Upload
lamtram
View
217
Download
0
Embed Size (px)
Citation preview
NEW HORIZONS ONLINE LIVE
Project Management Professional (PMP®)
– PMBOK Guide 6th Edition
DAY 4
Schedule Formulas
• Schedule Variance (SV): EV-PV
– Greater than zero indicates ahead of schedule
– Less than zero indicates behind schedule
SV = -
Cost Formulas
• Cost Variance (CV): EV-AC
– Greater than zero indicates under budget
– Less than zero indicates over budget
CV = -
Schedule Formulas
• Schedule Performance Index (SPI): EV/PV
– Greater than 1 indicates ahead of schedule
– Less than 1 indicates behind schedule
SPI = /
Cost Formulas
• Cost Performance Index (CPI): EV/AC
– Greater than 1 indicates under budget
– Less than 1 indicates over budget
CPI = /
CAPS
6
Lab Exercise - EVM
• A project manager performs Earned
Value Analysis and finds the following
results:
• AC: 220,000, PV: 250,000, EV: 220,000.
CV = 0.
CV = 30,000.
CV = -30,000.
CV = 1
7
Lab Exercise - EVM
• A project manager performs Earned
Value Analysis and finds the following
results:
• AC: 220,000, PV: 250,000, EV: 220,000.
CV = 0.
CV = 30,000.
CV = -30,000.
CV = 1
8
9
Lab Exercise - EVM
10
Lab Exercise - EVM
EV = AC – CV
EV = 4M – 500K
EV = 3.5 M
Earned Value Forecast Measures
and Formulas
• Estimate To Completion (ETC)
– The amount of money expected to be spent to complete the remaining work
– Management ETC: a new, detailed, bottom-up estimate for the remaining work (most accurate)
– Calculated/Statistical ETC: uses efficiencies to date: (BAC-EV)/CPI (or EAC-AC)
• Note: calculated ETC should be used to validate, but not replace, more detailed and accurate bottom up methods.
Estimate At Completion (EAC)
• Estimate At Completion (EAC) – The forecasted amount of money estimated to be spent
on the entire project
– Equals BAC before the work begins, but changes as actual spending varies from planned
– Several different calculations based on the assumptions of the project management team
1. EAC = AC + ETC – Most common and accurate. Add the costs to date (AC)
plus new bottom-up estimates for remaining work (ETC).
– Useful when the initial plan is no longer valid: when ETC is expected to be noticeably higher or lower than originally planned
Estimate At Completion (EAC)
Formulas
2. EAC = BAC/CPI – When past and current cost performance (good or
bad) is expected to continue for the rest of the work; a linear relationship between past and future is expected
3. EAC = AC + (BAC-EV) – When past and current cost performance (good or
bad) differed from planned, but future cost performance is expected to align with planned
4. EAC = AC + [(BAC-EV) / (CPI X SPI)] – When the schedule is a factor impacting ETC: (BAC-
EV) / (CPI X SPI)
– CPI and SPI can be assigned different weights such as 50/50, 20/80, etc.
Variance at Completion
• VAC = BAC – EAC
• The expected difference in money between what the project was originally expected to spend and what the project is currently expected to spend
• Greater than 0 indicates the project is expected to spend (or if completed, did spend) less money than originally anticipated
• Less than 0 indicates the project is expected to spend (or if completed, did spend) more money than originally anticipated
To-Complete Performance Index
(TCPI) • A ratio showing how cost efficient the project needs to
be to complete the remaining work with the funds originally established for the project (BAC)
• TCPI = Remaining Work/Remaining Money.
• Thus: TCPI = (BAC-EV)/(BAC-AC)
• Greater than 1 indicates the project is currently overbudget.
• Less than 1 indicates the project is currently underbudget
• E.g. A TCPI of 2.0 means the project team needs to get $2 of value for every $1 of money left. For some projects, this would be unachievable, prompting a significant change request to address this shortcoming.
To-Complete Performance Index
(TCPI)
• Alternatively, TCPI can use a revised estimate at completion (EAC) instead of the original BAC.
• Indicates the necessary efficiency to complete the current EAC
• TCPI = (BAC-EV)/(EAC-AC)
– Note: BAC-EV in this formula calculates the remaining work, whereas EAC-AC reflects the remaining money based on an updated cost estimate to complete (EAC)
EVM Formulas, Pg. 267
17
EVM Formulas, Pg. 267
18
19
Question
• One common way to compute
estimate at completion (EAC)
is to take the budget at completion
(BAC) and:
A. Divide by SPI
B. Multiply by SPI
C. Multiply by CPI
D. Divide by CPI
20
Answer
• One common way to compute
estimate at completion (EAC)
is to take the budget at completion
(BAC) and:
A. Divide by SPI
B. Multiply by SPI
C. Multiply by CPI
D. Divide by CPI
21
Question
• Estimate at completion (EAC) is a
periodic evaluation of:
A. The cost of work completed
B. The value of work performed
C. The anticipated total cost at project
completion
D. What it will cost to finish the job
22
Answer
• Estimate at completion (EAC) is a
periodic evaluation of:
A. The cost of work completed
B. The value of work performed
C. The anticipated total cost at project
completion
D. What it will cost to finish the job
23
Question
A particular project in the domain of civil
construction requires that every on-site worker be
insured. Which of the following inputs best
conveys this requirement to the Estimate Cost
process so that the insurance cost is estimated
and subsequently budgeted?
A. Enterprise Environmental Factor
B. Organizational Process Assets
C. Scope Baseline
D. Project Management Plan 24
Answer
A particular project in the domain of civil construction
requires that every on-site worker be insured. Which of
the following inputs best conveys this requirement to
the Estimated Cost process so that the insurance cost
is estimated and subsequently budgeted?
A. Enterprise Environmental Factor
B. Organizational Process Assets
C. Scope Baseline
D. Project Management Plan
25
Quality
27
Plan Quality Management
28
32
33
34
Fishbone (Ishikawa) diagram
Flowcharts
36
Histogram
37
38
Scatter diagrams
39
40
41
42
43
44