Mooring Experience Mooring For more information on InterMoor: www.intermoor.com [email protected] 12-2015 Print

Mooring - InterMoor Shelley FPSO 2008 Mooring Installation, Tow and Hookup Petrofac Northern Producer 2008 Mooring Installation, Tensioning and Hookup ATP Anadarko

Embed Size (px)

Citation preview

Page 1: Mooring - InterMoor Shelley FPSO 2008 Mooring Installation, Tow and Hookup Petrofac Northern Producer 2008 Mooring Installation, Tensioning and Hookup ATP Anadarko

MooringExperience

Moorin

g

For more information

on InterMoor:

www.intermoor.com

[email protected]

12-2015 Print

Page 2: Mooring - InterMoor Shelley FPSO 2008 Mooring Installation, Tow and Hookup Petrofac Northern Producer 2008 Mooring Installation, Tensioning and Hookup ATP Anadarko

CLIENT RIG YEAR WATER DEPTH (FT) APPLICATIONbpTT Ocean Victory

Offshore Trinidad2015 353 Hookup Ocean Victory at

Juniper

PetroSaudi Saturn Offshore Venezuela

2015 394 Disconnect from DR-8, recovery of presets

ExxonMobil Endeavor Offshore Romania 2015 427 – 2,888 Several rig moves

Pemex / Diamond Ocean Ambassador Offshore Mexico 2015 400 Rig move

Anadarko ENSCO 8500 at KC 919 #6 2014 -- Barge mooring installation and disconnect procedures

Anadarko Noble Bob Douglas at KC 919 #5 ST2 2014 -- Barge mooring installation and disconnect procedures

Anadarko Ensco 8505 Barge Hawser Installation 2014 -- Barge mooring installation and disconnect procedures

Anadarko Ensco 8500 at KC 874 No. 1 2014 -- Barge mooring installation and disconnect procedures

Atlantica Mooring Inspection Plan for BassDrill Beta

2014 4,380 Mooring inspection plan document written for TADU

in Brazil

Bennu Oil Ocean Victory at MC 941 Gulf of Mexico

2014 4,005 Mooring design and analysis using chain / wire /

polyester presets; also performed hurricane analyses

and risk assessment

Bennu Oil Ocean Victory at AT-63 Gulf of Mexico

2014 4,410 Mooring design and analysis using conventional chain / wire lines; also performed hurricane

analysis and risk assessment

Diamond Offshore Drilling Ocean Endeavor at Domino-2 2014 2,667 Mooring verification / mooring installation procedures for

chain / wire conventional lines with drag anchors

Diamond Offshore Drilling Ocean Endeavor at Pelican South-1 Offshore Romania

2014 427 Procedures for conventional mooring system

Diamond Offshore Drilling Ocean Quest at DH-10P Offshore Vietnam

2014 365 Mooring design and installation procedures

for conventional / preset hybrid as well as offshore

personnel

Diamond Offshore Drilling Ocean Yorktown at Kayab-101 Offshore Mexico

2014 1,183 Installation and recovery procedures for conventional

mooring system

Juniper Ocean Victory at Juniper Mooring Center Offshore Trinidad / Tobago

2014 353 Preset mooring system using chain / wire

and driven piles

LLOG Ocean Saratoga at MC 707 Gulf of Mexico

2014 1,542 Conventional mooring analysis using chain / wire / drag

anchors

Maersk Drilling Maersk Discoverer Offshore Morocco

2014 1,772 Mooring analysis using chain / wire / polyester presets

MooringExperience

CLIENT RIG YEAR WATER DEPTH (FT) APPLICATIONMarubeni Noble Driller at GC 155

Gulf of Mexico2014 2,000 Analysis and risk assessment

for BSEE approval and preset hurricane mooring system

Murphy Azurite FPSO Disconnect 2014 4,610 Mooring disconnect procedures for chain / wire /

polyester lines

Pemex Ocean Ambassador at Ayin-11 Offshore Mexico

2014 400 Mooring verification, conventional installation

procedures for chain / wire lines

Petro Saudi PetroSaudi Discoverer at El Mediouni-1 2014 787 Mooring design and analysis, written

