Upload
others
View
9
Download
0
Embed Size (px)
Citation preview
NOx Reduction using Reburning with Natural Gas
Final Report from Fuii-Scale Trial at SYSAV's Waste Incineration Plant in Malmö
Jan Bergström Miljökonsulterna
Nordisk Gasteknisk Center Nordie Gas Technology Centre
NOx Reduction using Reburning with Natural Gas
Final Report from Fuii-Scale Trial at SYSAV's Waste Incineration Plant in Malmö
Jan Bergström Miljökonsulterna
September 1993
NGC, GRI Disclaimer
LEGAL NOTICE. This report was prepared by Miljökonsulterna i Studsvik AB, as an account of work sponsored by the Gas Research Institute (GR!). Neither NGC, GRI, members ofNGC, members ofGRI, nor any person acting on behalf of either:
a. Makes any warranty or representation, express or implied, with respect to the accuracy, completeness, or usefulness of the information contained in this report, or that the use of any information, apparatus, method, or process di selosed in this report maynot infringe privately owned rights; or
b. Assumes an y Hability with respect to the use of, or for darnages resulting from the use of, any information, apparatus, method or process disciased in this report.
SYSAY ______________________ __
FOR EWO R D
In December 1991, SYSAV decided together with eight cc-funders to carry out a fullseale test at Malmö waste to energy plant with the purpose of reducing the contents of nitrogen oxides (NOx) in the tlue gas.
The method osed in this full-seale test is called "Reburning" and it irnplies injecting natural gas/landf1ll gas in to the fumace in order to establish a reducing zone.
The reburning method has been tested in USA at laboratory scale as weil as in a fullseale test with waste incineration and the tests showed a reduction of NOx emissions of up 60% with a moderate gas supply.
The objective of this full-seale test was to achieve an NOx reduction of at !east 50% without increasing the emission of other harmful substances.
The total budget of the project was SEK 8.5 mil!.
The overall responsibility and control of the project restedwith a steering committee set up by the funders:
Kaj Jönsson Jörgen Thunell Kerstin Larsson Karin Persson Bo Drougge Bent Karll Christer Pettersson Kjerstin Elevall
chainnan secretary
SYSAV SGC NUTEK SEU Naturvårdsverket NGC (representing GR!) REFORSK RVF
The responsibility for the practical implementation of the project rested with a project management group:
Erik Nord Kaj Jönsson Juhani Sirviö Bent Karll Lars Nilsson
project manager deputy project manager
SYSAV SYSAV SYSAV NGC Sydgas
The installation of the rebuming system and the fu11·scale test were carried out in 1992 and have resulted in this report
Malmö June 1993
~SAV B
A -~M--. önsson
Chainnan
Af;M!~t(_ Project manager
2
SUMMAR Y
Sydvästra Skånes Avfallsaktiebolag (SYSA V) operates a waste-to-energy
plant in Malmö with two units, incinerating 220.000 tonslyear of municipal
and industrial waste. These fumaces are since 1991 equipped with urea
injection to reduce emissions of nitrogen oxides.
In the autumn of 1991 SYSAV decided together with a number of co-funding
organizations to perfonn full-seale testing of "rebuming" with natural gas, as
an alternative or complement to urea injcction. Rebuming means injection of
natural gas to producc a reducing zone in the fumace where already fonned
nitrogen oxidcs are convertcd to nitrogen. Combustion air, in sufficient
quantity to accomplish complete combustion, is added after the rcducing
zone.
The rebuming system was designed by the Energy and Environmental
Research Corporation {EER) in California, USA, in ro-operation with the
Nordie Gas Tcchnology Centre in Denmark. In the design were also includcd
modifications of the airjetsto the fumace and supplementing with flue gas
recirculation to the fumace.
The aim of the project was to demoostrate that the above mentioned measures
could reduce the concentration of nitrogen oxides in the flue gas from nonnal
350 mg/m3 to lessthan 175 mg!m3, i.e. with more than 50% (m3 rueans
standard dry gas corrected to 10% C02).
The results showed that it is possible to reduce the concentration of nitrogen
oxides in the flue gas to 160 mg!m3 with injection of natural gas rorrespon
ding to 20% of the thermal input to the fumace and in combination with flue
gas recirculation. The operating conditions of the fumace were howcver less
stable than before and the frequency of earbon monoxide peaks increased.
160 mg!m3 of nitrogen oxides rorrespond to an emission of 75 mg!MJ (waste
and natural gas). The same emission level is achieved with injection of four
kg of urea per ton of waste.
3
CONTENTS
FOREWORD SUMMAR Y
l u 1.2 1.3 1.4
2 2.1 2.2
3 3.1 3.2 3.3
4 4.1 4.2 4.3 4.3 4.4.1 4.4.2
5 5.1 5.2 5.3 5.4 5.5
6 6.1 6.2 6.3
Rcferences
Appendix l Appendix2 Appendix 3
IN1RODUCTION General Objective The project Final report
BACKGROUND- REBURNING The reburning process The Olmsted tests
THE SYSA V PROJECf Background Conceptual design of gas rebuming Predieted NOcreduction
REALIZA TION OF THE PROJECf Design Calculation results Construction and planning Operating resnits Test-run l Test-run 2
CONCLUSIONS Primary combustion The reducing zone Bomout Operating experience Target compliance for the project
ALTERNATIVE METHODS FOR REDUCING NO, SNCR for NOcreduction METHANE de NO, Combination SNCR!Rebuming
Financing Organizations Technical data P&! diagram
4
Page 2 3
5 5 5 6 6
7 7 9
JO ]0 12 13
]5 15 17 18 19 21 23
26 26 27 28 28 28
29 29 30 33
l INTRODUCITON
l.l General
Acidification and the fertilizing effect of the nitrogen oxides (NOJ emitted
during combustion have been ascertained, and measures to reducc NOx
emissions are high-priority environmental targets. Wastc incineration plants
contribute only to a small proportion of the emissions in Swedcn, but tbese
days demands for severe rcstrictions are being stipulated as conditions for the
license. From 1992, environmcntal charges wcre also introduced on NOx
emissions. There is therefore a great interest in finding cost-effcctive methods
of NDx reduction.
SYSA V (Sydvästra Skånes Avfallsaktiebolag [The South-wcst Scania Waste
Co. Ltd. J) has a waste-to-cnergy plant in Malmö with two grate-fired
incinerator units, incinerating an annual total of 220,000 tonnes of municipal
and industrial waste. In the hoilers approximately 500 GWh ofthermal energy
is recovered and sopplied ~o Malmö's district heating network.In the course of
1991, SYSA V iostalled a SNCR system with urea dosage on both units in
order to reduce NO x emissions. These have been in operation since December
1991.
SYSA V was also interested in having one of its fumaccs act as an evaluation
plant for a full-seale trial with NOx reduction using rebuming. Reburning
involves natural gas being dosed into the fumace to create a secondary
combustion zone, with reducing conditions in which the nitrogen oxides
formed above thegrateare decomposed. In 1991, the Nordie Gas Technology
Centre ha d drawn up a report (1) demoostrating the applicability of the
rebuming technique on SYSA V's fumaces and, taking this as their basis, it
was decidcd that a project should be carried out with full-seale trials.
1.2 Objective
The aim of the project was to demonstrate, by converting one of the units at
SYSA V's facil ity, that the emissions of nitrogen oxides can be reduced by at
least 50% from 350 mglm3 to 175 mglm3 (m3 refers to standarddrygas
corrected to 10% C02). This was to be achieved without increasing the
emissions of other harmful substances or creating operational problems (2).
5
ln order to obtain these conditions in the fumace, natural gas and landtill gas
were to be used as the rebuming fuel. Landtill gas is of local interest, being
recovered from SYSA V's main landtill site very ncar to the waste incineration
plant.
1.3 The project
The projcct was budgeted at SEK 8.5 miiL Besides funding from SYSA V, the
project was financed by eight organizations in collaboration. Appendix l gives
a summarized presentation of these.
The project plan for implementation was divided into eight stages:
l. Establishing basic prercquisites.
2. Design studies.
3. Retrofitting the fumace.
4. Test-running.
5. Optimizing the rebuming process.
6. Evaluating results.
7. · Long-terin perfonnance.
8. Final repnrting.
The project schcdule encompasscd the period from J une 1991 up to and
including November 1992. A 90-day-long operating period for investigating
the Iong tenn perfonnance was included. That part was not cornpleted because
the short tenn trial periods were judged to provide sufficient information. No
test were carried out using landtill gas because of limited supply.
