35
Northeast Power Coordinating Council, Inc. Multi-Area Probabilistic Reliability Assessment For Winter 2008/09 Approved by the Reliability Coordinating Committee November 19, 2008 Conducted by the NPCC CP-8 Working Group

Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

Northeast Power Coordinating Council, Inc. Multi-Area Probabilistic Reliability

Assessment For

Winter 2008/09

Approved by the Reliability Coordinating Committee

November 19, 2008

Conducted by the

NPCC CP-8 Working Group

Page 2: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

This page intentionally left blank.

Page 3: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved – November 19, 2008 1 Final Report

CP-8 WORKING GROUP

Northeast Power Coordinating Council, Inc. Phil Fedora, Chairman

Hydro-Québec Distribution Pierre Poirier Hydro-Québec Production Thong Nguyen-

Phat Independent Electricity Market Operator Greg Hine ISO - New England, Inc. Fei Zeng National Grid Jack Martin New Brunswick System Operator Scott Brown New York Independent System Operator Gregory Drake New York State Reliability Council Al Adamson Nova Scotia Power Inc. Kamala

Rangaswamy Ontario Power Generation, Inc. Kevan Jefferies

The CP-8 Working Group acknowledges the efforts of Messrs. Glenn Haringa, GE Energy, and Andrew Ford, PJM and thanks them for their assistance in this analysis.

Page 4: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved – November 19, 2008 2 Final Report

TABLE OF CONTENTS

PAGE EXECUTIVE SUMMARY 4 Introduction ..................................................................................................................... 4 Results ..................................................................................................................... 4 Conclusions ..................................................................................................................... 6 INTRODUCTION 7 MODEL ASSUMPTIONS 8 Load Representation............................................................................................................ 8 Load Shape.............................................................................................................. 8 Load Forecast Uncertainty ...................................................................................... 9 Generation ................................................................................................................... 10 Unit Availability.................................................................................................... 11 Transfer Limits .................................................................................................................. 12 Operating Procedures to Mitigate Resource Shortages..................................................... 14

Assistance Priority............................................................................................................. 15 Modeling of Neighboring Regions.................................................................................... 15 WINTER 2007/08 SUMMARY ................................................................................................. 17 ANALYSIS 19 Winter 2008/09 Results ..................................................................................................... 19 Base Case Scenario ............................................................................................... 19

Severe Case Scenario ............................................................................................ 23 Conclusions ................................................................................................................... 26

Page 5: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved – November 19, 2008 3 Final Report

APPENDICES

PAGE A) OBJECTIVE AND SCOPE OF WORK 27

B) EXPECTED NEED FOR OPERATING PROCEDURES 28 Table 7 - Base Case Assumptions (2003/04 Load Shape) .................................... 28 Table 8 - Severe Case Scenario (2003/04 Load Shape) ......................................... 29 C) MULTI-AREA RELIABILITY SIMULATION PROGRAM DESCRIPTION 30

Page 6: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 4 Final Report

EXECUTIVE SUMMARY Introduction

This study estimated the use of NPCC Area Operating Procedures designed to mitigate resource shortages for the winter of 2008/09 (November 2008 through March 2009). The CP-8 Working Group closely coordinated its efforts with those of the CO-12 Working Group’s study, "NPCC Reliability Assessment for Winter 2008 - 09", November 2008. General Electric’s (GE) Multi-Area Reliability Simulation (MARS) program was selected for the analysis. GE Energy was retained by the Working Group to conduct the simulations. Results For the November 2008 - March 2009 period, Figure EX-1 displays the results for the expected load level (the expected load level results were based on the probability-weighted average of the seven load levels simulated) under the Base Case assumptions.

Figure EX-1

Potential Range of Use of Indicated Operating Procedures for Winter 2008/09 Considering Base Case Assumptions (November 2008 – March 2009)

(Expected Load Level) For the November 2008 - March 2009 period, Figure EX-2 shows the estimated use of the indicated operating procedures under the Severe Case assumptions for the expected load level (the expected load level results were based on the probability-weighted average of the seven load levels simulated).

0

1

2

Estimated Number of Occurrences (days/period)

NE NY ON MT Q

Reduce 30-min ReserveVoltage ReductionReduce 10-min ReserveAppealsDisconnect Load

Maritimes Area initiates interruptible loads instead of voltage reduction

Page 7: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 5 Final Report

Figure EX-2 Winter 2008/09 – Estimated Use of the Indicated Operating Procedures

Severe Case Assumptions, Expected Load Level (November 2008 – March 2009)

For the November 2008 - March 2009 period, Figure EX-3 shows the estimated use of the indicated operating procedures under the Severe Case assumptions for the extreme load level (representing the second to highest load level, having approximately a 6% chance of being exceeded) for the week with the highest risk.

Figure EX-3

Winter 2008/09 – Estimated Use of the Indicated Operating Procedures Severe Case Assumptions, Extreme Load Level – week of highest risk

(November 2008 – March 2009)

0

2

4

6

Estimated Number of

Occurrences (days/period)

NE NY ON MT Q

Reduce 30-min ReserveVoltage ReductionReduce 10-min ReserveAppealsDisconnect Load

Maritimes Area initiates interruptible loads instead of voltage reduction

0

2

4

6

Estimated Number of

Occurrences (days/weekof highest

risk)

NE NY ON MT Q

Reduce 30-min ReserveVoltage ReductionReduce 10-min ReserveAppealsDisconnect Load

Maritimes Area initiates interruptible loads instead of voltage reduction

Page 8: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 6 Final Report

Conclusions Use of operating procedures designed to mitigate resource shortages (specifically, reducing 30-minute reserve, voltage reduction, reducing 10-minute reserve, and public appeals) is not expected for Québec, Ontario, New England, and New York, during the 2008/09 winter period for the expected load level under both the assumed Base and Severe Case conditions. The expected load level results were based on the probability-weighted average of the seven load levels simulated. For the Maritimes Area there is an expectation for reducing 30-minute reserves and calling on interruptible loads in response to a capacity deficiency this winter for the expected load level under the Base Case assumptions. This expectation increases for the Severe Case assumptions for the expected load level. For the week with the highest risk in the November 2008 to March 2009 time period, New England, the Maritimes, and to lesser extent, Ontario may need to rely on their Operating Procedures under the Severe Case, extreme load assumptions (representing the second to highest load level, having approximately a 6% chance of being exceeded).

