Upload
hoangcong
View
224
Download
2
Embed Size (px)
Citation preview
NABHA POWER LIMITED Power to People
18th National Award for Excellence in Energy Management 2017
30th August – 1st September 2017, CII-Hyderabad
2 x 700 MW Super Critical Thermal Power Plant
NABHA POWER LIMITED
1
Nabha Power Limited – Power to People 2 8/31/2017
COMPANY PROFILE • PROJECT & KEY FEATURES
BENCHMARKING • >660 MW FY17 PERFORMANCE
• ENERGY BENCHMARKING
ASSESSMENT
• STATUS OF SEC OF NPL FOR LAST 3 YEARS (Y-O-Y)
• OBJECTIVES, MONITORING & REPORTING
• STRATEGY FOR SEC REDUCTION
ENCON PROJECTS
• ENCON FY 14-15
• ENCON FY 15-16
• ENCON FY 16-17
INNOVATION • CATEGORY A INNOVATION
• CATEGORY B INNOVATION
SUSTAINABILITY
• GREEN PROJECTS
• BEST PRACTICES
• CERTIFICATIONS
• AWARDS
AGENDA
Nabha Power Limited – Power to People 3 8/31/2017
Bidding
9th Oct 2009
LOI
18th Nov 2009
PPA
18 Jan 2010
FSA Signing 15
Sep 2013
Unit-1 COD
1 Feb 2014
Unit-2 COD
10 July 2014
Project Developed by Larsen & Toubro Ltd – India’s largest
and most reputed infrastructure company under Case-2 of
Tariff based Bidding
25 Years Power Purchase Agreement (PPA) signed in January 2010 with Punjab State Power Corporation Limited (PSPCL).
Long term FSA with SECL for 20 years.
Environment friendly supercritical technology.
All major equipment manufactured indigenously through technology tie-up or JV’s
Best in class heat rate.
Turbine Heat rate(design-1849): 2084 Kcal/KWh (Gross)
Boiler ƞ-88.7%
NPL AT A GLANCE
2*700MW INDIGENOUS PROJECT
Station Availability: FY 14-15: 84.18 % FY 15-16: 91.79 % FY 16-17: 93.06 %
• Zero Liquid Discharge • 100% Fly Ash utilisation • Water Consumption less than 2.5
cum/MWh
Nabha Power Limited – Power to People 4
COMPANY PROFILE
BENCHMARKING
ASSESSMENT & MONITORING
ENCON PROJECTS
INNOVATION
SUSTAINABILITY
8/31/2017
Nabha Power Limited – Power to People 5
ENERGY BENCHMARKING* (National & Global)
PARAMETERS ELECTRICAL SEC
(%)
THERMAL SEC
GROSS HEAT RATE (Kcal/KWh) PLANT
SEC (Specific Energy
Consumption) of the Unit 5.18% 2207 NPL, Rajpura
Competitor 1
(National) 7.7 % - 8.5% 2050 - 2142 CGPL, Mundra#
Competitor 2
(National) 5.0 % - 5.5 % 2151 - 2247 Adani Power, Tiroda
SEC (Specific Energy
Consumption) of the Unit
(Global)
4.5% 1870 Yuhuan Power, China
* Note: Data is indicative in nature # Coastal Gujarat Power Limited (Tata Mundra, Unit Size: 800 MW)
Roadmap to achieve national/global SEC
Reduction of APC through completion of projects considered under ENCON 2017-2018. Identification of energy saving area/equipment under ISO 50001:2011
Arresting of high energy drain valves passing Unit major overhaul to plug heat rate losses in BTG island Absorption of new technology/methodology to reduce part load heat rate losses
8/31/2017
S. No Name of IPP OEM TG/BLR Size APC % SHRKcal/Kwh PLF %
1 Nabha Power Ltd, Rajpura L&T MHI/L&TMHI 2 X 700 5.0 % - 5.5 % 2084 - 2178 77
2 CGPL(Tata Mundra), Gujarat Toshiba/Doosan 5 X 800 7.7 % - 8.5% 2050 - 2142 76
3 Adani Power, Tiroda SEC/SEC 5 X 660 5.0 % - 5.5 % 2151 - 2247 60
4 NTPC (Sipat), Stage-1 LMZ/Doosan 3 X 660 6.0 % - 6.5 % 2206 - 2306 90
5 Reliance Power, Sasan SEC/SEC 6 X 660 6.0 % - 6.5 % 2178 - 2276 85
PLANT PERFORMANCE COMPARISON*
6 Nabha Power Limited – Power to People
*Source: Order in Case of 2012/2014
8/31/2017
Global Benchmarks*
7 Nabha Power Limited – Power to People
Source: Siemens, SST-6000 steam turbine for future
coal-based thermal plants, 2011.