installation procedures, and offshore personnel

for installation of a turret moored vessel

Petro Saudi Petro Saudi Saturn at DR11 Offshore Venezuela

2014 400 Analysis and procedures for preset chain / wire /

polyester / drag embedment anchors and

offshore personnel

Walter Oil & Gas Ocean Victory at GC 6 Gulf of Mexico

2014 690 Analysis only for conventional mooring system

PetroSaudi PetroSaudi Saturn at DR-11 2013 400 Pre-sets

Signal Maersk Developer at VK-248 2013 220 Pre-sets for thruster change-out

PetroSaudi PetroSaudi Saturn at DR-5A 2013 400 Pre-sets

Walter Oil&Gas Ocean Saratoga at MC-583 2013 2500 Moored for hurricanes

Shell Noble Clyde Boudreaux 2012 6651 Deepwater Mooring

CGX Resources Ocean Saratoga (Guyana) 2012 300

Murphy Ocean Rover (Malaysia) 2012 4455 Moored with polyester

Murphy West Menang (Malaysia) 2012 4455

LLOG Amos Runner 2011 2460

ATP Ocean Victory 2011 3463

Walter Oil&Gas Ocean Victory 2011 1300 Moored for hurricanes

Walter Oil&Gas Saratoga 2011 1100 Moored over pipelines

Transocean DD-I, DD-II, DD-III 2010-2011 350 Pre-sets

Diamond Ocean Yorktown (Mexico) 2011 1000

Larsen Oil & Gas Petrolia (Mexico) 2010 1200

Walter Oil&Gas Ocean Voyager 2010 1300

ATP Ocean Victory 2009-2010 4418 Moored for hurricanes; Moored over pipelines

LLOG Lorris Bouzigard 2010 2952

Shell Arctic 1 (Brazil) 2008-2010 1895 Moored over pipelines

Walter Oil & Gas Ocean Saratoga 2009 2200 Moored for hurricanes

StatoilHydro Goodrich (GoM, Canada) 2009 3600 Moored for hurricanes

BP Marianas 2008-2009 5000 – 7040 Moored with polyester; Moored for hurricanes

Murphy Oil Ocean Rover 2009 4300 Moored over pipelines

Walter Oil & Gas Ocean Saratoga 2009 1400 Moored over pipelines

MODU Conventional, Pre-Set and Insert Experience (Americas/Asia continued)

MODU Conventional, Pre-Set and Insert Experience (Americas/Asia)

Page 3: Mooring - InterMoor Shelley FPSO 2008 Mooring Installation, Tow and Hookup Petrofac Northern Producer 2008 Mooring Installation, Tensioning and Hookup ATP Anadarko

MODU Conventional, Pre-Set and Insert Experience (West Africa)

MODU Conventional, Pre-Set and Insert Experience (West Africa continued)

CLIENT RIG YEAR WATER DEPTH (FT) APPLICATIONHess West Esperanza 2015 1,744 TAD disconnect