Page 9: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 7 Final Report

INTRODUCTION This study estimated the use of NPCC Area operating procedures to mitigate resource shortages for November 2008 through March 2009. The Working Group closely coordinated its efforts with the NPCC CO-12 Working Group’s study, "NPCC Reliability Assessment for Winter 2008 -09", November 2008. The development of this Working Group was in response to the following recommendation from the "NPCC Reliability Assessment for Winter 2004/05". 1

“The CO-12 assessment of the Summer Operating Period is accompanied by a corresponding multi area probabilistic assessment of Loss of Load Expectations and of the projected use of Operating Procedures designed to mitigate resource shortages. This assessment was not performed for this Winter Operating Period. For completeness in the assessment of the Winter Operating Period, the CO-12 Working Group recommends that TFCO and TFCP review the merits of having this assessment performed for future Winter Operating Periods.”

The database developed by the previous CP-8 Working Group's "NPCC Summer 2008 Multi-Area Probabilistic Reliability Assessment" 1 was used as the starting point for this analysis. Working Group members reviewed the existing data and made revisions to reflect the conditions expected for the winter 2008/09 assessment period. This report is organized in the following manner: after a brief Introduction, specific Model Assumptions are presented, followed by an Analysis of the results based on the scenarios simulated. The Working Group's Objective and Scope of Work is shown in Appendix A. Tables presenting the corresponding results for the Base Case and Severe Case simulations are listed in Appendix B. Appendix C provides an overview of General Electric's Multi-Area Reliability Simulation (MARS) Program.

1 See: http://www.npcc.org/documents/reports/Seasonal.aspx

Page 10: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 8 Final Report

MODEL ASSUMPTIONS Load Representation The loads for each Area were modeled on an hourly, chronological basis. The MARS program modified the input hourly loads through time to meet each Area's specified annual or monthly peaks and energies. Table 1 summarizes each NPCC Area's winter peak load assumptions for the winter 2008/09.

Table 1 Assumed NPCC 2008/09 Peak Loads – MW

(2003/04 Load Shapes)

2003/04 Load Shape

Area Expected Peak

Extreme Peak * Month

Québec (Q) 35,887 38,417 January

Maritimes Area** (MT) 5,507 6,058 February

New England (NE) 23,030 25,257 January

New York (NY) 25,293 26,077 December

Ontario (ON) 23,708 24,782 January

* Extreme Peak based on load forecast uncertainty for peak month. * * Maritimes Area represents New Brunswick, Nova Scotia, Prince Edward Island, and the area administrated by the Northern Maine Independent System Administrator (NMISA).

Load Shape The Working Group used one load shape assumption for this analysis. The 2003/04 load shape represents a weather pattern that includes a consecutive period of cold days. The growth rate in each month’s peak was used to escalate Area loads to match the Area's winter demand and energy forecasts for both load shapes. The impacts of Demand-Side Management programs were included in each Area's load forecast for both load shapes. 2 Figure 1 shows the diversity in the NPCC area load shapes used in this analysis for the 2003/04 load shape assumptions. 2 New England’s forecast does not include Demand-Side Management programs, as they are treated as supply resources.

Page 11: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 9 Final Report

Figure 1 – 2008/09 Projected Monthly Peak Loads for NPCC Areas

(2003/04 Load Shape) Load Forecast Uncertainty Peak load forecast uncertainty was also modeled. The effects on reliability of uncertainties in the peak load forecast, due to weather and/or economic conditions, were captured through the load forecast uncertainty model in MARS. The program computes the reliability indices at each of the specified load levels (for this study, seven load levels were modeled) and calculates weighted-average values based on input probabilities of occurrence. While the per unit variations in the load can vary on a monthly basis, Table 2 shows the values assumed for January 2009. Table 2 also shows the probability of occurrence assumed for each of the seven load levels modeled.

In computing the reliability indices, all of the Areas were evaluated simultaneously at the corresponding load level, the assumption being that the factors giving rise to the uncertainty affect all of the Areas at the same time. The amount of the effect can vary according to the variations in the load levels.

For this study, reliability measures are reported for two load conditions: expected and extreme. The values for the expected load conditions are derived from computing the reliability at each of the seven load levels, and computing a weighted-average expected value based on the specified probabilities of occurrence. The indices for the extreme load conditions provide a measure of the reliability in the event of higher than expected loads,

2008/09 Projected Coincident Monthly Peak Loads - MW2003/04 Load Shape

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

MW

Q MT NE NY ON

Page 12: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 10 Final Report

and were computed for the second-to-highest load level. These values are highlighted in Table 2.

Table 2 Per Unit Variation in Load Assumed for the Month of January 2009

Area Per-Unit Variation in Load

Q 1.0940 1.0705 1.0470 1.0000 0.9530 0.9295 0.9060

MT 1.1000 1.1000 1.0500 1.0000 0.9500 0.9000 0.9000

NE 1.2295 1.0967 0.992 0.9106 0.8706 0.8352 0.8266

NY 1.0430 1.0310 1.0160 0.9980 0.9750 0.9440 0.9050

ON 1.0680 1.0453 1.0227 1.0000 0.9773 0.9547 0.9320

Prob. 0.0062 0.0606 0.2417 0.3830 0.2417 0.0606 0.0062 Generation Tables 3 (a) and 3 (b) summarize the winter 2008/09 capacity assumptions for the NPCC Areas used in the analysis for the Base Case and the Severe Case Scenario, respectively. Base Case conditions were chosen to be consistent with the assumptions used in the companion report by the NPCC CO-12 Working Group, "NPCC Reliability Assessment for Winter 2008 - 09", November 2008.

Table 3 (a) NPCC Capacity and Load Assumptions for January 2009 - MW

Base Case - Expected Load

Q MT NE NY ON

Assumed Capacity 37,846 6,998 34,214 42,110 32,300

Purchase/Sale 307 0 80 1,132 0 Peak Load 3 35,887 5,336 23,030 24,940 23,708

Reserve (%) 6 31 49 73 36 Annual Weighted Average Unit Availability (%)

95.70 88.50 89.44 87.58 81.92

Scheduled Maintenance 4 - 658 47 1,231 719

3 Based on 2003/04 Load Shape assumption. 4 Maintenance shown is for the week of the monthly peak load. Maritimes value due solely to Point

Lepreau refurbishment.

