NCP Material & Equipment Mgt

Embed Size (px)

Citation preview

  • 7/28/2019 NCP Material & Equipment Mgt

    1/17

    ASSIGNMENT

    NICMAR / SODE

    MATERIALS AND EQUIPMENT

    MANAGEMENT

    Name of work: Constructing a new international airport 30 k.m.

    away from a city. The project is to be implemented in phases.

    Phase I: One strip of landing of 100 m width is to be constructed in

    100days. The scope of work is as follows:

    a) Cutting and Dozing of 100,000 cum of earth. Average height 0.75m.

    b) Transportation of 20,000 cum of surplus earth from site to dumping place 3

    k.m. away from site( including spreading) Filling of 80,000 kms in landing

    strip.

    c) Bringing in 3000cum of sand from 20k.m.(including spreading and leveling

    at site)

    1

  • 7/28/2019 NCP Material & Equipment Mgt

    2/17

    d) Procurement of 1, 50,000 litres of Bitumen. Duration of work 30days from

    60th day of starting of work. Bitumen to be obtained from refinery at

    Bongaigaon in Assam. Lead time up to site is 45 days. Storage facility

    available at site 50,000 litres tank.

    There are so many types of earth moving machines are available in the market.

    Of which we use the equipments that are useful for our scope of work only.

    Bulldozers the term bulldozer may be used in a broad sense to include both

    a bulldozer and angle dozer. These machines may be further divided on the

    basis of their mountings, in to crawler tractor or wheel tractor mounted. Based

    on the method of raising and lowering the blade a bulldozer may be classified

    as cable controlled or as hydraulically controlled. Bull dozers are mounted with

    blades perpendicular to the direction of shovel while angle dozers are mounted

    with blades at an angle with the direction of travel. The former push the earth

    forward while the latter push it forward and to one side. Some blades may be

    adjusted to permit their use of bulldozers or angle dozers. They may be used

    from the start to the finish of such operations as:

    - cleaning land timber and stumps

    - operating up pilot roads through mountains and rough terrains

    - moving earth for haul distances up to 100 m

    - helping load tractor pull scrapers

    - spreading earth fill

    - cleaning construction sites to debris

    - maintenance of haul roads

    - cleaning the floors of borrow and quarry pits

    2

  • 7/28/2019 NCP Material & Equipment Mgt

    3/17

    Scrapers:

    Tractors pulled scrapers have established an important position in the earth

    moving field. As they are self operating to the extent that they can load, haul and

    discharge material they are not dependent on other equipment. If one of them

    experiences a temporary breakdown it is not necessary to stop the job as would be

    the case of machine which is used exclusively for loading earth into hauling units

    for if the loader breaks down the entire job must stop until repairs can be made.

    The self loading scrapers are available with capacities up to 38 cum or more. These

    machines are the result of a compromise between the best loading and best

    hauling machines and as must be expected at any composite machines they are

    not superior to other equipment in both loading and hauling. Power shovels drag

    lines and belt loaders usually will surpass them in loading only while trucks may

    surpass them in hauling only especially when long, well maintained haul roads are

    used. The development of High speed haul tractors has increased the economic

    haul distance speed. Wheel type tractors have increased the economic haul

    distance for the type of equipment up to 0.5 to 2.0 km.

    Following equipments are used excavate earth and related materials and to lift

    them frequently in construction operation.

    The equipment includes the following machines:

    - Power shovels

    - Back hoes

    - Draglines

    - Clamshells and cranes

    - Trenching machines

    - Wheel mounted belt loaders

    Power shovels are used for excavation and loading into hauling units

    3

  • 7/28/2019 NCP Material & Equipment Mgt

    4/17

    Back hoes are used in excavation on natural surface. These are more rigid

    than draglines and advantageously used on close range work

    Clamshells are used mainly for lifting vertically and handling loose materials

    such as sand, crushed stones in dams, pier foundation and sheet piling etc.

