Objective ATC 17
ESSIP Plan 2013
Luca DELL’ORTODSS/EIPR
13.09.2013
2
Comprehensive Explanation
Target Date: 12/2018 SCOPE: ECAC – All States except SK
Electronic dialogue as automated assistance to controller during coordination and transfer addresses the facilities and processes between ATC components serving ATC units.
ATC17 complements ITY-COTR. Purpose:
Co-ordination prior to the transfer of flights from one ATC unit to the next;
Transfer of communication from one ATC unit to the next ATC unit of such flights;
Support the exchange of OLDI messages related to the Basic procedure and, if applicable, SSR Code Assignment Message.
ESSIP Plan 2013 / Objective ATC17
3
What is new or has changed for ESSIP Plan ed. 2013
Change in the applicability area: removal of SK
ESSIP Plan 2013 / Objective ATC17
4
Link to European ATM Master Plan and/or Interim Deployment Programme (IDP)
Eur. ATM Master Plan:[CM-0201] – Automated Assistance to Controller for Seamless Coordination, Transfer and Dialogue - ESSENTIAL
IDP:WP 5.2
ESSIP Plan 2013 / Objective ATC17
5
Most important SLoA(s)
All
Note: whereas this objective is defined with an ECAC scope, it will be the decision of the individual ATS Provider to: define its local applicability in terms of relevant ATSUs, and identify the processes to be implemented (refer to ATC17 SLoAs and in
particular, their finalisation criteria, for the complete list of processes).
ESSIP Plan 2013 / Objective ATC17
6
Finalisation Criteria and Closed Questions
For REG01: Formal acceptance by NSA of the proposed changes
For ASP01: Deliver safety arguments for all changes related to implementation of electronic
dialogue for Coordination and Transfer.
For ASP02/3/4 (important to clearly identify ATSUs involved and which processes are implemented):
Ground systems updated Technical File with evidences of compliance to EC Declaration of Verification; Functions (form the list in it he individual SLoAs) documented and in operational use.
For ASP05: Training plans updated and training package developed by the ANSP for the use of
electronic dialogue procedure.
ESSIP Plan 2013 / Objective ATC17
7
Supporting Material
EUROCONTROL-Specification for On-Line Data Interchange (OLDI) Edition 4.2 (OJEU Reference 2011/C 146/05)
EUROCONTROL-System Supported Coordination (SYSCO) Implementation Guidelines
ESSIP Plan 2013 / Objective ATC17
8
ESSIP Report 2012
Objective introduced in the ESSIP Plan in 2012. No ANSPs have reported it as completed; 6 reported it partially
completed (functionalities available and ATCOs trained but not implemented operationally). This requires agreement with neighbouring ACCs where the same functionalities must be available.
From the reported ANSP plans, the current estimate for achievement is 12/2016 for 80% of the applicable area.
ESSIP Plan 2013 / Objective ATC15
9
Links and contacts
Objective Coordinator: Dell’Orto Luca, +32 2 729 3325
EUROCONTROL Objective Expert:
Stephen Morton, +32 2 729 3492
ESSIP Plan 2013 / Objective ATC17