*Source: Powermag USA.
NAME MW MS
Pressure (KSC)
SH/RH TEMPERATURE
(DEG.C)
DESIGN THERMAL
EFFICIENCY OEM
HEKINAN UNIT # 3, JAPAN*
700 245 538/593 47.4% MHPS, JAPAN
HESSLER PLANT, GERMANY*
720 280 578/600 47.6% ALSTOM, UK
KAWAGOE UNIT #1 & #2, JAPAN*
700 316 566/566/566 48.4% TOSHIBA, JAPAN
NABHA POWER LIMITED RAJPURA UNIT #1 & #2
700 245 563/593 41.3% MHPS, JAPAN
8/31/2017
Best APC achieved @ Full Load
4.8%
Nabha Power Limited – Power to People 8
COMPANY PROFILE
BENCHMARKING
ASSESSMENT & MONITORING
ENCON PROJECTS
INNOVATION
SUSTAINABILITY
8/31/2017
NABHA POWER LIMITED – POWER TO PEOPLE 9
2365.74 2360.94
2321.3
2431
2381
2329
54.11%
62.64%
76.99%
40.00%
55.00%
70.00%
85.00%
100.00%
2260.0
2310.0
2360.0
2410.0
2460.0
14-15 15-16 16-17
PLF %
HEAT R
AT
E (
kcal/
kw
h)
Target SHR*(kcal/kwhr)
Actual SHR(kcal/kwhr)
PLF
SPECIFIC ENERGY CONSUMPTION (Kcal/KWh): NHR Y-O-Y
*Target SHR (Kcal/KWh) has been derived in consideration with PPA Heat rate of 2268 Kcal/KWh at full load
Unit #1 AOH;
November 2015
(22 days)
Unit #2 AOH;
March 2016
(19 days)
Unit #1 AOH November 2016
(33 days)
Unit #2 AOH April 2017
(31 days)
Generator Thread Out
Attending of duct leakages & RAPH seal replacement.
High energy drains attended (Unit #1: 38, Unit #2: 59)
GHR improvement: (Unit #1: 14 Kcal/kwh, Unit #2: 16 Kcal/Kwh)
LP Turbine Overhaul
High energy drains attended (Unit #1: 128, Unit #2: 141)
Insulation replacement in Boiler, MS/HRH/CRH piping, Feedwater Heaters
GHR improvement: (Unit #1: 30 Kcal/kwh, Unit #2: 34 Kcal/kwh)
8/31/2017
Nabha Power Limited – Power to People 10
Obje
cti
ves
Maximizing station availability >94.1% by reduction in outages
Minimize the gap between target heat rate and actual heat rate
Improving plant efficiency by plugging the energy losses in the system
To upgrade with latest technology for Energy Conservation & Sustainability
Perf
orm
ance M
onit
ori
ng Monitoring of Plant
availability, Forced Outage analysis
Heat Rate Monitoring (target vs actual),PADO-is used as tool for monitoring (Design Vs Actual)
APC deviation against standard curve developed based on 3 years of operations
Temperature & thermography mapping of drains and insulation
Report
ing
Monthly Energy Efficiency Review Report (Efficiency linked with commercial losses)
NHR deviation report circulation
Daily MIS circulation
Defect reporting through service request
Forced outage committee meeting: review and deviation reporting through trip report
OBJECTIVES, MONITORING & REPORTING
8/31/2017
Nabha Power Limited – Power to People 11
REPORTING FORMAT & IMPLEMENTATION METHODOLOGY
Initiation of Idea
Modification Note
Proposal to ENCON team in monthly
review meeting for feasibility study
Yes/
No
Implementation
Yes
No
ENERGY METER OF HT DRIVES
MASTER DPR DATA EXTRACTED FROM
DPR FOR ENERGY
CONSUMPTION REPORT
MAIL FOR
MONTHLY MIS
Improvement
Monitoring
8/31/2017
8.1, 13%
8.0, 13%
8.2, 13%
7.7, 12% 3.4, 5% 3.5, 6%
3.0, 5% 1.4, 2%
0.2, 0%
0.3, 0%
19.8, 31%
Other, 24.7, 38%
ENERGY CONSUMED IN JULY (MWH)
U#1 CW PUMP
U#1 FANS
U#2 CW PUMP
U#2 FANS
U#1 MILLS
U#2 MILLS
Plant AHP
Plant CHP
U#1 AIR
COMPRESOR
U#2 AIR
COMPRESSOR
Plant
MISCELLANEOUS*
Nabha Power Limited – Power to People 12
COMPANY PROFILE
BENCHMARKING
ASSESSMENT & MONITORING
ENCON PROJECTS INNOVATION