1.4 Final repnrt
The project has produced a number of reports and additional reports have been
used to complete the final report. The reports are Iisted as references.
This final report was compiled by Miljökonsultema. It presents the results and
an assessment of the project. In the concluding chapter three different methods
forachicving NOx-reduction in waste incinerations plants are discussed.
6
2 BACKGROUND- REBURNING
The concept of rebuming employed in this report is a term derived from the
natural gas rebuming technology. To facilitate an understanding of the project
planning and the interpretation of the results obtained, we give a description
here of rebuming as a tcchnique and of the process variables affecting NOx
reduction. We also report on the full-seale trials which were carricd out at the
Olmsted Waste-to-Energy Facility in Rochester, Minnesota, USA
2.1 The rebuming process
The description of the procedure enabling natural gas to reduce NOx
cmissions through rebuming is taken from a Nordie research project. This
involved researchers from four Nordie universities and is outlined in a project
report published by NGC entitled "Rebuming" (3).
It has Iong been known that hydrocarbon radieals rapidly rcact with the
nitrogen monoxide in combustion gases, and i t was attempted to exploit this
during the 1980s in the form of low-NOx engineering. By actding gaseous
fuel, reducing conditions are created in the fumace before actding combustion
air prior to final combustion. This generates combustion in three stages. Figurc
l shows rcbuming uscd for pulverized coal hoilers in which 20% of the heat
input is accounted for by natural gas.
Overfire air -
--80% coal --
Figure l
-w- 60% NOx reductlon
'---'~- Burnout Zone Nonnal excess air
--f--Reburnlng Zonc Sllghtlyfuelrtch NO x reduced to N2
Prlmary Combustlon Zon e
Reduced flring rate low excess air Lower NO x
The rebum technology applied to a wall fired hoiler
7
In the initial combustion stage, coal is fired with enough excess air to avoid
large quautities of combustible matter. Natural gas is subsequently mixed into
the hot combustion gases in sufficient arnount to make a fuelrich gas with
hydraearbon radieals but without oxygen. The best NO reduction isachicved
at air depletion corresponding to a stoichiometric ratio (SR) of about 0.9. At a
suitable distance from thelevelat which the natural gas is introduced,
combustion air is supplied in whatever volorne is required to achieve complete
humout with a controlied excess of air.
This three-stagc combustion is an effectivc method of reducing the NO
content, especially in coal-fircd boilers. Coal oftcn yields a high NO content
directly in the first stage of combustion. By mixing natural gas into the
combustion gas, the excess oxygen is consurned and the natural gas
contributes methane radieals which react with the oxygen in the NO at the
same time as N2 is formed. If reduction takes place at a high temperature with
sufficient residence time, NOx emission can be reduced by up to 70%.
The composition of the main fuel and its actmixture with the combustion air
determinc the temperature leveland excess air prevailing in the combustion
gas emitted from the primary stage. If the excess air is not greaterthan SR=
1.1, natural gas equivalent to 20% of the total heat input will be sufficient to
give SR = 0.9 in the reducing zone.
The rcsidence time of the gas in the reducing zone often imposes a constraint
when the reburning tcchnique is applied in existing bo il ers. The survcys
available from laboratory and pilot studies using pulverized coal firing show
that 0.5 secs is a sufficient residence time. In practical combustion terms,
however, it is obvious that the necessary residence time is greatly detennined
by the mixture ratios between the natural gas and the combustion gas from the
primary zone.
An clcvated gas temperature in the reducing zone prometes NOx reduction,
though there are reports showing a good effect at temperatures as low as
woo•c.
8
2.2 The Olmsted tests
A comprchcnsive research programme started in 1987 in the USA in order to
stud y the possibilities of reducing the NOx emission from waste incineration.
The aim was to minimize NOx emission by dosing natural gas above the grate
and optimizing operations by minimizing excess air during the final
combustion. The research programme was conducted by the Institute of Gas
Technology (IG1) and Riley Stoker Corporations (Riley) in association with
the Olmsted Waste-to-Energy Facility in Rochcster. The work carried out
included laboratory tests at IGT, pilot trials at Riley Research and full-seale
testing at Olmsted. The full-seale trials on rebuming- or as it is called
nowadays, the METIIANE de NOx System - were performed in Olmsted in
December 1990 and January 1991. A final report was made out in December
1992 (4).
The results from Olmsted were very promising; reductions in NOx and CO are
summarized in Figure 2.
20 L--------------+ CO, ppm 10 20 30 40 50 60 70 80 90
Figure 2
NOx and CO reduction at Olmsted
The officers supervising the SYSA V Project visited Olmsted (5). The
converted fumacc was 12 MW and produced an operating rcsult
corresponding to those found in the pilot-seale trials. By mixing in 12-15%
of the heat input as natural gas and 8% flue gas recirculation (FGR) to the
9
fumace to improve the mixing, it was possible to cut the total excess air from
100% to 40%. Combustion was rcndered more stable, halving the average
content of CO from a leve! of 50-60 ppm to 20-30 ppm. Togethcr, these
measures resulted in the NOx emission being rcduced by 60%. The flue gas
emitted bad a NOx content levet of approx. 50-60 ppm (at 12% 0 2).
The METHANE de NOx System is further diseossed later in this report.
3 THE SYSA V PROJECf
3.1 Background
At the time it was decided to go ahead with the project, there were preliminary
studies from EER (l) and experiences from full-seale trials at Olmsted bad
been obtained through the study visit (5).
EER found that the SYSA V facility was an ideal site for demonstration of
rebuming on a mass bum municipal waste incinerator. The design of the
facility and the romposition of the waste make the result potentially
applicable to many installations. Th~ design of the fumace and boiler in
Malmö is shown in Figure 3. A picture of the flow pattem for the entire
installation is shown in Appendix 2.
EER indicates that one potential concem with rcspect to application of gas
rcbuming to the SYSAV facility is the presencc of the wingwall (heat transfer
surface) in the upper fumace since this surface reduces the available residence
time for the process. However, this effect ma y be offset by the lower excess air
levels and higher fumace temperatures which the Malmö incinerator has in
comparison to units in the United States.
EER refers to the studies which have been referenced here, as these detail the
conditions under which NOx reduction is achieved. The volorne of natural gas
which is needed is statedas 15-25% of the total heat input.
10
13.1 m
.5m
Figure 3
Wingwall -
Grate .,.... Width = 4.7 m Length =8m
Fumace and hoiler at SYSA V.
3.6m o
3.9 m
The significance of an efficient mixing of gases, both in the rebuming zone
and in the bum out zone, is stressed. It is estimated that a good mixing can
reduce the total excess air and still yield low contents of CO in the flue gas
and unbumt in the fl y as h.
A high fumace temperature in the rebuming zone promates NO~ reduction,
hut dosing of natural gas must be done at a levet where the primary air is able
to oxidize the bulk of the volatile hydrocarbons from the fuel bed. The
temperature of the gas at the point where the bum out air is fed in does not
affect the reburning process, but it must be high enough to produce oxidation
of earbon monoxide and hydrocarbons from the reburning zone.
11
The significance of the residence time in the rebuming zone is emphasized. It
must allow adequate time for mixing of the gases and for rebuming, and is
given as 0.3-0.5 seconds. EER refers to the longer residence time indicated by
the IGT/Riley studies on waste combustion but notesthat this result depends
on reactions other than rebuming.
3.2 Conceptual design of gas reburning
Having outlined the underlying concept, EER presenteda design for
conversion of the facility. The principle is illustraled in Figurc 4.
MSW
Figure 4
---o, Fumace Width- 4.6 m
Bumout Zone
Rebuming Residance Ttme- 500 msec
c;~·········z········"-'._ .... ·-Il'= _L
Primary Gombustian Zone
Conceptual design for application of gas rcbuming
12
The EER concept includes
natural gas will be introduced from the front and rear wall of the
incinerator at an elevation slightl y a bo ve the current row of
upper overfire air jets
flue gas will be recycled to the rebuming fuel nozzles
the overfire air used to complete oxidation of the products from
the rebuming zone will be injected in new rectangular over fire
air ports at an elevation above the rebuming fuel jets correspon
ding to a rebuming zone residcnce time of approximatel y 0.5
see
the existing lower overfire airjetson the rear wall will be kept
in operation. The existing lower overfire airjetson the front
wall will be taken out of service. It may be necessary to recycle
flue gas to the airjetstaken out of service to kecp them from
overheating
i t may be necessary to recyclc flue gas to the grate if it is found
that the undergrate air flow can not be reduced to the desired
design conditions without resulting in overheating of the grate.