Page 13: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 11 Final Report

Table 3 (b) NPCC Capacity and Load Assumptions for January 2009 - MW

Severe Assumptions Scenario - Extreme Load Q MT NE NY ON

Assumed Capacity 37,133 6,434 28,994 42,110 30,568

Purchase/Sale 307 0 80 1,132 0

Peak Load 3 38,417 5,870 25,257 25,713 24,782

Reserve (%) -3 10 15 68 23 Scheduled Maintenance 4 658 843 2,264 719

Unit Availability Details regarding the NPCC Area’s assumptions for generator unit availability are described in the respective Area’s most recent "NPCC Comprehensive Review of Resource Adequacy" 5 In addition, the following Areas provided the following: Québec The planned outages for the winter period are reflected in this assessment. The volume of planned outages is consistent with historical volumes. Ontario Ontario’s generating unit availability was modeled as described in the September 23, 2008 “18-Month Outlook: An Assessment of the Reliability of the Ontario Electricity System From October 2008 to March 2010." 6 Ontario market participants provided the majority of generation data. F.O.R. and P.O.R. were based on forecast values for generating units, which reflect past experience and future expectations based on recent maintenance activities. However, for some of the generating units F.O.R. and P.O.R. values were based on North American Reliability Council (NERC) Generator Availability Data System 7 (GADs) data for similar type units. New England This probabilistic assessment reflects New England generating unit availability assumptions 8 based upon historical performance over the prior five-year period. Unit

5 See: https://www.npcc.org/adequacy.cfm 6 See: http://www.ieso.ca/imoweb/pubs/marketReports/18MonthOutlook_2008sep.pdf 7 See: http://www.nerc.com/page.php?cid=4|43 8 See: http://www.iso-ne.com/genrtion_resrcs/reports/nepool_oc_review/

Page 14: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 12 Final Report

availability modeled reflects the projected scheduled maintenance and forced outages. Individual generating unit maintenance assumptions are based upon each unit’s historical five-year average of scheduled maintenance. Individual generating unit forced outage assumptions were based on the unit’s historical data and North American Reliability Council (NERC) average data for the same class of unit. In the previous years’ reliability assessments, generating unit Equivalent Forced Outage Rate (EFOR) were used to represent the forced unavailability of the generating units. In this assessment, Equivalent Forced Outage Rate Demand (EFORd) was used to represent the forced unavailability of the units. New York Detailed availability assumptions used for the New York units can be found in the New York ISO February 28, 2008 report 9 - "Locational Installed Capacity Requirements Study covering the New York Control Area for the 2008 – 2009 Capability Year" and the “New York Control Area Installed Capacity Requirement for the Period May 2008 – April 2009” New York State Reliability Council, December 14, 2007 report. 10 Transfer Limits Figure 2 depicts the system that was represented in this Assessment, showing Area and assumed Base Case transfer limits for the winter 2008/09 period. New York Area internal transmission representation was consistent with the assumptions used in the New York ISO February 28, 2008 report 9 - "Locational Installed Capacity Requirements Study covering the New York Control Area for the 2008 – 2009 Capability Year" and the “New York Control Area Installed Capacity Requirement for the Period May 2008 – April 2009” New York State Reliability Council, December 14, 2007 report .10

New England internal transmission representation was consistent with the assumptions detailed in the 2008 Regional System Plan, ISO-NE, October 16, 2008.11

9 See: http://www.nyiso.com/public/webdocs/services/planning/resource_adequacy/LCR_report_2_28_08.pdf 10 See: http://www.nysrc.org/pdf/Reports/Final%202008%20IRM%20Report%2012-14-07%20_2_.pdf 11 See: http://www.iso-ne.com/trans/rsp/2008/rsp08_final_101608_public_version.pdf

Page 15: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 13 Final Report

Figure 2 - Assumed Transfer Limits Between Areas 12, 13 Tie transfer limits between Areas are indicated in Figure 2 with seasonal ratings (S- summer, W- winter) where appropriate. The acronyms and notes used in Figure 2 are defined as follows: Chur - Churchill Falls NOR - Norwalk – Stamford RFC - ReliabilityFirst Corp. MANIT - Manitoba BHE - Bangor Hydro Electric NB - New Brunswick ND - Nicolet-Des Cantons Mtl - Montréal PEI - Prince Edward Island BJ - Bay James C MA - Central MA CT - Connecticut MAN - Manicouagan W MA - Western MA NS - Nova Scotia NE - Northeast (Ontario) NBM - Millbank NW - Northwest (Ontario) MRO - Midwest Reliability VT - Vermont RFC - ReliabilityFirst Corp.

Organization Que - Québec Centre CSC - Cross Sound Cable NM - Northern Maine Centre 12 Phase angle regulators (PARs) are installed on three of the four Michigan - Ontario interconnections.

One PAR, on the Keith-Waterman 230 kV circuit J5D has been in service and regulating since 1975. The other two available PARs, on the Lambton-St. Clair circuits L51D and L4D, were placed in service on April 14, 2008, however, the PARs have been bypassed pending completion of agreements between the IESO, the Midwest ISO, Hydro One and International Transmission Company. The expected in service date is not known at the time of this report. The operation of the phase angle regulators will assist in the management of circulating flows. The fourth PAR, on 230 kV circuit B3N (Scott-Bunce Creek), is not expected to be available for service during the Winter Operating Period 2008-09. This PAR is located in Michigan at the Bunce Creek terminal of B3N.

13 If necessary, transmission congestion between generation in New Brunswick and load in Northern Maine can be overcome by switching additional load in Northern Maine to be radially served from the New Brunswick grid.

AC

D

FG

J

K

1,000 S 1,100 W

485 S 520 W

250

200

12,100

300 222

1,800

200

1,400

550

1,000

150

2,000

5,200

1,520 S 1,600 W

1,350

330 S400 W

1,000

1,500

2,080 S 2,400 W

800600

800

800

Total NY-NE(Excludes

CSC)

286

2,000

500

0

1,200RFC

-

NM

6,500

5,500

1,200 S0 W

124 350

NOR

CT

W-MA

BHE

CMA MRO - US

MANIT

140

90

325 375

330

VT

65 S 85 W

95 S110 W

NW West

Niagara

NE Ottawa

East 800

673 S 748 W

147 S167 W

420 S470 W

Total Ontario 4,000 In

5,550 Out-S 5,900 Out-W

0

1,640 S 1,800 W

330 S 342 W

262 S 274 W

West

Cent.

East

5,700 6,5008,400

(06/09)

550

300

9999

800

NY

ON MT

QB

NE

PJM-RTO

JB

ND

SW

Cent.

Chur.

CN

14,1000

17,900

100

200

200

810

1,015

7,500

7,5008,400 (06/09)

1,200 S1,325

W

1,525 S 1,600 W

660

PJM-SW

7,500

3,000

RFC + NY1330

3,000

7,500 1,000

330

0

1,200

300 S 360 W

NSPEI

NBM

NB

1,475 10,000

1,500

2,000

Page 16: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 14 Final Report

Operating Procedures to Mitigate Resource Shortages Each Area takes defined steps as their reserve levels approach critical levels. These steps consist of those load control and generation supplements that can be implemented before load has to be actually disconnected. Load control measures could include disconnecting interruptible loads, public appeals to reduce demand, and voltage reductions. Other measures could include calling on generation available under emergency conditions, and/or reduced operating reserves. The need for an Area to begin these operating procedures is modeled in MARS by evaluating the daily Loss of Load Expectation (LOLE) at specified margin states. The user specifies these margin states for each area in terms of the benefits realized from each emergency measure, which can be expressed in MW, as a per unit of the original or modified load, and as a per unit of the available capacity for the hour. Table 4 summarizes the load relief assumptions modeled for each NPCC Area. The Working Group recognizes that Areas may invoke these actions in any order, depending on the situation faced at the time; however, it was agreed that modeling the actions as in the order indicated in Table 4 was a reasonable approximation for this analysis.

