Upload
devesh-kumar
View
220
Download
0
Embed Size (px)
Citation preview
7/28/2019 NCP Material & Equipment Mgt
1/17
ASSIGNMENT
NICMAR / SODE
MATERIALS AND EQUIPMENT
MANAGEMENT
Name of work: Constructing a new international airport 30 k.m.
away from a city. The project is to be implemented in phases.
Phase I: One strip of landing of 100 m width is to be constructed in
100days. The scope of work is as follows:
a) Cutting and Dozing of 100,000 cum of earth. Average height 0.75m.
b) Transportation of 20,000 cum of surplus earth from site to dumping place 3
k.m. away from site( including spreading) Filling of 80,000 kms in landing
strip.
c) Bringing in 3000cum of sand from 20k.m.(including spreading and leveling
at site)
1
7/28/2019 NCP Material & Equipment Mgt
2/17
d) Procurement of 1, 50,000 litres of Bitumen. Duration of work 30days from
60th day of starting of work. Bitumen to be obtained from refinery at
Bongaigaon in Assam. Lead time up to site is 45 days. Storage facility
available at site 50,000 litres tank.
There are so many types of earth moving machines are available in the market.
Of which we use the equipments that are useful for our scope of work only.
Bulldozers the term bulldozer may be used in a broad sense to include both
a bulldozer and angle dozer. These machines may be further divided on the
basis of their mountings, in to crawler tractor or wheel tractor mounted. Based
on the method of raising and lowering the blade a bulldozer may be classified
as cable controlled or as hydraulically controlled. Bull dozers are mounted with
blades perpendicular to the direction of shovel while angle dozers are mounted
with blades at an angle with the direction of travel. The former push the earth
forward while the latter push it forward and to one side. Some blades may be
adjusted to permit their use of bulldozers or angle dozers. They may be used
from the start to the finish of such operations as:
- cleaning land timber and stumps
- operating up pilot roads through mountains and rough terrains
- moving earth for haul distances up to 100 m
- helping load tractor pull scrapers
- spreading earth fill
- cleaning construction sites to debris
- maintenance of haul roads
- cleaning the floors of borrow and quarry pits
2
7/28/2019 NCP Material & Equipment Mgt
3/17
Scrapers:
Tractors pulled scrapers have established an important position in the earth
moving field. As they are self operating to the extent that they can load, haul and
discharge material they are not dependent on other equipment. If one of them
experiences a temporary breakdown it is not necessary to stop the job as would be
the case of machine which is used exclusively for loading earth into hauling units
for if the loader breaks down the entire job must stop until repairs can be made.
The self loading scrapers are available with capacities up to 38 cum or more. These
machines are the result of a compromise between the best loading and best
hauling machines and as must be expected at any composite machines they are
not superior to other equipment in both loading and hauling. Power shovels drag
lines and belt loaders usually will surpass them in loading only while trucks may
surpass them in hauling only especially when long, well maintained haul roads are
used. The development of High speed haul tractors has increased the economic
haul distance speed. Wheel type tractors have increased the economic haul
distance for the type of equipment up to 0.5 to 2.0 km.
Following equipments are used excavate earth and related materials and to lift
them frequently in construction operation.
The equipment includes the following machines:
- Power shovels
- Back hoes
- Draglines
- Clamshells and cranes
- Trenching machines
- Wheel mounted belt loaders
Power shovels are used for excavation and loading into hauling units
3
7/28/2019 NCP Material & Equipment Mgt
4/17
Back hoes are used in excavation on natural surface. These are more rigid
than draglines and advantageously used on close range work
Clamshells are used mainly for lifting vertically and handling loose materials
such as sand, crushed stones in dams, pier foundation and sheet piling etc.
Trenching machines are either wheel or crawler type
Wheel excavators can cut weathered or broken rock.