At fullload the rebuming system will use natural gas corresponding to
approximately 23% of the total heat input. Approximately 3% of the flue gas
will be recycled to the rebuming fuel nozzles to enhance mixing of the natural
gas with the products from the primary combustion zone.
3.3 Predieted NOx-reduction
The estimated reduction of NOx-emissions are based on three factors.
l. Reduced thermal input to the grate. The capacity of the hoiter is
limited which means the heat input with the rebuming fuel must
be compensated with reduced heat input to the grate.
13
400
~300
~
"' 'O 200 M
E z o .s
• ~ 100
o
2.
3.
Lowering the excess air ratio in the lower fumace and the
overall excess air in the bumout zone.
The application of gas rebuming
Predieted overall NOx-emissions are shown in figure 5.
Baseine
Figurc 5
Load Reduction Excess Air Reduc:OOn
NO x Errissions after
Preliminary estimate of gas reburning perforrnance
Gas Rebuming
The reduced heat input to the grate is expected to lower the NOx-concentra
tion from 350 to 300 mg/nm3. Although the final NOx-emissions levet de
pends upon the absolute reductions in NOx contributed by each factor, this fi
gure shows that the anticipated emissions levet due to applying gas rebuming
is below the target value of 175 mglnm3 (dry corrected to 10% C02) at even
the lowest valuc of anticipated NOx reduction. Therefore i t is expected that the
projcct goal is casily achievable with gas rebuming.
14
4 REAUZATIONOFTHEPROJEIT
4.1 Design
When the project was set up, EER, together with SYSAV, carried out the
studies at the facility on which the design and projection of the rebuming
systern bad been based. That work is detailed in a separate report (6).
The design of the rebuming facility was complicated samewhat by the fact
that SYSAV simultaneously iostalled a SNCR system (urea dosage in the
fumace) with the airn of reducing NOx emissions.
Baseline data for the design of the rebuming system were generaled by rneans
of mcasurements at the facility. The contro l strategy u sed at the facility
involve controlling the excess air within a given range with a low CO content
by centrolling the feed of waste flow to the grate. The interrelation of 0 2 , CO
and fumace temperature is illustraled in Figure 6.
Temp c o
c o
_-_-_-_-_-_-~ _-_-_-_-1::=::(
Figure 6
Optimal operating excess air
Furnace Temperature
Excess Air (Optimal)
Excess o,
The process design was established by studying the flow behaviour in the
furnacc as rcalized in a physical plexiglass model. At the same time, thermal
conditions in the furnace were described together with the thermalload on the
hcating surfaces in a mathematical modets.
15
With the aid of the result from the model studies, the design and position of
the jets were determined in order to supply recirculated flue gas, natural gas
and combustion air to the fumace. The main dimensioning data as prescribed
by EER are shown in Figure 7.
UPPER FRONTWALL OFA PORTS o Elevation- 14.7 m
6 ports 156l( 405 mm 15' downward Wt Velacity-16m/s
FRONTWALL AEBURNING FUELJETS
Elevation- 12.6 m 6jets046mm 30' downward Velacity- 73 m/s FGR2%
LOWEA FRONTWALL OFAJETS
Elevation- 11.6 m 14 jets 0 50 mm
o Coo~ng FGA flow
Undergrate Air Plenums
FifWre 7
UPPER BACKWALL OFA JETS o Elevation- 14.7 m
6jets 0 52 mm 45' downward Vetocity-58 m/s
BACKWALL REBURNING FUELJETS
Elevation -12.7 m 5jets052mm 30' downward Velacity- 49 m/s FGR 1.5%
LOWER BACKWALL OFA JETS SR 1 = 1.07 o Elevation- 8.0 m
/
FGR-4%
)b=e:J 0105~ts (4 jets out of service)
"mm
c__vc'c"'cc''c-c"::"':'~------_j
Sommary of specifications for the reburning system
Figure 8 shows the design of the jets for natural gas and flue gas on the front
wall.
16
Jet design and position were selected to give the best distribution of air, flue
gas and natural gas on the basis of the modet trials that werc carried out.
MO
Figurc 8
) Sel Scl-@ 120' Tu H<>ld PD&Itlon
Conceptual design of the reburning fuel injector
4.2 Calculation results
EER computed the temperature profile in the fumace for a number of different
operating modes. One example is shown in Figure 9.
;:; ';! oo:L:; ~ =;3&:~ ~ ~ec ; ~ o
z .s 900
Reduced Load Cases:
u800 _:-:_ ~ ~ 5) Baseline - ' ' - '-. 7) Rebuming, SRg= !.05, SR1 = 1.15 o
100 o
Figure 9
~- · 8) Rebummg, SRg= l.OO, SR1= 1.10 \ - 9) Rebuming, SRg= l. lO, SR1 = l. !O
5 10 15 Mode! Height from Backwall OFA Nozzles (m)
Effects of reburning variations at rcduccd load on surface temperatures
17
The mathematical mode! shows no elevated temperature in the top of the
fumace in front of the wing wall, while the temperature is raised approx.
100°C in the lower part of the fumace. The temperature level increases with
the thermalload but the profile remains roughly the same.
In parallel with EER's efforts, mathematical modelling was done at SINTEF in
Nmway (7). Six different operating modes were simulated for rebuming in
SYSA V's fumace. The results showed that gases could be expected to be weil
mixed in the reducing zone but worsc in the burn out zone. The model pre
dieled that high temperature peaks would occur near the wing wall concurrent
with high contents of CO.
4.3 Construction and planning
A detailed structural design was finalized, producing guidelinesfor natural gas
pipelines, landfilt gas, flue gas ducts, safety equipment and measuring and
control system. The work was carried out by SYSA V in cooperation with
Sydkraft Konsult AB in Malmö. A P&l diagram for the process is outlined in
Appendix 3. A detailed functional description was compiled by Sören Lundh
Konstruktionsbyrå AB for the control system of the facility (8).
The installation work was demanding, as the space available for piping was
restricted at the facility. Trimming in the system and getting the process
computer function for the measuring and control equipments operational was a
time-consurning process. The facility was ready for shake down tests in May
and for test-running in Jul y 1992.
In conjunction with the planning work, a plan was designed by NGC for
testing the rebuming system. The measuring programrue was designed to
clarify the limits for utilizing the rebuming technique in the facility and to
establish optimized operating conditions (9). The principal parameters to be
studied were fumace load, excess air in the primary zone and the stoichio
metry of the rebuming zone. The trial was planned as a complete factor trial
with 27 operating modes.
18
The programme included extensive sampling and measurements of all
parameters which might be of interest in evatoating the rebuming and
determining optimized operating conditions as well as clarifying whether it
producedan y change in gas composition or unbumt material in the fly ash.
For all operating modes, part of the testing programrue involved analyzing the
occurrence of dioxins in the combustion gas leaving the boiler. Optimized
conditions for long-term testing were to be detennined by assessing the
results of the testing programme carried out.
Testing according to planning were not accomplished duc to the fact that
sufficient stable buming conditions could not be established.
4.3 Operating resulls
In April1992, the modified facility was put into service according to the
project plan. As mentioned before, calibration of the measuring equipments
and shake down of the control system Iasted longer than planncd. Then the
first trial with natural gas could not start until July 1992.
In order torunthe modified fumace solelywith waste, new baselinc operation
conditions bad to be established directl y after the rcconstruction. The new
design of the jets and the air ports did not result in acceptable bum out with
flue gas recycling. Air and flue gas ducts were thercfore rearrangcd in such a
way that air and flue gas was mixed and injected in the jets for fluc gas
recirculation.
An acceptable base Iine operation was established by supplying the major part
of the primary air to the two first zones of thegrateand only air to the jets.
Table l shows typical base Iine data.
The change in air distribution in the fumace occurring as a result of air jet
modifications renders fumace operations less stable. The frequency of time
with bad bum out was increased and was recorded by the number of CO
peaks. Particulart y when the fumace is not operated at maximum grate load.
19
Table l
Basline operation
Boiler output 28 MW
Primary air 33000 run3/h
Over fire air
upper frontwall OF A ports 3300 run3/h
upper backwall OF A jets 1500 nm•!h
FGR-jets (with air)
lower backwall OFAjets 5000 nm•!h
lower frontwall OF A jets 1000 run3/h
frontwall rebuming fuel jets 1900 nm•!h
backwall rebuming fuel jets 1100 run3/h
Furnace temperature 850 •c
Heat input
waste 35 MW
natural gas o MW
Flue gases:
flow 69500 nm3/h temperature 260 •c
o. 6.6 vol %wet gas
mo is ture 13.5 vol %wet gas
co 66 mg/run3 wet gas
NO 210 mg/nm3 wet gas
No. 3 mg/nm3 wet gas
At the same time the NO, emission was found to be 275 mg/nm3 (as N02 dry
gas corrected to 10% C02). The new air and flue gas distribution in the fur
nace resulted in reduced NOx emission but less stable combustion compared
with before retrofitting the furnace.
