30
1 ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 County: LUCAS Route: Taylor Rd Section: 2123 Table of Contents: Section Page 2 1 Project Identification 2 1A Prima Facie Speed Limit 2 1B Railroad Coordination 2 1C Airway/Highway Clearance 2 2 Pre-bid Meeting 2 3 Addenda Process 3 4 Pre-qualification 3 5 Design Consultant 3 6 Scope of Work 4 7 Field Office 4 8 General Provisions for The Work 4 9 Hazardous Materials 9 10 Environmental 10 11 Right of Way (ROW) 11 12 Utilities 11 13 Design and Construction Requirements: Maintenance Of Traffic (MOT) 17 14 Design and Construction Requirements: Location & Design 18 15 Design and Construction Requirements: Structures 21 16 Design and Construction Requirements: Traffic Control 23 17 Project Schedule Requirements 24 18 Plan Submittals and Review Requirements 24 19 Buildable Units 27 20 Index of Attachments 29

ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

1

ODOT

DESIGN BUILD

SCOPE OF SERVICES

OHIO BRIDGE PARTNERSHIP PROGRAM

PID # 97648

Package # LUC Taylor Rd Gp4 Muni FY15

County: LUCAS Route: Taylor Rd Section: 2123

Table of Contents:

Section Page

2

1 Project Identification 2

1A Prima Facie Speed Limit 2

1B Railroad Coordination 2

1C Airway/Highway Clearance 2

2 Pre-bid Meeting 2

3 Addenda Process 3

4 Pre-qualification 3

5 Design Consultant 3

6 Scope of Work 4

7 Field Office 4

8 General Provisions for The Work 4

9 Hazardous Materials 9

10 Environmental 10

11 Right of Way (ROW) 11

12 Utilities 11

13 Design and Construction Requirements: Maintenance Of Traffic (MOT) 17

14 Design and Construction Requirements: Location & Design 18

15 Design and Construction Requirements: Structures 21

16 Design and Construction Requirements: Traffic Control 23

17 Project Schedule Requirements 24

18 Plan Submittals and Review Requirements 24

19 Buildable Units 27

20 Index of Attachments 29

Page 2: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

2

1. PROJECT IDENTIFICATION

PID: 97648 State Project Number: 427462 Federal Project Number: E140436

County: LUCAS Route: Taylor Rd Section: 2123

Local Route Name: Taylor Rd

Highway Functional Classification & Federal Aid System: Local Road-Urban

1.1 Design Designation:

Current ADT: 250 (2014)

Design Year ADT: 500 (2034)

Peak Hour Factor: N/A

Directional

Distribution: N/A

Trucks: N/A

Design Speed: 35 MPH

Legal Speed: 25 MPH

Design Functional

Classification: Local Road-Urban

NHS Route: No

1.2 Existing plans: The existing plans are attached to this scope as part of Attachment B.

These are NOT as-built plans. The Design-Build Team (DBT) is advised to verify the preceding

referenced plans to determine if they accurately depict existing field conditions.

1A PRIMA FACIE SPEED LIMIT

Not applicable .

1B RAILROAD COORDINATION

Not applicable.

1C AIRWAY/HIGHWAY CLEARANCE

Not applicable.

2 PRE-BID MEETING

Not applicable.

Page 3: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

3

3 ADDENDA PROCESS

Direct all questions prior to the letting date to the following Pre-Bid Website (use submittal

form):

http://www.dot.state.oh.us/Divisions/ContractAdmin/Contracts/Pages/PBQs.aspx

4 PRE-QUALIFICATION

It is required that the bidder be an ODOT pre-qualified Contractor who has engaged the services

of an ODOT pre-qualified Consultant to perform all the design and construction work required in

these Conceptual Documents. If the Consultant and/or the Sub-Consultant(s) submitted do not

meet all the required qualifications, the Office of Contracts may reject the bid.

5 CONTRACTOR’S CONSULTANT

The Contractor must name the Consultant and all Sub-Consultant(s) in the space(s) provided

below. If the Contractor is going to submit an electronic bid, then the Consultant and all Sub-

Consultant(s) must be listed on the following web-page:

http://www.dot.state.oh.us/DIVISIONS/PRODMGT/CONSULTANT/Pages/default.aspx. The

Contractor must list relevant prequalification categories for prime and sub-consultants to show

that the prequalification requirements listed below are satisfied. All Consultant names and

addresses must be the same as that on file with the Department. The following work types must

be performed by members of the Consultant Team (combination of Consultant and Sub-

Consultant(s)):

Non-Complex Roadway Design, Level 1 Bridge Design,Geotechnical Engineering

Services

Consultant

Firm Name: _________________________________________________

Address: _________________________________________________

List work types the Consultant will perform:

_______________________________________________________________________

_______________________________________________________________________

_______________________________________________________________________

Sub-Consultant

Firm Name: _________________________________________________

Address: _________________________________________________

List work types the Sub-Consultant will perform:

_______________________________________________________________________

_______________________________________________________________________

Page 4: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

4

Sub-Consultant

Firm Name: _________________________________________________

Address: _________________________________________________

List work types the Sub-Consultant will perform:

_______________________________________________________________________

_______________________________________________________________________

Restrictions on Participation in Design-Build Contracts:

Any Consultant who provided services to the Department that has been directly utilized in this

design-build proposal or Scope of Services document will NOT be eligible to participate in this

design-build contract for this project, either as a prime consultant or as a sub-consultant.

6 SCOPE OF WORK

Approx. Work Limits: From: Sta. 9+15.00 To: Sta. 10+90.00

Approx. Work Length: 175 ft. Final Work Length and Limits shall be determined by

the DBT.

The Consultant shall provide for the engineering services, design, and preparation of detail

construction plans for the construction of the proposed project.

The Contractor shall provide for the furnishing of materials, construction and completion in every

detail of all the work described in the Conceptual Documents in order to fulfill the intent of the

contract.

Project Description: Remove entire existing bridge and approach pavement and

replace with a new bridge and any necessary wingwalls.

Completion date: August 1, 2015

Warranties: None

The Contractor will perform the work according to Proposal Note 129 and the Window

Contract Table below.

Project Calendar Days to Complete All

Work on Project

Taylor Rd. Bridge 90days – w/ a max. 45 day closure

7 FIELD OFFICE

Field office Type B, as required by Construction and Material Specification Item 619, shall be

available and completely functional no later than 1 week prior to the start of construction work.

8 GENERAL PROVISIONS FOR THE WORK

8.1 Governing Regulations:

Page 5: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

5

All services, including but not limited to survey, design and construction work, performed by the

DBT and all subcontractors (including sub-consultants), shall be in compliance with all

applicable ODOT Manuals and Guidelines.