CABGOC West Vencedor 2015 230 TAD disconnect

CABGOC Maersk Deliverer at LT-A Offshore Angola

2014 1,730 Analysis for preset mooring system using chain / wire /

drag anchors

CABGOC West Vencedor at North Sanha Offshore Angola

2014 230 Analysis and procedures for rig move and to relocate

preset anchors

CLIENT RIG YEAR WATER DEPTH (FT) APPLICATIONCABGOC Maersk Deliverer at Lianzi

Offshore Angola2014 2,992 Mooring and analysis to

install MODU

CABGOC Maersk Deliverer at LT-C Offshore Angola

2014 1,341 Analysis and wrote proce-dures to install MODU

CABGOC Tombua Landana Relief Well Offshore Angola

2014 1,150 Design of relief well mooring spread

Chevron Malange Field Study Offshore Angola

2014 900 Analyses for three (3) drill centers, proposed mooring

layouts

CNOOC Atwood Hunter at S-3 Equatorial Guinea

2014 3,002 Analysis and procedures for conventional mooring

system

CNOOC Atwood Hunter at S-4 Equatorial Guinea

2014 3,570 Analysis and procedures for conventional mooring

system

ENI Angola Scarabeo 9 at East Hub Mooring Study

2014 1,500 Mooring study for 3 well locations for

DP rig using chain / wire and drag anchors

Hess Echo TLP Preset Laydown Equatorial Guinea

2014 900 Procedures to wet store preset mooring lines

Transocean Sedneth 701 at Okono K Offshore Nigeria

2014 200 Analysis and procedures for conventional mooring

system

Transocean Transocean Honor Jack-Up Rig Offshore Angola

2014 98 Mooring analysis to assist jack-up for

positioning

Transocean Sedco Energy at Okono 10 Offshore Nigeria

2014 220 Analysis and procedures for conventional mooring

system

Transocean Tranocean GSF-135 at Okono 10 Offshore Nigeria

2014 220 Analysis and procedures for conventional mooring

system

Transocean Transocean GSF-135 at Okono-3 Offshore Nigeria

2014 220 Analysis only for preset mooring system (mooring

system not installed)

Transocean Transocean GSF-135 at Okono-4 Offshore Nigeria

2014 220 Analysis for preset mooring system; operations have not

occurred yet

Transocean Sedneth 701 at Pointe Noire 2014 164 Analysis and procedures for conventional mooring

system

Transocean / Total Mooring Study for Transocean GSF-135 at Moho Nord Offshore Congo

2014 2,690 Mooring study using chain / wire / polyester presets

Cabinda Gulf Oil Company Transocean R135 (Angola) 2013 1909 Analysis/Support

Addax GSF Rig 135 (Nigeria) 2012 250

Hess Ocean Valiant (Equatorial Guinea) 2011-2013 2640 + Pre-sets

ExxonMobil Transocean Rather (Angola) 2009-2012 4455

ExxonMobil GSF Celtic Sea (Angola) 2011-2012 4190

Maersk Ensco 5001 (Angola) 2011-2012 4059

ENI Transocean Marianas 2011-2012 221

Maersk Ocean Valiant (Angola) 2011 2640

Shell Sedco 702 (Nigeria) 2011 1739

MODU Conventional, Pre-Set and Insert Experience (Americas/Asia continued)

CLIENT RIG YEAR WATER DEPTH (FT) APPLICATIONLLOG Lorris Bouzigard 2009 3269

Deep Gulf Ocean Victory 2009 4397

Deep Gulf Ocean Victory 2009 448 Moored over pipelines

ENI Petroleum Marianas 2009 7141

Cabinda Gulf Oil Company Ocean Victory (GoM) 2008 4700 Moored with polyester; Moored for hurricanes

DeepStar Ocean Baroness 2008 6500 Moored for hurricanes

Walter Oil & Gas Ocean Saratoga 2008 1400 Moored over pipelines; Moored for hurricanes