1\vo test runs were carried out to study the influence of flue gas recirculation
and natural gas injection. A great nomber of data were collected and eva
luated. The first test run were carried out in July/Augost 1992 by SYSAV and
Miljökonsultema. The seeond test run were carried out in November 1992 by
SYSA V and EER.
20
4.4.1 Test-run l
The instruments for measurement and control were calibrated in connection
with the test-ron. The capacity of the process computer made it possible to
stud y and evaluate the different modes of operation directly during the test
periods. A great nomber of operationalmodes were tested in a few days time.
(lO)
According to the figurcs shown in table l, 9000 m3/h combustion air sopplied
in the lower FGR-jets achieved sufficient oxygen and creatcd enough
turbulence for complete bum out of the flue gas. When the air is replaced by
recirculated flue gas, the vetocity in thejetson the fumace wallsis definitcly
maintained, but the mass flow of gas decreases as the temperature of the gas
rises. The flue gas also contains less oxygen than air. As a result, it is
impossible to bum out the CO in the flue gas to attain the level required.
Despite systematic attempts to optimize the distribution of recirculated flue
gas, the CO content could not be brought down under 100 mg!m3. This fact
makesthat particular operationalmode unacceptable at this facility. Nor did it
prove possible to achieve satisfactory final combustion by increasing the
amount of bum out air in the airports high up in the fumacc. During those
operating periods when it was attempted to optimize final combustion by
FGR, the presencc of a low NOx content was ascertained w hen CO was high.
This observation is of no practical interest since the facility cannot be run with
an elevated content of CO in the flue gas. The earrelation between CO and
NOx is shown by Figure 10.
21
450
• 400 ...
\:: • 350
• .300 ' ..... •
o .. -. • • if' • • o •
250 • • 1ii .. • • • o E • c
"' E 200 x • o z
150
o "r - • o 500 1000 1500 2000 2500
CO in Flue Gas mglnm3
Figure 10
The correlation bctween CO and -NO x content
Natural gas injection does not produce better bum out conditions. It was not
possible to findamode of operation with FGR and natural gas with stable
bum out in the flue gas and CO below 100-150 mglrun3,
The periods of testing carried out using natural gas demoostrate reduced NOx
contents. With the proportion of natural gas forming 15% of the heat input, the
NOx content was measured to be the equivalent of 150 mg!nm3 at 10% C02.
However, the CO level in this case was 400 mglnm3. Natural gas and the gas
recirculation created conditions when the NOx reduction was betterthan the
target 50% but the bum out was not acceptable. It can be eaused by the gas
temperature in the fumace.
The temperatures measurcd in the fumace are low. Under basic operating
conditions, 850-900°C is recorded as the highest temperature at a boiler
output of 30 MW. The recorded fumace temperature increases by approx. 8°C
per MW of hoiler output - see Figure 11. 'The gas temperature drops as a result
of heat being transferred to the hoiler walls, sothat it is appreciably lower
when the flue gas reaches the wingwall at the top of the fumace.
22
"'"" 950
""" 650
""' u "'
700
650
600
sso
500
"' "
• • •
• • . .
22 25 JO " MW
Figure 11
Fumacc temperature as a function of hoiler load.
The fumace temperature is recorded with an unprotected thermocouple. The
gas temperature might therefore be a hundred °C higher. However, the fact
remains that to a !arge extent heat transfer to the hoiler walls already takes
place in the bottom part of the fumace, and those reactions promoted by a high
gas temperature, e.g. final oxidation of CO, do not occur to any notable extent
in the top section of the fumace.
The supply of natural gas in the fumacc does not increase the temperature
materially. 6 MW natural gas, making up 15% of the heat input, increases the
recorded fumace temperature only 80°C at the inlet to the wingwall. The
prevailing low temperature makes it difficult to ensure satisfactory bum out of
co.
4.4.2 Test-ron 2
The mcasuring results obtained during test-run l were evaluated by EER, who
conducted a series of complementary measurements and evaluations during
fourdaysin November 1992 (11). Thesetests were focused on both
23
400
ON 350 o
"' o o
300
"' ~ 250 M E z 200 -"' E
'" 150 c o
'" 100 ~
E w
" 50 o z
o 10:00
combustion air and FGR distribution effecting the burn out of CO and how
amount and distribution of natural gas influenced the NOx-reduction.
The tests confinned t hat sta bl e combustion condition on l y we re
obtained with air in the lower FGR -jets. With this mode of operation a
numbcr of tests were carried out with gas rebuming. Figure 12 shows NOx and
CO concentration in the flue gas during five hours of operation .
" ' ' ~-il j "
!
11:00
! ! ! tests
12:00
Figure 12
•
• o
!
13:00 Time ol Day
NOX
c o
! !
14:00
Gasrebuming with air through the lower BW jets.
24
! ! !
15:00
3000
2625
c 2250 u
M E
1875 z
1500 -"' E ~ c Q
1125 ~
750
375
o 16:00
E
"' o o
3000
~2500 ~
n
~ 2000 c, E vi 1500 c o
" -~ 1000 w o () 500
o 0.8
l l l l • l T l l
0.9
In order to obtain sufficient bum out with low CO-contents in the flue gas
excess air is required in the primary zone over the grate also with gas
rebuming. Air must earrespond to at least SR = 1.1 which means significant
amounts of natural gas must be injected to create reducing conditions in the
fumace. Figure 13 show SR in the primary zone with different amounts of
natural gas.
- 400 N • o
() 350
"' o o
o 300
"' :s 250 n
00 E o l z 200 c, k o
E
"' 150
c o
" 100 ~
E w 50
' ~ o
z o 1.0 1 1 1.2 13 14 0.8 o 9 1.0 1 1 1 2 1.3 1 4
Primary Zone Stoichiometry Primary Zone Stoichiometry
Figure 13
• Non GR Operation
n GR operation@ 1 O% NG input
" GR operation@ 15% NG input
o GR operation@ 20% NG input
The stoichiometry of the primary zone.
Figure 14 shows NOx and CO measured with SR between 1.1 and 1.2 in the
primary zone. Low CO-content is maintaincd also with reducing conditions in
the rebuming zone. The NOx content is reduced as the proportion of natural
gas increases.
The maximal natural gas flow corresponding to 8 MW or 20% of the total heat
input reduced the NOx to about 160 mglnm3 (drygas 10% C02) without an y
increase in CO content when SR in the primary zone were 1.1
25
400 n
N o 350 o
"/
"' O Q Il~ • ~ 300 () dl ) /l
"' Q]J~t~~ Il ~ 250
o~J~: "" " E ~ 200 }.-t\- cb rr Il
1 ۤJ 111 E o u
"' 150 c -~ • 100 ·~
•• w o" 50 • • • z • • • • .... LJ
o
load: 25-30 MW Out SRg =0.9-1 10 sR 1 = 1.1 -'-2
3000 400
N o 350
2500 u
' l'
" ~ 300
2000 ""E "' ~
~ 250 " E
1500 • z 200 c i> o E
" 150 ~ • c 1000 o w " • wo o e o
500 w o" 50 z
o o
Basel1ne NO emo<SIQM ---- _.__-- ---
o
"o
"' -"-f-~ _!ar.'!!I~•S~ns_tfä __ (~ _:(j_-, o
0_85 0.90 0.95 1.001.05 110 115 1 20 1 25 o 5 10 20 25 Reburniog Zone Sloich1ome1ry
Il NO ' • co
Fil;ure 14 NOx emissions at 25 to 30 MW load range.
5 CONCLUSIONS
NG Heatlnpul (%o! Tolal)
Realization of this project has resulted in one of SYSA V's units being
cquipped with a measuring system and process calculation resources, enabling
combustion results to be monitored inadear and lucid fashion. lt is therefore
possible to draw conclusions despite the fact that the total operating time with
natural gas is not extensive.
5.1 Primary combustion
The gas composition and excess air from the waste on the grate varles
significantly both with time and in different parts of the primary zone. The
combustion is very different from coal firing where gas rebuming first was
applied. In the homogeneous pulverized coal flame the temperature is high
and thennal NO contributes to a major part of the total nitrogen oxides.