The fact that the bid items for this Design-Build project are general rather than specific shall not

relieve the DBT of the requirement that all work performed and all materials furnished shall be in

reasonable conformity with the specifications. The Contractor’s Consultant shall reference in the

plans the appropriate Construction and Material Specifications Item Number for all work to be

performed and all materials to be furnished.

The attention of the Bidder is directed to the provisions of section 100 of the Construction and

Material Specifications as modified in the design-build proposal.

It will be the responsibility of the DBT to acquire and utilize the necessary ODOT manuals that

apply to the design and construction work required to complete this project.

The current edition, including updates released on or before the prebid meeting date, of the

following ODOT Manuals and Guidelines shall be met or exceeded in the performance of the

design and construction work required to complete this project:

Bridge Design Manual

Location and Design Manuals

Volume One - Roadway Design

Volume Two - Drainage Design

Volume Three - Plan Preparation

Pavement Design & Rehabilitation Manual

Specifications for Geotechnical Explorations

Survey Manual

Construction and Material Specifications

Proposal Notes for Construction and Material Specifications

Supplemental Specifications for Construction and Material Specifications

Item Master

Manual for Abandoned Underground Mines - Inventory and Risk Assessment

Pavement Design and Rehabilitation Manual

State Highway Access Management Manual

Standard Construction Drawings

Plan Insert Sheets

Traffic Engineering Manual

Ohio Manual of Uniform Traffic Control Devices

Real Estate Administration Policies and Procedures Manual:

Appraisal

Acquisition Property Management

Relocation

ROW Plans

Utilities

Wireless Communication Tower Manual

Environmental Services Handbooks and Guidelines

Waterway Permit Manual

Design Mapping Specifications

CADD Engineering Standards Manual

Geotechnical Bulletins

Page 6: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

6

Project Development Process Manual (Appendix B)

8.2 Basis of Payment:

All Items covered by Construction and Material Specifications, Supplemental Specifications,

Proposal and Special Provision notes with unit price as a basis of payment will be paid for under

the appropriate Lump Sum bid item, unless a unit line price item has been established in the

Scope of Services.

The Consultant shall be required to furnish the Department with a complete breakdown of the

lump sum bid items. The breakdown shall include materials to be used in the work, and shall be

in sufficient detail to provide ODOT with a means to check partial payment requests.

8.3 Final Payment:

The DBT shall prepare and submit the following prior to the request for final payment:

1. All original project files and notes utilized in the preparation of the survey, design and

construction of the project

2. Record-Drawings Plans as required in section 8.4 below.

8.4 Record-Drawing Plans:

A. General: At the completion of the work, prior to final acceptance of the construction, the

Consultant shall furnish the Department Record-Drawing construction plans. When the Record-

Drawing plans are completed the Consultant shall professionally endorse (sign and seal) the title

sheet.

Record-Drawing plans will be submitted as TIFF Images as per the Electronic Plan File

Submissions Guidelines as shown on the ODOT Web Site at:

(http://www.dot.state.oh.us/DIVISIONS/CONTRACTADMIN/CONTRACTS/Pages/TIFF.aspx)

In addition to the information shown on the construction plans, the Record-Drawing plans shall

show the following:

- All deviations from the original approved construction plans which result in a

change of location, material, type or size of work.

- Any utilities, pipes, wellheads, abandoned pavements, foundations or other major

obstructions discovered and remaining in place which are not shown, or do not

conform to locations or depths shown in the plans. Underground features shall be shown

and labeled on the Record-Drawing plan in terms of station, offset and elevation.

- The final option and specification number selected for those items which allow

several material options under the specification (e.g., conduit).

- Additional plan sheets may be needed if necessary to show work not included in the

construction plans.

- Notation shall also be made of locations and the extent of use of materials, other

than soil, for embankment construction (rock, broken concrete without reinforcing

steel, etc.).

- The Plan index shall show the plan sheets which have changes appearing on them.

- Each plan sheet shall have its last revised date noted on the sheet and clearly

marked ‘As Built’.

Two copies of the Record-Drawing plans shall be delivered to the Project Engineer for approval

upon completion of the physical work but prior to the request for final payment. After the

Page 7: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

7

Department has approved the Record-Drawing plans, the original tracings and the associated

electronic files shall be delivered to the District Production Administrator. Acceptance of these

plans and delivery of the original tracings and the associated electronic files is required prior to

the work being accepted and the final estimate approved.

The delivered original tracings shall be prepared in conformance with the Location and Design

Manual, Volume 3, Section 1200 - Plan Preparation.

B. CADD files supplied by Consultant: X Yes No

If marked yes, the Consultant shall comply with ODOT’s CADD Standards, and supply files in

accordance with the CADD Engineering Standards Manual. All data shall be provided to the

Department according to the provisions as detailed under the appropriate CADD links accessed

from the Department’s Office of Production’s web site. This includes, but is not limited to, the

level assignments, symbols, lines and line styles that are to be used, line weights, cells, placement

of text and file naming conventions. The web site can be accessed at the following URL address:

http://www.dot.state.oh.us/Divisions/ProdMgt/Production/CADD/Pages/default.aspx

http://www.dot.state.oh.us/Divisions/ProdMgt/Production/Pages/default.aspx

The following can be accessed from the above URL addresses:

1. ODOT CADD Standard files by selecting the “Microstation Downloads” link

2. ODOT’s Location and Design, Volume 3 by selecting the “L&D Manual Vol. 3" link

3. ODOT’s GEOPAK Standards by selecting the “GEOPAK Downloads” link

The Department will accept CADD files on CD ROM or DVD electronic media.

1. The Consultant shall submit all CADD information produced in the process of plan

development. All CADD information shall be submitted in the current version of

MicroStation (*.dgn) format as indicated in the CADD Engineering Standards Manual.

This requirement ensures that ODOT receives an end product that is directly usable on

ODOT’s CADD systems without additional work. The responsibility to provide the

Department with correct and complete CADD data rests with the consultant.

2. The Consultant shall submit all GEOPAK information produced in the process of plan

development according to L&D Volume 3, Section 1500. The submission shall include

all files generated by GEOPAK as the result of the plan processing and these files shall

include but are not limited to the following:

a. Coordinate databases (*.gpk)

b. Digital terrain models (*.tin)

c. Original cross section (XS) cell design files

d. Edited observation files (*.obs)

e. ASCII text files containing all raw point data (PT #, X, Y, Z, Linking

Code/Mapping Code)

f. ASCII text files containing all adjusted point data (PT #, X, Y, Z, Linking

Code/Mapping Code, Attribute data if any)

g. ASCII text file(s) listing chain data for all existing and proposed horizontal

alignments; including the centerline of construction, the centerline of right of

way and ramp baselines.

Page 8: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

8

h. ASCII text file(s) listing vertical alignment data for all existing and proposed

profiles.

i. ASCII text files listing the Northing, easting, station, offset and elevation for all

existing and proposed monuments.