Estimated productivity of 90ck, 0.9cum back hoe bucket
1. Bucket capacity (cum) - 0.9
2. Soil condition Average
3. Bucket fill factor 1.05
4. Actual Bucket Capacity 0.945Cum
5. Swing angle 180degrees
6. Standard cycle time - 15sec
7. Digging condition Deeper
8. Digging depth / Specified maximum digging depth Above 70%
9. Dumping condition Rather difficult
10. Conversion factor 1.5
11. Actual cycle time 22.5 sec
12. Operating conditions Average
13. Job efficiency 0.75
14. Hourly production (cum) 113
15. Number of hours of operation per day 12
16. Total production achieved per day 1362cum
17. Number of days of operation per month -25
4
7/28/2019 NCP Material & Equipment Mgt
5/17
18. Total monthly production (Cum) 34020
19. Annual production (Cum) 48240
Estimated productivity of 180ck, 1.6cum back
hoe bucket
1. Bucket capacity (cum) - 1.6
2. Soil condition Average
3. Bucket fill factor 1.05
4. Actual Bucket Capacity 1.68Cum
5. Swing angle 180degrees
6. Standard cycle time - 19sec
7. Digging condition Deeper
8. Digging depth / Specified maximum digging depth Above 70%
9. Dumping condition Rather difficult
10. Conversion factor 1.5
11. Actual cycle time 28.5 sec
12. Operating conditions Average
13. Job efficiency 0.75
14. Hourly production (cum) 159
15. Number of hours of operation per day 12
16. Total production achieved per day 1910cum
17. Number of days of operation per month -25
18. Total monthly production (Cum) 47747
19. Annual production (Cum) 572968
5
7/28/2019 NCP Material & Equipment Mgt
6/17
Estimated productivity of 180ck, 1.85cum back hoe
bucket
1. Bucket capacity (cum) - 1.85
2. Soil condition Average
3. Bucket fill factor 1.05
4. Actual Bucket Capacity 1.9425Cum
5. Swing angle 180degrees
6. Standard cycle time - 19sec
7. Digging condition Deeper
8. Digging depth / Specified maximum digging depth Above 70%
9. Dumping condition Rather difficult
10. Conversion factor 1.5
11. Actual cycle time 28.5 sec
12. Operating conditions Average
13. Job efficiency 0.75
14. Hourly production (cum) 184
15. Number of hours of operation per day 12
16. Total production achieved per day 2208cum
17. Number of days of operation per month -25
18. Total monthly production (Cum) 55208
19. Annual production (Cum) 662495
Estimated productivity of 300ck, 2.7cum back hoe bucket
1. Bucket capacity (cum) - 2.7
2. Soil condition Average
3. Bucket fill factor 1.05
6
7/28/2019 NCP Material & Equipment Mgt
7/17
4. Actual Bucket Capacity 2.835Cum
5. Swing angle 180degrees
6. Standard cycle time - 24sec
7. Digging condition Deeper
8. Digging depth / Specified maximum digging depth Above 70%
9. Dumping condition Rather difficult
10. Conversion factor 1.5
11. Actual cycle time 36 sec
12. Operating conditions Average
13. Job efficiency 0.75
14. Hourly production (cum) 213
15. Number of hours of operation per day 12
16. Total production achieved per day 2552cum
17. Number of days of operation per month -25
18. Total monthly production (Cum) 63788
19. Annual production (Cum) 765450
Take two 180ck, 1.6cum backhoe buckets and one 90ck, 0.9cum backhoe buckets.
For 100,000cum of earthwork excavation use two 180ck, 1.6cum backhoe buckets.
Number of days required to get the output 30
Number of hours required 360
Calculation of owning and operating cost of two 180ck excavators
Basic cost 45, 00,000INR
Life of equipment - 12000Hrs
Life of equipment 12years
Maintenance constant 50%
Depreciation cost 4500000 x 0.9/12000 = 337.50INR
7
7/28/2019 NCP Material & Equipment Mgt
8/17
Fuel charges 18litres@38/- per litre = 684INR
Labour charges 25% x 684 = 171INR
Repair Charges Depreciation cost x Maintenance constant
337.5 x 50% = 168.25
Operator cost = 20INR
Helper cost = 15INR
Foreman cost = 7.5INR
Mechanic = 6INR
Watchman = 3INR
Total crew cost =51.5INR
Total usage cost = 51.5+168.25+171+684+337.50 =1412.3INR
Operating cost per hr = 4500000/12000 = 375INR
= 1412.3+375
=1787.3
= 1787INR (say)
Total cost of operation for excavation = 360 x 1787 = 643428INR
Owning cost = 4500000 +1412.3x360
= 4500000+508410
= 5008410INR
For two equipments it is equal to 10016820INR
Calculation of owning and operating cost of 90ck excavator
Basic cost 40, 00,000INR
8
7/28/2019 NCP Material & Equipment Mgt
9/17
Life of equipment - 10000Hrs
Life of equipment 10years
Maintenance constant 50%
Depreciation cost 4000000 x 0.9/10000 = 360INR
Fuel charges 18litres@38/- per litre = 684INR
Labour charges 25% x 684 = 171INR
Repair Charges Depreciation cost x Maintenance constant
360 x 50% = 180
Operator cost = 20INR
Helper cost = 15INR
Foreman cost = 7.5INR
Mechanic = 6INR
Watchman = 3INR
Total crew cost =51.5INR
Total usage cost = 51.5+180+171+684+360 =1446.5INR
Operating cost per hr = 4000000/10000 = 400INR
= 1446.5+400
=1846.5
= 1847INR (say)
Three types of records are maintained at site and they are
i) Progress records
ii) Work output records of individual machines and team of machines
iii) Equipment records
Progress records:
9
7/28/2019 NCP Material & Equipment Mgt
10/17
Records of progress may be kept in a variety of forms, but the method adopted
should be as simple as possible, and to be of real value, must allow for immediate
comparison with planned programme and show at a glance, the actual break up
made, often on percentage basis.