Waste firedon the grate results in relatively low temperatures and fluctuating
excess oxygen. The limitedamount of overfire air or flue gasthat is possible
to add to the fumacc will not create sufficient mixing before the reburning
zone.
26
Stable combustion conditions in the primary zone are achieved when the gratc
load is high and the SR at !east 1.1. This is due to the combined effect of the
fuel bed covcring the grate and the higher temperatures which are obtained in
the combustion gas. The large-scale transfer of heat to the fumace walls
provides a quick drop in temperature. When the planning of the project were
carried out the significance of this was underestimated, and during the project
it has not been possible to improve the primary combustion conditions
enough.
The NOx emission increases with the increase in waste load. The evaluations
made of the data from test -run l show that in the rang c 26-34 MW, the bo il er
load increases the NOx content by 10 mg/nm3 per MW, all other conditions
being equal.
5.2 Tbe redodog zone
The natural gas which is dosed in eonsornes the excess oxygen in the
combustion gas and raises the gas temperature through the input of heat.
However, heat transfer to the fumace wallstakes place quickly, preventing
temperatures in excess of 1000°C from occurring in the rebuming zone. The
gas temperature is lower than predicted in the models by EER and SINTEF. In
the fumace the highest recorded gas temperature is between 850 and 900°C.
Compared with successful rebuming in coal fired hoilers it is considerably
lower.
The project result shows NOx-reduction with use of natural gas. The NDx
reduction is the same when natural gas lower SR from high level eg 1.2 to 1.1
compared with SR from 1.0 to 0.9. Consurning oxygen with natural gas
corresponding to SR 0.1 gives a NOx-reduction of 60 mglnm3 which can be
seen in figure 14.
Whether there would be a better reduction in NDx if the residence time were
incrcased above the 0.5 secs provided for by the fumace is beyond
clarification in this project.
27
5.3 Burn out
When the gas mixture from the reducing zone is mixed with bum out air, the
temperature is too low. Natural gas only contribute to a marginal increase in
gas tcmperature. The final excess oxygen levet to reach low CO in the flue gas
is the same both with and without natural gas in the fumacc. Excess oxygen is
nonnally 6-7% (by volume wet gas).
Increasing the 0 2 content from 5 to 8% only serves to raise the NO x content by
25-40 mg!nm3 at JO% co2.
5.4 Operating experience
The operating conditions have changed due to installation of the gas reburning
system. After trimming, a base linemode of operation was obtained. Calibra
tion of the process instruments and the experience from the first test -run made
the facility operating wcll.
The recirculatcd flue gas, taken from the dust precollector outlet, still
contained considerable amounts of dust as result of which:
the FGR jets have to be cleaned;
occasionall y coating of dust eauses disruptive speils of vibration
in the FGR-fao;
dust deposits occur in the FGR ducts;
dust coatings accumulate on the flow transmitters at low flue
gas temperatures.
5.5 Target compliance for tbe project
The project successfully completed the installations and realized the set-ups at
the facility, as planned. The facility has since functioned in ordinary operating
mode. The prime target of rcducing NOx emission with 50% from the original
Icvel of 350 mg/nm3 was achieved. The changcd operating mode due to mo
dified air distribution reduced the NOx emission to the level of 275 mg!nm3.
With natural gas accounting for 20% of the total heat input, the NOx content is
28
reduced to a levet of 160 mfVnm3. NOx is always calculated as equivalent N02
calculated in dry gas corrected to 10% co2.
The modifications to the air distribution in the furnace have resulted in a less
stable Combustion. The incidence of cases where difficultics in achieving
satisfactory complete burn out have increased. It has not been tested if the
emissions of other harmful substances have been affected, bu t Iikely there is
no increased emission of arornatics in the flue gas after the fabric filter.
6 ALTERNATIVE METHODS FOR REDUCING NOx
Instead of gas rebuming reduced NOx emissions can be achieved using a
selective noncatalytic reduction (SNCR) system with urea injection or the
METIIANE de NOx system developed byIGT and tested at the Olmsted
Facility in the USA.
As a general principle, selective catalytic reduction (SCR) systems can be
iostalled but considerably greater costs arethen entailed the NOx-reduction
both for investment and operation. It is also possible to combine SNCR and
gas rebuming.
In the following section the SNCR, METHANE de NOx and the combined
system are described in slightly greater detail.
6.1 SNCR for NOx-reduction
Since December 1991, both fumaccs at SYSA V Plant have been fittcd with
equipment toprepare the urea solution and dose this into the fumaces with
nozzles at two levels. Appreciable NOx reduction is thus achieved. At the time
of the periodic inspection of the installation (12) in August 1992, a NOx
content of 125 mfVnm3 drygas at 10% co2 was measured in the flue gas from
unit 2. This corresponds to 60 ~g!MJ fuel input.
The urea dosage, which rises to something in the order of 4 kg/ tonne wastc,
results in a measurable emission of ammonium in the flue gas. On inspection,
the content of N~-ions in the flue gas was 13-19 mg/nrn3 drygas at 10%
C02• The annual mcan valne of the NOx emissions at the plant is somewhat
greaterthan the inspcction value, rising to a Ievel of 80 mg/MJ fuel input.
29
Similarly, the measurements show that the ammonium slip is lower than it was
during inspection.
6.2 METHANE de NOx
The conversion of the waste-to-heat facility in Olmsted and the installation of
natural gas yielded a result of up to 60% reduction in NOx emissions. At the
same time, the excess air in the flue gas was hal ved, as was the content of CO.
The results achieved in the development work carried out over several years
are shown in Table 2.
Table 2
Averagc operating data -1990/1991 field evaluation tests (13)
FGR + NGas At Normal A<
19!!7 Normal Basel in.: 1991
Ba~e!tn.: MSW Input Basdine
!987 1991 (Averag.: MSW Input
Test Test FGR Only Data} Test
MSW,· lb/h 6,450 7,900 7,400 6,650 7,100
Natural Gas,% o Il Il 14.8 \2.9
Total Heat Input," 106 Bw/h 33.5 41.2 JH.6 40.5 42.5
FGR,% o o 7.9 8.7 10.6
Total Flue Gas, lb/h 46,000 59,000 46,0()() 48,000 45,400
Stcam Flow, lb/h 23,500 2H,2SO 27,300 28,600 JO,SOO
Economtzer Exit Tempera ture, °F 417 425 4){} 422 422
Precipitator lnlet
o.,% _, 9.3 10.5 H.9 6.5 5.9
CO, vppm, at 7% Oz 47 72 ]{)() 35 33
NOx, vppm, at 7% Oz 210 IR5 150 75 75
"Estimated.
The ME1HANE de NOx system stems from the fundamental expcrience
gained from the rebuming developed for pulverized coal boilers. Rebuming
involvcs that NO formed primarit y at a high temperature are being reduced in
the flue gas at a high temperature when reducing conditions are created
through the addition of natural gas. The development work has however
shown that other factors have great importance for waste combustion.
ln waste incinerators, only a minor portion of the nitrogen oxides are formed
primarily as NO above the bed. The creation of an oxygen-free combustion
30
gas at a high temperature is thus not essential to the final result. Instead, the
natural gas which is doscd in is instrumental in reducing the 02 content
downstream of the primary combustion zone and thus in minimizing the
formation of NO x from other nitrogen compounds such as N~ and HCN.
Figure 15 illustrates the METHANE de NOx approach for waste incinerators
iostalled at the Olmsted facility. Natural gas and recirculated flue gas are
injected above thegrateand the secondary overfire air is injected at a higher
elevation in the furnace.
Undergrate Air
Figure 15 The METIIANE de NO, process
Natural Gas/ Recirculating Flue Gases
ln order to derive the most favorable effect from the natural gas, combustion
on the grate needs to tak e p~ace in a controlied way, minimizing the
differenccs in excess air between the various parts of the grate exterior.
Natural gas together with recirculated flue gas for mixing provide an oxygen
deficient secondary combustion zone that promotes the destruction of NOx
precursors as weil as NOx. In the Olmsted facility the good results were
obtained with 12 to 14% of the flue gas recirculated.
31
Figure 16 shows that the flue gas in the reducing zone is not oxygen free, yet
NOx-reduction still takes place. [t is the same result found in the full scale test
at the SYSA V facility
=.------------------------------------.
