Upload
manh-tu
View
219
Download
0
Embed Size (px)
Citation preview
8/10/2019 Noi Bai International Airport Termination 2 Construction Project
1/2
NOI BAI INTERNATIONAL AIRPORTTERMINATION 2 CONSTRUCTION PROJECTHA NOI, VIET NAM
BAUER Asia Pacific Network APN_BVN 2012/168
Owner: The Government of Viet Nam
Project:
Noi Bai International Airport Terminal 2, Ha Noi, Vietnam
Engineer: JAC Japanese Airport Consultant
Main Contractor: TVJV Taisei Vinaconex Joint Venture
Foundation Contractor: BAUER Vietnam Limited
Scope of Works: 256 nos. of Bored Piles 800, 1200,1500mm
Construction Period: From June 2012 to August 2012
Main Equipment: 1nos BG 40 Drilling Rig & 1nos BG 28 Drilling Rig
8/10/2019 Noi Bai International Airport Termination 2 Construction Project
2/2
NOI BAI INTERNATIONAL AIRPORT
TERMINATION 2 CONSTRUCTION PROJECT
HA NOI, VIETNAM
BAUER Asia Pacific Network APN_BVN_2012/168
PURPOSE OF WORKS
Due to the existing Noi Bai International Airport
already surpassing its designed capacity in 2007, the
construction of passenger terminal 2 of Noi Bai
international airport which is capable to
accommodate 10 million international passengers
per annum is one of the most important transport
infrastructure projects being implemented in order to
contribute to the economic and social development
of Hanoi and all Vietnam.
The terminal 2 is a 4-storied international passenger
terminal building with floor area of approximately
139,216 m2, fully equipped with electro-mechanical
and other facilities was awarded to Taisei-Vinaconex
Joint Venture.
Due to the piling package tight construction
schedule, the package was divided between two
subcontractors. Bauer Vietnam Ltd. has been
awarded as specialist subcontractor for more than
50% of foundation works for the main building and
the east-wing building consisting of 256 bored piles.
SOIL / ROCK CONDITION
First 20m below ground level is mainly sandy clayfollowing with eluvium derived from in-situ weathered
rock and bed rock underneath.
Design of this building adopted a one-column-one-
pile foundation system which requires a high
capacity of pile in both vertical and horizontal. In
consideration of that all the piles are designed to
socket 6m in bed rock which is up to 20MPa in
unconfined compressive strength.
Foundation of the building consists of bored piles
with diameter varying from 800 to 1500mm and
length varying from 25 to 40m.
CONSTRUCTION WORKS & SPECIAL FEATURES
One high performance drilling rigs model BG 40 and
one smaller model BG 28 have been deployed to
optimize of the overall performance, whereas the
other subcontractor on this Project utilise an
assortment of eight different drilling rigs for the
works.
Bauer with the appropriate equipment and tools, an
experienced site team has also been deployed
together with well planning and strong logistics,
managed to complete our whole works including all
variations well ahead of the contract schedule
helping the Main Contractor to recover their loss time
schedule caused by others.