Suitable methods are
i) Work programme as progress records
ii) Bar graph progress chart
iii) Line graphs
iv) Pictorial records
Work output records:
Records of actual output of individual machines and if desired, of team of
machines, will not only be useful on the projects itself to help in analyzing any
causes of delay in progress of work but will prove of great value for further
planning and estimating. To enable these records to be compiled, plant
supervisors reports will be necessary.
Plant supervisors reports:
Each plant supervisor should be required to complete shift report at the end of
each shift, showing relevant information about the machines which have been
under his control during the shift. The report should not be confused with plant
operators daily log which is mainly concerned with servicing and fuel consumption.
Typical items to be entered on plant supervisors report for each machine are:
i) Task on which employed
ii) Total work carried out e.g. number of trips performed, total mileage or
number of vehicles loaded , depending on type of task
iii) Number of minutes worked per hour
iv) Servicing periods
10
7/28/2019 NCP Material & Equipment Mgt
11/17
v) Remarks on delay and waiting times with reasons.
Basic record of equipment maintained
i) Log book
ii) Daily / Monthly working data
iii) History book
Log book:
The log book is to utilized for two purposes
a) For a technical control to evaluate how the machine is performing, and
b) For getting the Plant hours performance classified by works
To determine performance, the total plant hours put in by a machine must be
known and causes of trouble should be classified. The log book records the
consumption of fuels and lubricants, since the performance of the machine can be
judged readily from these figures. It records the work on which the machine was
employed indicating the officer on whose requisition the machines was utilized.
Daily / monthly working data:
Log book also gives record of utilization of machinery. Other data such as sickness,
idleness etc. is not readily available in logbook. The data is equally important to
indicated performance of machine. For this purpose the data is to be maintained in
the form of daily working machinery. Monthly abstract should be prepared.
Maintenance registers:
The maintenance register for the following should be maintained:
i) Daily maintenance
ii) Weekly maintenance
iii) 100 to 175 hours maintenance
iv) 250 hours maintenance
11
7/28/2019 NCP Material & Equipment Mgt
12/17
v) 500 hours maintenance
vi) 1000 hours maintenance
vii) 2000 hours maintenance
Supervision:
The purpose of supervision is not only to see that work is carried out correctly to
specifications laid down and the machines are properly used and output
maintained at consistently high level but also to foresee difficulties and likely
bottlenecks which may reduce output and to take steps to obstacle them before
they occur.
Supervisors responsibility to:
i) Ensure that all the concerned under his command are clear on their
task.
ii) See that machines are used to best advantage and operators take their
task correctly.
iii) Ensure that the work is properly done to the specification laid down.
iv) Take early steps to deal with difficulties in order to assist the operators
to maintain their output where difficulties develop which he cannot deal
with satisfactorily from his own resources, report them without delay to
next supervisor, with the recommendation as to how they can best be
overcome.
v) Always be thinking ahead to foresee likely difficulties and bottlenecks to
the progress of work before they occur so that steps can be taken in
time to prevent them of failing this to reduce this adverse effect on out-
put.
12
7/28/2019 NCP Material & Equipment Mgt
13/17
Transportation of 20,000 cum of surplus earth from site to dumping place 3 k.m.
away from site (including spreading)
Calculation of Disposal of earth for tippers
i) Lead for 3+3 = 6k.m.
ii) Average speed = 25kmph
iii) Loading time = 5.00mins
iv) Travel time = (6/25)x60 = 14.40mins
v) Unloading time = 4.00mins
vi) Idle time = 2.00mins
vii) Time per trip = 5+14.40+4+2 = 25.40mins
viii) Add for break down 10% = 2.54mins
ix) Total time per trip = 25.4+2.54 = 27.94
x) Working time per day 16hours a day = 16 x 60 = 960mins
xi) Number of trips per day per vehicle = 960/27.94 = 34.35 = 35(say)
xii) Quantity per vehicle per day = 35 x4 = 140cum
xiii) Distance travelling per day = 6x35 = 210k.m.
xiv) Quantity per vehicle per month(assuming 25days per month) = 140x25
=3500cum
xv) Distance travelled per month = 210x25 = 5250k.m.