Marathon Henry Goodrich 2008 3400 Moored over pipelines; Moored for hurricanes

Noble Energy Ocean Quest 2008 3450 Moored for hurricanes

Stone Energy Hornbeck Test Barge 2008 130

LLOG Ocean Saratoga 2008 1035 Moored for hurricanes

Amoco Paul Romano 2008 5840 Moored for hurricanes

Noble Energy Ocean Quest 2007 2900 Moored over pipelines; Moored with polyester

Walter Oil & Gas Lorris Bouzigard 2007 3200 Moored with polyester

Hess Ocean Baroness 2007 3800 Moored for hurricanes

ChevronTexaco Versabar Bottom Feeder (Brazil) 2007 225 Moored over pipelines

Murphy Oil Ocean Rover (Malaysia) 2006-2008 4300 – 8431 WORLD RECORD

Marathon Henry Goodrich 2007 3400 Moored over pipelines

Noble Energy Versabar Bottom Feeder 2007 250

Shell Arctic 1 (Brazil) 2007 5250 Moored over pipelines; Moored with polyester

ATP Rowan Midland 2006 3000 Moored with polyester

Global DD 1 2006 300

Kerr-McGee Ocean Concord 2006 2300 Moored for hurricanes

ChevronTexaco Cajun Express (Jack Well Test) 2006 7000 Moored with polyester

Spinnaker Arctic 1 2005 1750

POGO Lorris Bouzigard 2005 590 Moored over pipelines

Walter Oil & Gas Ocean Quest 2005 3200 Moored over pipelines

Stone Energy Lorris Bouzigard (VK 773) 2004 470

Atwood/Shell Atwood Seahawk (Malaysia) 2004 230 Moored over pipelines

Page 4: Mooring - InterMoor Shelley FPSO 2008 Mooring Installation, Tow and Hookup Petrofac Northern Producer 2008 Mooring Installation, Tensioning and Hookup ATP Anadarko

CLIENT PROJECT YEAR WATER DEPTH (FT) APPLICATIONNoble Energy EG Ensco 5001 (Equatorial Guinea) 2010-2011 3020 Pre-sets

Noble Energy EG Atwood Hunter (Equatorial Guinea) 2009-2012 3020 Pre-sets

Chevron West Setia (Angola) 2010-2012 4389

Chevron West Vencedor (Angola) 2010-2012 386

ENI Scarabeo 7 (Angola) 2009-2012 4620

Cabinda Gulf Oil Company Sedneth 701 (Angola) 2008-2010 1500

Cabinda Gulf Oil Company Richardson (West Africa) 2009 5380

Cabinda Gulf Oil Company Pride Venezuela (Angola) 2009 900

Cabinda Gulf Oil Company West Setia (Angola) 2008 1200 Moored with polyester

Cabinda Gulf Oil Company Transocean Richardson (Angola) 2008-2009 3200 – 6000 Moored over pipelines

Total Angola Transocean Richardson (Angola) 2008 3500

Noble Energy Sedco 700 (Equatorial Guinea) 2008 3400

Cabinda Gulf Oil Company Transocean Richardson (Angola) 2007 5000 – 6200

Cabinda Gulf Oil Company Barge CMC 450-10 (Angola) 2007 250 Moored over pipelines

Esso Angola Multiple MODUs 2007 690

ChevronTexaco Sedneth 701 (Angola) 2006 3400

Hess Sedco 700 (Equatorial Guinea) 2006 2400

Esso Angola Pride South Pacific (Angola) 2005 4200

FPS Jamestown (Nigeria) 2004 60 Moored with polyester

Esso Angola Pride South Pacific 2004 4000

MODU Conventional, Pre-Set and Insert Experience (West Africa continued)

CLIENT PROJECT YEAR LOCATION APPLICATIONAnadarko Neptune Spar 2014 GOM Spar riser decommissioning

Anadarko Innovator 2014 GOM FPU decommissioning

MODEC FPSO Baobab Ivorian MV10 2014 Ivory Coast Temporary repair for mooring lines of the FPSO:

Murphy West Africa, Ltd.

Azurite FDPSO 2014 Republic of Congo

Decommissioning services

Sabah Shell Petro-leum

Malikai Field TAD/ DTV 2014 Malaysia Engineering Consultancy for TAD Hook up, Installation Analysis of cross and surge lines

between the TAD and TLP.

KPOC KBB Platform – TAD 2014 Malaysia Mooring analysis/ heavy lift analysis/ weather management/ pre lay & hook up.

Hook up of soft leg hawsers.

Petronas / SKD SKD T9 and SKD T19 2014 Malaysia Mooring analysis/ heavy lift analysis/ pre lay operations and tad hook up.

LLOG Delta House 2014 GOM Mooring Analysis / Pile design, fabrication, installation / Pre-lay Operations and Hook-up

Anadarko Red Hawk Spar 2014 GOM Engineering procedures, disconnecting existing mooring lines, preparing vessel for towing, cutting and removing the

riser pull-in tubes, decommissioning, towing and reefing.