Table 4

NPCC Operating Procedures to Mitigate Resource Shortages 2008/09 Winter Load Relief Assumptions - MW

Actions Q MT NE NY ON 1. Curtail Load / Utility Surplus Appeals LRP/SCR/EDRP EDRP & Manual Volt. Red.

975 - - - -

- - - - -

- - -

1,128 -

- - -

1,066 5.26% of load

154 1% of

load - -

2. No 30-min Reserves 500 229 1,185 600 473 3. Voltage Reduction or

Interruptible Loads * ELRP

250

-

509

-

2.18% of load

-

1.64% of load

-

1.50% of load

179 4. No 10-min Reserves General Public Appeals

750 -

593 -

1,000 -

- 217

945 -

5. EDRP 5% Voltage Reduction No 10-min Reserves

-

-

-

-

-

-

-

1,200

109 1.10%

of load -

* Interruptible Loads for Maritimes Area (implemented only for this Area), Voltage Reduction for all others

Page 17: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 15 Final Report

Assistance Priority Table 5 indicates the priority order followed when allocating reserves and assistance to Control Areas with a resource deficiency. In this analysis, each step was initiated simultaneously in all Areas and sub-Areas.

Table 5

Priority Order for Providing Emergency Assistance

Priority of Assistance Area Providing Assistance 1ST 2ND

Millbank Units Q MT Modeling of Neighboring Regions For the scenarios studied, a detailed representation of the neighboring regions of RFC (ReliabilityFirst Corp.) and the MRO-US (Midwest Reliability Organization – US portion) was assumed. The assumptions are summarized in Table 6.

Table 6

PJM, RFC-OTH, and MRO 2008/09 Base Case Assumptions 14

PJM RFC-OTH MRO

Peak Load (MW) 115,784 82,489 26,614

Peak Month January January December

Assumed Capacity (MW) 159,229 134,721 38,231

Purchase/Sale (MW) -1,111 0 0

Reserve (%) 37 63 44

Weighted Unit Availability (%) 88.32 87.77 88.63

Operating Reserves (MW) 3,400 2,206 1,700

Curtailable Load (MW) 2,144 2,000 1,666

No 30-min Reserves (MW) 2,099 1,470 1,200

Voltage Reduction (MW) 2,201 0 1,100

No 10-min Reserves (MW) 1,300 736 500

Appeals (MW) 400 0 200

Load Forecast Uncertainty (%) 93.66 +/- 5.5, 11.0, 16.5

91.83 +/- 7.0, 14.0, 21.0

92.75 +/- 6.2, 12.4, 18.7

Figure 3 shows the 2008/09 Projected Monthly Expected Peak Loads for NPCC, RFC, PJM and the MRO for the 2003/04 Load Shape.

14 Load and capacity assumptions based, in part, on NERC’s Electricity and Supply Database (ES&D)

available at: www.nerc.com/~esd/.

Page 18: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 16 Final Report

Figure 3 - 2008/09 Projected Monthly Expected Peak Loads for NPCC, RFC, PJM and the

MRO (2003/04 Load Shape)

2008/09 Projected Coincident Monthly Peak Loads - MW2003/04 Load Shape

0

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

MW

NPCC PJM RFC-OTH MRO

Page 19: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 17 Final Report

Winter 2007/08 Summary Major Highlights The average temperature across both the contiguous U.S. and the globe during December 2007-February 2008 (climatological boreal winter) was the coolest since 2001, according to scientists at NOAA's National Climatic Data Center in Asheville, N.C. 15 In terms of winter precipitation, Pacific storms brought heavy precipitation to large parts of the Western U.S. U.S. Winter Temperature Highlights In the contiguous United States, the average winter temperature was 33.2°F (0.6°C), which was 0.2°F (0.1°C) above the 20th century average - yet still ranks as the coolest since 2001. It was the 54th coolest winter since national records began in 1895. Winter temperatures were warmer than average from Texas to the Southeast and along the Eastern Seaboard, while cooler-than-average temperatures stretched from much of the upper Midwest to the West Coast. With higher-than-average temperatures in the Northeast and South, the contiguous U.S. winter temperature-related energy demand was approximately 1.7 percent lower than average, based on NOAA's Residential Energy Demand Temperature Index. Northeast Winter Precipitation Highlights Record February precipitation in the Northeast helped make the winter the fifth wettest on record for the region. New York had its wettest winter, while Pennsylvania, Connecticut, Vermont, and Colorado to the West, had their second wettest. Snowfall was above normal in northern New England, where some locations posted all-time record winter snow totals. Concord, N.Y., received 100.1 inches, which was 22.1 inches above the previous record set during the winter of 1886-87. Burlington, VT., received 103.2 inches, which was 6.3 inches above the previous record set during the winter of 1970-71. January Temperature Highlights For the contiguous United States, the average temperature was 30.5°F (-0.83°C) for January, which was 0.3°F (0.2°C) below the 20th century mean and the 49th coolest January on record, based on preliminary data. The Northeast region had its 20th warmest January on record, the middle part of the country experienced near-normal average temperatures, and the far western regions (Southwest, West and Northwest regions) experienced cooler than average temperatures for the month. The anomalous warmth in the Northeast reduced energy demand for heating and helped keep the nation's overall temperature-related residential energy demand near average. Based on NOAA's Residential Energy Demand Temperature Index, contiguous U.S.

15 See: http://www.ncdc.noaa.gov/oa/climate/research/2008/feb/feb08.html

Page 20: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 18 Final Report

temperature-related energy demand was approximately 1 percent below average in January. February Temperature Highlights February was 61st warmest in the contiguous U.S. and 15th warmest globally on record. For the U.S., the temperature was near average, 0.2°F (0.1°C) above the 20th century average of 34.7°F (1.5°C), which was 2.0°F (1.1°C) warmer than February 2007. Globally, the February average temperature was 0.68°F/0.38°C above the 20th century mean of 53.8°F/12.1°C. During the 2007 – 2008 Winter period, ISO-NE instituted Operating Procedure 4 16 (OP 4) Action 6 (begin depletion of 30-minute reserves) on December 1, 2007 due to a combination of higher than forecast loads, higher than expected external sales and higher than expected generator outages. In addition, on December 2nd, OP 4 Actions were implemented locally within Maine due to gas supply issues causing approximately 1,200 MW of generator reductions in Maine. The previous analysis of the 2007-2008 winter period by the CP-8 Working Group 17 estimated less than one occurrence of the use of operating procedures for New England.

