1
Musselwhite Mine
Location and Site Video
https://www.youtube.com/watch?v=-y5G0BaxtZw
2
Currently 540 active full time employees, 300 contractors
• Currently 255 full time employees from Thunder Bay (~50%)
• ~90% of all hires in the last 12 months from or re-located to Thunder Bay
• Local hire policy in place June 2017• Operational impacts – 5-10 year plan
TOGETHER, CREATING SUSTAINABLE VALUE
2
Thunder Bay Our Home Video
Musselwhite – Making Thunder Bay Our Home
https://vimeo.com/234837072
3
Materials Handling Project on schedule and within budget• Ore tonnage movement restricted to 3,600 tonnes per
day until winze online, expanding to 4,300 tonnes per day thereafter
Investing in technology to improve efficiencies and further reduce costs• Tele-remote mucking, dispatch, autonomous drilling
Consistently replacing mine reserves and discovering new mineralization• Cost of discovery under $25/oz
• Potential for resource growth
Ownership 100%
Location Ontario, Canada
P&P gold reserves1 1.9 moz
M&I gold resources1 0.3 moz
Inferred gold resources1 1.2 moz
2018 exploration budget2 $10 M
2018 capital budget2 $75 M
265kozProduction22018
$775/ozAISC22018
1 As of June 30, 2017. Refer to the reserve and resource statement on Goldcorp’s website for more details2 Initial guidance as of January 2018. Figures are +/- 5%
4
Musselwhite Mine Long Section
(~10km Meters via Ramp)
5
1170 mL RB/Grizzly Access
Shaft Leg1 O/P
O/P
Shaft Bottom
Sheave Deck & Hoist RoomHoist Room Access
Existing 280 Expl. Ramp
Truck Loading Station
1220/1245 Main Ramp In progress
657/WEL Access
Mucking Level for
Leg 1 (280/657L)
WEL Truck Dump
Material Handling Project - Existing Ramps & MH DevelopmentIsometric View (Apr 22, 2017)
N
1170 mL
MH – Planned Development
MH – Completed Development
Non MH - Existing Development
Skip Change Drift
1245 mL
LDG Pocket
Shaft Leg2
6
MHP Construction Update
7
280 Hoist room RB90 drill set up
8
657 Raise bore reamer install
9
MHP Construction Update
Reamer BT on 280
10
RB90-1 breakthrough
11
Installation of Galloway in shaft
12
View look out to access to Hoist room
13
MHP Construction UpdateBuilding electrical trenches Hoist foundations
14
View hoist pit from the Electrical house
15
Installing Overhead crane beams in hoist room
16
Musselwhite Opportunities for Value Creation
• Efficiencies in material movement through improved communication and traffic flow
• Increased development, stope drilling and trucking capabilities
• Drive compliance to plan through lower dilution
• Exploring partnerships with Sandvik for MX 650
• Increasing lateral development rates will unlock value
• Large land package with considerable exploration potential (77K hectars)
• Reserve replacement strategy
• Focus on discovery of new zones
Control Room/ UG Dispatch
Autonomous Drills and Trucks Tunnel Boring Machine Exploration
17
Technology – Our ore body is moving further away every day and we need to react
Scoop Trams
Crusher/Rock Breaker
Jumbo Drill Longhole Drill Haul Trucks
TOGETHER, CREATING SUSTAINABLE VALUE
UG Dispatch/ControlCenter
18
Thunder Bay IROC Integrated Remote Operations Center
• UG dispatch with real-time monitoring- Personnel, energy, etc.
• Real-time data for production and maintenance- Improves maintenance planning- Increases reliability
• Set up for tele-remote- Scoops, Jumbos, LH Drills, Rock
Breaker, Crusher
• Dual setup in both Musselwhite and Thunder Bay
19
Q & A
Musselwhite MineSlide Number 2Slide Number 3Musselwhite Mine Long SectionMaterial Handling Project - Existing Ramps & MH Development�Isometric View (Apr 22, 2017)�MHP Construction Update280 Hoist room RB90 drill set up657 Raise bore reamer installMHP Construction UpdateRB90-1 breakthroughInstallation of Galloway in shaft View look out to access to Hoist roomMHP Construction UpdateView hoist pit from the Electrical house Slide Number 15Musselwhite Opportunities for Value CreationTechnology – Our ore body is moving further away every day and we need to react Thunder Bay IROC Integrated Remote Operations Center Q & A