameter Open-Ended Pipe Piles (LDOEP) at the Piers for the New Martin Luther King Connector Bridge in East St. Louis.
•Upon construction of Pier 3, one of its piles was damaged during driving.
•Numerous solutions were considered to resolve the issue.
• A repair plan was chosen, implemented, and the problem was resolved.
Midwest Geotechnical Conference, September 17-19, 2019 2
PROJECT OVERVIEW
•Total Replacement of existing ~60 year old Martin Luther King Bridge Approach (“MLK Connector”, Existing Structure Number 082-6003) in East St. Louis, Illinois.
•The existing 15-Span structure consists of a 250’ long Steel Through Truss with multiple Curved Steel Girder Approach Spans.
•The new structure will be a 1286’ long 5-Span 96” deep Plate Girder Bridge with Pile Bent Abutments supported by H-Piles to Rock and Open Pile Bent Piers made up by Large Diameter Open-Ended Pipe Piles (LDOEPs) to Rock.
•New MLK Connector Bridge will carry traffic over relocated Illinois Route 3, Missouri Avenue, various R.R. tracks, and Interstates 55 and 64.
Midwest Geotechnical Conference, September 17-19, 2019 3
PROJECT OVERVIEW
•Proposed IDOT Structure Number: 082-0374
•Route: FAP 799
•Section 1BR-1-1
•County: St. Clair
•Contract Number 76G39
Midwest Geotechnical Conference, September 17-19, 2019 4
MLK CONNECTORSITE LOCATION
City of East St. Louis (St. Louis Metro East Region)
St. Clair County, Illinois
IDOT District 8
Midwest geotechnical conference, September 17-19, 2019 5
Midwest Geotechnical Conference, September 17-19, 2019 6
Midwest Geotechnical Conference, September 17-19, 2019 7
Midwest Geotechnical Conference, September 17-19, 2019 8
PROJECT OVERVIEW
•Each Open Pile Bent Pier (Piers 1-4) comprised of 4 Large Diameter Open-Ended Pipe Piles (LDOEPs) driven to Rock.
•All LDOEPs are 48-in Dia. with ¾-in wall thickness.
•All piles to be driven to rock to a Nominal Required Bearing of 3006 kips with a Factored Resistance Available of 1954 kips.
•All piles driven with Wave Equation (WEAP) with PDA Testing.
Midwest Geotechnical Conference, September 17-19, 2019 9
PROJECT OVERVIEW
•All piles are to be equipped with shoes.
•Axial Capacity includes components of both Side Resistance and End Bearing.
•No geotechnical losses were included in the design.
•LDOEPs are to be filled with concrete to a minimum of 35 ft below ground elevation. Any material that may encroach above the proposed bottom of concrete inside the pipe shall be removed prior to filling.
Midwest Geotechnical Conference, September 17-19, 2019 10
Midwest geotechnical conference, September 17-19, 2019 11
Midwest geotechnical conference, September 17-19, 2019 12
PROJECT OVERVIEW
WHY LDOEPs ?
Midwest Geotechnical Conference, September 17-19, 2019 13
BACKGROUND-PIER FOUNDATION TREATMENTS
FOUNDATION TREATMENTS CONSIDERED:
•Driven Metal Shell (Friction) Piles
•H-Piles Driven to Rock
•Drilled Shafts with Rock Sockets
•Large Diameter Open-Ended Pipe Piles (LDOEPs) Driven to Rock
Midwest Geotechnical Conference, September 17-19, 2019 14
BACKGROUND-PIER FOUNDATION TREATMENTS
METAL SHELL (FRICTION) PILES AND H-PILES DRIVEN TO ROCK
•The required number of metal shells or H-Piles would be considerably greater than
that required for either drilled shafts or LDOEPs since one drilled shaft or one LDOEP
can be substituted for a number of piles.
•Metal shells and H-Piles both would require footings; along with the number of piles
required, this would create and require a much larger “footprint” than the other two
treatment types.
Midwest Geotechnical Conference, September 17-19, 2019 15
BACKGROUND-PIER FOUNDATION TREATMENTS
METAL SHELL (FRICTION) PILES AND H-PILES DRIVEN TO ROCK (CONTD.)
•Along with taking up more space, pile supported footings would also require
temporary soil retention adjacent to IL-3 and the railroads.
