72
MLK CONNECTOR LARGE DIAMETER PILE REPAIR Presented by Brad Hessing & Heather Shoup Midwest Geotechnical Conference, September 17-19, 2019 1

MLK CONNECTOR - Pages MWGC... · 2019. 9. 26. · PROJECT OVERVIEW •Total Replacement of existing ~60 year old Martin Luther King Bridge Approach (“MLK Connector”, Existing

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • MLK CONNECTOR LARGE DIAMETER PILE REPAIR

    Presented by

    Brad Hessing & Heather Shoup

    Midwest Geotechnical Conference, September 17-19, 2019 1

  • PRESENTATION OVERVIEW

    •Installation of Large Diameter Open-Ended Pipe Piles (LDOEP) at the Piers for the New Martin Luther King Connector Bridge in East St. Louis.

    •Upon construction of Pier 3, one of its piles was damaged during driving.

    •Numerous solutions were considered to resolve the issue.

    • A repair plan was chosen, implemented, and the problem was resolved.

    Midwest Geotechnical Conference, September 17-19, 2019 2

  • PROJECT OVERVIEW

    •Total Replacement of existing ~60 year old Martin Luther King Bridge Approach (“MLK Connector”, Existing Structure Number 082-6003) in East St. Louis, Illinois.

    •The existing 15-Span structure consists of a 250’ long Steel Through Truss with multiple Curved Steel Girder Approach Spans.

    •The new structure will be a 1286’ long 5-Span 96” deep Plate Girder Bridge with Pile Bent Abutments supported by H-Piles to Rock and Open Pile Bent Piers made up by Large Diameter Open-Ended Pipe Piles (LDOEPs) to Rock.

    •New MLK Connector Bridge will carry traffic over relocated Illinois Route 3, Missouri Avenue, various R.R. tracks, and Interstates 55 and 64.

    Midwest Geotechnical Conference, September 17-19, 2019 3

  • PROJECT OVERVIEW

    •Proposed IDOT Structure Number: 082-0374

    •Route: FAP 799

    •Section 1BR-1-1

    •County: St. Clair

    •Contract Number 76G39

    Midwest Geotechnical Conference, September 17-19, 2019 4

  • MLK CONNECTORSITE LOCATION

    City of East St. Louis (St. Louis Metro East Region)

    St. Clair County, Illinois

    IDOT District 8

    Midwest geotechnical conference, September 17-19, 2019 5

  • Midwest Geotechnical Conference, September 17-19, 2019 6

  • Midwest Geotechnical Conference, September 17-19, 2019 7

  • Midwest Geotechnical Conference, September 17-19, 2019 8

  • PROJECT OVERVIEW

    •Each Open Pile Bent Pier (Piers 1-4) comprised of 4 Large Diameter Open-Ended Pipe Piles (LDOEPs) driven to Rock.

    •All LDOEPs are 48-in Dia. with ¾-in wall thickness.

    •All piles to be driven to rock to a Nominal Required Bearing of 3006 kips with a Factored Resistance Available of 1954 kips.

    •All piles driven with Wave Equation (WEAP) with PDA Testing.

    Midwest Geotechnical Conference, September 17-19, 2019 9

  • PROJECT OVERVIEW

    •All piles are to be equipped with shoes.

    •Axial Capacity includes components of both Side Resistance and End Bearing.

    •No geotechnical losses were included in the design.

    •LDOEPs are to be filled with concrete to a minimum of 35 ft below ground elevation. Any material that may encroach above the proposed bottom of concrete inside the pipe shall be removed prior to filling.

    Midwest Geotechnical Conference, September 17-19, 2019 10

  • Midwest geotechnical conference, September 17-19, 2019 11

  • Midwest geotechnical conference, September 17-19, 2019 12

  • PROJECT OVERVIEW

    WHY LDOEPs ?

    Midwest Geotechnical Conference, September 17-19, 2019 13

  • BACKGROUND-PIER FOUNDATION TREATMENTS

    FOUNDATION TREATMENTS CONSIDERED:

    •Driven Metal Shell (Friction) Piles

    •H-Piles Driven to Rock

    •Drilled Shafts with Rock Sockets

    •Large Diameter Open-Ended Pipe Piles (LDOEPs) Driven to Rock

    Midwest Geotechnical Conference, September 17-19, 2019 14

  • BACKGROUND-PIER FOUNDATION TREATMENTS

    METAL SHELL (FRICTION) PILES AND H-PILES DRIVEN TO ROCK

    •The required number of metal shells or H-Piles would be considerably greater than

    that required for either drilled shafts or LDOEPs since one drilled shaft or one LDOEP

    can be substituted for a number of piles.

    •Metal shells and H-Piles both would require footings; along with the number of piles

    required, this would create and require a much larger “footprint” than the other two

    treatment types.