A separate file name should be used for each horizontal or vertical alignment. The CADD

Engineering Standards Manual provides specific requirements for the content of the

required ASCII reports and provides directions on how to create these reports using

GEOPAK software.

These requirements and procedures may be updated from time to time with notification in the

Design Reference Resource Center (DRRC) website which is located at the following URL,

http://www.dot.state.oh.us/drrc/. Organizations exchanging ODOT CADD data are responsible

for ensuring they are using the current version of these requirements, CADD reference manuals,

ODOT cell files and ODOT seed files.

8.5 Post-Letting Conference:

Within 10 days after bid opening, the DBT will attend a mandatory post-award meeting. This

confidential meeting will be held with the Estimating Office of the Division of Contract

Administration to discuss the Lump Sum estimate with the Department of designated

representative.

8.6 Partnering Agreement:

The Contractor is required to enter into a self-facilitated partnering agreement with the

Department on this project per CMS 108.02. The objective of this agreement is the timely

completion of the work and a quality product that will be a source of pride to both the Department

and the Contractor. Partnering will not affect the terms and conditions of the contract.

8.7 Communication:

All communication during design and construction shall be with the District Project Manager and

the District Project Engineer.

District’s Project Manager’s Name: Natina Ariss

Phone number: 419-373-4440

E-mail: [email protected]

The District Project Engineer shall be named at the pre-design meeting.

At the pre-design meeting, the Contractor shall name a Project Manager who will act as a liaison

between the DBT and the Department.

8.8 Permits:

Contractor will be required to obtain a permit from the State or local government having

jurisdiction, to perform any non-construction work within the existing Right of Way and/or

limited access.

Page 9: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

9

8.9 Entry On Private Property:

The DBT, acting as The Department’s agent, may enter upon any lands within the State

for the purpose of inspecting, surveying, leveling, digging, drilling, or doing any work deemed

necessary in the execution of any survey authorized by the Director of Transportation in

accordance with Section 5517.01 of the Ohio Revised Code and Section 102.6 (inclusive of

Sections 102.61 through 102.66) of ODOT’s Survey Manual. Prior to performing said survey,

the DBT will send notification letters indicating the date and duration of entry to the affected

property owners no less than forty-eight hours nor more than 30 days prior to the date of entry for

said survey in accordance with 102.6 of ODOT’s Survey Manual. The DBT shall forward copies

of all notification letters distributed to ODOT’s Project Manager. Any subsequent claims for

compensation due to damages incurred while said survey was being performed will be negotiated

between the DBT and the affected property owners with final approval from ODOT’s Project

Manager. Crop and property damage minimization and reimbursement information, together

with the crop damage reimbursement formula and Special Waiver of Damage form, will be

provided to the DBT by ODOT’s Project Manager. Any subsequent entries onto private property

for the purpose of obtaining additional survey or soil information prior to the submission of the

bid will be made in accordance with the procedures outlined in this section.

9 HAZARDOUS MATERIALS

The following plan note is required:

DISPOSAL OF EXCAVATED CREEK SEDIMENT

SEDIMENT MATERIALS EXCAVATED AND REMOVED FROM OTTER CREEK (AT OR

BELOW THE NORMAL WATER LEVEL) MAY CONTAIN POTENTIALLY

CONTAMINATED MATERIALS. ANY OF THE SAID EXCAVATED MATERIAL SUCH

AS, BUT NOT LIMITED TO, DRUMS, TANKS, OR STAINED EARTH OR ANY UNUSUAL

ODORS, SUCH AS, BUT NOT LIMITED TO, A HYDROCARBON, SHALL BE

CONSIDERED POTENTIALLY CONTAMINATED MATERIALS.

POTENTIALLY CONTAMINATED MATERIALS EXCAVATED BY THE CONTRACTOR

ARE TO BE STOCKPILED AND APPROPRIATELY DEWATERED IN AN AREA

PROVIDED BE THE CONTRACOR AND APPROVED BY THE ENGINEER. THE

ENGINEER MAY PERMIT TEMPORARY STORAGE OF THE EXCAVATED MATERIALS

IN LINED AND COVERED ROLL-OFF BOX. THE ENGINEER MAY PERMIT

TEMPORARY STORAGE OF THE EXCAVATED MATERIALS ON AN IMPERMEABLE

MEMBRANE. THE EXCAVATED MATERIALS SHALL BE APPROPRIATELY MANAGED

PER ENGINEER APPROVAL TO PREVENT THE EXCAVATED MATERIALS FROM

COMING IN CONTACT WITH THE UNDERLYING ORIGINAL SOILS. AN

IMPERMEABLE MEMBRANE SHALL BE PLACED OVER THE STOCKPILE TO

PREVENT CONTACT WITH PRECIPITATION AND/OR SURFACE RUNOFF. ANY

LIQUID RUNOFF FROM THE EXCAVATED MATERIALS SHALL BE APPROPRIATELY

MANAGED IN ACCORDANCE WITH LOCAL, STATE AND FEDERAL LAWS.

THE CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING ALL NECESSARY

PERMITS AND APPROVALS AND TO TRANSPORT THE MATERIALS TO A LICENSED

(BY THE LOCAL HEALTH DEPARTMENT) AND PERMITTED (BY THE OHIO

ENVIRONMENTAL PROTECTION AGENCY) SOLID WASTE DISPOSAL FACILITY TO

DETERMINE IF ANY ADDITIONAL TESTING IS REQUIRED FOR DISPOSAL AND WILL

BE RESPONSIBLE FOR CONDUCTING ANY ADDITIONAL SAMPLING AND ANALYSIS

OF THIS MATERIAL.

Page 10: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

10

THE CONTRACTOR SHALL FURNISH ALL THE LABOR, EQUIPMENT, AND

MATERIALS NECESSARY TO PROPERLY HANDLE, STORE (IF NECESSARY), TEST

FOR DISPOSAL, TRANSPORT AND DISPOSE OF REGULATED MATERIALS,

INCLUDING ANY REQUIRED PERMITS, APPROVALS OR FEES WITHIN THE PROJECT

LIMITS. PAYMENT FOR THIS WORK SHALL BE MADE AT THE CONTRACT PRICE

BID PER TON.

10 ENVIRONMENTAL

10.1 Waterway Permits:

ODOT will obtain the applicable Nationwide Permit or Regional General Permit required to

perform the work in this Scope of Services. The DBT should be aware of the specific Nationwide

Permit or Regional General Permit conditions as issued by the USACE and the State of Ohio and

should design the projects to meet the requirements of these permits to avoid having to modify

the permits, if possible. The permit applications can be found in Attachment D. The permits will

be made available from the Department to the DBT through the special provisions upon approval

from the appropriate agency(ies).

The following plan note is required:

NO WORK SHALL BE PERFORMED BELOW THE ORDINARY HIGH WATER MARK

(OHWM) OF OTTER CREEK UNTIL A WATERWAY PERMIT IS OBTAINED BY ODOT.