    Trenching machines are either wheel or crawler type

    Wheel excavators can cut weathered or broken rock.

    Estimated productivity of 90ck, 0.9cum back hoe bucket

    1. Bucket capacity (cum) - 0.9

    2. Soil condition Average

    3. Bucket fill factor 1.05

    4. Actual Bucket Capacity 0.945Cum

    5. Swing angle 180degrees

    6. Standard cycle time - 15sec

    7. Digging condition Deeper

    8. Digging depth / Specified maximum digging depth Above 70%

    9. Dumping condition Rather difficult

    10. Conversion factor 1.5

    11. Actual cycle time 22.5 sec

    12. Operating conditions Average

    13. Job efficiency 0.75

    14. Hourly production (cum) 113

    15. Number of hours of operation per day 12

    16. Total production achieved per day 1362cum

    17. Number of days of operation per month -25

    4

  • 7/28/2019 NCP Material & Equipment Mgt

    5/17

    18. Total monthly production (Cum) 34020

    19. Annual production (Cum) 48240

    Estimated productivity of 180ck, 1.6cum back

    hoe bucket

    1. Bucket capacity (cum) - 1.6

    2. Soil condition Average

    3. Bucket fill factor 1.05

    4. Actual Bucket Capacity 1.68Cum

    5. Swing angle 180degrees

    6. Standard cycle time - 19sec

    7. Digging condition Deeper

    8. Digging depth / Specified maximum digging depth Above 70%

    9. Dumping condition Rather difficult

    10. Conversion factor 1.5

    11. Actual cycle time 28.5 sec

    12. Operating conditions Average

    13. Job efficiency 0.75

    14. Hourly production (cum) 159

    15. Number of hours of operation per day 12

    16. Total production achieved per day 1910cum

    17. Number of days of operation per month -25

    18. Total monthly production (Cum) 47747

    19. Annual production (Cum) 572968

    5

  • 7/28/2019 NCP Material & Equipment Mgt

    6/17

    Estimated productivity of 180ck, 1.85cum back hoe

    bucket

    1. Bucket capacity (cum) - 1.85

    2. Soil condition Average

    3. Bucket fill factor 1.05

    4. Actual Bucket Capacity 1.9425Cum

    5. Swing angle 180degrees

    6. Standard cycle time - 19sec

    7. Digging condition Deeper

    8. Digging depth / Specified maximum digging depth Above 70%

    9. Dumping condition Rather difficult

    10. Conversion factor 1.5

    11. Actual cycle time 28.5 sec

    12. Operating conditions Average

    13. Job efficiency 0.75

    14. Hourly production (cum) 184

    15. Number of hours of operation per day 12

    16. Total production achieved per day 2208cum

    17. Number of days of operation per month -25

    18. Total monthly production (Cum) 55208

    19. Annual production (Cum) 662495

    Estimated productivity of 300ck, 2.7cum back hoe bucket

    1. Bucket capacity (cum) - 2.7

    2. Soil condition Average

    3. Bucket fill factor 1.05

    6

  • 7/28/2019 NCP Material & Equipment Mgt

    7/17

    4. Actual Bucket Capacity 2.835Cum

    5. Swing angle 180degrees

    6. Standard cycle time - 24sec

    7. Digging condition Deeper

    8. Digging depth / Specified maximum digging depth Above 70%

    9. Dumping condition Rather difficult

    10. Conversion factor 1.5

    11. Actual cycle time 36 sec

    12. Operating conditions Average

    13. Job efficiency 0.75

    14. Hourly production (cum) 213

    15. Number of hours of operation per day 12

    16. Total production achieved per day 2552cum

    17. Number of days of operation per month -25

    18. Total monthly production (Cum) 63788

    19. Annual production (Cum) 765450

    Take two 180ck, 1.6cum backhoe buckets and one 90ck, 0.9cum backhoe buckets.

    For 100,000cum of earthwork excavation use two 180ck, 1.6cum backhoe buckets.

