New Stormwater NPDES Construction General Permit Effective August 3, 2011 Samir Dumpor, PE Division of Water Quality 1

New Stormwater NPDES Construction General Permit Effective August 3, 2011

  • Upload
    lise

  • View
    43

  • Download
    3

Embed Size (px)

DESCRIPTION

New Stormwater NPDES Construction General Permit Effective August 3, 2011. Samir Dumpor, PE Division of Water Quality. State - Erosion and Sedimentation Control Plan. Federal Clean Water Act – NCG01 Construction Gen . Permit (Since 1995). NCG01 Permit Conditions. - PowerPoint PPT Presentation

Citation preview

Page 1: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

1

NewStormwater NPDES

Construction General Permit

Effective August 3, 2011

Samir Dumpor, PEDivision of Water Quality

Page 2: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

2

• State - Erosion and Sedimentation Control Plan

• Federal Clean Water Act – NCG01 Construction Gen. Permit (Since 1995)

Page 3: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

3

NCG01 Permit Conditions

• Weekly inspections/ Records• Rain gauge on site

• Report mud in streams

• Comply with E&SC permit

Page 4: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

4

How Did We Get to ELGs for Construction Activities?

2006 – Court ruled that EPA must promulgate ELGs for the construction industry by December of 2009

ELGs published December 1, 2009

EPA was sued by environmental groups

10 + years

New!

Page 5: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

5

EFFLUENT LIMITATIONS

GUIDELINES (ELG) New!

Page 6: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

6

Court said that the quality of these

discharges must be controlled.

Page 7: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011
Page 8: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

8

FINAL PERMIT

•No Discharge Monitoring

•No Turbidity Limit

Page 9: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

9

FINAL PERMIT

•No Discharge Monitoring

•No Turbidity Limit

Five-year Permit

Page 10: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

10

What Does Permit Require?

1. Quicker Ground Stabilization

• Steep slopes + perimeter areas stabilized in 7 days.

• Remainder of site stabilized in 14 days.

Page 11: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

11

August 4, 2009

GROUND COVER HERE =

7 DAYS

Page 12: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

12

August 4, 2009

GROUND COVER HERE =

7 DAYS

Page 13: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

13

August 4, 2009

GROUND COVER HERE =

7 DAYS

GROUND COVER HERE =

14 DAYS

Page 14: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

14

GROUND COVER WITHIN 14 DAYS-except-

All perimeter slopes, swells & ditches = 7 days

All slopes > 3:1 = 7 days except 10’ or less = 14 days

All slopes > 50’ = 7 daysexcept flatter than 4:1 = 14 days

Page 15: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

15

Reliance on Erosion Control

Rely on Downstream

Sediment Control

OR

Page 16: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

16

Sediment basins

Page 17: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

17

Sediment control device

RELIANCE ON SEDIMENT CONTROL

Page 18: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

18

When used, ground cover works.

RELIANCE ON EROSION CONTROL

Page 19: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

19

Timely application of temporary ground cover can drastically reduce sediment discharge.

80-90%

Page 20: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

20

Nearly Clear Effluent

Page 21: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

21

MANY STATES FOCUS ON TEMPORARY GROUND COVER

FLORIDA

“Stabilization measures shall be initiated as soon as practicable, but in no case more than 7 days where construction activities have temporarily or permanently ceased.

Page 22: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

22

Wisconsin“ESC plans required for all sites over 4,000 ft3. Temporary or permanent stabilization is required within seven days.”

Ground cover within 7 days – enacted 19 years ago

Maryland

Page 23: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

23

King Co. Washington

• “Temporary cover shall be installed if an area is to remain un-worked for more than seven days during the dry season or for more than two days during the wet season.“

Page 24: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

24

2. Withdraw water from surface of pond(except when drainage area < 1 acre)

USE SKIMMERS ON PONDS Skimmer device

Page 25: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

3. LOCATION OF STOCK PILES, DEMOLITION DEBRIS, AND OTHER WASTES SOURCES

• 50’ away from streams and storm drains unless “no reasonable alternative” available

25

Page 26: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

26

Continued Requirements• Weekly inspections/ Records

• Rain gauge on site

• “Normal business hours”

• Report mud in streams

Page 27: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

27

Who will implement new requirements?

Page 28: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

28

Delegated Local

Governments

Page 29: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

29

Local governments will instruct plan developers that:

• Plans must show areas where 7-day and 14-day ground cover applies.

• Plans must show locations of ponds with > 1 acre drainage area.

Page 30: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

30

If plan does not include:• 14-day stabilization areas• 7-day stabilization areas• Basins with >one acre drainage areas

“You DO NOT HAVE COVERAGE UNDER THE NPDES CONSTRUCTION STORMWATER GENERAL PERMIT and you are not allowed to discharge stormwater from the construction site.”

Page 31: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

WHO WILL ENFORCE?

Page 32: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

WHO WILL ENFORCE? BMP

failure?

Page 33: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

BMP failure?

Delegated Local

Government

WHO WILL ENFORCE?

Page 34: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

No 7-day stabilization

No 14-day stabilization

Page 35: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

No 7-day stabilization

No 14-day stabilization

Regional Staff

Page 36: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

BMP failure?

Page 37: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

BMP failure?

Delegated Local

Government

Page 38: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011
Page 39: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011
Page 40: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

Regional Staff

Water Quality Violation

Page 41: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

41

Go to DWQ Home Page “DWQ Hot Topics”

NEW Construction General Permit

Samir [email protected]

http://portal.ncdenr.org/web/wq/ws/su/npdessw

Page 42: New Stormwater NPDES  Construction  General  Permit Effective August 3, 2011

42

Questions?