•Although metal shells and H-Piles are technically feasible, due to limited
space, interferences with existing foundations, shoring requirements for IL-3
and the railroads, and additional utility and deep well conflicts, they were not
considered favorable treatments for the interior bent locations.
Midwest Geotechnical Conference, September 17-19, 2019 16
BACKGROUND-PIER FOUNDATION TREATMENTS
DRILLED SHAFTS WITH ROCK SOCKETS
• Drilled Shafts can be designed as an open pile bent and would not require a
footing or soil retention.
•Considerably less drilled shafts would be required than conventional piles.
•However, shafts were less economical and would take longer and more effort
to construct than LDOEPs.
Midwest Geotechnical Conference, September 17-19, 2019 17
BACKGROUND-PIER FOUNDATION TREATMENTS
LARGE DIAMETER OPEN-ENDED PIPE PILES (LDOEPS)
•LDOEPs can be designed as an open pile bent and would not require a
footing or soil retention.
•Considerably less LDOEPs would be required than conventional piles.
•Construction issues common to drilled shafts can be avoided since they are
driven and not drilled.
•They are more economical and faster and easier to construct than drilled
shafts.
Midwest Geotechnical Conference, September 17-19, 2019 18
BACKGROUND-FINAL SELECTION OF LDOEPS
FINAL SELECTION OF LDOEPS WAS BASED ON:
•Its advantages over the other treatments as previously discussed above
•Being the most economical and efficient foundation design
•Overall Constructability
•Heavily favored by IDOT District 8 (recently used on nearby structure)
Midwest Geotechnical Conference, September 17-19, 2019 19
BACKGROUND-SUBSURFACE DATA
•The subsurface at Pier 3 generally consists of a sequence of sandy fill,
clay, sand, and cobbles and gravel overlying sandstone and limestone
bedrock.
•The top of rock is on average approximately 120 feet below ground
surface.
•Boring data for Pier 3 is supplied by Boring BB-304.
Midwest Geotechnical Conference, September 17-19, 2019 20
Midwest Geotechnical Conference, September 17-19, 2019 21
5
EAST ABUTMENT
WEST ABUTMENT
#1 #2#3
#4
Midwest geotechnical conference, September 17-19, 2019 22
Midwest geotechnical conference, September 17-19, 2019 23
PROJECT OVERVIEW (CONTD.)
•Project was let in June of 2018 and is currently under construction.
•During Pile Driving at Pier 3, Pile 4 was crushed at its toe (OUCH!!!).
•As a result, the axial capacity of Pile 4 was compromised.
•Consequently, this problem needed to be resolved in a timely manner!
LET’S NOW TALK CONSTRUCTION AND THE FIX………
Midwest Geotechnical Conference, September 17-19, 2019 24
CONSTRUCTION …
Midwest Geotechnical Conference, September 17-19, 2019 25
ASTM A252 Grade 3 steel
50 ksi min. yield strength
45 ksi max allowable driving stress (90%)
48-in OD
0.75 inch wall thickness
Drive shoes
2 planned splices
Midwest Geotechnical Conference, September 17-19, 2019 26
THE PILES
THE HAMMER:
Hammer: APE D160-42
Single acting diesel
397 kip-ft rated energy max at fuel setting,
35.28 kip ram weight
11.25 ft max rated hammer stroke
Midwest Geotechnical Conference, September 17-19, 2019 27
WEAP ANALYSIS SUMMARY
Drivability Analysis:Assesses Driving Conditions with depth
Assessed both with and without soil plug
Bearing Graph Analysis
Did not use API method because of experience with the adjacent MLK Connector LDOEPs
Max fuel setting 4 modeled
Hammer modeled with 80% efficiency
Boring used BB-301 (W. Abut & Pier 1)
Limestone bedrock assumed 2,500 ksf unit end bearing
Full soil plug not expected
Partial plug simulated by increasing end area linearly from no plug at top to 50% plug at bottom in dense granular layer just above the bedrock surface.
Midwest Geotechnical Conference, September 17-19, 2019 28
Midwest Geotechnical Conference, September 17-19, 2019 29
Midwest Geotechnical Conference, September 17-19, 2019 30
Midwest Geotechnical Conference, September 17-19, 2019 31
WEAP DRIVABILITY ANALYSIS SUMMARY
Max 10 bpi (IDOT spec.)