SUSTAINABILITY
8/31/2017
Nabha Power Limited – Power to People
ENCON PROJECTS UNDERTAKEN (FY 14-15)
13
Sl No. Project
Annual Electrical Saving
Annual Thermal Saving
Investment
(INR Million)
Payback
(Months) (MWH) (INR
Million) (Tonnes)
(INR
Million)
1
Optimisation of PA header
pressure set point from 943 to
860 mmWC resulted in
reduction of PA Fan current
197 0.55 Nil Nil Nil Nil
2
Optimisation of HVAC cooling
system operation during
favourable ambient conditions
(1.2 MW for 150 days, OCT 2014
- MAR 2015)
4320 12.10 Nil Nil Nil Nil
Total 4517 12.65 Nil Nil Nil Nil
8/31/2017
Nabha Power Limited – Power to People
ENCON PROJECTS UNDERTAKEN (FY 15-16)
14
Sl No. Project
Annual Electrical Saving
Annual Thermal Saving
Investment
(INR Million)
Payback
(Months) (MWH) (INR
Million) (Tonnes)
(INR
Million)
1
Stopping of one nos. of CW pumps
during winter season (November to
March) by utilising interconnection
lines. System Design: 2 x 50%
15372 41.5 Nil Nil Nil Nil
2
APC reduction in Fan currents (Pro-
active initiative to identify the air
ingress and leakage points in Air & Flue
Gas ducting through soap bubble test
and arresting the same by welding all
the joints)
1858 5.02 Nil Nil 2.05 8
3
Complete Switchover from HFO to LDO
(LDO is less viscous and doesn’t require
steam source for heating)
Nil Nil 15107 80.23 3.75 Nil
8/31/2017
Nabha Power Limited – Power to People
ENCON PROJECTS UNDERTAKEN (FY 15-16)
15
Sl No. Project
Annual Electrical Saving
Annual Thermal Saving
Investment
(INR Million)
Payback
(Months) (MWH) (INR
Million) (Tonnes)
(INR
Million)
4
Optimization of cycle make-up by
arresting the high energy drain valve
passing (Minimizing system losses)
Nil Nil 15466 79.96 1.5 0
5
Optimization of Unit Cold Start-up
Operation (Optimization of coal firing
and unit cold start-up turbine rolling
pressure)
Nil Nil 1339
(oil) 62.2 Nil Nil
Total 17230 46.52 30573 222.40 7.3 8
8/31/2017
Nabha Power Limited – Power to People
ENCON PROJECTS UNDERTAKEN (FY 16-17)
16
Sl No. Project
Annual Electrical Saving
Annual Thermal Saving
Investment
(INR Million)
Payback
(Months) (MWH) (INR Million) (Tonnes) (INR
Million)
1 Improvements in Ash Handling
Plant 4234 11.431 NIL NIL 1.828 2
2 Improvements in Coal Handling
Plant 384 1.037 NIL NIL NIL NIL
3 Replacement and servicing of
high energy drains NIL NIL 4083 20.99 11.586 7
4
Provision of interconnection
line between Service water
header and ESP/BBD water
header
640 1.728 NIL NIL 0.003 NIL
8/31/2017
Nabha Power Limited – Power to People
ENCON PROJECTS UNDERTAKEN (FY 16-17)
17
Sl No. Project
Annual Electrical Saving
Annual Thermal Saving
Investment
(INR Million)
Payback
(Months) (MWH) (INR Million) (Tonnes) (INR
Million)
5
Optimization of CEP Minimum
re-circulation flow during part
loading
990 2.674 NIL NIL NIL NIL
6
Tap position optimization of all
lightning transformers in plant
830 2.241 NIL NIL NIL NIL
7
Hotwell make-up pump
switched off by using vacuum
drag line
373 1.006 NIL NIL NIL NIL
8
Lube oil and hydraulic oil
pumps of standby mills in
standby and stop condition
during part load condition
112 0.303 NIL NIL NIL NIL
Total 7563 20.42 4083 20.99 13.417 9
8/31/2017
Nabha Power Limited – Power to People
FUTURE ENCON PROJECTS PLANNED (FY 17-18 onwards)
18
Sl No. Project Planned Investment (Cr.)
