NEW YORK STATE DEPARTMENT OF TRANSPORTATION
Superstructure and Bridge Replacements
At Various Locations in Regions 2 & 9
PIN 2805.65, Contract No. D900022
Herkimer, Schoharie and Oneida Counties
Draft Request for Proposals
RFP Informational Meeting
September 18, 2014
Peter RussellAttn: Superstructure and Bridge
Replacements in Regions 2 and9 Design-Build Project
Office of Contract ManagementNew York State Department of Transportation
50 Wolf Road, 6th FloorAlbany, New York [email protected]
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Rules of Contact2
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Agenda
Project Overview Department’s Goals & Project Requirements Scope of Work Status of: ROW and Utilities General Contract Information Alternative Technical Concepts Procurement Schedule One-on-One Meetings RFP Content Quality Control & Quality Assurance Evaluation and Selection Additional Information and Submission Guidelines Questions and Answers
3
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) General Location
4
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) General Location
5
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) General Location
6
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) General Location
7
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) General Location
8
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Goals9
Replace superstructure of four bridges in Herkimer, Schoharie, and Oneida Counties
Full Replacement of one bridge in Oneida County Ensure the safety of the traveling public Ensure coordination with all utility owners, third
parties, and the surrounding residential community
Ensure a long-service life for all Project elements to satisfy long term preservation goals
Ensure compliance with the Project’s environmental commitments and conditions
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Goals (Continued)10
Maximize the beneficial impact of the public investment by Providing cost-effective solutions that maximize value
over the lifespan of the Bridges; Sequencing construction to minimize effects on
vehicular traffic operations; Reducing future maintenance requirements; Minimizing effects on residential neighborhoods and
business communities Minimize impacts on the environment
Deliver Project Safely, On Schedule, On Budget, and Environmentally Compliant.
Provide best value to the Department
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) General Scope of Work
Superstructure replacement for four bridges in Herkimer (BIN1002720), Schoharie (BINs 1007890 & 1007900), & Oneida (BIN 2206680) counties Removal of the existing superstructure for all of the bridges; Construction of new superstructure and approach slabs; Approach sidewalk reconstruction at West Main Street (BIN
1002720); Modifications to each of the substructures as necessary to
accommodate each new superstructure. Full Bridge Replacement for one bridge in Oneida County
(BIN 1051810) Removal of existing substructure and superstructure; Replacement of the existing bridge; including new
foundations, substructure, superstructure and approach slabs
11
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) General Scope of Work (Continued) Reconstruction of approach roadways as necessary to
connect to the new structures, including correction of superelevation rates
Development of WZTC Plan for each site Coordination with and/or preservation of existing utilities Design, fabrication and installation of new guide railing /
bridge railing. Potential remediation and disposal of asbestos and or
lead containing materials; Avoid existing environmental constraints
Threatened and endangered species Farmlands Wetlands
12
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Right-of-Way
The Department owns all Right-of-Way for the existing structures. Right of Way has been purchased for BIN 2206680
(Chenango Rd/Sauquoit Creek) Acquisition maps have been posted as reference
documents. No additional Right-of-Way acquisitions or
temporary easements are anticipated to be required for this project.
13
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Utility Coordination – Existing Utilities
In accordance with Part 4 – Utility Requirements, Design-Builder is responsible for:
Verifying utility facility locations; Identifying & resolving any conflicts not yet
documented; Coordinating with utility owners for utility
relocations; Providing stakeout and final layout of utility
relocations; Protecting existing utilities; Cost to repair damages to utilities caused by
Design-Builder; Informing the Department of all
meetings/correspondence with utility owners.
14
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Utility Coordination – Existing Utilities – Relocations by Others
BIN 1002720 - Village of Ilion, West Main Street Over Steele Creek
Village of Ilion (Electric): Village of Ilion (Electric) shall relocate utility poles, overhead
lines and any facilities necessary so that the superstructure can be removed and replaced, including any necessary tree pruning.
Northland Communications, Time Warner Cable, Verizon: Telecommunication companies shall relocate overhead lines
and any facilities necessary so that the superstructure can be removed and replaced, including splice notifications to customers (usually 30 to 45 days notice).
National Grid (Gas): National Grid shall perform all work necessary to relocate
the underground gas main and any facilities necessary so that the superstructure can be removed and replaced.
15
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Utility Coordination – Existing Utilities – Relocations by Others
BIN 1007890 - Town of Sharon, Route 10 over Brimstone Creek
No utility relocations are anticipated in connection with this structure.