ALL CONDITIONS OF THE PERMIT SHALL BE FOLLOWED THROUGHOUT

CONSTRUCTION.

10.2 National Pollutant Discharge Elimination System (NPDES) permit:

The DBT shall submit to the ODOT Project Manager the total number of acres of earth

disturbance activities for both off project and on project work in a timely manner. This

information will be used to develop the NOI if required. The NOI will be submitted to the OEPA

within 10 days after this information is received from the DBT. Approval from the OEPA takes

21 days and the ODOT Project Manager has 10 days to file the NOI so these 31 days will be

counted for in the project.

All temporary erosion control is the responsibility of the Contractor even if a SWPPP is not

required. Earth disturbing activity is not permitted prior to the OEPA permit approval. For

projects that require an NOI, the SWPPP must be in place prior to the initiation of any earth

disturbing activity. All temporary erosion control work and the SWPPP if required will be per

SS832. For information about OEPA's NPDES permit requirements see

http://www.epa.state.oh.us/dsw/storm/index.html.

Items used to implement the DBT's Erosion Control requirements are paid from an encumbered

amount included in the proposal as a non-bid reference number. The proposal specifies the unit

prices for the erosion control items. Payments for erosion control items that exceed the

encumbered amount will be made by an Extra Work Change Order using the specified unit prices.

The specified unit prices are fixed for the contract and may not be negotiated or adjusted for

inflation or claimed changed condition.

If required, the preparation of the SWPPP, along with all requirements of SS832 for maintaining,

inspecting, modifying and updating the SWPPP are considered incidental to the Project.

Page 11: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

11

The following plan note is required:

BEST MANAGEMENT PRACTIES FOR SOIL EROSION AND SEDIMENTATION

CONTROL SPECIFICATIONS SET FORTH IN THE MOST CURRENT VERSION OF

ODOT’S “CONSTRUCTION AND MATERIAL SEPCIFICATIONS, LOCATION AND

DESIGN MANUAL SUPPLEMENTAL SPECIFICATION 832, AND STANDARD

DRAWINGS” SHALL BE USED TO ENSURE ADEQUATE EROSION AND SEDIMENT

CONTROL, ALONG WITH ADDITIONAL PROTECTIVE MEASURES TO AVOID

IMPACTS TO ADJACENT PROPERTIES AND WETLANDS FROM CONSTRUCTION

ACTIVITIES. EROSION/SEDIMENTATION IMPACTS SHALL BE KEPT TO A MINIMUM

THROUGH THE USE OF BEST MANAGEMENT PRACTICES FOR SOIL EROSION AND

SEDIMENTATION CONTROL. ALL SOIL EROSION AND SEDIMENT CONTROL

MEASURES AS SPECIFIED IN THE PLAN SHALL BE IN PLACE PRIOR TO ANY

EXCAVATION, GRADING OR FILLING OPERATIONS AND INSTALLATION OF

PROPOSED STRUCTURES OR UTILITIES. THEY SHALL REMAIN IN PLACE UNTIL

CONSTRUCTION IS COMPLETE AND THE AREA IS STABILIZED AS ACCEPTED BY

THE ENGINEER. THEY SHALL ALSO COMPLY WITH ODOT’S “HANDBOOK FOR

SEDIMENT AND EROSION CONTROL.”

10.3 Removal of Temporary Erosion Control Items:

All temporary erosion control items shall be removed before the project is accepted. Removed

materials shall become the property of the Contractor and shall be disposed of in accordance with

the appropriate C&MS specifications.

10.4 Stream Crossing Investigations (flood plain analysis):

The Consultant shall perform a detailed flood plain analysis for each waterway crossing. The

analysis shall be as per the Location & Design Manual and The Bridge Design Manual and as

follows : The extent of the analysis shall be from a minimum of 500' downstream, to the greater

of either one bridge opening/width upstream, or to the limits of the area inundated by the 100-

year event. The results of the detailed flood plain study, supporting hydraulic calculations, and

recommendations shall be submitted to the District for review and comment prior to construction

of the drainage structure. If the proposed crossing is located in a special flood hazard area as

defined by FEMA, the detailed flood plain analysis shall be submitted concurrently to the local

flood plain coordinator.

A floodplain permit will be obtained, if deemed necessary by the local Floodplain Administrator.

The following plan note is required:

ALL CONDITIONS OF THE FLOODPLAIN PERMIT SHALL BE FOLLOWED

THROUGHOUT CONSTRUCTION.

10.5 Endangered Species Protection:

The following plan note is required:

ENDANGERED SPECIES HABITAT-INDIANA BAT

NO BAT TREES ARE EXPECTED TO BE REMOVED DUE TO PROJECT WORK.

HOWEVER, THE ODOT DISTRICT ENVIRONMENTAL COORDINATOR SHALL BE

NOTIFIED IF CONSTRUCTION ACTIVITIES CHANGE TO INCLUDE THE CUTTING OF

TTREES WITH SUITABLE ROOSTING AND BROOD-REARING HABITAT FOR BATS

Page 12: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

12

(LIVING OR STANDING TREES OR NAGS WITH EXFOLIATING, PEELING OR LOOS

BARK, SPLIT TRUNKS AND/OR BRANCHES OF CAVITIES) PRIOR TO ANY TREE

CUTTING.

PRIOR TO ANY REHABILITATION/REMOVAL, THE UNDERSIDE OF THE EXISTING

BRIDGES SHALL BE CAREFULLY EXAMINED FOR THE PRESENCE OF BATS

ESPECIALLY FROM APRIL 1 TO SEPTEMBER 30. IF ANY BATS ARE FOUND

ROOSTING IN THE UNDERSIDE OF A BRIDGE, THE UNITED STATES FISH AND

WILDLIFE SERVICE, ECOLOGICAL SERVICES DIVISION, THE ODOT OFFICE OF

ENVIRONMENTAL SERVICES, ODOT OFFICE OF ENVIRONMENTAL SERVICES AND

ODOT DISTRICT 2 ENVIRONMENTAL SECTION SHALL BE CONTACTED OR

PROVIDED WITH INFORMATION.

11 RIGHT OF WAY (ROW)

All necessary construction work for the project will be performed within the existing right of

way.

Existing right of way lines will be located by the DBT based on requirements specified in Chapter

4733-37 of the Ohio Revised Administrative Code (Board Rules) governed by regulations

outlined in Chapter 4733, Ohio Revised Code (Regulation Laws). It is the responsibility of the

DBT to research existing right of way information from all available sources including but not

limited to ODOT records, County road records, Commissioners’ Journals and records of other

County offices to the extent necessary to provide an accurate basis for the establishment of the

existing right of way.

The DBT will stake and flag the existing right of way in the field prior to the start of construction

and will maintain said stakes and flags throughout the duration of the project.