Petrobras / Floatec Papa –Terra, TAD-TLP 2013 Brazil Engineering, Consulting, and offshore execution of the pre-installation of the World’s First Dual Layer Hawser

System on the Papa Terra P-61 TLWP.

Hess Echo/Foxtrot 2013 Replaced hawser system and TAD/TLP wires (EG)

Tioman / KPOC KBB Platform 2013 Malaysia TAD hookup

CABGOC / Seadrill West Vencedor TAD 2012 Malaysia Mooring analysis

COOEC Lufeng 2012 China Project management, installation engineering and procurement for the installation of a new buoy turret

mooring system

Murphy Oil Kikeh Field, TAD-Spar DTU. 2011 Malaysia Disconnect TAD, pre-lay mooring install

Murphy Oil West Menang TAD 2011 Malaysia Disconnect, hawser change-out, hookup

Shell Auger 2011 Replaced all 4 lateral moorings

Murphy Kikeh Spar 2011 Malaysia Hawser change-out and TAD hookup

ATP Mirage 2010 Mooring Design, Installation, Tow, Upending and Hookup

Hess Okume & Oveng Field Development. TAD-TLP

2009 Equatorial Guinea

Disconnect hawser and replace hawser lines

Cabinda Gulf Oil Company

Tombua Landana 2008 Angola Provided the design, engineering, procurement, and installation for the permanent preset taut-leg moorings

for the TAD at the Tombua Landana location

Oilexco Shelley FPSO 2008 Mooring Installation, Tow and Hookup

Petrofac Northern Producer 2008 Mooring Installation, Tensioning and Hookup

ATP MinDOC 2008 Mooring with Polyester

Nexen Ettrick 2007 North Sea Jacketed Spiral Strand Installation and Tensioning, Tow of Submerged Turret Buoy and Hookup

ATP Gomez 2006 US GOM Mooring Design, Supply, Installation and Hookup

Husky White Rose FPSO 2006 Mooring Installation, Tow and Hookup

Cabinda Gulf Oil Company

Lobito-Tomboco 2005 Angola Permanent Drilling Rig Preset Mooring 2007 - Maintenance of wire lubrication

and equipment for the permanent pre-sets

Permanent Mooring and TAD-TLP Experience (continued)

CLIENT PROJECT YEAR LOCATION APPLICATIONTotal / HHi Moho –Nord Field Development.

TAD -TLWP2015 Congo Engineering study

MODEC FPSO Baobab Ivorian MV10 2015 Ivory Coast Engineering, procedures and offshore operations for the maintenance of one mooring line.

Bumi Armada Armada Perkasa 2015 Nigeria Top chain replacement of all ten (10) mooring lines of the FPSO and repositioning of two (2) mooring lines,

with no production shutdown required.

Anadarko Boomvang Spar 2015 GOM Engineering, procedures and offshore operations services to disconnect and lay down three (3) risers and one (1) umbilical.

Boskalis / MEGI Zafiro Producer 2015 Equatorial Guinea

Engineering and offshore operations services to inspect and replace old mooring chains and wire ropes for nine (9) of the

twelve (12) mooring lines along with two (2) drag anchors.

Anadarko Heidelberg Spar 2015 GOM Engineering and offshore operations services for the installation and hook-up of first 3 moorings (storm safe). Provided analyses, procedures, and offshore support for

polyester stretch removal activities.

COOEC Enping FPSO 2014 South China Sea

Onshore and offshore project management, installation engineering and procedures development and installation

of a new FPSO – including full single point mooring system, a fixed manned drilling and pipeline production platform,

and a 2.2 km subsea flexible.

COOEC Panyu FPSO 2014 South China Sea

Planning, engineering and installation of the mooring system using the existing mooring pattern

and ensuring that the existing FPSO remained in production throughout the installation.

Chevron Kuito FPSO 2014 Angola FPSO decommissioning including disconnect and laydown twenty (20) risers and umbilicals, release mooring lines.

Disconnection, recovery, and abandonment of the CALM buoy.

Permanent Mooring and TAD-TLP Experience