16 See: http://www.iso-ne.com/rules_proceds/operating/isone/op4/index.html 17 See: http://www.npcc.org/documents/reports/Seasonal.aspx

Page 21: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 19 Final Report

ANALYSIS

Winter 2008/09 Results Base Case Scenario Table 7 (see Appendix B) shows the estimated need for the indicated operating procedures (in days/period) for November 2008 through March 2009 period for the Base Case assumptions for all NPCC Areas for the 2003/04 load shape assumptions. Only the Maritimes Area is expected to need to use these procedures in response to a capacity deficiency for this Scenario. Figure 4 shows the indicated operating procedures occurrences for the NPCC Areas for the expected load (the expected load level results were based on the probability-weighted average of the seven load levels simulated) for the Base Case assumptions. Figure 5 shows the corresponding results for the extreme load (representing the second to highest load level, having approximately a 6% chance of being exceeded).

Figure 4 Winter 2008/09 – Estimated Use of the Indicated Operating Procedures

Base Case Assumptions, Expected Load Level (November 2008 – March 2009)

Maritimes Area initiates interruptible loads instead of voltage reduction

0

1

2

Estimated Number of

Occurrences (days/period)

NE NY ON MT Q

Reduce 30-min ReserveVoltage ReductionReduce 10-min ReserveAppealsDisconnect Load

Maritimes Area initiates interruptible loads instead of voltage reduction

Page 22: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 20 Final Report

Figure 5 Winter 2008/09 – Estimated Use of the Indicated Operating Procedures

Base Case Assumptions, Extreme Load Level (November 2008 – March 2009)

The following summary of Base Case assumptions represents system conditions consistent with those assumed in the NPCC CO-12 Working Group's "NPCC Reliability Assessment for Winter 2008 - 09", November 2008. The Base Case assumptions are summarized below: NPCC System

As-Is System for the 2008/09 period Transfers allowed between Areas No imports from Manitoba or Minnesota 2003/04 Load Shape adjusted to Area’s latest forecast expected and extreme

assumptions 18 Ontario

Based on IESO “18-Month Outlook: An Assessment of the Reliability of the Ontario Electricity System” (September 23, 2008). 6

Maritimes

No fuel disruptions assumed Pt. Lepreau scheduled outage through October 2009

New England

~225 MW capacity additions by December, 2008 18 The 2003/04 load shape represents a weather pattern that includes a consecutive period of cold days.

02468

101214

Estimated Number of

Occurrences (days/period)

NE NY ON MT Q

Reduce 30-min ReserveVoltage ReductionReduce 10-min ReserveAppealsDisconnect Load

Maritimes Area initiates interruptible loads instead of voltage reduction

Page 23: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 21 Final Report

New York All Long Island cables in-service 30 MW of planned uprate for Gilboa unit 1 6.4 MW uprate of high Acres 17.4 MW of new methane units 292 MW (nameplate) of new wind units upstate (Noble Wind Farms) 19 263.5 MW of retirements Upstate ~ 1,565 MW (ICAP value) of load reduction due to SCR Program (winter value)

Québec

Entire Peribonka Hydro Power Plant (408 MW) in-service Chute–Allard Hydro Power Plant (62 MW) : commissioning of the first unit was

held on July 2008 and the last of the total of six units will be held on the end of May 2009

In the same manner, the first unit of Rapides-Des-Coeurs Hydro Power Plant (76 MW) is in-service on October 2008 and the last unit is expected to be in service on June 2009

In service a wind unit in Gaspesia for 109.5 MW; Economic shutdown (Reserve Shutdown) of a unit of natural gas (Bécancour -

547 MW) until January 2010 Retirement of a jet fuel unit (Cadillac 162 MW)

PJM-RTO

As-Is System for the 2008/09 period, consistent with PJM’s 2008 Reserve Requirement Study Report 20

2003-04 Load Shapes adjusted to the latest forecast & load forecast uncertainty provided by PJM

Operating Reserve ~3,400 MW (30-min.~ 2,099 MW; 10-min. ~ 1,300 MW) RFC ‘Other’

As-Is System for the 2008/09 period 2003-04 Load Shapes adjusted to the latest forecast & load forecast uncertainty

provided by PJM Operating Reserve ~2,206 MW (30-min. ~ 1,470 MW; 10-min. ~ 736 MW)

MRO-US

As-Is System for the 2008/09 period 2003-04 Load Shapes adjusted to the latest forecast & load forecast uncertainty

provided by PJM Operating Reserve ~1,700 MW (30-min ~ 1,200 MW; ~ 10-min. 500 MW)

19 Represents 84.8 MW assuming a 30% capacity value 20 See: http://www.pjm.com/committees/planning/downloads/20081015-item-04-2008-pjm-reserve-requirement-study.pdf

Page 24: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 22 Final Report

Québec Load management programs are discounted to reflect operational constraints such as number of interruptions per day, week or year. Hydroelectric unit capacity is adjusted to reflect the impact of reservoir level on the head available. Unit capacity is also discounted to take into account operational restrictions such as ice cover formation, run-of -river conditions. New York The Base Case assumes that the New York City and Long Island localities will meet their locational installed capacity requirements as described in the February 28, 2008 New York ISO report - "Locational Installed Capacity Requirements Study covering the New York Control Area for the 2008 – 2009 Capability Year" 9 and New York State will meet the capacity requirements described in the “New York Control Area Installed Capacity Requirement for the Period May 2008 – April 2009” New York State Reliability Council, December 14, 2007 report. 10 The New York unit ratings were obtained from the “2008 Load & Capacity Data of the NYISO” (Gold Book 21). All in-service New York generation resources were modeled. Special Case Resources and Emergency Demand Response Programs Special Case Resources (SCRs) are loads capable of being interrupted on demand, and distributed generators, rated 100 kW or higher, that are not directly telemetered. SCRs are ICAP resources that only provide energy/load curtailment when activated in accordance with the NYISO Emergency Operating Manual. The Emergency Demand Response Program (EDRP) is a separate program that allows registered interruptible loads and standby generators to participate on a voluntary basis, and be paid for their ability to restore operating reserves.

For December, the New York ISO recommended that the SCR programs be modeled as a 929 MW operating procedure step; the EDRPs were modeled as a 137 MW operating procedure with a limit of five calls per month. The amounts modeled in other months vary proportionally to the monthly peak load.

Since customer participation in these programs varies over time, it is recognized that the actual amount of SCR/EDRP resources available for this winter may be different than the amount assumed in this study. The New York ISO believes the values modeled in this study represent a reasonable approximation for this analysis.