The Consultant will identify and show all right of way encroachments on the construction plans at

the Conceptual Review Submission. ODOT’s Project Manager will be responsible for clearing

all encroachments on Federal-aid projects in accordance with standard encroachment removal

12 UTILITIES

Utilities Special Provisions in addition to the Governing Regulations listed in section 8.1 of this

document and section 153.64 of the Ohio Revised Code.

12.1 Existing Utilities:

The District Utility Coordinator, in concurrence with the registered Underground Utility

Protection Services- Ohio Underground Protection Service (OUPS) and Oil and Gas Producers

Underground Protection Service (OGPUPS) and other utility owners that are non-members of any

utility protection services, has determined that the following utilities are located in the area of the

project :

City of Oregon City of Oregon

Water Department Street Department (Sewers)

5330 Seaman Rd 5330 Seaman Rd

Oregon, OH 43616 Oregon, OH 43616

(419) 698-7038 (419) 678-7016

Page 13: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

13

Toledo Edison Buckeye Cable System

300 Madison Ave 4818 Angola Rd

Toledo, OH 43652 Toledo, OH 43615

(419) 249-5218 (419) 724-9820

12.2 General Requirements:

The DBT shall be responsible for coordination with the owners of all public and private/investor

utility facilities affected by the project. The resolution of any conflicts between utility facilities

and the construction of the project shall be the responsibility of the DBT.

The following list further describes the assignment of responsibilities with respect to various

issues related to utilities impacted by the project:

A. DBT shall coordinate with the utility owners and stakeholders to resolve all utility

conflicts encountered on this project. The DBT shall also coordinate the completion of all

utility relocations with the respective utility owners and stakeholders.

B. All effort required to resolve utility conflicts shall be included in the DBT’s schedule and

is entirely the DBT’s risk, regardless of the entity performing the work except as

described in 12.4.3 (Deadlines and Delays).

C. The Department will solely determine compensable rights related to utility design,

relocation, modification and construction for each conflict. When warranted, the

Department will compensate the respective utility owner directly as outlines in section

12.4.7. No additional compensation will be made to the DBT.

D. No additional compensation will be made to the DBT for delays, inconveniences, or

damages sustained by the DBT due to interference from the utilities or utility work.

E. The DBT shall be responsible to verify all utility relocation to ensure that the relocation

work does not interfere with other proposed construction activities, including relocations

of other utilities.

F. All new utility installation requests within L/A right of way shall be subject to the ODOT

permitting process.

G. The cost of all utility coordination will be bid as a Lump Sum Item.

12.3 Governing Regulations for Utility Design and Construction:

All utility work performed by the DBT shall be consistent with the Department’s Utility

Relocation Manual and must meet the Federal Highway Administration (FHWA) “Buy America”

policy requirements of 23 USC313 and 23 CFR 635.410. Utility work shall be in accordance

with ODOT’s 8100 Policy for Accommodation of Utilities and 8200 Procedure for Utility

Relocations, Adjustments and Reimbursement.

This utility work shall comply with the utility owner’s specifications, standards of practice and

construction methods, as well as any applicable Department or LPA and/or railroad permit

requirements.

The utility Relocation Plans prepared by the DBT for the design of the utility relocation work

shall meet requirements of the Contract Documents for plan preparation and show, at a minimum,

the following information: Existing topography, right-of-way, lanes of travel, and the location of

the existing utilities. When the DBT develops utility relocation plans, they shall be subject to

Page 14: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

14

review and approval by the utility owner in accordance with the design submittal requirements of

the Contract Documents.

All utility design, relocation, modification and construction shall be performed in accordance

with the applicable ODOT standards or accepted industry standards as applicable.

12.4 Utility Coordination:

Utility conflicts shall be identified and located by the DBT. The DBT shall design the project

construction work to minimize the scope and extent of utility conflicts and relocations. The work

shall not be designed to preclude legal occupancy of the highway right-of-way by the relocated

utility. When utility relocations are necessary, coordination and scheduling of these relocations

with the involved utilities shall be the responsibilities of the DBT. The DBT shall minimize

potential delays and coordinate the efficient relocation of affected utilities.

Only those utilities affected by the project shall be relocated or adjusted. If the DBT desires the

temporary or permanent relocation or adjustment of the utilities for the DBT’s benefit, the DBT

shall conduct all negotiations with the utility owners and pay all costs associated with the

relocation or adjustment. The DBT shall assume all schedule impacts from these relocations or

adjustments.

The DBT shall perform all of the following:

A. Confirm the identification and contact information of the utilities within the project area

as provided by the District Utility Coordinator to verify the nature, extent and location of

their existing facilities.

B. Identify all utility impacts.

C. Provide all project construction documents, other utility relocation plans, subsurface

utility engineering (SUE) information, and geotechnical information for relocation of

utilities.

D. Coordinate all project work and utility work with the affected utility owners.

E. Schedule and conduct utility coordination meetings during the project design and

construction process.

The DBT shall be responsible for maintaining and updating the utility coordination

information on a monthly basis and making that information available to the District

Utility Coordinator.

12.4.1 Notification

According to ORC 153.64 and at least two (2) days prior to commencing construction operations

in an area that may affect underground utilities, the DBT shall notify the Department, the

Registered Utility Protection Service (OUPS) and the utility owners that are not members of the

Registered Utility Protection Service.

12.4.2 Utility Coordination Activities

The DBT is responsible for establishing a schedule of utility coordination meeting commensurate

with the complexity of each utility’s relocation issues. The DBT shall notify the Department at

least three (3) business days in advance of each of the meetings. The Department will participate

as necessary. The DBT is responsible for generating meeting minutes within two (2) business

days after the meeting and submitting those meeting minutes to the Department.

12.4.3 Scheduling of Utility Relocation Work

Page 15: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

15

The DBT shall obtain activity durations for all utility relocation work-related activities from the

representative utility owner for incorporation into the DBT’s Project Schedule. The DBT shall

provide all documentation supporting the utility owner’s concurrence with the activity durations

included in the project schedule.

If the DBT requests acceleration of utility relocation work, the DBT shall pay all related

acceleration costs incurred by the utility owner. These acceleration costs are NOT eligible for

reimbursement by the Department.

If the DBT prepares a utility relocation plan, the utility owner will review and approve/reject the

design prepared by the DBT no later than 28 calendar days after its submission to the utility

owner, unless a different time period is agreed to by both parties. I a utility owner rejects and

design work, the DBT shall immediately notify the Department, in writing, of the grounds for

rejection and suggestions for correcting the problem. The DBT shall correct the design and

resubmit to the utility owner for review. This compliance review is anticipated to take fourteen

(14) calendar days.

When a utility owner prepares a utility relocation plan, the DBT shall review the design and/or

permit application to ensure that the relocation does not interfere with other proposed

construction activities, including relocations of other utilities. This review shall be completed no

later than fourteen (14) calendar days after its submission to the DBT, unless a different time

period is expressly agreed to by both parties. The DBT shall compile and provide written review

comments to the Department and the utility owner.