1 HIP turbine major overhaul in both the units.
Unit #1 (Nov – Dec 2018); Unit #2 (Apr- May 2019) 12
2 Phase – 1: 200 KW roof top solar panel installation to further reduce auxiliary
power consumption of the plant. Phase – 2 : 200 KW (2019-20) 3
3 Implementation of VFD in CEP for energy conservation during part load operation
in both units phase wise. 3
4 Use of natural lighting for MPHB roof lighting by provision of transparent poly-
carbonate sheet 0.080
5 Stopping of one no. of Instrument Air (IA) compressor in Ash Handling Plant by introducing an air receiver tank
0.015
6 Introduction of topping desuperheater and modification of LP Bypass warm-up
drain in both unit phase wise 20
7 Coating of internals of CW, CCW, ACW pumps and associated piping 1
Total 39.095
8/31/2017
Nabha Power Limited – Power to People
NPL Energy Conservation Journey (FY15 – FY17 cumulative)
19
12.65
281.57
322.98
0. 7.3 17.
30573 34656 4517.5
176747.2 184310.3
0.
50000.
100000.
150000.
200000.
0.
87.5
175.
262.5
350.
FY 15 FY 16 FY 17
SAVINGS (INR Million) INVESTMENT (INR Million) COAL (MT) MWHR
8/31/2017
Nabha Power Limited – Power to People 20
COMPANY PROFILE
BENCHMARKING
ASSESSMENT & MONITORING
ENCON PROJECTS
INNOVATION SUSTAINABILITY
8/31/2017
Nabha Power Limited – Power to People 21
INNOVATION AT NPL
CATEGORY B : New concept (risks taken/self driven/beyond OEM)
TITLE OF THE PROJECT: Implementation of modified cage in HP Heater #6, #7 & #8 cascading normal drain
DESCRIPTION: Due to severe cyclic operation of units, frequent choking was observed in HP Heaters #6, #7 & #8 normal
drain control valve cages. On an average monthly 7 to 8 times cages cleaning was required, which was leading to
frequent outages of HP heaters consequently deteriorating the heat rate.
ACTION TAKEN: Modified cages installed in one unit as pilot project to eradicate the frequent choking problem with an
increase in 38% total opening, decrease in opening of HP heater #6, #7 drain by 16% and 4% respectively.
OBSERVATIONS: With an investment of 10.2 lacs the problem of repeated heater outage for drain cleaning was resolved.
The pilot project has proved to be successful and same has been implemented in the other unit and the issue of the
heat rate deterioration on account of cage choking was eliminated.
HPH-06 Old Cage HPH-06 Modified Cage HPH-07 Modified Cage HPH-07 Old cage HPH-08 modified cage HPH-08 Old cage
8/31/2017
Nabha Power Limited – Power to People 22
INNOVATION AT NPL
CATEGORY A : (Known concept with unique application)
TITLE OF THE PROJECT: ESP BBD pump switched off by providing interconnection with service water line
DESCRIPTION: ESP/APH/BBD pumps each of 150 KW (2W + 1S)
• Washing of Electrostatic Precipitator (Shutdown)
• Washing of Air Preheater (Shutdown)
• Quench the hot drains in Boiler Blow Down Tank (Daily operation).
