    NOI BAI INTERNATIONAL AIRPORTTERMINATION 2 CONSTRUCTION PROJECTHA NOI, VIET NAM

    BAUER Asia Pacific Network APN_BVN 2012/168

    Owner: The Government of Viet Nam

    Project:

    Noi Bai International Airport Terminal 2, Ha Noi, Vietnam

    Engineer: JAC Japanese Airport Consultant

    Main Contractor: TVJV Taisei Vinaconex Joint Venture

    Foundation Contractor: BAUER Vietnam Limited

    Scope of Works: 256 nos. of Bored Piles 800, 1200,1500mm

    Construction Period: From June 2012 to August 2012

    Main Equipment: 1nos BG 40 Drilling Rig & 1nos BG 28 Drilling Rig

  • 8/10/2019 Noi Bai International Airport Termination 2 Construction Project

    2/2

    NOI BAI INTERNATIONAL AIRPORT

    TERMINATION 2 CONSTRUCTION PROJECT

    HA NOI, VIETNAM

    BAUER Asia Pacific Network APN_BVN_2012/168

    PURPOSE OF WORKS

    Due to the existing Noi Bai International Airport

    already surpassing its designed capacity in 2007, the

    construction of passenger terminal 2 of Noi Bai

    international airport which is capable to

    accommodate 10 million international passengers

    per annum is one of the most important transport

    infrastructure projects being implemented in order to

    contribute to the economic and social development

    of Hanoi and all Vietnam.

    The terminal 2 is a 4-storied international passenger

    terminal building with floor area of approximately

    139,216 m2, fully equipped with electro-mechanical

    and other facilities was awarded to Taisei-Vinaconex

    Joint Venture.

    Due to the piling package tight construction

    schedule, the package was divided between two

    subcontractors. Bauer Vietnam Ltd. has been

    awarded as specialist subcontractor for more than

    50% of foundation works for the main building and

    the east-wing building consisting of 256 bored piles.

    SOIL / ROCK CONDITION

    First 20m below ground level is mainly sandy clayfollowing with eluvium derived from in-situ weathered

    rock and bed rock underneath.

    Design of this building adopted a one-column-one-

    pile foundation system which requires a high

    capacity of pile in both vertical and horizontal. In

    consideration of that all the piles are designed to

    socket 6m in bed rock which is up to 20MPa in

    unconfined compressive strength.

    Foundation of the building consists of bored piles

    with diameter varying from 800 to 1500mm and

    length varying from 25 to 40m.

    CONSTRUCTION WORKS & SPECIAL FEATURES

    One high performance drilling rigs model BG 40 and

    one smaller model BG 28 have been deployed to

    optimize of the overall performance, whereas the

    other subcontractor on this Project utilise an

    assortment of eight different drilling rigs for the

    works.

    Bauer with the appropriate equipment and tools, an

    experienced site team has also been deployed

    together with well planning and strong logistics,

    managed to complete our whole works including all

    variations well ahead of the contract schedule

    helping the Main Contractor to recover their loss time

    schedule caused by others.