21 See: http://www.nyiso.com/public/webdocs/services/planning/planning_data_reference_documents/2008_goldbook.pdf

Page 25: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 23 Final Report

New England The New England generating unit’s ratings were consistent with those published in the “NEPOOL 2007-2012 Forecast Report of Capacity, Energy, Loads and Transmission” (CELT Report) April 2008. 22 All in-service New England generation resources were modeled. Demand Response Program (DRP) It is anticipated that the New England DRP 23 program will provide additional load relief utilizing market mechanisms in the New England System. As of October 1, 2008 there were 3,019 assets registered in the Demand Response program representing approximately 1,951 MW of possible load relief.

For this study, ISO-NE has assumed a total of 1,128 MW under the ISO-NE Load Response Program. As NEPOOL Participants continue to sign up additional resources under the DRP, it is recognized that the actual amount of DRP resources may be different than the amount assumed in this study. ISO-NE believes the value modeled in this study represents a reasonable approximation for this analysis.

Ontario For the purposes of this study, the Base Case assumptions for Ontario are consistent with the IESO “18-Month Outlook: An Assessment of the Reliability of the Ontario Electricity System” (dated September 23, 2008, available from the IESO web site). 6 All in-service Ontario generation resources were modeled. Price sensitive demand response is assumed to be 527 MW during the study period.

Severe Case Scenario Table 8 (see Appendix B) shows the estimated need for the indicated operating procedures (in days/period) during November 2008 through March 2009 period for the Severe Case Scenario for all NPCC Areas for the 2003/04 load shape assumptions, respectively. Only the Maritimes Area is expected to need to use these procedures in response to a capacity deficiency for this Scenario. Figure 6 shows the indicated operating procedures occurrences for the NPCC Areas for the expected load (the expected load level results were based on the probability-weighted average of the seven load levels simulated) for the Severe Case assumptions.

22 See: http://www.iso-ne.com/trans/celt/report/2008/ 23 See page 24: http://www.iso-ne.com/committees/comm_wkgrps/prtcpnts_comm/prtcpnts/mtrls/2008/oct102008/nepool_committee_meeting_october_10_2008.pdf

Page 26: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 24 Final Report

Figure 6 Winter 2008/09 – Estimated Use of the Indicated Operating Procedures

Severe Case Assumptions, Expected Load Level (November 2008 – March 2009)

Figure 7 shows the estimated use of the indicated operating procedures under the Severe Case assumptions for the extreme load level (representing the second to highest load level, having approximately a 6% chance of being exceeded) for the week with the highest risk.

Figure 7 Winter 2008/09 – Estimated Use of the Indicated Operating Procedures Severe Case Assumptions, Extreme Load Level – week of highest risk

(November 2008 – March 2009)

0123456

Estimated Number of

Occurrences (days/period)

NE NY ON MT Q

Reduce 30-min ReserveVoltage ReductionReduce 10-min ReserveAppealsDisconnect Load

Maritimes Area initiates interruptible loads instead of voltage reduction

0

2

4

6

Estimated Number of

Occurrences (days/weekof highest

risk)

NE NY ON MT Q

Reduce 30-min ReserveVoltage ReductionReduce 10-min ReserveAppealsDisconnect Load

Maritimes Area initiates interruptible loads instead of voltage reduction

Page 27: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 25 Final Report

The Severe Case Scenario assumptions are summarized below: NPCC System

As-Is System for the 2008/09 period Transfers allowed between Areas Transfer capability between Ontario and Michigan reduced by 50% No imports from Manitoba or Minnesota 2003/04 Load Shape adjusted to Area’s latest forecast 18 expected and extreme

assumptions Ontario

Planned outage returns delayed by 6 weeks (~ 750 MW reduction) Additional dispatchable demand participation does not materialize for winter peak 10% lower hydroelectric capacity and energy assumed

Maritimes

No generation capacity from wind resources in January and February Natural gas units (without dual-fuel capability) unavailable during the months of

January and February (~ 459 MW) New England

~225 MW capacity additions delayed Scheduled maintenance overrun by 4 weeks Gas-Fired only capacity not having firm pipeline transportation contracts assumed

unavailable (~ 5,000 MW) New York

1,000 MW on extended maintenance in the Lower Hudson valley Québec

Chutes-Allard (62 MW) and rapides-Des_Coeurs ( 76 MW) Hydro Power plant are assumed to be not present during the Peak Winter demand

Late return from maintenance for the nuclear unit (Gentilly 2 - 647 MW) in March 2009

PJM-RTO

Gas-Fired only capacity not having firm pipeline transportation, assumed unavailable – ~ 4,200 MW

Increased load forecast uncertainty provided by PJM Ice Storm; ice blocking fuel delivery to all units. ~ 8,400 MW

Page 28: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 26 Final Report

Conclusions Use of operating procedures designed to mitigate resource shortages (specifically, reducing 30-minute reserve, voltage reduction, reducing 10-minute reserve, and public appeals) is not expected for Québec, Ontario, New England, and New York, during the 2008/09 winter period for the expected load level under both the assumed Base and Severe Case conditions. The expected load level results were based on the probability-weighted average of the seven load levels simulated. For the Maritimes Area there is an expectation for reducing 30-minute reserves and calling on interruptible loads in response to a capacity deficiency this winter for the expected load level under the Base Case assumptions. This expectation increases for the Severe Case assumptions for the expected load level For the week with the highest risk in the November 2008 to March 2009 time period, New England, the Maritimes, and to lesser extent, Ontario may need to rely on their Operating Procedures under the Severe Case, extreme load assumptions (representing the second to highest load level, having approximately a 6% chance of being exceeded).

Page 29: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 27 Final Report

APPENDIX A

Objective and Scope of Work 1. Objective

Using the G.E. Multi-Area Reliability Simulation (MARS) program, review NPCC Area reliability resulting from the anticipated resource and transmission capacity reported for the 2008 – 2009 winter period under Base Case and Severe Case assumptions, and summarize the range of results for the winter and shoulder season months (the period from November 2008 to March 2009).

