Upload
sydney-walsh
View
213
Download
0
Embed Size (px)
Citation preview
New Jersey Water Supply Authority1
NEW JERSEY WATER SUPPLY AUTHORITYDredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Public Open House
December 13, 2010
New Jersey Water Supply Authority
New Jersey Water Supply Authority Henry Patterson Ed Buss Sharmila Rahman
Urban Dredging Consultants Joint Venture Ram Mohan Robert DeLorenzo
Other Joint Venture Members Carol Beske – ACT Engineers Eric Rosina – ACT Engineers Lynn Brass-Smith – Amy S. Greene
Environmental Consultants, Inc.
URS Anthony McNichol
Introductions
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Introductions
Primary objective, goals, and critical elements
Dredging technologies evaluated
Sediment characteristics and beneficial reuse
Phasing of construction
Traffic control
Agenda
Cultural resource investigation
Permitting requirements
Environmental information document and public hearing
Public outreach
Project schedule
Open discussion
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Project Objective Remove an estimated 250,000 cubic yards of
sediment from the Canal in order to restore its flow capacity
Project Goals Protect the historical integrity
of the Canal
Maintain technical quality
Maintain water supply
Critical Project Elements Develop dredging plan acceptable
to stakeholders
Focused outreach to public officials and stakeholders
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Project Area
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Dredging Technologies Evaluated
Dry Excavation Mechanical Dredging Hydraulic Dredging
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Pre-Sediment Removal Activities Tree Trimming
Trimming trees to allow equipment access to sediment
Submerged Aquatic Vegetation (SAV) Removal Remove SAV to prevent clogging of
sediment removal equipment
Debris Removal Remove debris to maximize sediment
removal production
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Dry Excavation Canal separated into reaches
varying in manageable lengths
Each Reach with Access Area and Truck Ramp
Flow Bypassed through Work Area (portadam or other structure with piping to convey flow into the Millstone)
Flow diversion structures to facilitate removal on short notice to safeguard against high flow (flood) events
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Dry Excavation (cont.) Low-ground pressure excavators
and dozers used to excavate sediment
Sediment within the dewatered Canal section will be reworked and air dried prior to excavation
Allows for higher degree of accuracy during removal (increased volume control)
Requires intensive water management operations
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Mechanical Dredging Conducted in the wet using
hydraulic excavator operating from shallow-draft barge or flexi-float system
Hydraulic clamshell bucket to be used on dredge to minimize turbidity (1-3 cubic yard bucket)
Dredge maneuvering with non-penetrative methods (anchors, guidelines, etc.)
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Mechanical Dredging (cont.) Dredged sediment to be placed
into 10-20 cy scows or 20 cubic yard containers on flexi-floats
Scows unloaded to trucks or hydraulically pumped to dewatering area
Sediment dewatered by air-drying, stabilization, geobags, or mechanical dewatering system
Potential for multiple dredge units operating simultaneously
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Hydraulic Dredging Conducted in the wet using
hydraulic cutterhead dredge
Requires separate Submerged Aquatic Vegetation (SAV)/debris removal operations prior to dredging to prevent clogging
Dredge maneuvering with non-penetrative methods (anchors, guidelines, etc.)
