Monthly Stakeholder Meeting
June 17, 2019
2
This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity
other than FDOT staff is not official. Any questions can be sent to [email protected].
This presentation may not be altered.
3
CURRENT DESIGN STATUS
• Roadway plans for I-95 north segment (segment 2A) complete
• 90% roadway plans for SR 836 and I-395
• Roadway plans for NE 13th Street complete
• Phase I TCP plans complete for I-95, I-395 and SR-836
• 60% signature bridge plans
• TCP generic plans and detour routes complete
OVERALL DESIGN STATUS
• Roadway - 80% • Structures – 45% • Maintenance of Traffic (MOT) – 50%
MAJOR DESIGN SUBMITTALS TO DATE:
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
4
• Installation of new drainage (Phase 1 - completed)
• Construction of foundations for new overhead sign structures. This work will require
continuous weekend lane closures starting at 11 p.m. on Friday until 5:30 a.m. on
Monday (Ongoing)
• Construction of median barrier wall (Ongoing)
• Begin concrete pavement replacement – Grading operations ongoing, concrete
placement expected to begin end of June
UPCOMING CONSTRUCTION ACTIVITIES
THREE MONTH LOOK AHEAD
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
5
Foundation work on northbound I-95 bridge approaching ramp to I-195 (Ongoing)
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
6
NB I-95
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
7
Pile driving operations for widening of the eastbound SR 836 ramp to northbound I-95 (Ongoing)
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
8
Demolition of I-95 median barrier wall over NW 20 Street. Will require full closure of NW 20 Street under I-95 (Ongoing)
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
9
• Installation of ITS devices for the Smart Workzone Management System (Ongoing)
• Nighttime single and double lane closures on SR 836 (Ongoing)
• Begin foundation work for bridges on eastbound SR 836 over the Lawrence Canal and
NW 17 Avenue (July)
• Eastbound SR 836 traffic shifted to the north side of the roadway from NW 12 Avenue to
I-95 to allow for construction of bridge widening (August/September)
UPCOMING CONSTRUCTION ACTIVITIES
THREE MONTH LOOK AHEAD
10
SR 836 PHASE 1 – STEP 1
Widening of SR 836 to the
south to create future
eastbound lanes
Future widening for
westbound SR 836
Shift eastbound SR 836 traffic to the median to begin widening to the south (this week)
WESTBOUND SR 836 EASTBOUND SR 836
11
SR 836 PHASE 1
N
LEGEND Median Work Zone
Demolition of bridges on eastbound SR 836 over the Lawrence Canal and NW 17 Avenue (this week)
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
12
Drainage work inside the loop ramp on NW 12 Avenue to eastbound SR 836 for future
courthouse supplemental parking (Ongoing)
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
13
• Utility relocations (Ongoing)
• Widening activity on NE 13 Street between Biscayne Boulevard and NE 2 Avenue
(July/August)
• Bridge foundation work for I-395 collector-distributor bridges (July/August)
• Permanent closure of NE 12 Street between Biscayne Boulevard and NE 2 Avenue;
Traffic to be routed to NE 13 Street and NE 11 Street. (July/August)
UPCOMING CONSTRUCTION ACTIVITIES
THREE MONTH LOOK AHEAD
Widening activity on NE 1 Avenue to convert to two-way traffic from I-395 to NE 13 Street – will require closure of left lane on NE 1 Avenue between I-395 and NE 13 Street (this week)
14
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
15
16
• SR 836 UPCOMING CONSTRUCTION ACTIVITIES
17
UPCOMING CONSTRUCTION ACTIVITIES
THREE MONTH LOOK AHEAD
Demolition of barrier wall on I-395 and I-95 ramps to eastbound I-395 to allow for future bridge foundation construction (July)• The southbound I-95 ramp to eastbound I-395 will be reduced from two lanes to
one lane for approximately four years. • The travel lane and shoulder widths on northbound I-95 ramp to eastbound I-395
will be reduced. Will require nighttime closures at times• Traffic shift to the south on I-395 eastbound from I-95 to NW 1 Avenue
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
18
NB I-95 Ramp to EB I-395 ramp will have lane and shoulder
widths reduced
SB I-95 Ramp to EB I-395 two lane ramp will be reduced to one lane
EB I-395 Travel Lanes shifted to the south
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
19
Bridge foundation work for westbound Signature Bridge (December)
UPCOMING CONSTRUCTION ACTIVITIES
THREE MONTH LOOK AHEAD
MAINTENANCE OF TRAFFIC (MOT)/HOURS
I-395 SPECIFICMainline Nightly Closures
• 10 pm to 5:30 am Sunday thru Thursday
• 1 am to 7 am Saturday and Sunday
SR 836 SPECIFICMainline Nightly Closures
• 8 pm to 5:30 am Sunday thru Thursday
• 8:30 pm to 9 am Friday
• 8:30 pm to 11 am Saturday
I-95 SPECIFICMainline Nightly Closures
• 9 pm to 5:30 am Sunday thru Thursday
RAMPS• 10 pm to 6:30 am Sunday thru Thursday
• 11 pm to 7 am Friday and Saturday
SPECIAL NOTES:• Special events will be taken into account when scheduling closures
• Hours noted above are for single lane closures, multi-lane closures will occur later
• Weekend lane closures will be permitted on I-95 from 11 p.m. on Friday to 5:30 a.m. on Monday• The contract documents allows for weekend closures on certain ramps
20
• Provide drivers with real-time
travel information;
• Encourage motorists to take
alternate routes;
• Clear incidents more quickly,
thereby reducing secondary
incidents; and
• Make work zones safer for
highway workers and motorists.
Smart Work Zone Management
System (SWZMS) - The project will
implement a SWZMS that will utilize
Intelligent Transportation System
(ITS) Devices such as traffic
cameras, data collection devices
and portable message signs to:
TRAFFIC MANAGEMENT SYSTEM
21
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
22
Media Availability- June 7,
2019
Media Outlets
• WSVN: Channel 7
• WFOR: Channel 4
• WTVJ: Channel 6
• WSVN: Channel 7
• Telemundo
• Univision
• Estrella TV
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
23
2019 FIU PARENT/CHILD BRIDGE ENGINEERING SUMMER CAMP
24
COMMUNITY OUTREACH
PROJECT WEBSITE
• www.i-395miami.com
• Sign-up for project alerts/updates
Lane Closure information
Upcoming construction activities
Presentations
• Calendar of events
OUTREACH OFFICE IN THE OVERTOWN COMMUNITY
• 1035 NW 3 Avenue, Miami, Florida 33136
STAKEHOLDER MEETINGS
• Ongoing individual stakeholder meetings and presentations
• Next stakeholder meeting – July 15, 2019