180 O BASEUNE
N o
'"' "rf!. 140 ,._
E "' o_ o_ > x- 100
o z •
e METHANE de·NOX
•• •
• •
•
• •
eo • • • •
•o L_----~----L-----~----"-----"------i_----~-----J
' • ' w
SECONDARY ZONE OXYGEN,%
Figure 16
Effect of excess oxygen concentration on NOx-formation
The residence time of the combustion gas in the reducing zone is of crucial
importance to NOx reduction. In the Olmsted fumace, the residence time was
1.1-2 seconds. When the air for bum out was mixed in earlier, NOx reduction
was less good.
The mixture ratio of the combustion gas already in the primary zone and the
actmixture of natural gas to form a homogeneons gas in the reducing zone are
decisivefor the successful exploitation of the ME11lANE de NOx system.
The results achieved through the project at the SYSA V facility tall y with
those from Olmsted, although the impact of the residence time cannot be
verified. The great importance of the mixtureratio in generating a
homogeneons gas in the reducing zone means that each separate fumace and
32
each operating mode must be optimized separately in order to achieve
maximum NOK reduction by means of the natural gas injected.
6.3 Combinatlon SNCR/Reburnlng
lnjection of natural gas may be combined with injection of urea in the fumace.
The combined system may provide higher NOK-reductions than expected by
the individual reductions. EER has patentedthis combination and narned it:
"Advanced rebuming". The system is developed for coal firing. In a pilot
plant, 80% NOx reduction is demonstrated with 10% of the total fuel heat
input being natural gas and urea injected with the bum out air. (14)
Injection of nitrogen containing compounds like urea in the fumace forther
reduces NO in the hum out stage. The earobined effect of gas rebuming and
SNCR as NOx-reducing methods will be very effective in tbose situations
where it is possible to modify the fumace, so the rigth temperature zones and
residential times are obtained.
The METHANE de NOx, full scale tests with waste incinerations show that
the NOx-reducing effect of natural gas injection in the fumace is not primaril y
a rebuming effect. Natural gas mainly contributes to create homogeneons gas
mixture with low oxygen content. in which the NOx-precursors like N~ and
HCN are prevenled from destruction, before they enter temperature zones
suitable for SNCR-reactions. It is not known, if an addition of urea improve
the NOK reduction in the same way as demonstrated for pulverized coal firing.
Obviously, the SYSA V facility has most of the installations necessary in order
to test the additional effects of the combined systems for NOx-reduction.
33
REFERENSER
l
2
3
4
5
6
7
Technical Support for Field Evaluatian of MSW Combustion with Natural Gas Rebuming Phase l - Final Report Energy and Environmental Research Corporation June 1991
NOx reduktion genom Reburning med naturgas/deponigas Fullskaleförsök vid SYSA Vs avfallsvärmeverk i Malmö Projektbeskrivning Nordisk Gastekoisk Center (NGC) Juni 1991
Rebuming Process Parameters, Implementation and NOx-reduction Potential Peter Glarborg, Technical University of Denmark Bent Karll, Nordie Gas Technology Centre September 1991
Emissions Reduction from MSW Combustion Systems Using Natural Gas Task 3, Field Evaluatian Harnid A. Abbasi, Institute of Gas Technology Frank J. Zon e, Riley Stoker Corporation December 1992
Reserapport, D nr SGD-91 04-12 Besök på- Olmsted Waste -to Energy - Municipal solid Waste U nit, Rochester, Minnesota, USA Lan; Nilsson, Sydgas Erik Nord, Sysav Maj 1991
Technical Support for Field Evaluation of MSW Combustion with Natural Gas Rebuming Phase II - Final Report Energy and Environmental RCscarch Corporation November 1991
Mathematical Modelling and Numerical Simulation of the Rebuming Process in Waste Incinerators Description of Methods and Application to the SYSA V Incincrator B. Lakså, S. Byggst0yl, S. Aune, B.F. Magnussen, S!NTEF December 1992
34
8 SYSA V AB Malmö Avfallsverk Funktionsredovisning Rebuming Panna 2 Sören Lundh konstruktionsbyrå AB April1992
9 Choice of Operating Parameters and Test Design for Phase 5 Peter Blinksbjerg, dkTEKNIK Bent Karll, Gas Technology Center Henrik Madsen, DPI September 1991
10 SYSA V REBURNING Lägesrapport juli/augusti 1992 PM/MKS-92/1598 Jan Bergström, Miljökonsultema i Studsvik AB Augusti 1992
11 Technical Support for Field Evaluation of MSW Combustion with Natural Gas Rebuming Energy and Environmental Research Corporation November 1992
12 Periodisk besiktning 1992 MKS-92/128 Per-Åke Gustafsson, Miljökonsultema i studsvik AB December 1992
13 Field Evaluation of Mcthane de-NOx at Omsted Waste-to-Energy Facility Richard Biljetina and Harnid A. Abbasi, Institute of Gas Technology Michael E. Cousino and Rob Duonett e, Olmsted County, Minnesota January 1992
14 Large Pilot Scale Testing Results of the COMBINO" Process J.N. Pont, A.B. Evans, G.C. England, R.K. Lyon and W.R. Seeker, Energy and Environmental Research Corporation Charles Schmidt, Department ofEnergy-Pittsburgh Energy Technology Center
35
Financing Organizations
Nordie Gas T echnology Centre r s owned by a number of large energy cancerns rn Norway. Sweden. Finland and Denmark_ NGC's mandaters to promate the usc of natural gas rn the Nordie reg1on through Nordrc research proteets
The Gas Research Institute. Chrcago. 1s a member organizatron for the natural gas rndustry in the USA_ GRI plans. manages and frnances research rnto the recovery, transportation. storage and applicatlon of natural gas.
Swedish Gas Technology Centre rs owned by a number of Swedrsh gas and energy enterpnses and the Swedrsh Gas 1\ssocration SGC"s JOb is to coordinate and rationalize the R& D activ!lres of the Swedish gas rnduslry
Svensk Energ1 Utveckling AB rs a dovetopment company owned by the Swedish power 1ndustry. 1ts mandate •s to promate the development of env1ronment · fnend!y and economical energy technology
Sweden·s National Board for !ndustnal and T echn•cal Oevelopment
Sweden's Nat•onat Environment Proteetlon Board
The JOint research and development agency of Swedish government. local authonhes and 1ndustry 1n the held of waste and recovery.
The Swed•sh Association for Refuse Collection Interest orgamzat1on for tocal authorit1es and enterpnses with activ1ties afflliated w•th waste management and sanitation in the public seetar
Sydvästra Skånes Avfallsaktiebolag is a municipal undertak1ng in charge of was te management in 9 municipalities w1th a total of 470.000 res1dents and a waste volume of 500,000 tonnes a year
36
Nordisk Gasteknisk Center
SGC~s""'~ Gastekniskt Center AB
SVENSK ENERGI UTVECKLING
=-======= i~ U i;,..;{
''""'"" "·"'""'·'' "'""' '''''"·''""'·'' ·"'·' '··'"'"·'''''"''"''""'"'
Naturvårdsverket
Stiftebcn REFORSK
RY.E
S \"S4\' Sydvaslra Skånes Avlallsakliebolag
Appendix l
Appendix 2
FROM REFUSE TO DISTRICT HEATING SYSAV is responsible forwaste management in South-West Scania. Household and Industrialf commercial waste is incinerated at Malmö Avfallsverk. The plant, which came into operation in 1973, consists of two units.ln order to further reduce emissions the existing cleaning equipment was expanded to include advanced flue gas cleaning in 1981. T wo years later additional hot water units were iostalled to increase energy yield from waste.
Malmö Avfallsverk produces 500.000 MWh yearly fordistrict heating. This represents 25% of the total district heating /oad in the City of Malmö. Connected to the incinerator thereareal so a special furnace for cremation of dead animals, toxic waste, etc. and a gasfired hot w ater bo il er utilizing landtill gas.