12.4.4 Deadlines and Delays

The DBT shall monitor the progress of all activities associated with utility relocations and

promptly notify the Department when the progress of the activity controlled by a utility owner or

a duration of relocation provided by the utility is not consistent with the project schedule. Upon

receipt of sufficient documentation confirming that a utility owner has failed to perform within

the schedule activity durations developed in Scope Section 12.4.3, the Department will be asked

to issue an Obstructive Removal Notice. The Department will solely determine if the Obstruction

Removal Notice is to be issued. An Obstruction Removal Notice only governs the relocation

process when the utility in question is located within the public road right-of-way. If a utility is

located within the utility owner’s easement, the notice does not apply and the relocation delay

responsibility is based on the relocation schedule provided by the utility.

The Department will not be responsible for payment of delay claims associated with utility

coordination/relocation, unless the DBT is able to provide the Department with sufficient

documentation for an Obstruction Removal Notice or lack of the utility meeting its utility

relocation schedule.

12.4.5 Changes to Utility Relocation Work

Once a utility relocation has begun, the DBT shall not make any changes to the project that would

necessitate an additional relocation of the utility. If changes occur, the DBT shall absorb the

schedule impact and provide full compensation for One Hundred (100) percent of all costs

(design and construction) associated with the additional relocation incurred by the utility owner.

The DBT shall provide all documentation related to changes in utility relocation work.

12.4.6 Utility Owner Inspections

Page 16: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

16

The utility owner may inspect construction of any utility work performed by the DBT on the

utility owner’s facility. The DBT shall notify the Department of any such inspections. The DBT

shall provide the Department with written documentation of all utility comments and resolutions.

The DBT shall provide safe access, including any necessary traffic control, for any utility work

inspections performed by the utility owner.

12.4.7 Reimbursement and Deposit Processes

If a utility owner notifies the DBT that is believes any utility relocation work is reimbursable to

that utility owner or the utility requires an easement acquisition by the Department, the DBT shall

immediately notify the Department. The Department’s District Utility Coordinator will work the

with utility owner to confirm the compensable position and perform the Department’s utility

reimbursement process.

If the project contains construction work to support the installation of a private/investor owned

utility company’s facilities, the DBT shall work with the District Utility Coordinator to determine

how the utility will be made responsible for providing a deposit to cover the cost of that utility

installation support.

12.4.8 Continuity of Utility Service

The DBT shall ensure that all utilities remain fully operational during all phases of the project,

except as specifically approved by the utility owner. The DBT shall obtain approvals from the

applicable utility owners for all necessary interruptions of service, including proposals for

shutdowns and temporary diversions of affected utilities.

In the event of an emergency involving utility interruption, the DBT shall immediately alert the

occupants of nearby premises as to any emergency that the accidental breakage may create at or

near such premises. The DBT will immediately notify the utility owner, in accordance with utility

company standards, and the Department of the disruption and cooperate with the said utility

owner in the restoration service. If water service is interrupted, repair work must continuously be

performed until the water service is restored. Work around fire hydrants will not begin until the

local fire department authority approves provisions for continued service.

Where the DBT is responsible for performance of utility relocation work, the DBT shall:

A. Maintain service continuity to the extent practicable while performing the utility

relocation work.

B. Keep the utility owner fully informed of schedules, including coordinating with the utility

owner with regard to the DBT’s design, construction and inspection of the utility

relocation work.

C. Coordinate any changes with the utility owner.

D. Keep the utility owner involved in making decisions that affect the utility owner’s

facilities so the utility owner is able to provide uninterrupted service to its customers, or

be subject to the least interruptions practicable.

12.5 Existing Utility Locations:

Existing underground utilities to be abandoned, including service connections, must be

disconnected and removed or abandoned to ground (abandoned in place). Utility poles and other

above ground utility facilities shall be removed in their entirety.

12.5.1 Underground Utilities

The DBT is responsible for verifying the actual location of all underground utilities, including

type, number and depth.

Page 17: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

17

12.5.2 Overhead Utilities

The DBT is responsible for verifying the actual location of all overhead utilities including type,

number, and elevation of lines and all above ground utility facilities.

12.5.3 Utility Conflicts

Additional unknown utilities may be present that may or may not conflict with the project. The

DBT shall identify, verify and document all utility conflicts and potential utility conflicts

encountered during the performance of both design and construction work.

12.5.4 Protection of Utilities

The DBT shall take all necessary precautions to prevent disturbance to utility facilities and

coordinate project design and construction with utility adjustments.

The DBT shall perform work in a manner that will cause the least reasonable inconvenience to

the utility owner and those being served by the utility. Existing, adjusted or new utilities that are

to remain within the right-of-way of the project shall be properly protected by the DBT to prevent

disturbance or damage resulting from project construction operations. If the DBT encounters a

previously unknown utility that requires adjustment, the DBT shall not interfere with the utility,

but shall take the proper precautions to protect the utility or take appropriate actions, per Contract

Documents, to coordinate the adjustment of the facility.

12.6 Utility Relocations:

The DBT shall coordinate and resolve all utility conflicts with the affected utility owner at no

additional cost to the Department.

12.7 Utility Betterments:

The cost of any ineligible, unnecessary or betterment to the utility facility will be the

responsibility of the utility owner and not the DBT. Determination of eligibility shall be

coordinated through the Department. Payment for betterment or ineligibility shall be coordinated

through the Department. Payment for betterment or ineligibility costs shall be made by the

appropriate utility owner through the Department. Betterment procedures shall follow the

Department’s Utilities Relocation Manual.

12.8 Subsurface Utilities Engineering (SUE): Yes x No

13 DESIGN AND CONSTRUCTION REQUIREMENTS: MAINTENANCE OF TRAFFIC

(MOT)

Maintenance of Traffic (MOT) Special Provisions in addition to the Governing Regulations listed

in section 8.1 of this document:

13.1 General: All temporary MOT devices shall comply with the National Cooperative Highway

Research Program (NCHRP) 350 Hardware report.

Page 18: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

18

13.2 MOT Restrictions:

Minimum number of lanes in each direction to remain open during construction: N/A

Minimum lane width: N/A

Maximum duration of detour: 45 days.

Restrictions on lane closures during special events (sports events, fairs, concerts, etc.)

Restriction related to hospitals, fire and police, schools, etc.: None

13.3 Additional Description of Required Work and special provisions:

The detour routes are as follows:

Northbound: West on Seaman Rd, North on N. Wheeling St, East on Corduroy.

Southbound: West on Corduroy, South on N. Wheeling St, East on Seaman Rd.

- Closure of the roadway will not be permitted prior to the approval of final planes.

- The DBT will inform the Department, Lucas County, the City of Toledo and the City of Oregon

eighteen (18) days prior to the beginning of work and/or road closure.

