Nuclear power plant siting

International Nuclear Power ConferenceOctober 23, 2009, Tallinn

Page 2: Nuclear power plant siting International Nuclear Power Conference October 23, 2009, Tallinn

Pohjonen, 23rd October 2009

2

Pöyry - Global expert in consulting and engineering

• We offer our clients in-depth industry expertise, innovative solutions and lifecycle engagement

• 17 000 projects annually

• Annual turnover 820 M€ (2008)

• 7 000 employees in 49 countries

• Project experience in more than 100 countries

Page 3: Nuclear power plant siting International Nuclear Power Conference October 23, 2009, Tallinn

Pohjonen, 23rd October 2009

33

Pöyry group - Five business groups

Core operations are based on five know-how clusters

(c) grafikdienst.com

Energy Water & Environment

Forest Industry Construction Services

Transportation

Page 4: Nuclear power plant siting International Nuclear Power Conference October 23, 2009, Tallinn

Pohjonen, 23rd October 2009

4

Pöyry‘s Consulting and Engineering Services cover the entire life-cycle of nuclear energy

Development & Pre-Construction

Project implementation

Assets Operation Decommissioning

• Project Strategy &Organisation

• Financial modelling

• ICT studies & solutions

• Stakeholder management & public consultation

• Siting Studies

• Reactor technology studies

• Infrastructure studies & solutions

• Decommissioning, waste management & fuel strategies

• Environmental impact assessment

• Fuel studies

• (Pre- )Feasibility studies

• Conceptual & Basic Engineering

• Tender documentation & bid evaluation

• Safety assessment & licensing support (to Owner’s and Regulators)

• Consulting to Lenders

• Project management

• Project controlling

• Design review

• Supervision of construction & commissioning

• Quality Assurance & Quality Control

• Shop Inspections & Expediting

• Site & Construction supervision

• Commissioning supervision

• Safety assessment & licensing support

• Detailed and site engineering for vendors

• Safety assessment for regulators

• Consulting to Lenders

• Engineering and supervision of back-fitting/upgrades

• Power uprate studies

• Organisation review and design

• Operational optimization studies

• Life extension studies

• Alternative fuel studies

• Waste characterisation & inventory studies

• Decommissioning studies

• Safety assessment & licensing support

• Safety assessment for regulators

• Consulting to Lenders

• Detailed decommissioning studies & engineering

• Supervision of decommissioning and dismantling operations

• Waste treatment & packaging studies & engineering

• Waste repository studies & engineering

• Waste characterisation & inventory studies

• Safety assessment & licensing support

• Safety assessment for regulators

Page 5: Nuclear power plant siting International Nuclear Power Conference October 23, 2009, Tallinn

Pohjonen, 23rd October 2009

55

Permitting procedures for a nuclear plant in Finland

Other clarifications to be appended to the decision-in-principle application

EIA programme

DECISION-IN-PRINCIPLE Pursuant to the Nuclear Energy Act

•Preliminary safety assessment from the Radiation and Nuclear Safety Authority•Approval from the location municipality•Decision-in-principle from the Government•Ratification from the Parliament

LAND USE PLANNING

•National Land Use Guidelines

•Regional Land Use Plan•Local Master plan•Local Detailed plan

Construction license pursuant to the Nuclear Energy Act from the Government

Permits pursuant to the Environmental Protection Act

Construction of the plant and infrastructure

Building permitPermits pursuant to the Water Act

Operation license pursuant to the Nuclear Energy Act from the Government

Commissioning of the power plant

Monitoring and potential renewal of permits

EIA report

Page 6: Nuclear power plant siting International Nuclear Power Conference October 23, 2009, Tallinn

Pohjonen, 23rd October 2009

6

The purpose of site screening is to justify the selection of few sites for further development

• Site screening is done in the very beginning of the NPP project development when several possible NPP sites have been identified

• The target of the screening is to analyse and rank several sites in order to enable further development of only a few sites without major surprises – in other words, to optimally allocate the substantial investment required for further development

• More detailed assessment is carried out in the chosen sites as the project proceeds to permitting phases

Permits in accordance with the Finnish Nuclear Energy Act

Decision in Principle Construction License Operation License

Page 7: Nuclear power plant siting International Nuclear Power Conference October 23, 2009, Tallinn

Pohjonen, 23rd October 2009

7

Guidelines used in site screening

International:• Site Survey for Nuclear Power Plants IAEA Safety Series No.  50-SG-S9

(1984)• Site Evaluation for Nuclear Installations Safety Requirements

IAEA Safety Standards Series No. NS-R-3 (2003)• External Human Induced Events in Site Evaluation for Nuclear Power

Plants Safety Guide IAEA Safety Standards Series No. NS-G-3.1 (2002)• Dispersion of Radioactive Material in Air and Water and Consideration of

Population Distribution in Site Evaluation for Nuclear Power Plants Safety Guide IAEA Safety Standards Series No. NS-G-3.2 (2002)

• Evaluation of Seismic Hazards for Nuclear Power Plants Safety Guide IAEA Safety Standards Series No. NS-G-3.3 (2003)

• Meteorological Events in Site Evaluation for Nuclear Power Plants Safety Guide IAEA Safety Standards Series No. NS-G-3.4 (2003)

• Flood Hazard for Nuclear Power Plants on Coastal and River Sites Safety Guide IAEA Safety Standards Series No. NS-G-3.5 (2004)

• Geotechnical Aspects of Site Evaluation and Foundations for Nuclear Power Plants Safety Guide IAEA Safety Standards Series No. NS-G-3.6 (2005)

National (Finland):• Safety criteria for siting a nuclear power plant STUK YVL 1.10

(2000)• Other related regulations

International Atomic Energy Agency

The Radiation and Nuclear Safety Authority of Finland

Page 8: Nuclear power plant siting International Nuclear Power Conference October 23, 2009, Tallinn

Pohjonen, 23rd October 2009

8

Pöyry approach to the assessment of alternative nuclear power plant sites

Land use Political Socioeconomic Environmental

GridCoolingGeology

2) Political, socioeconomic and environmental feasibility

1) Technical and commercial feasibility

Logistics Nuclear specific

In addition, careful identification of “show stoppers” and major risks is of crucial importance.

The sites are assessed and scored against two main sets of criteria, which are divided to several subsets of criteria

Page 9: Nuclear power plant siting International Nuclear Power Conference October 23, 2009, Tallinn

Pohjonen, 23rd October 2009

9

0

10

20

30

40

50

60

70

80

90

100

0 20 40 60 80 100

Technical and commercial feasibility

Po

litic

al, e

nvi

ron

men

tal a

nd

so

cio

-ec

on

om

ic f

easi

bili

ty

Site 1

Site 2

Site 3

Site 4

Site 5

Site 6

Site 7

Site 8

Site 9

Site 10

Site N

Site 1Site 2

Site 3

Site 4Site 5

Site 6

Site 7

Site 8

Site 9

Method enables trade- offs and decision making

between different site specific risks in project

development

Illustrative summary of the results shows strengths and weaknesses of each area or site

Method enables clear presentation of

unfeasible or excluded areas.

Page 10: Nuclear power plant siting International Nuclear Power Conference October 23, 2009, Tallinn

Pohjonen, 23rd October 2009

10

Conclusion

A comprehensive, versatile and professional site-screening results in optimal selection of the site and thus

decreases project risks related to site-spesific issues

however, as the issue of nuclear power is complex in any society, this does not mean that everybody would be happy with the project or even with the site selection.