    Number of days required to get the output 30

    Number of hours required 360

    Calculation of owning and operating cost of two 180ck excavators

    Basic cost 45, 00,000INR

    Life of equipment - 12000Hrs

    Life of equipment 12years

    Maintenance constant 50%

    Depreciation cost 4500000 x 0.9/12000 = 337.50INR

    7

  • 7/28/2019 NCP Material & Equipment Mgt

    8/17

    Fuel charges 18litres@38/- per litre = 684INR

    Labour charges 25% x 684 = 171INR

    Repair Charges Depreciation cost x Maintenance constant

    337.5 x 50% = 168.25

    Operator cost = 20INR

    Helper cost = 15INR

    Foreman cost = 7.5INR

    Mechanic = 6INR

    Watchman = 3INR

    Total crew cost =51.5INR

    Total usage cost = 51.5+168.25+171+684+337.50 =1412.3INR

    Operating cost per hr = 4500000/12000 = 375INR

    = 1412.3+375

    =1787.3

    = 1787INR (say)

    Total cost of operation for excavation = 360 x 1787 = 643428INR

    Owning cost = 4500000 +1412.3x360

    = 4500000+508410

    = 5008410INR

    For two equipments it is equal to 10016820INR

    Calculation of owning and operating cost of 90ck excavator

    Basic cost 40, 00,000INR

    8

  • 7/28/2019 NCP Material & Equipment Mgt

    9/17

    Life of equipment - 10000Hrs

    Life of equipment 10years

    Maintenance constant 50%

    Depreciation cost 4000000 x 0.9/10000 = 360INR

    Fuel charges 18litres@38/- per litre = 684INR

    Labour charges 25% x 684 = 171INR

    Repair Charges Depreciation cost x Maintenance constant

    360 x 50% = 180

    Operator cost = 20INR

    Helper cost = 15INR

    Foreman cost = 7.5INR

    Mechanic = 6INR

    Watchman = 3INR

    Total crew cost =51.5INR

    Total usage cost = 51.5+180+171+684+360 =1446.5INR

    Operating cost per hr = 4000000/10000 = 400INR

    = 1446.5+400

    =1846.5

    = 1847INR (say)

    Three types of records are maintained at site and they are

    i) Progress records

    ii) Work output records of individual machines and team of machines

    iii) Equipment records

    Progress records:

    9

  • 7/28/2019 NCP Material & Equipment Mgt

    10/17

    Records of progress may be kept in a variety of forms, but the method adopted

    should be as simple as possible, and to be of real value, must allow for immediate

    comparison with planned programme and show at a glance, the actual break up

    made, often on percentage basis.

    Suitable methods are

    i) Work programme as progress records

    ii) Bar graph progress chart

    iii) Line graphs

    iv) Pictorial records

    Work output records:

    Records of actual output of individual machines and if desired, of team of

    machines, will not only be useful on the projects itself to help in analyzing any

    causes of delay in progress of work but will prove of great value for further

    planning and estimating. To enable these records to be compiled, plant

    supervisors reports will be necessary.

    Plant supervisors reports:

    Each plant supervisor should be required to complete shift report at the end of

    each shift, showing relevant information about the machines which have been

    under his control during the shift. The report should not be confused with plant

    operators daily log which is mainly concerned with servicing and fuel consumption.

    Typical items to be entered on plant supervisors report for each machine are:

    i) Task on which employed

    ii) Total work carried out e.g. number of trips performed, total mileage or

    number of vehicles loaded , depending on type of task

    iii) Number of minutes worked per hour

    iv) Servicing periods

    10

  • 7/28/2019 NCP Material & Equipment Mgt

    11/17

    v) Remarks on delay and waiting times with reasons.

    Basic record of equipment maintained

    i) Log book

    ii) Daily / Monthly working data

    iii) History book

    Log book:

    The log book is to utilized for two purposes

    a) For a technical control to evaluate how the machine is performing, and

    b) For getting the Plant hours performance classified by works

    To determine performance, the total plant hours put in by a machine must be

    known and causes of trouble should be classified. The log book records the

    consumption of fuels and lubricants, since the performance of the machine can be

    judged readily from these figures. It records the work on which the machine was

    employed indicating the officer on whose requisition the machines was utilized.

