SIPD-‐621 MAJNOON SITE INVESTIGATION Morning Update
HSE 08.04.14: 0000-‐2400hrs.
Ø STOP WORKS for Drilling activities since 07.04.14 @ 1350 Ø HSE Weekly Walkabout postponed due that CSR vehicle breakdown. Ø PSD escorted CTR’s PM and CSR for the jointly MOF site visit. After the site visit it was concluded
by both parties that personnel will struggle to be under the heat during summer months with body armour. Extra precautions to be implemented.
Ø CTR had a problem (not disclosed yet) with the PTW for PCPT Rig. Unfortunately CTR didn’t report it CSR to seek for assistance.
09.04.14: 0000-‐-‐-‐0700 hrs.
Ø CTR to complete incidents investigations and undergo inspection from CPY’s HSE. Ø CPY HSE and CSR to visit CTR’s Camp for equipment inspection related to the incidents and advice
on closure in order to go back operational again. Ø HSE Weekly Walkabout to be conducted.
OPERATIONS 08.04.14: 0000-‐2400hrs.
Ø RIG 1 (WELL PAD Site) • No production as CTR had a problem with PTW
Ø RIG 2 (TIGRIS Site)
• No production as CTR was on STOP WORK due to unreported incident • Tidy up site, load truck and prepare for transit.
Ø RIG 3 (WELL PAD G22)
• No production as CTR was on STOP WORK due to unreported incident Next 24 Hrs and beyond.
Ø RIG 1 (WELL PAD Site) • Pursue PTW
Ø RIG 2 (TIGRIS Site) • Close incident and continue with works, once CPY HSE approves it.
Ø RIG 3(TIGRIS Site) • Close incident and continue with works, once CPY HSE approves it.
SIPD-‐621 MAJNOON SITE INVESTIGATION Morning Update
ANTICIPATED EVENTS CTR
Ø CTR showed reluctant to report on time any HSE issues or work problems encountered during the last week (e.g. incidents with bailer in Drill Rigs leading to the Stop Works, problems obtaining PTW, etc). CSR discusses this problem with CTR’s PM and he committed not to happen again
Ø HSE Weekly Walkabout to be completed once CSR vehicle is repaired Ø CTR to amend and submit again the EUPHRATES Borehole and PCPT Logs Ø CTR to amend and resubmit DPRs from 01.04.14 to 07.04.14 Ø CTR is addressing HSE and TECHNICAL findings, reported by CSR back to CTR on 01.04.14 (e-‐mail
“SIPD-‐621_MAJNOON_20140401_1300-‐ HSE-‐Technical-‐Admin pending issues – HG”) Ø CTR to submit pending Survey Reports for all location since beginning of Fieldworks. CTR has been
submitting Actual Coordinates and Elevations of completed locations only and after several requests, rather than producing the reports as Fieldworks progress.
CPY
Ø Joint visit with CTR’s PM on 08.04.14 to JETTY & CONSTRUCTION CAMP Sites to assess logistics and rig access to proposed locations.
Ø CPY to provide Site Instructions to CTR for at least 1 week ahead to allow CTR to plan and to avoid any standby times.
Ø CPY to instruct CTR which locations will require down-‐the-‐hole instrumentation and tentative dates to mobilize the Geophysical crews.
PLANNING Ø CSR and CTR’s PM joint visit to MOF on 08.04.14 showed that access to locations is better than
expected, however 1 or 2 locations will be offset due to marshes. Ø CTR needs extra SOW to plan ahead properly and avoid standby, and use the WELL PADS Site as a
bumper in case no other project has been defined in order to carry on works there. CPY is providing new SOW for MOF and CONSTRUCTION CAMP Sites.
Ø CTR submitted Gannt Diagram including resources, locations of Rigs and PTW coverage. To be done before every Weekly Meeting.
Ø It is anticipated that with the new arrival of an assistant to PM, paperwork and reporting will be submitted in time and form.
ADMIN
Ø CSR submitted New DPR Template to CTR for discussion. Due to poor Admin skills, CTR hasn’t submitted the New DPR Template. As well they are very disorganized with their internal reporting (Drillers to PM and Surveyors to PM. The only team that reports efficiently back to PM is the PCPT track). CSR assists them with how and what to report, as well as with a new Reporting template for CTR to use internally. The problem is not lack of resources but poorly administrated, and therefore struggle to plan.
SIPD-‐621 MAJNOON SITE INVESTIGATION Morning Update
Ø CSR and Jaydeep implemented filing system for received data from CTR. During this week all transferred data will be available from a link .
Ø CPY to revert with signed Site Instruction for proper filing and follow up.
DATA RECORDING & TRANSFER Ø Submitted data starts to show consistency between different Engineers producing the reports. Ø CTR has to resubmit EUPHRATES data as its not properly
PROJECT TRACKTIME
• Rig 1 – PCPT track
SIPD-‐621 MAJNOON SITE INVESTIGATION Morning Update
• Rig 2 – Drill Rig DANDO 2000
• Rig 3 – Drill Rig DANDO 3000
SIPD-‐621 MAJNOON SITE INVESTIGATION Morning Update
Reference
CPY: Company CTR: Contractor CSR: Company Site Representative All times and depths are approximately, official figures are in DPR
Kind regards, Hernan Goldemberg Senior Geotechnical Engineer Company Site Representative -‐ CSR MAJNOON OIL FIELD M1: +(964) 78 26 49 15 83 (Iraq) M2: +(44) 78 81 49 53 78 (when away) SIPD-‐Geomatics-‐Geotechncial-‐Site-‐[email protected]