11 bpi at 9.7 ft stroke (no plug)
19 bpi at 9.4 ft stroke (partial plug)
8 bpi at 9.8 ft stroke (Bearing Graph Analysis)
31 – 35 ksi estimated driving stresses
Average Transfer Efficiency is 39% (COV = 26) for diesel hammers (Appendix B3 of the 2010 version GLRWEAP manual)
Midwest Geotechnical Conference, September 17-19, 2019 32
PDA TESTING TIMELINE FOR DRIVING PIER 3 ON 11/27/18
10:44 am
15:25 pm
24:46 pm
33:07 pm
4
Midwest Geotechnical Conference, September 17-19, 2019 33
Midwest Geotechnical Conference, September 17-19, 2019 34
Pier 3, Pile 1, EOID
Midwest Geotechnical Conference, September 17-19, 2019 35
Pier 3, Pile 4, EOID
PLAY BACK OF PDA RECORD FOR PIER 3, PILE 4
Midwest Geotechnical Conference, September 17-19, 2019 36
Midwest Geotechnical Conference, September 17-19, 2019 37
DRIVE TIMELINE VIEWED IN PDA RECORD
Midwest Geotechnical Conference, September 17-19, 2019 38
Midwest Geotechnical Conference, September 17-19, 2019 39
Blow 339: Just prior to
stopping the hammer
3:15:54 pm
Midwest Geotechnical Conference, September 17-19, 2019 40
Blow 339: F2 Strain Sensor Wiggly
Midwest Geotechnical Conference, September 17-19, 2019 41
Restart Driving: Blow 348
3:19:52 pm
Midwest Geotechnical Conference, September 17-19, 2019 42
Blow 349: Velocity Bump Starts
3:19:53 pm
Midwest Geotechnical Conference, September 17-19, 2019 43
Blow 385: Velocity Bump
3:20:54 pm
Midwest Geotechnical Conference, September 17-19, 2019 44
Blow 450: Initial return
shifted to left
It should be here!
3:25:21 pm
45
Pier 3, Pile 4, EOID
3:30:05 pm
Midwest Geotechnical Conference, September 17-19, 2019
WELL, THAT DIDN’T GO AS PLANNED!
Midwest Geotechnical Conference, September 17-19, 2019 46
Pile is damaged, but the show must go on …
Moved to Pile 3 and lowered the fuel setting to 1.
Midwest Geotechnical Conference, September 17-19, 2019 47
Pier 3, Pile 3, EOID
Midwest Geotechnical Conference, September 17-19, 2019 48
Pier 3, Pile 2, EOID
PIER 3 PILE STATS
Pile No.
Nominal Required
Bearing (Kips)
CAPWAP Total
Driven Bearing
(Kips)
CAPWAP Shaft/ End
Bearing(Kips)
LP (ft) Damage Depth 1st
Indicated (ft)
Final Penetration
(blows/in.)
PDA Calc.
CSB (ksi)
PDA Calc.
ETR%
Stroke(ft)
Fuel Setting
1 3006 4,200 400 / 3,800 117.75 13 @ 1 in 42.85 55.8% 11.7 4
2 3006 4,330 630 / 3,700 117.94 15 @ 1 in 34.09 33.9% 8.4 1
3 3006 4,310 710 / 3,600 118.17 10 @ 3/8in 36.00 40.6% 9.0 1
4* 3006 495 495 / --- 123.0 118.78 54 @ 1 in 39.14 61.1% 11.2 4
Midwest Geotechnical Conference, September 17-19, 2019 49
* Pile 4 damaged about 5 ft above the bottom. Only use shaft resistance above damage.
PILE IS DAMAGED: NOW WHAT?
• What was the cause?
• Review Soil Borings
• Review WEAP analysis
• Review PDA files
• Review PDA/CAPWAP Report
• Can the pile still be used?
• How can it be fixed?
50
Meetings
Emails
Calls
Midwest Geotechnical Conference, September 17-19, 2019
FHWA REVIEW OF THE DAMAGED PILE IN THE MLK BRIDGE
Reviewed project documents, mainly GRL documents for the damaged Pile 4 of Pier 3 and FHWA’s findings, conclusions, and recommendations for this pile are listed next.
Damage at the toe of the pile is indicated, but extent of the damage is not clear.
Blow count and PDA capacity for the damaged pile kept increasing with depth and reached 2800 kips when driving stopped.