For the disposal of 20,000cum of earth we need 20,000/3500 = 5.71= (6 say)
6no. of tippers are enough to dispose the earth to the dumping yard.
Calculation of Bringing of Sand for tippers
i) Lead for 20+20 = 40k.m.
13
7/28/2019 NCP Material & Equipment Mgt
14/17
ii) Average speed = 25kmph
iii) Loading time = 5.00mins
iv) Travel time = (40/25)x60x2 = 192mins
v) Unloading time = 4.00mins
vi) Idle time = 2.00mins
vii) Time per trip = 5+192+4+2 = 213mins
viii) Add for break down 10% = 21.3mins
ix) Total time per trip = 213+21.3 = 234.3
x) Working time per day 16hours a day = 16 x 60 = 960mins
xi) Number of trips per day per vehicle = 960/234.3 = 4.09 = 4(say)
xii) Quantity per vehicle per day = 4 x4 = 16cum
xiii) Distance travelling per day = 40x4 = 160k.m.
xiv) Quantity per vehicle per month(assuming 25days per month) = 16x25
=400cum
xv) Distance travelled per month = 160x25 = 4000k.m.
For bringing of 3000cum of sand from 20k.m. we need 3000/400 =7.25(8say)
8no. of vehicles are required to get the 3000cum of sand with 20k.m. lead.
Procurement of 150,000 litres of bitumen from refinery which is located
Bonagaigaon in Assam.
Lead time up to site is 45days.
Calculation of Economic order of quantity for Bitumen:
Take Wilson Harris square root formula
The quantity of order corresponding to the frequency is known as Economic order
of quantity. The economic order quantity or lot size can be war analytically. The
14
7/28/2019 NCP Material & Equipment Mgt
15/17
relation between various parameters was developed by RH Wilson and F. Harris
and is known as Wilson Harris Square Root Formula.
The relation is worked out below and is based on assumptions.
a. The demand over the period of the cycle (normally a year) constant and is
known in advance.
b. Consumption of material occurs at the uniform rate.
c. The price of the material is independent of the order.
d. There is no lead time in the replenishment.
Let
A: be the annual demand in terms of units
Q: is the lot size ordered at a time in units
P: Price of the material in terms of
H: Annual inventory carrying / holding cost expressed in Rs. per Rupee of the
inventory
S: Ordering cost (i.e. cost of placing one order) in Rs.
Since the stock in depleted at uniform rate over the cycle period, inventory
carrying cost or holding cost can be the cost over the average stock.
As Q increases the number of orders hence ordering costs reduce, but inventory
carrying costs increase and vice-a-versa. The economic lot size will have to
balance the two costs of opposing nature.
If Q is the lot size the average inventory will be Q/2
Inventory carrying cost will be
Q/2 x p x h
Number of orders over a year = A/ Q
Total Ordering costs = A/Q x S
Thus the total cost T = Q x p x h/2 + Ax S/Q
15
7/28/2019 NCP Material & Equipment Mgt
16/17
We have to find the most economic order quantity for which T is minimum.
dT /dQ should be equated to zero.
dT/ dQ = p x h /2 = A x S/Q^2 = 0
A x s / Q^2 = p x h/2
Q^2 / A x S = 2/ p x h
Therefore Q = Square root of (2x A x S/p x h)
Assume 300 working days in a year
Annual consumption 300 x 3333litre a day = 1000000 litres
Inventory carrying cost Rs. 4 per litre i.e. 20Rs. Inventory
As we need 50000 litres per order because we have only the capacity of
50000litres of storage capacity and the lead time is 45 days from the refinery to
site office. We place 3 orders of 15 days duration from the start of the work. By
which we can get the bitumen by 45days, 60th day and 75th day the total quantity
of bitumen. On 60th day Bitumen work is to be started. Bitumen is planned per day
is 3500litres. Within 15 days 50000litres of bitumen can be consumed. The storage
capacity will be available for another 50000 litres. As the excavation progresses
and the site is available for runway works. Consumption bitumen increases and by
that bitumen procurement from the refinery to site storage cann be made. The
planned quantity of utilization of bitumen can be done within the stipulated
duration of 100days. During storage of bitumen the temperature of 100 degree
Celsius is maintained. Maintaining the boiling temperature of bitumen is important
site storage tank. So the planned schedule is going to be maintained at the site.
Conclusion:
The equipment and materials management can be achieved with
perfect planning and execution. Spare parts for the equipment
should be made available for emergency repair works
16
7/28/2019 NCP Material & Equipment Mgt
17/17
Bibliography:
1. Materials and Equipment management - NICMAR
17