    Daily / monthly working data:

    Log book also gives record of utilization of machinery. Other data such as sickness,

    idleness etc. is not readily available in logbook. The data is equally important to

    indicated performance of machine. For this purpose the data is to be maintained in

    the form of daily working machinery. Monthly abstract should be prepared.

    Maintenance registers:

    The maintenance register for the following should be maintained:

    i) Daily maintenance

    ii) Weekly maintenance

    iii) 100 to 175 hours maintenance

    iv) 250 hours maintenance

    11

  • 7/28/2019 NCP Material & Equipment Mgt

    12/17

    v) 500 hours maintenance

    vi) 1000 hours maintenance

    vii) 2000 hours maintenance

    Supervision:

    The purpose of supervision is not only to see that work is carried out correctly to

    specifications laid down and the machines are properly used and output

    maintained at consistently high level but also to foresee difficulties and likely

    bottlenecks which may reduce output and to take steps to obstacle them before

    they occur.

    Supervisors responsibility to:

    i) Ensure that all the concerned under his command are clear on their

    task.

    ii) See that machines are used to best advantage and operators take their

    task correctly.

    iii) Ensure that the work is properly done to the specification laid down.

    iv) Take early steps to deal with difficulties in order to assist the operators

    to maintain their output where difficulties develop which he cannot deal

    with satisfactorily from his own resources, report them without delay to

    next supervisor, with the recommendation as to how they can best be

    overcome.

    v) Always be thinking ahead to foresee likely difficulties and bottlenecks to

    the progress of work before they occur so that steps can be taken in

    time to prevent them of failing this to reduce this adverse effect on out-

    put.

    12

  • 7/28/2019 NCP Material & Equipment Mgt

    13/17

    Transportation of 20,000 cum of surplus earth from site to dumping place 3 k.m.

    away from site (including spreading)

    Calculation of Disposal of earth for tippers

    i) Lead for 3+3 = 6k.m.

    ii) Average speed = 25kmph

    iii) Loading time = 5.00mins

    iv) Travel time = (6/25)x60 = 14.40mins

    v) Unloading time = 4.00mins

    vi) Idle time = 2.00mins

    vii) Time per trip = 5+14.40+4+2 = 25.40mins

    viii) Add for break down 10% = 2.54mins

    ix) Total time per trip = 25.4+2.54 = 27.94

    x) Working time per day 16hours a day = 16 x 60 = 960mins

    xi) Number of trips per day per vehicle = 960/27.94 = 34.35 = 35(say)

    xii) Quantity per vehicle per day = 35 x4 = 140cum

    xiii) Distance travelling per day = 6x35 = 210k.m.

    xiv) Quantity per vehicle per month(assuming 25days per month) = 140x25

    =3500cum

    xv) Distance travelled per month = 210x25 = 5250k.m.

    For the disposal of 20,000cum of earth we need 20,000/3500 = 5.71= (6 say)

    6no. of tippers are enough to dispose the earth to the dumping yard.

    Calculation of Bringing of Sand for tippers

    i) Lead for 20+20 = 40k.m.

    13

  • 7/28/2019 NCP Material & Equipment Mgt

    14/17

    ii) Average speed = 25kmph

    iii) Loading time = 5.00mins

    iv) Travel time = (40/25)x60x2 = 192mins

    v) Unloading time = 4.00mins

    vi) Idle time = 2.00mins

    vii) Time per trip = 5+192+4+2 = 213mins

    viii) Add for break down 10% = 21.3mins

    ix) Total time per trip = 213+21.3 = 234.3

    x) Working time per day 16hours a day = 16 x 60 = 960mins

    xi) Number of trips per day per vehicle = 960/234.3 = 4.09 = 4(say)

    xii) Quantity per vehicle per day = 4 x4 = 16cum

    xiii) Distance travelling per day = 40x4 = 160k.m.

    xiv) Quantity per vehicle per month(assuming 25days per month) = 16x25

    =400cum

    xv) Distance travelled per month = 160x25 = 4000k.m.