CAPWAP capacity results were reported for all Pier 4 piles except damaged Pile 4. (no end bearing or side resistance along damaged area)
Analysis results for the damaged pile show CAPWAP capacity of 2520 kips.
The required capacity for each pile in Pier 3 is 3006 kips. The capacity of the damaged Pile 4, 2520 kips, is close to the required capacity.
Midwest Geotechnical Conference, September 17-19, 2019 51
FHWA REVIEW OF THE DAMAGED PILE IN THE MLK BRIDGE
A pile cap will tie the 4 piles in Pier 3 together to function as a group of piles in supporting the pier loads.
Total capacity of four piles in Pier 3 is 15,360 kips larger than required capacity of 12,024 kips.
Conclusions/Recommendations:
Although Pile 4 in Pier 3 is damaged to some extent, it is still has good capacity, that will be supplemented if needed by capacity of neighboring piles.
Review FHWA findings and recommendations in the assessment process.
Midwest Geotechnical Conference, September 17-19, 2019 52
WHO NEEDS TO BE INVOLVED IN THE FIX?
• Solution Path: IDOT allowed the
Contractor to hire Structural
Engineer of Record to assess
and develop a repair
IDOT
ContractorStructural
Engineer of Record
Midwest Geotechnical Conference, September 17-19, 2019 53
REPAIR OPTIONS:
DO NOTHING
• Accept and move on (Contractor's 1st choice)
• Load test
Use residual capacity
• 495 kips skin• Neglect end
bearing
Make it a drilled shaft
• Drill 3' Dia rock socket
• Pressure grout bottom
Pull and Replace
Dive more piles
• Adjacent• In the center• Bigger one
around it
Midwest Geotechnical Conference, September 17-19, 2019 54
?
CONTRACTOR DECIDES TO CORE THE BEDROCK INSIDE THE DAMAGED PILE
Midwest Geotechnical Conference, September 17-19, 2019 55
PILE
CORING LOCATIONS
REPAIR OPTIONS
DO NOTHING
• Accept and move on (Contractor's 1st choice)
• Load test
Use residual capacity
• 495 kips skin• Neglect end
bearing
Make it a drilled shaft
• Drill 3' Dia rock socket
• Pressure grout bottom
Pull and Replace
Dive more piles
• Adjacent• In the center• Bigger one
around it
Drive a 60-in Dia LDOEP around the 48-in Dia Pile
Midwest Geotechnical Conference, September 17-19, 2019 56
PROPOSED REPAIR FOR PIER 4 SHOWING SHEAR STUD ARRANGEMENT ALONG SPLICE ZONE
48” φ Pile with rebar cage (Typical at all Piers) prior to repair
Pier 3, Pile 4 repair showing Outer 60” φ Pile and Inner 48” φ Pile with rebar cage along Splice Zone with “Interlocking” Shear Studs
Midwest Geotechnical Conference, September 17-19, 2019 57
Midwest Geotechnical Conference, September 17-19, 2019 58
Midwest Geotechnical Conference, September 17-19, 2019 59
Midwest Geotechnical Conference, September 17-19, 2019 60
Midwest Geotechnical Conference, September 17-19, 2019 61
Midwest Geotechnical Conference, September 17-19, 2019 62
Midwest Geotechnical Conference, September 17-19, 2019 63
Midwest Geotechnical Conference, September 17-19, 2019 64
Midwest geotechnical conference, September 17-19, 2019 65
REPAIR CONSTRUCTION MONITORING
•IDOT D8 Construction performing visual on blows/ft and blows/in
•PDA testing (GRL & IDOT)• Double the accelerometers and strain sensors
•Wireless (GRL)
• Cabled (IDOT)
•CAPWAP results
Midwest geotechnical conference, September 17-19, 2019 66
Midwest geotechnical conference, September 17-19, 2019 67
Midwest geotechnical conference, September 17-19, 2019 68
Midwest Geotechnical Conference, September 17-19, 2019 69
Midwest geotechnical conference, September 17-19, 2019 70
PDA AND CAPWAP
Midwest geotechnical conference, September 17-19, 2019 71
Nominal Required: 3,769 kips
CAPWAP Capacity: 3,733 kips
• Shaft Resistance: 1,113 kips
• End Bearing: 2,620 kips
THANK YOU
BRAD [email protected]
HEATHER [email protected]
Midwest geotechnical conference, September 17-19, 2019 72