    Midwest Geotechnical Conference, September 17-19, 2019 15

  • BACKGROUND-PIER FOUNDATION TREATMENTS

    METAL SHELL (FRICTION) PILES AND H-PILES DRIVEN TO ROCK (CONTD.)

    •Along with taking up more space, pile supported footings would also require

    temporary soil retention adjacent to IL-3 and the railroads.

    •Although metal shells and H-Piles are technically feasible, due to limited

    space, interferences with existing foundations, shoring requirements for IL-3

    and the railroads, and additional utility and deep well conflicts, they were not

    considered favorable treatments for the interior bent locations.

    Midwest Geotechnical Conference, September 17-19, 2019 16

  • BACKGROUND-PIER FOUNDATION TREATMENTS

    DRILLED SHAFTS WITH ROCK SOCKETS

    • Drilled Shafts can be designed as an open pile bent and would not require a

    footing or soil retention.

    •Considerably less drilled shafts would be required than conventional piles.

    •However, shafts were less economical and would take longer and more effort

    to construct than LDOEPs.

    Midwest Geotechnical Conference, September 17-19, 2019 17

  • BACKGROUND-PIER FOUNDATION TREATMENTS

    LARGE DIAMETER OPEN-ENDED PIPE PILES (LDOEPS)

    •LDOEPs can be designed as an open pile bent and would not require a

    footing or soil retention.

    •Considerably less LDOEPs would be required than conventional piles.

    •Construction issues common to drilled shafts can be avoided since they are

    driven and not drilled.

    •They are more economical and faster and easier to construct than drilled

    shafts.

    Midwest Geotechnical Conference, September 17-19, 2019 18

  • BACKGROUND-FINAL SELECTION OF LDOEPS

    FINAL SELECTION OF LDOEPS WAS BASED ON:

    •Its advantages over the other treatments as previously discussed above

    •Being the most economical and efficient foundation design

    •Overall Constructability

    •Heavily favored by IDOT District 8 (recently used on nearby structure)

    Midwest Geotechnical Conference, September 17-19, 2019 19

  • BACKGROUND-SUBSURFACE DATA

    •The subsurface at Pier 3 generally consists of a sequence of sandy fill,

    clay, sand, and cobbles and gravel overlying sandstone and limestone

    bedrock.

    •The top of rock is on average approximately 120 feet below ground

    surface.

    •Boring data for Pier 3 is supplied by Boring BB-304.

    Midwest Geotechnical Conference, September 17-19, 2019 20

  • Midwest Geotechnical Conference, September 17-19, 2019 21

    5

    EAST ABUTMENT

    WEST ABUTMENT

    #1 #2#3

    #4

  • Midwest geotechnical conference, September 17-19, 2019 22

  • Midwest geotechnical conference, September 17-19, 2019 23

  • PROJECT OVERVIEW (CONTD.)

    •Project was let in June of 2018 and is currently under construction.

    •During Pile Driving at Pier 3, Pile 4 was crushed at its toe (OUCH!!!).

    •As a result, the axial capacity of Pile 4 was compromised.

    •Consequently, this problem needed to be resolved in a timely manner!

    LET’S NOW TALK CONSTRUCTION AND THE FIX………

    Midwest Geotechnical Conference, September 17-19, 2019 24

  • CONSTRUCTION …

    Midwest Geotechnical Conference, September 17-19, 2019 25

  • ASTM A252 Grade 3 steel

    50 ksi min. yield strength

    45 ksi max allowable driving stress (90%)

    48-in OD

    0.75 inch wall thickness

    Drive shoes

    2 planned splices

    Midwest Geotechnical Conference, September 17-19, 2019 26

    THE PILES

  • THE HAMMER:

    Hammer: APE D160-42

    Single acting diesel

    397 kip-ft rated energy max at fuel setting,

    35.28 kip ram weight

    11.25 ft max rated hammer stroke

    Midwest Geotechnical Conference, September 17-19, 2019 27

  • WEAP ANALYSIS SUMMARY

    Drivability Analysis:Assesses Driving Conditions with depth

    Assessed both with and without soil plug

    Bearing Graph Analysis

    Did not use API method because of experience with the adjacent MLK Connector LDOEPs

    Max fuel setting 4 modeled

    Hammer modeled with 80% efficiency

    Boring used BB-301 (W. Abut & Pier 1)

    Limestone bedrock assumed 2,500 ksf unit end bearing

    Full soil plug not expected

    Partial plug simulated by increasing end area linearly from no plug at top to 50% plug at bottom in dense granular layer just above the bedrock surface.