Booster pumps required to facilitate transport of dredged sediment through plastic pipeline to dewatering area
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Hydraulic Dredging (cont.) Dredged sediment to be
dewatered using geobags or mechanical dewatering system
High comparative production rate
Water generation significantly more than other investigated removal methods
Requires extensive water treatment/water management operations
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Sediment Dewatering/Stabilization Technologies evaluated:
Air-drying Stabilization Geotextile tubes Centrifugation (hydrocyclones) Mechanical presses (belt filter, plate and frame) Rapid dewatering
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Air-Drying Allow dredged sediment to
passively dewater by gravity draining and evaporating water from stockpiled sediment
Small dozer to work sediment to increase speed of dewatering
Stabilization Blend dredged sediment with
portland cement or other material to absorb free water
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Geotextile Tubes Pump dredged sediments through HDPE
pipeline directly to geotextile tubes
Dose polymers to increase dewatering efficiency
Following dewatering, cut tubes and excavate material
Produce “truckable” material
Centrifugation (Hydrocyclones) Quickly separate solids from a slurry
Typically only the initial step in a series of dewatering procedures
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Mechanical Presses (Belt Filter, Plate and Frame) System receives sediment slurry
Use combinations of presses to extract free water from sediment
Produces “truckable” material
Rapid Dewatering System receives sediment slurry
Use multiple steps and dewatering polymers to rapidly separate solids and reduce water content of sediment
Produces “truckable” material
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Sediment Characteristics and Beneficial Reuse
Frequently Detected Compounds/Constituents
32 individual samples Represent vertical
average at each location
Gravel = 6% Sand = 29% Silt/Clay = 63% Organics = 2%
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Phasing of Construction Number of reaches
Reach delineation
Reaches dredged in Year 1 (2013)
Reaches dredged in Year 2 (2014)
Intermediate reaches (minimize disruptions to recreational boaters-canoe rental)
Signage Towpath and Road Detours
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Conceptual Traffic Routes
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Section 106 of the National Historic Preservation Act: Cultural Resources Investigations and SHPO Review
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Section 106 Review of the NHPA – requires the consideration of potential adverse effects on cultural resources within the project areaAs the consultant, URS will conduct a Phase IA Background Research Investigation, identifying areas of potential sensitivity within designated project footprints
Phase IA report is submitted to the New Jersey State Historic Preservation Office for comment and consultation
The SHPO then makes recommendations to the client for the treatment of resources within a given Area of Potential Effect (APE)
These recommendations may include one or more of the following: No impact, limited subsurface testing, or on-site monitoring during
project implementation
URS carries out Phase IB Investigations within the Project Area
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Potential Resources within the Dredging Project Area Features directly associated with the Canal:
Clay liner
Rip-rap
Armor stone
Waste weirs
Dams
Spillways
Wharves and dock features
Slips and scuttled vessels
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Potential Resources within the Dredging Project Area Historic Structures and Archeological Resources
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Potentially Required Permits U.S. Army Corps of Engineers
Delaware and Raritan Canal Commission
NJ Department of Environmental Protection Freshwater wetlands Flood hazard area No net loss reforestation Water lowering Fish stocking Water Quality Certification Section 106 consultation
Somerset-Union County Soil Conservation District NJPDES Construction Soil erosion and sediment
control
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Level II Environmental Information Document Key Environmental Issues
Public use
Surface water
Floodplains and riparian zones
Biotic (plant and animal communities)
Forest
Wetlands
Threatened and endangered species
Cultural resources
Impact on water users
New Jersey Water Supply Authority
Staging Area and Site Access Selection Process Wetland Investigation Secondary source data
Preliminary field investigation
Wetland delineation and survey
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Project Schedule
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
Public Officials Briefings: July, September, FebruaryMontgomeryRocky HillFranklin TownshipHillsboroughSouth BrunswickMillstone BoroughSomerset County
Coordination MeetingsNJDEPD&R Canal State ParkD&R Canal CommissionD&R Canal interest groups briefing
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
D&R Canal Interest Groups Mapleton Preserve Commission Millstone Valley Preserve Coalition Kingston Historical Society Kingston Village Advisory Committee Raritan Millstone Heritage Alliance Somerset County Cultural Heritage Meadows Foundation Griggstown Historical Society Griggstown Canoe Canal Society of New Jersey D&R Canal Watch
Future Meetings: February 2011 Public officials briefings Public hearing
New Jersey Water Supply Authority
Dredging of the Delaware and Raritan Canal from Kingston to Amwell Road
http://www.njwsa.org/html/canaldredging.html
View NJWSA Website for Continuing Project Updates
New Jersey Water Supply Authority
Open Discussion