44
NEW HORIZONS ONLINE LIVE Project Management Professional (PMP®) PMBOK Guide 6th Edition DAY 4

NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

  • Upload
    lamtram

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

Page 1: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

NEW HORIZONS ONLINE LIVE

Project Management Professional (PMP®)

– PMBOK Guide 6th Edition

DAY 4

Page 2: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Schedule Formulas

• Schedule Variance (SV): EV-PV

– Greater than zero indicates ahead of schedule

– Less than zero indicates behind schedule

SV = -

Page 3: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Cost Formulas

• Cost Variance (CV): EV-AC

– Greater than zero indicates under budget

– Less than zero indicates over budget

CV = -

Page 4: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Schedule Formulas

• Schedule Performance Index (SPI): EV/PV

– Greater than 1 indicates ahead of schedule

– Less than 1 indicates behind schedule

SPI = /

Page 5: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Cost Formulas

• Cost Performance Index (CPI): EV/AC

– Greater than 1 indicates under budget

– Less than 1 indicates over budget

CPI = /

Page 6: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

CAPS

6

Page 7: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Lab Exercise - EVM

• A project manager performs Earned

Value Analysis and finds the following

results:

• AC: 220,000, PV: 250,000, EV: 220,000.

CV = 0.

CV = 30,000.

CV = -30,000.

CV = 1

7

Page 8: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Lab Exercise - EVM

• A project manager performs Earned

Value Analysis and finds the following

results:

• AC: 220,000, PV: 250,000, EV: 220,000.

CV = 0.

CV = 30,000.

CV = -30,000.

CV = 1

8

Page 9: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

9

Lab Exercise - EVM

Page 10: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

10

Lab Exercise - EVM

EV = AC – CV

EV = 4M – 500K

EV = 3.5 M

Page 11: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Earned Value Forecast Measures

and Formulas

• Estimate To Completion (ETC)

– The amount of money expected to be spent to complete the remaining work

– Management ETC: a new, detailed, bottom-up estimate for the remaining work (most accurate)

– Calculated/Statistical ETC: uses efficiencies to date: (BAC-EV)/CPI (or EAC-AC)

• Note: calculated ETC should be used to validate, but not replace, more detailed and accurate bottom up methods.

Page 12: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Estimate At Completion (EAC)

• Estimate At Completion (EAC) – The forecasted amount of money estimated to be spent

on the entire project

– Equals BAC before the work begins, but changes as actual spending varies from planned

– Several different calculations based on the assumptions of the project management team

1. EAC = AC + ETC – Most common and accurate. Add the costs to date (AC)

plus new bottom-up estimates for remaining work (ETC).

– Useful when the initial plan is no longer valid: when ETC is expected to be noticeably higher or lower than originally planned

Page 13: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Estimate At Completion (EAC)

Formulas

2. EAC = BAC/CPI – When past and current cost performance (good or

bad) is expected to continue for the rest of the work; a linear relationship between past and future is expected

3. EAC = AC + (BAC-EV) – When past and current cost performance (good or

bad) differed from planned, but future cost performance is expected to align with planned

4. EAC = AC + [(BAC-EV) / (CPI X SPI)] – When the schedule is a factor impacting ETC: (BAC-

EV) / (CPI X SPI)

– CPI and SPI can be assigned different weights such as 50/50, 20/80, etc.

Page 14: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Variance at Completion

• VAC = BAC – EAC

• The expected difference in money between what the project was originally expected to spend and what the project is currently expected to spend

• Greater than 0 indicates the project is expected to spend (or if completed, did spend) less money than originally anticipated

• Less than 0 indicates the project is expected to spend (or if completed, did spend) more money than originally anticipated

Page 15: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

To-Complete Performance Index

(TCPI) • A ratio showing how cost efficient the project needs to

be to complete the remaining work with the funds originally established for the project (BAC)

• TCPI = Remaining Work/Remaining Money.

• Thus: TCPI = (BAC-EV)/(BAC-AC)

• Greater than 1 indicates the project is currently overbudget.

• Less than 1 indicates the project is currently underbudget

• E.g. A TCPI of 2.0 means the project team needs to get $2 of value for every $1 of money left. For some projects, this would be unachievable, prompting a significant change request to address this shortcoming.

Page 16: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

To-Complete Performance Index

(TCPI)

• Alternatively, TCPI can use a revised estimate at completion (EAC) instead of the original BAC.

• Indicates the necessary efficiency to complete the current EAC

• TCPI = (BAC-EV)/(EAC-AC)

– Note: BAC-EV in this formula calculates the remaining work, whereas EAC-AC reflects the remaining money based on an updated cost estimate to complete (EAC)

Page 17: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

EVM Formulas, Pg. 267

17

Page 18: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

EVM Formulas, Pg. 267

18

Page 19: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

19

Page 20: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Question

• One common way to compute

estimate at completion (EAC)

is to take the budget at completion

(BAC) and:

A. Divide by SPI

B. Multiply by SPI

C. Multiply by CPI

D. Divide by CPI

20

Page 21: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Answer

• One common way to compute

estimate at completion (EAC)

is to take the budget at completion

(BAC) and:

A. Divide by SPI

B. Multiply by SPI

C. Multiply by CPI

D. Divide by CPI

21

Page 22: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Question

• Estimate at completion (EAC) is a

periodic evaluation of:

A. The cost of work completed

B. The value of work performed

C. The anticipated total cost at project

completion

D. What it will cost to finish the job

22

Page 23: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Answer

• Estimate at completion (EAC) is a

periodic evaluation of:

A. The cost of work completed

B. The value of work performed

C. The anticipated total cost at project

completion

D. What it will cost to finish the job

23

Page 24: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Question

A particular project in the domain of civil

construction requires that every on-site worker be

insured. Which of the following inputs best

conveys this requirement to the Estimate Cost

process so that the insurance cost is estimated

and subsequently budgeted?

A. Enterprise Environmental Factor

B. Organizational Process Assets

C. Scope Baseline

D. Project Management Plan 24

Page 25: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Answer

A particular project in the domain of civil construction

requires that every on-site worker be insured. Which of

the following inputs best conveys this requirement to

the Estimated Cost process so that the insurance cost

is estimated and subsequently budgeted?

A. Enterprise Environmental Factor

B. Organizational Process Assets

C. Scope Baseline

D. Project Management Plan

25

Page 26: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Quality

Page 27: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

27

Page 28: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Plan Quality Management

28

Page 29: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular
Page 30: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular
Page 31: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular
Page 32: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

32

Page 33: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

33

Page 34: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

34

Page 35: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Fishbone (Ishikawa) diagram

Page 36: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Flowcharts

36

Page 37: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Histogram

37

Page 38: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

38

Page 39: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

Scatter diagrams

39

Page 40: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

40

Page 41: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

41

Page 42: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

42

Page 43: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

43

Page 44: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular

44