BIN 1007900 - Town of Sharon, Route 10 over Brimstone Creek
No utility relocations are anticipated in connection with this structure.
16
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Utility Coordination – Existing Utilities – Relocations by Others
BIN 2206680 - City of Utica, Chenango Road over Sauquoit Creek
National Grid (Electric): No impacts to National Grid’s Sub-T tower will be allowed.
National Grid shall perform all work necessary to relocate utility poles, risers, overhead lines and any other impacted facilities so that the superstructure can be removed and replaced.
Northland Communications, Time Warner Cable, Verizon: Telecommunication companies shall relocate overhead lines
and any facilities necessary so that the superstructure can be removed and replaced, including splice notifications to customers (usually 30 to 45 days notice).
National Grid (Gas): National Grid shall perform all work necessary to relocate the
underground gas main and any facilities necessary so that the superstructure can be removed and replaced.
17
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Utility Coordination – Existing Utilities – Relocations by Others
BIN 1051810 - Town of Marcy, Route 291 over Nine Mile Creek
National Grid (Electric): National Grid shall perform all work necessary to relocate
utility poles, overhead lines and any facilities necessary so that the bridge can be removed and replaced.
Northland Communications, Time Warner Cable, Verizon: Telecommunication companies shall relocate overhead
lines and any facilities necessary so that the superstructure can be removed and replaced, including splice notifications to customers (usually 30 to 45 days notice).
18
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Utility Coordination – Existing Utilities – Relocations by DB
BIN 1002720 - Village of Ilion, West Main Street Over Steele Creek
Village of Ilion (Water): The Design-Builder shall relocate water line to avoid impact with the
removal and replacement of the superstructure. All work shall be performed in accordance with the standards and requirements of the Village of Ilion.
Village of Ilion (Sanitary): Prior to final pavement placement, the Design-Builder shall coordinate
an inspection of all structures within the limits of the project with the Village, and if the Village then determines that repairs and/or replacements of manholes, sewer mains, or sanitary facilities are required, the Design-Builder may contract separately with the Village to perform the work.
However, any sanitary facilities damaged as a result of the Design-Builder shall be repaired and/or replaced in accordance with the standards and requirements of the Village of Ilion at no cost to the Village or the Dept.
In addition, the Design-Builder shall adjust the rim elevations of any manholes located within the paving limits to meet finished grade. Payment for the adjustment of manholes to finished grade shall be included in the Lump Sum price bid for BIN 1002720.
19
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Utility Coordination – Existing Utilities – Relocations by DB
BIN 1007890 - Town of Sharon, Route 10 over Brimstone Creek
No utility relocations are anticipated in connection with this structure.
BIN 1007900 - Town of Sharon, Route 10 over Brimstone Creek
No utility relocations are anticipated in connection with this structure.
20
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Utility Coordination – Existing Utilities – Relocations by DB
BIN 2206680 - City of Utica, Chenango Road over Sauquoit Creek
Mohawk Valley Water Authority (Water) : The Design-Builder shall relocate the existing water line to avoid
impact with the removal and replacement of the superstructure. All work shall be performed in accordance with the standards and requirements of the Mohawk Valley Water Authority.
City of Utica (Sanitary): Prior to final pavement placement, the Design-Builder shall coordinate
an inspection of all structures within the limits of the project with the City, and if the City then determines that repairs and/or replacements of manholes, sewer mains, or sanitary facilities are required, the Design-Builder may contract separately with the City of Utica to perform the work.
However, any sanitary facilities damaged as a result of the Design-Builder shall be repaired and/or replaced in accordance with the standards and requirements of the City of Utica at no cost to the City or the Department.
In addition, the Design-Builder shall adjust the rim elevations of any manholes located within the paving limits to meet finished grade. Payment for the adjustment of manholes to finished grade shall be included in the Lump Sum price bid for BIN 2206680.
21
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Utility Coordination – Existing Utilities – Relocations by DB
BIN 1051810 - Town of Marcy, Route 291 over Nine Mile Creek Mohawk Valley Water Authority (Water) :
There is an existing underground water line approximately 20’ east of the bridge. Any work regarding this utility shall be performed in accordance with the standards and requirements of the Mohawk Valley Water Authority.
Town of Marcy (Sanitary): Prior to final pavement placement, the Design-Builder shall
coordinate an inspection of all structures within the limits of the project with the Town, and if the Town then determines that repairs and/or replacements of manholes, sewer mains, or sanitary facilities are required, the Design-Builder may contract separately with the Town of Marcy to perform the work.