- The DBT shall maintain access to all adjacent driveways within the project area at all

times.

- The contractor will furnish, erect, and maintain, and subsequently remove all flags,

barricades, signs and support and maintain all flaggers, watchers, and incidentals

related thereto.

- Payment for all items required by the OMUTCD, the Standard Construction Drawings,

the Construction and Material Specifications, the proposal, and this Scope of Services

will be included in the Lump Sum payment for Item 614, Maintaining Traffic and will

include all labor, materials, equipment, fuels, lubricating oils, software, hardware, and

incidentals to perform the required work.

14 DESIGN AND CONSTRUCTION REQUIREMENTS: LOCATION & DESIGN

Location & Design Special Provisions in addition to the Governing Regulations listed in section

8.1 of this document:

14.1 Survey

A. ODOT Survey Responsibilities: The Department survey crews have provided the following

survey information, listed below:

1. Centerline control and bench marks

2. Beginning and ending centerline points for the project

3. At least two bench marks for the project (the datum used was that which the project was

originally laid out by)

4. Critical points such as P.C., P.I., P.T., T.S., C.S.

B. Survey Responsibilities: All survey data shall be submitted using ODOT’s standard field

codes and GEOPAK’s standard mapping codes. Reduced point data, in comma delimited ASCII

text format, will be provided for all surveyed points. This data will include: point number, x

Page 19: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

19

coordinate, y coordinate, elevation and point ID. Customized GEOPAK information is available

on the ODOT CADD web site.

Monumentation shall not be disturbed. If the Contractor does disturb the monumentation, then it

shall be replaced, in-kind, by a Registered Surveyor, with a current registration, recognized by the

Ohio State Board of Registration for Professional Engineers and Surveyors. Costs associated for

this item shall be borne by the Contractor. Copies of all monumentation changes shall be

forwarded to the District Real Estate Administrator.

All control points, provided by ODOT, shall be included in the ASCII file supplied by the DBT to

ODOT. They should retain the original point numbers and coordinate values as assigned by

ODOT.

The DBT shall provide the following items prior to final acceptance of the Record-Drawing

plans:

1. Copies of all field notes (written or electronic) which shall include the following

information:

a. Date

b. Crew members

c. Weather conditions, including temperature, barometric pressure, etc.

d. Instrument(s) used (Serial Number)

e. Raw observation field data

f. Other notes as needed

2. Copies of all Deeds, Plats, Maps and other written evidence used to establish points

related to the project including summaries of all parole evidence acquired as a part of the

survey operation.

3. Listing of all found monumentation (Horizontal and Vertical).

4. Listing of all monumentation set as part of the project (Horizontal and Vertical) including

reference ties for recovery.

5. All monumentation shall be located utilizing NAD 83 (Horizontal Data), NAVD 88

(Vertical Data).

6. Short report indicating adjustment factors and methods, signed and certified by a

Registered Surveyor (State of Ohio). The Registered Surveyor (State of Ohio) shall

include in the report the datum used and all associated adjustments used.

14.2 Vertical and Horizontal Alignment:

The horizontal and vertical alignments shown in the attached Site Plans (Attachment C) were

used to estimate the limits of disturbance for the proposed improvements. Environmental

commitments are based on these limits and shall not be exceeded during the building/build phase

of the project. Final vertical and horizontal alignments shall result in all work staying within the

existing right-of-way

Horizontal Alignment: The horizontal alignment shall match the alignment shown in the

Site Plan (Attachment C) as close as possible. Any adjustments to

the horizontal alignment shown must be approved by the

Page 20: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

20

Engineer.

Vertical Alignment: The vertical alignment shall match the alignment shown in the Site

Plans (Attachment C) as close as possible. Any adjustments to the

vertical alignment shown must be approved by the Engineer. Any

modification by the DBT to the alignment shown in the Site Plan

shall be performed with the following restrictions.

1. Work limits, as shown in the Site Plan, shall not be exceeded.

2. Raise of the roadway profile in combination with the chosen

structure hydraulic opening shall not result in an increase in the

upstream water surface elevation nor a violation of local

floodplain zoning regulations.

3. The termini of the final proposed profile shall not be less than

25-feet behind the proposed abutments.

14.3 Pavement:

All existing pavement within the limits of the final proposed profile shall be removed and

replaced based on the final proposed roadway and shoulder widths and the following cross

sectional buildup:

1 ¼” Item 448 Asphalt Concrete Surface Course, Type 1, PG64-22

1 ¾” Item 448 Asphalt Concrete Surface Course, Type 2, PG 64-22

4” Item 301 Bituminous Aggregate Base

Item 408 Bituminous Prime Coat

6” Item 304 Aggregate Base

Item 204 Subgrade Compaction

Preliminary Plan Profile Limits: Sta. 9+25.00 to Sta. 10+75.00

14.4 Roadway:

Traveled Way width: Tapers from 10’-0”± to each side

Treated Shoulder: Included in traveled way width

Any treated shoulder work performed outside of the station limits of full depth pavement

placement shall have the following cross sectional buildup:

8” Item 304 Aggregate Base

The contractor is not bound by Section 300 of the Location and Design Manual as it pertains to

the treaded shoulder width. The width of graded shoulder shall be determined by the design of the

roadside barrier provided.

Roadside barrier shall be provided on all approached to the proposed structure, regardless of the

average daily traffic (ADT). Where guardrail is used as the roadside barrier, the guardrail design

guidelines set forth in the Location and Design Manual shall be supplemented with the following

directives:

1. The length of guardrail for locations along roadways with design speeds of 40 mph or

less is 37.5-feet, not including bridge terminal assemblies or portions of anchor

assemblies which cannot be applied to the length of need (LON).

Page 21: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

21

2. The minimum distance from face to face of guardrail is four feet from each side of the

edge of traveled way, not to exceed the distance from face of barrier to face of barrier

on the proposed structure. For example, if the narrowest traveled way width equals 20-

feet and the distance from the face of barrier to face of barrier on the proposed

structure equals 24-feet, the minimum distance from face of guardrail to face of

guardrail on the approach equals 24-feet.

It is recognized the placement of a roadside barrier will impact existing private drives or existing

access points to fields at some approach to the proposed structures. At these locations, the

roadside barrier shall be extended as far as possible without impacting the drives or access points.

Furthermore, the termination of the roadside barrier at these locations must be approved by the

engineer.

14.5 Drainage: Yes X ; No .

Roadside drainage, including all side of roadway ditches, shall be maintained as existing

and shall be returned to perform equal to or better than their original configuration

following construction.

Any adjustments to the existing drainage system or installation of new drainage structures

shall meet the requirements of the Location and Design Manual.

14.6 Design Exceptions:

Previously approved Design Exceptions: None

The Consultant shall advise of any future design features that does not meet the minimum design

criteria. The Consultant shall prepare all future design exceptions and submit to ODOT for

approval.