    Midwest Geotechnical Conference, September 17-19, 2019 28

  • Midwest Geotechnical Conference, September 17-19, 2019 29

  • Midwest Geotechnical Conference, September 17-19, 2019 30

  • Midwest Geotechnical Conference, September 17-19, 2019 31

  • WEAP DRIVABILITY ANALYSIS SUMMARY

    Max 10 bpi (IDOT spec.)

    11 bpi at 9.7 ft stroke (no plug)

    19 bpi at 9.4 ft stroke (partial plug)

    8 bpi at 9.8 ft stroke (Bearing Graph Analysis)

    31 – 35 ksi estimated driving stresses

    Average Transfer Efficiency is 39% (COV = 26) for diesel hammers (Appendix B3 of the 2010 version GLRWEAP manual)

    Midwest Geotechnical Conference, September 17-19, 2019 32

  • PDA TESTING TIMELINE FOR DRIVING PIER 3 ON 11/27/18

    10:44 am

    15:25 pm

    24:46 pm

    33:07 pm

    4

    Midwest Geotechnical Conference, September 17-19, 2019 33

  • Midwest Geotechnical Conference, September 17-19, 2019 34

    Pier 3, Pile 1, EOID

  • Midwest Geotechnical Conference, September 17-19, 2019 35

    Pier 3, Pile 4, EOID

  • PLAY BACK OF PDA RECORD FOR PIER 3, PILE 4

    Midwest Geotechnical Conference, September 17-19, 2019 36

  • Midwest Geotechnical Conference, September 17-19, 2019 37

  • DRIVE TIMELINE VIEWED IN PDA RECORD

    Midwest Geotechnical Conference, September 17-19, 2019 38

  • Midwest Geotechnical Conference, September 17-19, 2019 39

    Blow 339: Just prior to

    stopping the hammer

    3:15:54 pm

  • Midwest Geotechnical Conference, September 17-19, 2019 40

    Blow 339: F2 Strain Sensor Wiggly

  • Midwest Geotechnical Conference, September 17-19, 2019 41

    Restart Driving: Blow 348

    3:19:52 pm

  • Midwest Geotechnical Conference, September 17-19, 2019 42

    Blow 349: Velocity Bump Starts

    3:19:53 pm

  • Midwest Geotechnical Conference, September 17-19, 2019 43

    Blow 385: Velocity Bump

    3:20:54 pm

  • Midwest Geotechnical Conference, September 17-19, 2019 44

    Blow 450: Initial return

    shifted to left

    It should be here!

    3:25:21 pm

  • 45

    Pier 3, Pile 4, EOID

    3:30:05 pm

    Midwest Geotechnical Conference, September 17-19, 2019

  • WELL, THAT DIDN’T GO AS PLANNED!

    Midwest Geotechnical Conference, September 17-19, 2019 46

    Pile is damaged, but the show must go on …

    Moved to Pile 3 and lowered the fuel setting to 1.

  • Midwest Geotechnical Conference, September 17-19, 2019 47

    Pier 3, Pile 3, EOID

  • Midwest Geotechnical Conference, September 17-19, 2019 48

    Pier 3, Pile 2, EOID

  • PIER 3 PILE STATS

    Pile No.

    Nominal Required

    Bearing (Kips)

    CAPWAP Total

    Driven Bearing

    (Kips)

    CAPWAP Shaft/ End

    Bearing(Kips)

    LP (ft) Damage Depth 1st

    Indicated (ft)

    Final Penetration

    (blows/in.)

    PDA Calc.

    CSB (ksi)

    PDA Calc.

    ETR%

    Stroke(ft)

    Fuel Setting

    1 3006 4,200 400 / 3,800 117.75 13 @ 1 in 42.85 55.8% 11.7 4

    2 3006 4,330 630 / 3,700 117.94 15 @ 1 in 34.09 33.9% 8.4 1

    3 3006 4,310 710 / 3,600 118.17 10 @ 3/8in 36.00 40.6% 9.0 1

    4* 3006 495 495 / --- 123.0 118.78 54 @ 1 in 39.14 61.1% 11.2 4

    Midwest Geotechnical Conference, September 17-19, 2019 49

    * Pile 4 damaged about 5 ft above the bottom. Only use shaft resistance above damage.

  • PILE IS DAMAGED: NOW WHAT?

    • What was the cause?

    • Review Soil Borings

    • Review WEAP analysis

    • Review PDA files

    • Review PDA/CAPWAP Report

    • Can the pile still be used?

    • How can it be fixed?

    50

    Meetings

    Emails

    Calls

    Midwest Geotechnical Conference, September 17-19, 2019

  • FHWA REVIEW OF THE DAMAGED PILE IN THE MLK BRIDGE

    Reviewed project documents, mainly GRL documents for the damaged Pile 4 of Pier 3 and FHWA’s findings, conclusions, and recommendations for this pile are listed next.

    Damage at the toe of the pile is indicated, but extent of the damage is not clear.

