11
NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

Embed Size (px)

Citation preview

Page 1: NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

NAVITUS BAY UPDATE

Sean MatthewsProject Engineer

20 March 2013

Page 2: NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

➤ UK overview

➤ Project stages

➤ Navitus Bay specifics

➤ Update on activity

➤ Conclusions

AGENDA

Page 3: NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

UK OFFSHORE WIND

➤ 2.7GW in 2013 > rest of EU

➤ 18GW in 2020 still 40% of European market

➤ Round 3 is varied pipeline of projects 2015 to beyond 2020

➤ Variety of site conditions, geography and scale

Page 4: NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

PROJECT STAGES

Page 5: NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

PROJECT STAGES

➤ 3-4 years of development and consent work

➤ 12-18 months contracting and finance

➤ 2 years construction for a 500MW project

➤ 20 years operation

Page 6: NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

➤ Navitus Bay Development Ltd is a 50:50 JV between Eneco and EDF Energy created to develop Zone 7 of Round 3

➤ Eneco is a Dutch utility with 2 million customers in the Netherland. It has been operating the Prinses Amalia windpark since 2008 and will begin construction of Luchterduinen in 2014

➤ EDF Energy is the UK subsidiary of EDF with over 5 million customers in the UK. They have 20 onshore wind farms and will complete construction the Teesside offshore wind farm in 2013

WHO IS NBDL?

Page 7: NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

NAVITUS BAY WINDPARK

➤ 1100MW

➤ 12 miles from Bournemouth/8.6 miles from Needles

➤ Construction due 2017 onshore and 2018-2020 offshore

➤ Design is for 5-8MW (136 to 218 turbines)

➤ Jacket or concrete gravity base foundations

Page 8: NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

➤ Larger than any project in operation today but one of the smaller round 3 zones

➤ Our water depths vary between 25m and 50m➤ Soil conditions are stiff clay in north and rock

and chalk in south➤ We will use prototype and next generation

turbines and foundations• We will use around 250km of inter-array cable

and up to 180km of subsea export cable• South coast ports are likely to be used as the

base for construction and for O&M

PROJECT SPECIFICS

Page 9: NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

➤ Environmental statement completed and further consultation – 2013

➤ Development Consent application – Q1 2014➤ Potential Development Consent award – Q2

2015➤ Financial close/award contracts – Q2 2016 to

2017➤ Start of construction – 2017 onshore and

offshore enabling➤ Operational Wind Park– 2021

TIMESCALES

Page 10: NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

➤ UK is seen as centre of global offshore wind

➤ Real opportunity for UK industry given change in manufacturing logistics and technology

➤ Technology landscape is changing fast with innovation and increased scale to reduce costs

➤ Navitus Bay is a key round 3 project that will support a balanced portfolio of projects in terms of geography and site conditions

➤ As a project we are committed to supporting UK and local supply to create a benefit for the region

➤ 2017 to 2021 will see £3-4 billion of investment if we gain consent

CONCLUSIONS

Page 11: NAVITUS BAY UPDATE Sean Matthews Project Engineer 20 March 2013

THANK YOU. QUESTIONS?

[email protected]