2. Scope

In meeting this objective, the CP-8 Working Group will review the short-term resource adequacy of NPCC and neighboring regions for the 2008 and 2009 winter period, recognizing uncertainty in forecasted demand, scheduled outages of transmission, forced and scheduled outages of generation facilities, including fuel supply disruptions, and the impact of proposed load response programs. Reliability will be measured by calculating the Loss of Load Expectation (LOLE) and estimated use of Area operating procedures used to mitigate resource shortages. A report summarizing the results of the assessment will be published no later than November 24, 2008. The assessment will: 1. Review last winter’s CP-8 Working Group Winter assessment with

respect to actual NPCC Area’s experience;

2. Consider the impacts of Sub-Area transmission constraints;

3. Incorporate, to the extent possible, a detailed GE MARS reliability representation for the regions bordering NPCC;

4. Coordinate assessment assumptions with the NPCC Task Force on Coordination of Operations (CO-12 Working Group); and,

5. Examine any impact of evolving market rules on overall NPCC interconnection assistance and other assumptions.

Page 30: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 28 Final Report

APPENDIX B

Table 7 - Base Case Assumptions (2003/04 Load Shape Assumption) Expected Need for Indicated Operating Procedures (days/period)

(Occurrences 0.5 or greater are highlighted)

Base Case Québec Maritimes Area New England New York Ontario 30-min VR 10-min Appeal 30-min IL 10-min Appeal 30-min VR 10-min Appeal Disc 30-min VR Appeal 10-min Disc 30-min VR 10-min Appeal /Disc /Disc /Disc 03/04 Load Shape-Expected Load

Nov - - - - 0.006 0.001 - - - - - - - - - - - - - - - - Dec - - - - 0.669 0.246 - - 0.001 - - - - - - - - - - - - - Jan 0.005 0.001 - - 0.247 0.119 - - - - - - - - - - - - 0.004 0.001 - - Feb - - - - 0.184 0.080 - - - - - - - - - - - - - - - - Mar - - - - 0.180 0.065 - - - - - - - - - - - - - - - -

Nov-Mar 0.005 0.001 - - 1.286 0.511 - - 0.001 - - - - - - - - - 0.004 0.001 - - 03/04 Load Shape-Extreme Load

Nov - - - - 0.074 0.019 - - - - - - - - - - - - - - - - Dec - - - - 6.554 2.459 - - 0.005 0.001 0.001 - - - - - - - - - - - Jan 0.041 0.009 0.003 - 1.981 1.213 0.001 - - - - - - - - - - - 0.028 0.005 0.004 - Feb 0.002 - - - 1.767 0.867 - - - - - - - - - - - - - - - - Mar - - - - 1.645 0.624 - - - - - - - - - - - - - - - -

Nov-Mar 0.043 0.009 0.003 - 12.021 5.182 0.001 - 0.005 0.001 0.001 - - - - - - - 0.028 0.005 0.004 - Notes: "30-min" - reduce 30-minute Reserve Requirement; "VR" - and initiate Voltage Reduction (" IL" - Interruptible Loads for the Maritimes Area);

"10-min" - and reduce 10-minute Reserve Requirement; "Appeal" - and initiate General Public Appeals; "Disc" - and disconnect customer load.

Page 31: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved - November 19, 2008 29 Final Report

APPENDIX B

Table 8 - Severe Case Scenario (2003/04 Load Shape Assumption) - Expected Need for Indicated Operating Procedures (days/period)

(Occurrences 0.5 or greater are highlighted)

Severe Case Results Québec Maritimes Area New England New York Ontario

30-min VR 10-min Apl Disc 30-min IL 10-min Apl Disc 30-min VR 10-min Apl Disc 30-min VR Apl 10-min Disc 30-min VR 10-min Apl Disc

03/04 Load Shape-Expected Load

Nov - - - - 0.006 0.001 - - - 0.005 - - - - - - - - - - - - - - Dec - - - - 0.670 0.247 - - - 0.444 0.229 0.141 0.042 0.042 - - - - - 0.073 0.037 0.023 0.010 0.009 Jan 0.065 0.018 0.007 0.001 0.001 1.839 1.044 0.003 - - 0.015 0.005 0.002 - - - - - - - 0.063 0.018 0.007 0.001 0.001 Feb 0.002 - - - - 1.144 0.602 - - - - - - - - - - - - - 0.001 - - - - Mar - - - - - 0.180 0.065 - - - - - - - - - - - - - - - - - -

Nov-Mar 0.067 0.018 0.007 0.001 0.001 3.839 1.959 0.003 - - 0.464 0.234 0.143 0.042 0.042 - - - - - 0.137 0.055 0.030 0.011 0.010 03/04 Load ShapeExtreme Load

Nov - - - - - 0.074 0.019 - - 0.011 - - - - - - - - - - - - - - Dec 0.001 - - - - 6.561 2.460 - - - 5.075 2.419 1.172 0.083 0.081 - - - - - 0.776 0.360 0.189 0.023 0.021 Jan 0.621 0.141 0.045 0.005 0.005 9.444 6.543 0.027 - - 0.010 - - - - - - - - - 0.636 0.148 0.043 0.007 0.005 Feb 0.013 0.002 0.002 - - 7.682 4.048 0.004 - - - - - - - - - - - - 0.006 - - - - Mar - - - - - 1.645 0.624 - - - - - - - - - - - - - - - - - -

Nov-Mar 0.635 0.143 0.047 0.005 0.005 25.406 13.694 0.031 - - 5.096 2.419 1.172 0.083 0.081 - - - - - 1.418 0.508 0.232 0.030 0.026 Notes: "30-min"- reduce 30-minute Reserve Requirement; "VR" - and initiate Voltage Reduction (" IL" - Interruptible Loads for the Maritimes Area); "10-min" - and reduce 10-minute Reserve Requirement; "Apl" - and initiate General Public Appeals; "Disc" - and disconnect customer load.

Page 32: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved – November 19, 2008 30 Final Report

APPENDIX C

Multi-Area Reliability Simulation Program Description

General Electric’s Multi-Area Reliability Simulation (MARS) program 24 allows assessment of the reliability of a generation system comprised of any number of interconnected areas. Modeling Technique A sequential Monte Carlo simulation forms the basis for MARS. The Monte Carlo method allows for many different types of generation and demand-side options. In the sequential Monte Carlo simulation, chronological system histories are developed by combining randomly generated operating histories of the generating units with the inter-area transfer limits and the hourly chronological loads. Consequently, the system can be modeled in great detail with accurate recognition of random events, such as equipment failures, as well as deterministic rules and policies that govern system operation. Reliability Indices The following reliability indices are available on both an isolated (zero ties between areas) and interconnected (using the input tie ratings between areas) basis:

. Daily Loss of Load Expectation (LOLE - days/year)

. Hourly LOLE (hours/year)

. Loss of Energy Expectation (LOEE -MWh/year)

. Frequency of outage (outages/year)

. Duration of outage (hours/outage)

. Need for initiating Operating Procedures (days/year or days/period)

The Working Group used both the daily LOLE and Operating Procedure indices for this analysis.