SHUTDOWN: No vibration symptoms and optimum design operation
NORMAL OPERATION: Shut-off pressure operation with high vibration causing repeated failure
8/31/2017
Nabha Power Limited – Power to People 23 8/31/2017
ROOT CAUSE: Temperature Control Valve (TCV) provided for
quenching purpose was open in the range of 10-20%, creating
severe back-pressure on pump. Issue couldn’t be resolved through
RC as it is designed for 30% as per standard design.
ACTION TAKEN: Alternate source of water supply from service
water which had margin was utilized through interconnection
between the discharge header of both the pumps (Service water
and ESP BBD pumps)
BENEFITS: This, out of the box modification resulted in stopping
of the ESP/BBD pump. It thereby resulted in an energy saving as
well as preventing the breakdown of ESP BBD pumps during normal
operation. SAVING : 6400000 KWH, INR 1.728 MILLION p.a.
Nabha Power Limited – Power to People 24 8/31/2017
INNOVATION AT NPL
CATEGORY B : New concept (risks taken/self driven/beyond OEM)
TITLE OF THE PROJECT: Use of one no. of crusher and vibrating grizzly feeder for washed Indian coal
against earlier philosophy of two no. of crushers and VGFs
DESCRIPTION: One no. crusher and One no. VGF of both stream taken into operation instead of two nos.
each . Use of one no. of crusher and vibrating grizzly feeder for washed Indian coal against earlier
philosophy of two no. of crushers and VGFs.
ROOT CAUSE: The deck plate of VGF had one solid stretch (2310 mm x 600 mm) which was directly below
the chute area and was obstructing the free flow of coal mass in forward movement causing severe
chokage thus loading had to be frequently reduced for smooth operation.
Nabha Power Limited – Power to People 25 8/31/2017
ACTION TAKEN: By modification in the perforating deck plate of
VGF (2310 mm x 600 mm with 70 mm dia. holes) the loading of
crusher was raised from 1100 TPH to 1500 TPH. This helped in
stopping of one stream of VGF and crusher.
BENEFITS: This, out of the box modification resulted in improving
the crusher loading and also stopping on stream of VGF & Crusher
with washed coal in operation. SAVING : 384070 KWH, INR 1.037
MILLION p.a.
RISK INVOLVED: The problem was addressed to OEM but they
couldn't come up with suitable solution. An in-house RCA was
carried out and the modification was done which was self-driven
and didn't involve OEM support. With risk element involved, the
modification was done as a pilot project and it was successful.
SO
LID
DECK P
LATE
(2310 M
M X
600 M
M)
BEFORE MODIFICATION
AFTER MODIFICATION
Nabha Power Limited – Power to People 26 8/31/2017
COMPANY PROFILE
BENCHMARKING
ASSESSMENT & MONITORING
ENCON PROJECTS
INNOVATION
SUSTAINABILITY
COAL YARD MANAGEMENT
Wind shield barrier erection on three sides to avoid direct
air impact on inclined portion (12 m x 600 m)
Compact stacking of received coal in stock yard, water
sprinkling on condition basis
Homogenous coal blending in stock yard.
100% Use of Auto Coal Sampler for sample Collection
Zero outage due to CHP downtime
20 September 2016 27 28 8/31/2017 Nabha Power Limited – Power to People
28
Rooftop Solar PV panel of 5 KWp installed for lighting of CHP building
Use of solar heater of 4.8 KWp for water heating in Field hostel
Proposed another 200KWp roof top solar planned for lighting of:
DM plant building: 130 KWp
Clarified and fire water pump house: 30 KWp
Field Hostel: 40KWp
Proposed use of Sky lighting in main plant TG building for lighting during day hours
Clean Sources of Energy at NPL
8/31/2017 Nabha Power Limited – Power to People
GHG EMISSION DATA: (as per GHG Protocol)
FY Generation (MU) Scope-1
CO2e Emission (MT)
Scope-2
CO2e Emission (MT) Source Considered
2014-15 5727.29 4343269.17 7067.57 Scope-1 : Coal + LDO
Scope-2 : Start-up
Power
2015-16 7703.31 6042853.12 2396.92
2016-17 9441.75 7165538.49 227.09
FY Specific CO2 emission % Reduction in emission intensity since
baseline year study
2014-15 863931 Baseline Year
2015-16 851676 1.41 %
2016-17 837632 3.04 %
% Reduction in emission intensity since baseline year study = {Specific CO2 emission (Baseline Year) - Specific CO2 emission (Year in
consideration)}/ Specific CO2 emission (Baseline Year) %
Scope-3 emission is not applicable to us.