15
13
~~~~J==o="~~~~~Jr~~~~np~1ngl!h:a,:l::::~ 2 Receiving bunker 3 Travelfing crane 4 Feed shaft
7 Slag discharge 8 Hot water boi/er 9 Precol/ector
12 Reactor 13 Bag filter
Location:
Latest permit
Operating Since: Extension:
Capacity: Population in operation area: Incineration: Operating time: Weighing bridges: Bunker capacity: Travelling cranes: Incineration g rate:
5 Operator ca bin 6 lncinerator fumace
10 Hot water ecnomizer 1 and 2
11 Limesilo
14 Fluegasfan 15 Slack 16 Dust si/o
TECHNICAL DATA Spillepeng. Phone (040) 93 64 55 licence from Board for Environment Proteetian Sept1986
1973 {2 u nits) 1981 (flue gas cleaning) 1983 (hot water economizer) 2 x 14 ton/h
470,000 220,000 ton/year 8000 h/fumace {Continuous three-shitt operation)
5Fiintab
11,000m'
3 x Aarhus, 1 x Kone Martin (reverse grate) gross thermalload 2 x 40 MW
Bo i lers:
Energy recovery: Energy yield: Slagashes:
Fluegas cleanlng: stack: Emissions:
Incineration temp, approx. 1000"C Wagner-Bira 2 x 32 MW Generator 2 x 3.75 MW Pressure 16 alm, hot water temp. in 120GC, out 160°C, flue gas temp. a fler stack 140°C District heating, approx. 500,000 MWh/year 2.4 MWhfton refuse Martin slag discharge. Slag to sarting plant approx. 60,000 ton/ year . .Ashes to landtill approx. 4,000 ton/year Precollector, lime reactor(dry system) and bag filter by Fläkt Concrete, 74 m high Dust 10 mg/nm' Hydrochloric acid 150mgfnm' Mercuty0.005 mg/nm' Oioxines less.'than 0.1 nglnm'
Sydvästra Skånes Avfallsaktiebolag Östergatan 30, S-211 22 Malmö, Sweden. In t. teL + 46-4010 19 20
37
-
38
Appendix 3
l Il !i Il III
' '
'!;t
' ' ,, '
10;~~ 11!!•
~L:.~ _ej ~ ·~~.~ > l c==~:!d_ L~~ J: 41}
Publikationer fra Nordisk Gasteknisk Center/ Publications from Nordie Gas Technology Centre:
1: Titei/Dato/Forfatter: ISBN nr.: l Titei/Dato/Forfatter: ISBN nr.:
~ Konferencerapporter/Conference reports: l Naturgasfyrade decentrale kraft/-varmevcerker - 1988
Naturgas i industrin - 1988
Forskning och utveckling inom naturgasanvändning - 1988
Forskning og utvikling innanfor naturgassanvendelse - 1988
Naturgas och milj0 - 1989
Industrielle t0rringsprocesser- 1989
Naturgasanvändning inom kraftvärme-saktom - 1990
Naturgas og Milj0 - 1992
Fuel Cell Workshop l - 1989
Reburning Workshop - 1990
Fuel Cell Workshop Il- 1991
Nordisk FUD-Workshop "Naturgasanvendelse" - 1991
Nordisk FUD-Workshop "Naturgasanvendelse" - 1992
Workshop Paper Drying with Gas - 1992
Nordisk FUD-Workshop "Naturgasanvendelse" - 1993
'*' 87-89309-00-6 ~ 87-89309-02-2 ~~
f~
87-89309-04-9
87-89309-13-8
87-89309-06·5
87-89309-08-1 ~:>
~ 87-89309-19-7 i: 87-89309-92-8 1.~ .. ': .. :' 87-89309-27-8 ~!j
87-89309-33-2 f;:: X•: ::::::::::::: l
87-89309-84-7 l ~ 87-89309-90-1 """ ~ w ~>.~
87-89309·95-2 w
Motorer och kraftvärmeaggregat för naturgasdrift - 6/91 E. Danielsson, AF-Energikonsult Syd AB
Cheng Cycle -Et nyt kraftvarmesystem • 9/91 M. Straarup, Axel Nielsen as Rådg. /ng.
Drift· och underhållskostnader vid gasturbinanläggningar i Mellaneuropa • 9/91 H. Gährisch & J. Sjödin, AF-Energikonsult
Användning av gasturbiner vid torkprocesser • Gyprocs gipsskivafabrik i Varberg · 12/91 L. Eriksson & L. De/in, AF Energikonsult
Gasturbinteknologi · Nuläge och utvecklingstrender· 7/92 Jyrl<i Ha/me, Ekono Oy
Kraftvärme med liten gasturbin • Utveckling av koncept för moduluppbyggning • 2/93 A. Sihvola, IVO Intern. Ltd.
Uppgradering av kraftverk • Komplettering med gasturbin • 8/93 Jussi Manninen, Endat Oy
Gasturbineanvendelse ved industriel wrreproces • T0rring af grces- og fjernvarmeproduktion l 01god · 8/93 B. Holm Christensen, dk· TEKNIK
87-89309-48-0
87-89309-78-2
87·89309-41 -3
87-89309-4 7 ·2
87-89309-69-3
87 -89309-83·9
87-89990-00-5
87-89990-02-1
i ~ lndustrlelanvendelsellndustrlal Appllcatlons: r/
Projektrapporter/Research reports: t j
l Industriell gasanvändning i Norden -En branschanalys.
Kraftvarme/Co·Generatlon:
Gasturbinernas tekniska nivå och utvecklingsriktningar - 7/89 Ekono Oy
Erfarenheter från finska gasturbinanläggningar • 4/90 Vesa Junttila, CTS-Engineering Oy
Erfaringer med danske og andre europceiske naturgasdrevne gasmotoraniceg • 1 0/90 Jan de Wit, Dansk Gastekn. Center
Små gasturbiners tekniska nivå och utvecklingsriktningar • 2/91 Ekona Oy
Energiproduktionskostnader med naturgas· 2/91 JP-International Oy
Gassmotorer for kraft/varmeproduksjon: Teknologler for emisjonsbegrensninger - 2/91 O. Stenersen, Marintek!Sintef
Utredning av små gasturbin· och motorkraftverksanläggningar · 2/91 J. Hittunen et al., Neste Oy
~:g ®
l Bind 1 : Uvsmedelsindustri • 4/90 dk-Teknik et al.
i 87-89309-24-3 $ ~:~
Industriell gasanvändning l Norden • En branschanalys. Bind 2: Massa- och pappersindustri • 4/90 dk-Teknik et al. t
~ 87 -89309·15·4 ~
~
l Industriellgasanvändning i Norden -En branschanalys. Bind 3: Kemisk industri • Jord- og stenvaruindustri • Verkstadsindustri - 4/90 dk· Teknik et al. 87-89309-29-4 ~]
~:
87-89309-37-5
87-89309-35-9
87-89309-39-1
87 -89309-40·5
,,.. Autoprofiling with Gas lnfrared t Paper Dryer- 7/91 i ALemaitre & D. G/ise, C. Techn. du Papier
t~ Möjligheten till cogenerering .:~ vid direkttorkning - 8/91 ~ C. Rehn, Lunds Tekniska H6gskola ,;.;:
i~
~i ;::~;
Luftkvaliteter i lokaler vid direktutsläpp av rökgaser från naturgasförbranning - 8/91 U. Jantze & M. Jedeur-Palmgren Theore/1 + VBB Energikonsulter AB
=i: Naturgas vid betongelementtillverkning - 8/91 )~ T. Ehrstedt, Sydkraft Konsult
87 -89309-05· 7
87-89309-11 -1
87-89309-07-3
87-89309-56-1
87-89309-58-8
87 -89309-62·6
87-89309-64-2
.. 21
Publlkatlonerne kan erhverves ved henvendelse tll Nordisk Gasteknisk Center/ The publications are available from the Nordie Gas Technology Centre.