    For bringing of 3000cum of sand from 20k.m. we need 3000/400 =7.25(8say)

    8no. of vehicles are required to get the 3000cum of sand with 20k.m. lead.

    Procurement of 150,000 litres of bitumen from refinery which is located

    Bonagaigaon in Assam.

    Lead time up to site is 45days.

    Calculation of Economic order of quantity for Bitumen:

    Take Wilson Harris square root formula

    The quantity of order corresponding to the frequency is known as Economic order

    of quantity. The economic order quantity or lot size can be war analytically. The

    14

  • 7/28/2019 NCP Material & Equipment Mgt

    15/17

    relation between various parameters was developed by RH Wilson and F. Harris

    and is known as Wilson Harris Square Root Formula.

    The relation is worked out below and is based on assumptions.

    a. The demand over the period of the cycle (normally a year) constant and is

    known in advance.

    b. Consumption of material occurs at the uniform rate.

    c. The price of the material is independent of the order.

    d. There is no lead time in the replenishment.

    Let

    A: be the annual demand in terms of units

    Q: is the lot size ordered at a time in units

    P: Price of the material in terms of

    H: Annual inventory carrying / holding cost expressed in Rs. per Rupee of the

    inventory

    S: Ordering cost (i.e. cost of placing one order) in Rs.

    Since the stock in depleted at uniform rate over the cycle period, inventory

    carrying cost or holding cost can be the cost over the average stock.

    As Q increases the number of orders hence ordering costs reduce, but inventory

    carrying costs increase and vice-a-versa. The economic lot size will have to

    balance the two costs of opposing nature.

    If Q is the lot size the average inventory will be Q/2

    Inventory carrying cost will be

    Q/2 x p x h

    Number of orders over a year = A/ Q

    Total Ordering costs = A/Q x S

    Thus the total cost T = Q x p x h/2 + Ax S/Q

    15

  • 7/28/2019 NCP Material & Equipment Mgt

    16/17

    We have to find the most economic order quantity for which T is minimum.

    dT /dQ should be equated to zero.

    dT/ dQ = p x h /2 = A x S/Q^2 = 0

    A x s / Q^2 = p x h/2

    Q^2 / A x S = 2/ p x h

    Therefore Q = Square root of (2x A x S/p x h)

    Assume 300 working days in a year

    Annual consumption 300 x 3333litre a day = 1000000 litres

    Inventory carrying cost Rs. 4 per litre i.e. 20Rs. Inventory

    As we need 50000 litres per order because we have only the capacity of

    50000litres of storage capacity and the lead time is 45 days from the refinery to

    site office. We place 3 orders of 15 days duration from the start of the work. By

    which we can get the bitumen by 45days, 60th day and 75th day the total quantity

    of bitumen. On 60th day Bitumen work is to be started. Bitumen is planned per day

    is 3500litres. Within 15 days 50000litres of bitumen can be consumed. The storage

    capacity will be available for another 50000 litres. As the excavation progresses

    and the site is available for runway works. Consumption bitumen increases and by

    that bitumen procurement from the refinery to site storage cann be made. The

    planned quantity of utilization of bitumen can be done within the stipulated

    duration of 100days. During storage of bitumen the temperature of 100 degree

    Celsius is maintained. Maintaining the boiling temperature of bitumen is important

    site storage tank. So the planned schedule is going to be maintained at the site.

    Conclusion:

    The equipment and materials management can be achieved with

    perfect planning and execution. Spare parts for the equipment

    should be made available for emergency repair works

    16

  • 7/28/2019 NCP Material & Equipment Mgt

    17/17

    Bibliography:

    1. Materials and Equipment management - NICMAR

    17