Procurement of goods at NPL is done as per energy efficiency criteria.
Note: Supercritical technology is an Environment friendly technology and therefore with higher loading of the machine the
specific CO2 emission reduces
29 8/31/2017 Nabha Power Limited – Power to People
QMS ISO 9001:2015
Nabha Power Limited – Power to People 8/31/2017 30
EMS ISO 14001:2004 OHSAS 18001:2007 EnMS 50001:2011 NABL ISO 17025
AWARDS:
❖ BEE National Energy Conservation Award 2016 in thermal power plant category >100 MW from MOP, Gov. of India
❖ IPPAI 2016, first runner up in best thermal power generator category
❖ Bronze award in “Coal Power Project of the Year” & “Independent Power Producer of the year” at Asian Power-2016
❖ Environment Excellence Award-2016 Clean Generator of the year –Coal from Mission Energy
❖ Greentech Environment Award-2017 – Gold Award in Thermal Power Plant
Nabha Power Limited – Power to People 31 8/31/2017
NPL has planted 2,30,000 trees in and around the vicinity of the plant.
Thank You
Nabha Power Limited – Power to People 32 8/31/2017
DAMAGE IN SEAT & PLUG BLUE MATCH CHECKING IN SEAT & PLUG
Agency that executed the project (with complete address and email):
1) EFCO Maschinenbau India Pvt. Ltd. Address: 55/A, Annaram Village, Jinaram Mandal. Medak, Andhra Pradesh – 502313 Email:
ENERGY CONSERVATION MEASURES IN ASH HANDLING PLANT
Action Taken:
• Duct hopper to buffer hopper line re-routed resulting in
reduced line length from 69 to 29 m.
• Reduction in number of bends from 6 no. to 2 no.
• Hopper fluidizing line rerouting done to provide
improve fluidizing air to ash in ESP hoppers.
• Use of additional Knife Gate Valve in downstream of air
intake valve for improving vacuum of ash conveying
line.
Poking of hoppers reduced to Zero
All hoppers evacuation possible Three times a
day
System idle time of Seven hours/day
achieved
Housekeeping levels improved
Specific Power consumption reduced from 24.8 KWH/T –
16.76 KWH/T
Benefits: AHP Specific Power Consumption Source: NPL operations record; AHP energy meters
33 8/31/2017 Nabha Power Limited – Power to People
24.85 24.63
24.38 22.57
21.08 17.42 17.40 17.38
17.35
17.32 17.11
16.76
0
5
10
15
20
25
30
Mar-16 Jul-16 Oct-16 Jan-17
SPC (
kw
hr/
MT)
Specific Power Consumption in AHP (kwhr/ MT of Ash)
ENERGY CONSERVATION MEASURES IN COAL HANDLING PLANT Action Taken:
• Improving the belt utilization factor by increasing the loading of conveyor belt from 1800 – 2200 TPH during coal
reclaiming process
• By-passing of Vibrating Grizzly Feeder (VGF) and Crushers for imported coal.
• Use of one no. of crusher and vibrating grizzly feeder for washed Indian coal against earlier philosophy of
two no. of crusher and VGF.
Benefits:
• Reduction in over-crushing and fine generation in imported coal.
• Crusher Loading improved from
1100 TPH to 1500 TPH (design-1600 TPH)
• Aux. power savings by stopping of
one VGF (37 KW), Crusher (372 KW) and other auxiliary (15 KW).
Source: CHP operations record
34 8/31/2017 Nabha Power Limited – Power to People
1.71
2.3
1.6 1.6
1.42 1.4 1.3
1.35 1.3
1.25
1.4 1.4 1.32
1.42 1.31
1.45
1.
1.2
1.4
1.6
1.8
2.
2.2
2.4
2.6
2.8
3.
Sep-1
5
Dec-1
5
Apr-
16
Jul-
16
Oct-
16
Jan-1
7
May-1
7
Specific Power Consumption in CHP (KWh/MT of Coal)