@;:;:;:::::w;;~;::::;:':::::::::::':''"":!l:~:r.-w..m;::::~-w.;;;:;:~;;:::::::'~~~~=~:::;;;:::~;;,~~''':':'''"'''::;m.:<:;:m=.t;;~;~:m,~:'''''~;;:';'T~'*;;;;:~;~:;':'m::?:!m;::;:~~!jj:~i?i!W.~~~==~=:::::::::::''''''''~'~<<i:'::m::~~=~''''::m:<:S?.<;~~~,:::;;;:::::::::::::::r::::
Gasformiga bränslen i glasugnar - 8/91 S. Linzander, Glafo 87-89309-66-9
Mätprogram. Arbetsmiljöförhållanden vid förbränning av naturgas för koldioxidgödsling l växthus- 2/91 A-B. Antonsson, lnst. för Vatten- och Luftv. 87-89309-70-7
Mätprogram. Arbetsmiljöförhållanden vid förbränning av naturgas för koldioxidgödsling i växthus. Kortversion- 2/91 A-B. Antonsson, lnst. för Vatten- och Luftv. 87-89309-72-3
Konvertering av aluminiumsmältugnar -Förstudie - 12/91 O. Hall & C. Rehn, Sydkraft Konsult 87-89309-49-9
Optical Properties of Wet Paper and Simulation of the Effect of Autoprofiling on Gas-flred IR Drying- 12/91 K. T. Oja/a & M.J. Lampinen, Helsinki University of Technology 87 -89309-51 ·0
Användning av en gasturbin för tillverkning av raffinör- (TMP) och slipmassa (PGW)- 1/92 R. Askola & V. Junttila, CTS Engineer/ng OY 87-89309-55-3
Användning av en gasdriven dieselmotor för tillverkning av raffinör- (TMP) och slipmassa (PGW)- 1/92 R. Askola & V. Junttila, CTS Engineer/ng OY 87-89309·59·6
Naturgasanvändning l schaktugn för blysmältning - 3/92 B. Lundborg, Sydkraft Konsult 87·89309-61-8
Diract Gas Firad Cylinder Heater for Paper Drying - 9/92 Vesa Junttila, Jamcon Oy 87-89309-77-4
Gas-lA på wellpappmaskin - Försök vid SCA Emballage AB, Värnamo - 9/92 T. Gustafsson, SCA Research AB & l. Gunnarsson, Energi Analys AB 87-89309-79-0
Rekuperativa naturgasbrännare - Utvärdering av konvertering från olja till naturgas i en vagnugn hos Svedala Arbrå- 11/92 B. Leden & A. Rensgard, MEFOS-BTF 87-89309-82-0
Koldioxidgödsling i växthus med hjälp av naturgas · 11/92 S-A. Moten, Mäster Grön, Hetsingborg 87-89309-86-3
Forbramdlngsteknlk/Combustlon Technology:
Modeling and Chemical Reactions - Review of Turbulence and Combustion Models • 7/89 N.!. Lilleheieetal., SINTEF 87-89309-10-3
Modellering og Kemisk Reaktion -Statusrapport: Reaktionskinetisk databaset Den kemisk kinetiske modal- 7/89 P. G/arborg & S. Hadvig, DTH 87-89309-16-2
The Fuei-Rich Hydrocarbon/Nitrogen Chemistry - lmplications for Reburning with Natural Gas - 11/89 P. Glarborg & S. Hadvig, DTH 87-89309-32-4
ti ~ i Modelling and Chemical Reactions -f Development and Test of a Kinatic Modal ~~ for Natural Gas Combustion - 3/91
'_.l_,k_,;_,~_,l ~·o~~~~:::: ~~:~~~~~~=lons -. Development and Test of Reduced Chemical i Kinatic Maehanism for Combustion of ~,' Mathane - 5191 -~
l N./. Lillehele et al., SINTEF ;.i!:
*~ Reburnlng - International Experiences with Reburning with Special Emphasis on Reburning Fuellnjection and Mixing- 7/89 S. Byggsteyl et al., SINTEF l
~ Reburning - Status over internatlonale ~® erfaringer- 7/89 w P. Glarborg & S. Hadvig, DTH
l~=~ Reburnlng - Reburning using Natural Gas • Polentialin Finland • 2/90
t;· S. Boström & M. Hupa, Abo Akademi
Reburning • Reburning med naturgas på ifiii kulsltavsfyrede kedler -!if~ Polantiale i Danmark - 2/90
~~~ ~~~~;~~~a~=~:::~~:n:ad naturgas -~® Potential l Sverige - 2/90
l :=~n~:·. ~~:~;i:::~~:~:~olan if Analy1ical and Experimental Study - 4/90
87 ·89309-36-7
87-89309-31-6
87 ·89309-44-8
87-89309-50-2
87-89309-14-6
87-89309-18-9
87·89309-34-0
87-89309-01-4
87 ·89309-03-0
a.:.:···.:·::· !~::~~:~~ ;:~~~:~:'·s~~;::~:~b:t:~~:olm 87-89309-17-0
\~= teknikkan på kulst0vsfyrede kedler- 8/90 :§: A. N0rregaard, dk-Teknik .f '''~ Reburning - Injektion av strålar i en
r-.,~_,',~.'.;_',: ~~~~~::'e~ :~~~ung/iga Tekn. Högskolan
Reburning • Parametric Study of Natural
~~! ~~~~l~nb~~s~:Oemistry using Kinatic
jj)j P. Kilpinen et al., Abo Akademi Univ.
:_._,i_~.·._f,i HDevelopment Projaet in Limhamn District . eating Central. - Reburning, Modelling {' Wand Experiments in a 125 MW Hot ·· ater Boiler - 3/91 .] R. Go/lin, Kungliga Tekniska Högskolan ) t !l'{ i§·
t J
Mathematlcal Modelling of Reburnlng -Oescrlption of Methods and Appllcation to the Limhamn Boiler andAmager Boller . 7/91 B. Laksb et al., SINTE F
87-89309-21·9
87-89309-23-5
87-89309-25-1
87-89309-42-1
87 ·89309-54-5
... 31
Publikationerna kan erhverves ved henvendeJsa t11 Nordisk Gasteknisk Center/ The publications are available from the Nordie Gas Technology Centre.
Reburnlng - Process Parameters, lmplementation and NO.-reductlon Potential - 9/91 P. Glamorg, DTH & B. Karl, NGC
Technlcal and Economic Feaslbllity of Reburnlng using Natural Gas in Finland - 9/91 A. Ahola et al., Neste Oy
~~ ;;~
~J i t
87-89309-76-6 ~~ ~
l f;
Naturgas tll Fur Fmrgen- Teknisk/0konomlsk studium af mulighederne for N-gas drift af fmrgen Branden-Fur- 7/92 L Nielsen, Dansk Teknologisk lnst.
Bedrift0konomisk analyse av naturgassdrift av busser l Norden • Fase Il. Delprosjekt: Marked - 8/92
87 ·89309-75-8
Rebumlng Simulator- Implementallan of a General Formalism for the Eddy Dissipation Concept in KAMELEON Il • 5/92
87-89309-45-6 ~ K.-E. Hagen et al., Transportekon. lnst., Oslo 87-89309-73-1
N./. L/lleheie et al., SINTE F
Reburnlng Rlch-Lean Kinatics -Annual Report 1991 - 6/92
87-89309-63-4
Gas Research Institute 87-89309-65-0
statusrapport for methanudslip fra naturgasanlmg i de nordiske lan de - 10/89 K. Christiansen, dk-Teknik 87-89309-20-0
status Report concerning Mathane Release from Natural GasSystems in the Nordie Countries - 1 0/89 K. Christiansen, dk-Teknik 87-89309-38-3
Energi og Milj0 i Norden - 5/91 B. Holm Christensen, dk· Teknik 87-89309-46-4
Reduction of Np from Combustion in Circulating Fluidized Beds with Afterbumlng of Gas - 11192 L Gustavsson & B. Leckner, Chalmers Univ. 87-89309-80-4
Modellng and Reburning Actlvities 1992 • 6/93 N./. Lillehele et al., SINTEF 87-89309-89-8
Modellng of the Holstebro-Struer furnace • 6/93 N./. Lillehele et al., SINTEF 87 -89309-93-6
Reburnlng Rich-Lean Kinatics -Annual Report 1992 - 6/93 Gas Research Institute 87-89309-97-9
Reduktion af NO.-emission fra naturgasfyreda industrikedler- 7/93 Jan de Wit et al., DGC 87-89309-99-5
NO. Reduction using Reburning with Natural Gas - Final Report from Fuii-Scale Trial at SYSAV's Waste Incineration Plant in Malmö - 9/93 Jan Bergström, Miljökonsulterna 87-89990-04-8
Energi- og mlljsanalyser/ Energy and Envlronmental Analyses :
Naturgas l kelaprocesser - 12/91 G. Minds et al., Dansk Teknologisk lnst.
Gas as Vehicle Fuel in the Nordie Region -Ongolng Field Tests invalving Natural Gas, Biogas and Propane - 8/92 A.M. Hansen, NGC
87-89309-53-7
87-89309· 71 -5
C02-Teknologi- Litteraturstudie om utskilling
J og deponering - 3/93 M. Matre et al., Berdal Stremme a. s.
Metanreduktion i katalysatorer för ~ naturgasmotorer - 3/93
m. ~ H. Boman, Vattentall Energisystem
~~ ~
* t i t i
m w. ?::
~ i
l l i l*
l l @ .; .. , f~j
' ;il
NGAS Database:
Nordie R& D Projaets within the field of Natural Gas Oownstream TechnologiesDlrectory 1990 -
Nordiske FUD projakter lndenfor naturgasanvandeisa - Katalog 1992
87-89309-85-5
87-89309-87-1
87-89309-30-8
87-89309-67.7
20.993