However, any sanitary facilities damaged as a result of the Design-Builder shall be repaired and/or replaced in accordance with the standards and requirements of the Town of Marcy at no cost to the Town or the Department.
In addition, the Design-Builder shall adjust the rim elevations of any manholes located within the paving limits to meet finished grade. Payment for the adjustment of manholes to finished grade shall be included in the Lump Sum price bid for BIN 1051810.
22
Three Way Coordination – DB, Utility & State Coordination meeting will be held between the
Department, all short-list firms, and the utility companies before or shortly after issuance of Final RFP.
DB Responsibilities DB Team responsible for holding utility coordination
meetings; DB Team to provide supporting documents for utility
design, including: plans, Table of Conflicts & Special Note of Utility Coordination;
Table of Conflicts to include existing & proposed locations;
Special Note of Utility Coordination must include work description, proposed locations and time frames.
23
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Utility Coordination
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Contract Information Lump Sum Design-Build Contract; Best Value Selection Process (50% Price, 50% Quality); Project Completion Date shall be the earlier of:
November 30, 2016; or The number of days past NTP proposed by the successful
Proposer on Form SCD (ITP Appendix E) Liquidated Damages will be imposed for not meeting
the Project Completion date and for Impacts to Traffic in excess of the number of calendar days indicated on Form SCD;
Early Completion Bonus if Project Completion is achieved ahead of the Project Completion Date;
Escrow Submission of Bid Documents for Successful Proposer.
24
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Contract Information There is a Payment Schedule provided in the RFP;
Form SP Construction (5 BINS) Design Construction Inspection Quality Control (Material Testing) Force Account Work (amount provided by Department)
Form WPS Breakdown of construction work items Input by Proposer (100% max)
25
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Contract Information (Continued) Stipend to Unsuccessful Proposers (50% of Qualified
Costs, $75K max.); Must satisfy criteria in ITP General Instructions; Pass All Pass/Fail Factors Achieve at least 60 points on Quality Factors Proposal must be Competitive and Reasonable Proposal not Selected by Department as providing the Best
Value There is a Buy America Clause There is an Iran Divestment Act Clause There is a DBE Participation Goal of 11% All ROW owned by NYSDOT Any additional Environmental and Construction
Related Permits by Design-Builder
26
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) ATCs
Alternate Technical Concepts (ATCs) are proposals from the Proposer to design and construct the Project in a manner that is different than the Contract Requirements and which: are submitted to the Department for review,
consideration and approval prior to Proposal submittal; have significant savings in time, and/or reduction of
traffic impacts, and/or community disruption, and/or project costs, and/or environmental impacts, and/or other beneficial impacts to Project parameters;
in the Department’s judgment offers an equal or superior Project.
27
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) ATCs (Continued)
Proposers may submit, on a confidential basis, up to five (5) ATCs, using Form ATC, for the Department’s pre-approval;
The proposed end product of each alternative must, in the Department’s judgment, be equal to or better than the Work product described in the Contract Documents;
Department may provide ‘Conditional Approval’ of an ATC. Proposers must respond to Conditional Approvals by the established date;
The Design-Builder is solely responsible for obtaining approvals from any local municipality, public agency or permit issuing agency for ATC concepts which would affect their facilities, operations or issued permit.
28
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022)Anticipated Procurement Schedule
Activity Due Date
Draft RFP Informational Meeting September 18, 2014
Final RFP to Shortlisted Firms October 1, 2014
Date Proposers may start submitting ATCs for review October 3, 2014
Proposal period one-on-one meetings with all Proposers, specific dates to be determined. October 29 to November 26, 2014
Final date for Proposers to submit ATC’s for review December 10, 2014
Final date for requests for changes to Proposer’s organization and personnel December 10, 2014
Final date for Department’s responses to ATCs submitted for review December 17, 2014
Final date for receipt of Proposer questions December 19, 2014
Final Date for proposers to respond to conditional approval of ATC’s December 23, 2014
Issue Date for Final Addendum and/or answers to Proposer questions December 23, 2014
Proposal Due January 7, 2015
Post Proposal meetings (if required) TBD
Selection of Best Value Late January, 2015
Contract Award Beginning March, 2015
Notice to Proceed March 25, 2015
29
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) One-On-One Meetings
If One-On-One Meetings are held, at least one meeting will be held with each Proposer;
One-on-One Meetings will be recorded; Department reserves the right to disclose to all
Proposers any issues raised during the meetings that may materially affect the project;
Department will not disclose information pertaining to an individual Proposer’s technical concepts, proposal or ATCs;
Additional One-on-One Meetings may be held if required to review ATCs or if the Department believes it is warranted.