    Blow count and PDA capacity for the damaged pile kept increasing with depth and reached 2800 kips when driving stopped.

    CAPWAP capacity results were reported for all Pier 4 piles except damaged Pile 4. (no end bearing or side resistance along damaged area)

    Analysis results for the damaged pile show CAPWAP capacity of 2520 kips.

    The required capacity for each pile in Pier 3 is 3006 kips. The capacity of the damaged Pile 4, 2520 kips, is close to the required capacity.

    Midwest Geotechnical Conference, September 17-19, 2019 51

  • FHWA REVIEW OF THE DAMAGED PILE IN THE MLK BRIDGE

    A pile cap will tie the 4 piles in Pier 3 together to function as a group of piles in supporting the pier loads.

    Total capacity of four piles in Pier 3 is 15,360 kips larger than required capacity of 12,024 kips.

    Conclusions/Recommendations:

    Although Pile 4 in Pier 3 is damaged to some extent, it is still has good capacity, that will be supplemented if needed by capacity of neighboring piles.

    Review FHWA findings and recommendations in the assessment process.

    Midwest Geotechnical Conference, September 17-19, 2019 52

  • WHO NEEDS TO BE INVOLVED IN THE FIX?

    • Solution Path: IDOT allowed the

    Contractor to hire Structural

    Engineer of Record to assess

    and develop a repair

    IDOT

    ContractorStructural

    Engineer of Record

    Midwest Geotechnical Conference, September 17-19, 2019 53

  • REPAIR OPTIONS:

    DO NOTHING

    • Accept and move on (Contractor's 1st choice)

    • Load test

    Use residual capacity

    • 495 kips skin• Neglect end

    bearing

    Make it a drilled shaft

    • Drill 3' Dia rock socket

    • Pressure grout bottom

    Pull and Replace

    Dive more piles

    • Adjacent• In the center• Bigger one

    around it

    Midwest Geotechnical Conference, September 17-19, 2019 54

    ?

  • CONTRACTOR DECIDES TO CORE THE BEDROCK INSIDE THE DAMAGED PILE

    Midwest Geotechnical Conference, September 17-19, 2019 55

    PILE

    CORING LOCATIONS

  • REPAIR OPTIONS

    DO NOTHING

    • Accept and move on (Contractor's 1st choice)

    • Load test

    Use residual capacity

    • 495 kips skin• Neglect end

    bearing

    Make it a drilled shaft

    • Drill 3' Dia rock socket

    • Pressure grout bottom

    Pull and Replace

    Dive more piles

    • Adjacent• In the center• Bigger one

    around it

    Drive a 60-in Dia LDOEP around the 48-in Dia Pile

    Midwest Geotechnical Conference, September 17-19, 2019 56

  • PROPOSED REPAIR FOR PIER 4 SHOWING SHEAR STUD ARRANGEMENT ALONG SPLICE ZONE

    48” φ Pile with rebar cage (Typical at all Piers) prior to repair

    Pier 3, Pile 4 repair showing Outer 60” φ Pile and Inner 48” φ Pile with rebar cage along Splice Zone with “Interlocking” Shear Studs

    Midwest Geotechnical Conference, September 17-19, 2019 57

  • Midwest Geotechnical Conference, September 17-19, 2019 58

  • Midwest Geotechnical Conference, September 17-19, 2019 59

  • Midwest Geotechnical Conference, September 17-19, 2019 60

  • Midwest Geotechnical Conference, September 17-19, 2019 61

  • Midwest Geotechnical Conference, September 17-19, 2019 62

  • Midwest Geotechnical Conference, September 17-19, 2019 63

  • Midwest Geotechnical Conference, September 17-19, 2019 64

  • Midwest geotechnical conference, September 17-19, 2019 65

  • REPAIR CONSTRUCTION MONITORING

    •IDOT D8 Construction performing visual on blows/ft and blows/in

    •PDA testing (GRL & IDOT)• Double the accelerometers and strain sensors

    •Wireless (GRL)

    • Cabled (IDOT)

    •CAPWAP results

    Midwest geotechnical conference, September 17-19, 2019 66

  • Midwest geotechnical conference, September 17-19, 2019 67

  • Midwest geotechnical conference, September 17-19, 2019 68

  • Midwest Geotechnical Conference, September 17-19, 2019 69

  • Midwest geotechnical conference, September 17-19, 2019 70

  • PDA AND CAPWAP

    Midwest geotechnical conference, September 17-19, 2019 71

    Nominal Required: 3,769 kips

    CAPWAP Capacity: 3,733 kips

    • Shaft Resistance: 1,113 kips

    • End Bearing: 2,620 kips

  • THANK YOU

    BRAD [email protected]

    HEATHER [email protected]

    Midwest geotechnical conference, September 17-19, 2019 72