The use of Monte Carlo simulation allows for the calculation of probability distributions, in addition to expected values, for all of the reliability indices. These values can be calculated both with and without load forecast uncertainty. The MARS program probabilistically models uncertainty in forecast load and generator unit availability. The program calculates expected values of Loss of Load Expectation (LOLE) and can estimate each Area's expected exposure to their Emergency Operating Procedures. Scenario analysis is used to study the impacts of extreme weather conditions, variations in expected unit in-service dates, overruns in planned scheduled maintenance, or transmission limitations. Resource Allocation Among Areas The first step in calculating the reliability indices is to compute the Area margins on an isolated basis, for each hour. This is done by subtracting from the total available capacity in the Area for the hour the load demand for the hour. If an Area has a positive or zero margin, then it has sufficient capacity to meet its load. If the Area margin is negative, the load exceeds the capacity available to serve it, and the area is in a loss-of-load situation. 24 See: http://www.gepower.com/prod_serv/products/utility_software/en/ge_mars.htm

Page 33: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved – November 19, 2008 31 Final Report

APPENDIX C If there are any Areas that have a negative margin after the isolated Area margins have been adjusted for curtailable contracts, the program will attempt to satisfy those deficiencies with capacity from Areas that have positive margins. Two methods are available for determining how the reserves from Areas with excess capacity are allocated among the Areas that are deficient. In the first approach, the user specifies the order in which an Area with excess resources provides assistance to areas that are deficient. The second method shares the available excess reserves among the deficient Areas in proportion to the size of their shortfalls. The user can also specify that areas within a pool will have priority over outside Areas. In this case, an Area must assist all deficient areas within the same pool, regardless of the order of areas in the priority list, before assisting Areas outside of the pool. Pool-sharing agreements can also be modeled in which pools provide assistance to other pools according to a specified order. Generation MARS has the capability to model the following different types of resources:

. Thermal

. Energy-limited

. Cogeneration

. Energy-storage

. Demand-side management

An energy-limited unit can be modeled stochastically as a thermal unit with an energy probability distribution (Type 1 energy-limited unit), or deterministically as a load modifier (Type 2 energy-limited unit). Cogeneration units are modeled as thermal units with an associated hourly load demand. Energy-storage and demand-side management impacts are modeled as load modifiers. For each unit modeled, the installation and retirement dates and planned maintenance requirements are specified. Other data such as maximum rating, available capacity states, state transition rates, and net modification of the hourly loads are input depending on the unit type. The planned outages for all types of units in MARS can be specified by the user or automatically scheduled by the program on a weekly basis. The program schedules planned maintenance to levelize reserves on either an area, pool, or system basis. MARS also has the option of reading a maintenance schedule developed by a previous run and modifying it as specified by the user through any of the maintenance input data. This schedule can then be saved for use by subsequent runs. Thermal Units In addition to the data described previously, thermal units (including Type 1 energy-limited units and cogeneration) require data describing the available capacity states in which the unit can operate. This is input by specifying the maximum rating of each unit and the rating of each capacity state as a per unit of the unit's maximum rating. A maximum of eleven capacity states are allowed for each unit, representing decreasing amounts of available capacity as governed by the outages of various unit components.

Page 34: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved – November 19, 2008 32 Final Report

APPENDIX C Because MARS is based on a sequential Monte Carlo simulation, it uses state transition rates, rather than state probabilities, to describe the random forced outages of the thermal units. State probabilities give the probability of a unit being in a given capacity state at any particular time, and can be used if you assume that the unit's capacity state for a given hour is independent of its state at any other hour. Sequential Monte Carlo simulation recognizes the fact that a unit's capacity state in a given hour is dependent on its state in previous hours and influences its state in future hours. It thus requires the additional information that is contained in the transition rate data. For each unit, a transition rate matrix is input that shows the transition rates to go from each capacity state to each other capacity state. The transition rate from state A to state B is defined as the number of transitions from A to B per unit of time in state A: Number of Transitions from A to B TR (A to B) = _____________________________

Total Time in State A If detailed transition rate data for the units is not available, MARS can approximate the transition rates from the partial forced outage rates and an assumed number of transitions between pairs of capacity states. Transition rates calculated in this manner will give accurate results for LOLE and LOEE, but it is important to remember that the assumed number of transitions between states will have an impact on the time-correlated indices such as frequency and duration. Energy-Limited Units Type 1 energy-limited units are modeled as thermal units whose capacity is limited on a random basis for reasons other than the forced outages on the unit. This unit type can be used to model a thermal unit whose operation may be restricted due to the unavailability of fuel, or a hydro unit with limited water availability. It can also be used to model technologies such as wind or solar; the capacity may be available but the energy output is limited by weather conditions. Type 2 energy-limited units are modeled as deterministic load modifiers. They are typically used to model conventional hydro units for which the available water is assumed to be known with little or no uncertainty. This type can also be used to model certain types of contracts. A Type 2 energy-limited unit is described by specifying a maximum rating, a minimum rating, and a monthly available energy. This data can be changed on a monthly basis. The unit is scheduled on a monthly basis with the unit's minimum rating dispatched for all of the hours in the month. The remaining capacity and energy can be scheduled in one of two ways. In the first method, it is scheduled deterministically so as to reduce the peak loads as much as possible. In the second approach, the peak-shaving portion of the unit is scheduled only in those hours in which the available thermal capacity is not sufficient to meet the load; if there is sufficient thermal capacity, the energy of the Type 2 energy-limited units will be saved for use in some future hour when it is needed.

Page 35: Northeast Power Coordinating Council, Inc. Multi-Area ... · National Grid Jack Martin New Brunswick System Operator Scott Brown ... TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 4 Introduction

NPCC WINTER 2008/09 MULTI-AREA PROBABILISTIC RELIABILITY ASSESSMENT

RCC Approved – November 19, 2008 33 Final Report

APPENDIX C Cogeneration MARS models cogeneration as a thermal unit with an associated load demand. The difference between the unit's available capacity and its load requirements represents the amount of capacity that the unit can contribute to the system. The load demand is input by specifying the hourly loads for a typical week (168 hourly loads for Monday through Sunday). This load profile can be changed on a monthly basis. Two types of cogeneration are modeled in the program, the difference being whether or not the system provides back-up generation when the unit is unable to meet its native load demand. Energy-Storage and DSM Energy-storage units and demand-side management impacts are both modeled as deterministic load modifiers. For each such unit, the user specifies a net hourly load modification for a typical week which is subtracted from the hourly loads for the unit's area. Transmission System The transmission system between interconnected areas is modeled through transfer limits on the interfaces between pairs of areas. The transfer limits are specified for each direction of the interface and can be changed on a monthly basis. Random forced outages on the interfaces are modeled in the same manner as the outages on thermal units, through the use of state transition rates. Contracts Contracts are used to model scheduled interchanges of capacity between areas in the system. These interchanges are separate from those that are scheduled by the program as one area with excess capacity in a given hour provides emergency assistance to a deficient area. Each contract can be identified as either firm or curtailable. Firm contracts will be scheduled regardless of whether or not the sending area has sufficient resources on an isolated basis, but they can be curtailed because of interface transfer limits. Curtailable contracts will be scheduled only to the extent that the sending Area has the necessary resources on its own or can obtain them as emergency assistance from other areas.