30
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Request for Proposals (RFP) Documents RFP Documents:
Instructions to Proposers Part 1: D-B Agreement Part 2: General Provisions, Section DB 100 and Appendices Part 3: Project Requirements (Scope of Work) Part 4: Utility Requirements Part 5: Special Provisions Part 6: RFP Plans Part 7: Engineering Data Part 8: Special Specifications (Including New DB
Specifications) Part 9: The Design-Builder’s Proposal Part 10: RFP Addenda (If Any)
Reference Documents: On Department’s web site (Not Part of the Contract Documents)
31
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Request for Proposals (RFP) Documents (Continued)32
RFP Documents: Instructions to Proposers• General Instructions• Appendix A – Project Information• Appendix B – Administrative Submittal
Requirements• Appendix C – Technical Submittal Requirements• Appendix D – Price Proposal Submittal
Requirements• Appendix E – Forms• Appendix F – Conflicts of Interest Policy• Appendix G – Abbreviations and Definitions
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Quality Control (QC)
QC is Design-Builder’s Responsibility Design-Builder shall appoint a QC Manager responsible for
QC Plan for both Design and Construction Design QC shall be the Design-Builder’s responsibility and
shall be performed in accordance with the QC Plan Construction Inspection shall be performed by an
Independent Engineering Firm (Hired by the Design-Builder) Materials Testing shall be performed by an Independent
Materials Testing Firm or Laboratory (Hired by the Design-Builder)
The Materials Testing Firm shall report to the Construction Inspection Firm
Offsite Plant Quality Control shall be performed by the Department
33
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Quality Assurance (QA) Design and Construction QA is the Department’s
Responsibility The Department may perform QA on any of the
Design-Builder’s Design and Construction activities The Department will utilize an independent
Consultant to perform QA of the Design-Builder’s Designs
Construction QA will be performed by Department staff
Offsite Plant Quality Assurance will be performed by the Department
34
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) RFP Evaluation and SelectionPass/Fail Evaluation Factors
Legal – Financial – Administrative – DBE Compliance - Price Proposal (Bond/Conformance)
Quality Evaluation Factors (50%) Key Personnel (30 points) Management Approach (25 points)
Overall Design-Build Team Organization (7 points) Design Management Plan (5 points) Construction Management Plan (6 points) Quality Control Plan (7 points)
Technical Solutions (35 points) Design Approach (10 points) Construction Approach (10 points) Initial Baseline Schedule (15 points)
Project Support (5 points) Proposal Format(5 points)
Price (50%)
Design-Builder must obtain a
minimum score of 60 points on
Quality Evaluation factors
35
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Additional Information – Submission Guidelines
All proposals must be self-contained.• Proposals should not have links to external web
sites.• Proposals should contain all information needed
for evaluation. Do not “assume the Department knows” your firm
and it’s experience/qualifications.
36
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Additional Information – Submission Guidelines
Submit ALL Forms required Do not alter any Form unless indicated on the Form. Do not add any appendices or attachments to the
Forms. Do not include photographs or illustrations unless
specifically indicated. Do not submit with Proposal:
Form SA (Stipend Agreement) => 20 Days after Proposal Due Date
Form BDEA (Bid Document Escrow Agreement) PAB (Payment Bond (Labor and Material Bond)) PEB (Performance Bond (Faithful Performance Bond))
37
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Additional Information
Responses to Proposer Questions will be posted on the Department’s Project Web Site
Reference Documents are Posted on the Department’s Project Web Site:
https://www.dot.ny.gov/main/business-center/designbuildproject9 Reference Documents include:
Project Location Maps; Bridge Inspection Reports; Bridge Record Plans; Final Design Reports; Asbestos Assessment Reports; ROW Acquisition Maps; BIN 1051810 Route 291 - Preliminary Plans; Subsurface Exploration Boring Logs; and Potentially others (To be Determined).
38
Peter RussellAttn: Superstructure and Bridge
Replacements in Regions 2 & 9 Design-Build Project
Office of Contract ManagementNew York State Department of Transportation
50 Wolf Road, 6th FloorAlbany, New York [email protected]
Superstructure and Bridge Replacements in Regions 2 & 9Design-Build Project (PIN 2805.65; D900022) Rules of Contact39