14.7 Interchange Modification/Justifications Studies: N/A

14.8 Landscape: Yes ; No X .

14.9 Fencing: Yes _____; No _X_

Note: Existing fencing that may interfere with the proposed work shall be temporarily

relocated by the DBT until the work is complete. If the fence is used to contain

livestock, the DBT shall ensure that alternate means of livestock containment are

established during construction. The DBT shall re-erect the original fencing back

to its original condition and location after work is completed with any damaged portions

repaired or replaced to the owner’s satisfaction.

14.10 Additional Description of Required Work and Special Provisions:

Any slopes steeper than 2:1 shall be reinforced type soil slopes using a geogrid material

and per ODOT Supplemental Specification 863. Slopes shall be not steeper than 1:1

Page 22: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

22

15 DESIGN AND CONSTRUCTION REQUIREMENTS: STRUCTURES

15.1 Hydraulic data provided by ODOT: The Department has provided the following items listed

below:

1. Soil boring information in structure areas.

It is expected that the new Taylor Road Bridge structure will have a minimum 28’ span and a 7’

high opening. The City of Oregon’s 1974 Ditch Study called for this structure to be replaced with

a 30’ span structure.

15.2 Existing Structures Identification:

Bridge: Taylor Road over Otter Creek Structure File Number: 4863135

15.3 Design and Construction Requirements:

In addition to the Governing Regulations listed in section 8.1 of this document:

Existing Structure Data

Length: 26’±

Width: 24’-0” roadway

Design Loading: unknown

Type: Simple span concrete slab bridge on concrete abutments

Spans: 1- 20’-8” Span

Date Built: 1927

Proposed Alignment & Profile

Alignment: Match Existing

Relocated

By ODOT

By DBT -Final

Profile: Match Existing

Relocated

Feathered (Adjustment)

By ODOT/City of Oregon-Preliminary Plan provided

By DBT-Final

Transverse Sections

Roadway Width: 28’ f/f of rail.

Railing: Type: Per ODOT BDM 304

Height: Minimum per AASHTO LRFD Bridge Design Specifications

(section 13)

Fence: Yes No Height/Configuration N/A .

Sidewalks: Yes No Width N/A .

Page 23: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

23

The Consultant shall use a span length that maintains or increases the hydraulic opening as shown

on the existing original plans for the design, and preparation of the detail construction plans for

the construction of this structure. The number of spans must also be equal to or less than the

existing structure.

All Shop Drawings shall comply with Item 501.

The Department is providing Geotechnical Exploration information as shown in Attachment E.

Note that the collection of additional soils information shall be the responsibility of the DBT and

considered incidental to this design effort.

15.4 Additional Description of Structure Required Work and Special Provisions:

1. The Consultant shall determine the appropriate span length for the design and preparation

of the detail construction plans for the construction of the proposed structure. The span

length selected shall not be smaller than the existing and shall provide a waterway

opening greater than or equal to the existing opening.

2. The number of proposed spans may not be greater than the number of existing spans.

3. This project does not require the use of approach slabs. However, low strength mortar

backfill (Per ODOT CMS 613) shall be placed behind the proposed abutments, below the

proposed approach pavement, and above a line that extends at a 1:1 slope from the top of

each abutment footing and away from the bridge span.

4. The following are prohibited from being used on this project:

a. Multi-cell or side by side box culverts or pipes

b. Timber decks or any permanent timber elements

c. Weathering steel details.

5. The DBT shall provide their proposed hauling routes to the City of Oregon’s office for

approval. The City will accept or reject the proposed routes within five (5) working days

of receipt. Construction shall not commence until the DBT has received written approval

from the City of the proposed hauling routes.

6. The benchmark on the rear left abutment is to be reset during construction.

7. Utilize the details given in Attachment F for integral or semi-integral abutments with

prestressed concrete box beam superstructures as appropriate.

15.5 Noise Barrier

Not applicable.

16 DESIGN AND CONSTRUCTION REQUIREMENTS: TRAFFIC CONTROL

16.1 Pavement Markings and Delineators Special Provisions in addition to the Governing

Regulations listed in section 8.1 of this document:

A. Pavement Markings: Yes No None existing.

B. Raised Pavement Marker: Yes No

C. Delineators: Yes No

Page 24: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

24

All flexible delineators shall conform to Item 620 and shall be placed in accordance with

current design standards. Confirmation that no conflicts exist between the proposed

locations of delineators and any underground utilities shall be made prior to the

installation of the delineators.

D. Barrier Deflectors: Yes No

All barrier reflectors shall confirm to Item 626 and shall be placed on bridge parapets,

concrete barrier walls, retaining walls and guardrail, in accordance with current design

standards. Guardrail blockout reflectors shall be installed on the side of the blockout

away from traffic.

E. Object Markers: Yes No

All object markers shall conform to Item 630, Sign, Flat Sheet.

16.2 Signing Special Provisions in addition to the Governing Regulations listed in section 8.1

of this document:

Unless noted otherwise, all signing on this project is only to be removed and stored if necessary

to perform the work required and is to be re-erected once work is complete.

16.3 Lighting Special Provisions in addition to the Governing Regulations listed in section 8.1 of this

document:

Not applicable.

16.4 Traffic Signal Special Provisions in addition to the Governing Regulations listed in section 8.1

of this document:

Not applicable.

16.5 Intelligent Transportation Systems (ITS):

Not applicable.

17 PROJECT SCHEDULE REQUIREMENTS

Construction and Materials Specifications, section 108.03 will be met or exceeded.

18 PLAN SUBMITTALS AND REVIEW REQUIREMENTS

18.1 Plan Components: All plans submitted by the DBT shall be in conformance with the following

ODOT manuals:

1. Real Estate Policies and Procedures Manual Section 3100.

The DBT shall also identify all topographic features within the existing and proposed

Right-Of-Way limits, including underground utilities.

2. Bridge Design Manual

3. CADD Standards Manual

Page 25: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

25

4. Location and Design Manual, Volume 3:

The following sections of the Location and Design Manual, Volume 3 are NOT required:

1302.13 Plan Signatures

1307.2 General summary sheet

1307.3 Subsummaries

1307.4 Quantity Calculations

1310.3 Earthwork and Seeding Quantities

Units of measure are NOT required.

Simplified plans (section 1301.2) are NOT allowed.

18.2 Quality Control:

The DBT will be responsible for the professional quality, technical accuracy and adherence to the

Governing Regulations listed in section 8.1 of this document, for all plan submittals required

under this contract.

The DBT shall immediately notify the Department of any apparent discrepancy between the

various design and construction manuals and the Conceptual Documents.

Unless stated otherwise, review comments do not revise the scope or intent of the project and do

not constitute a request for changes beyond the current contracted Scope of Services.

In the event the Department determines that any required submission is incomplete, contains

inaccuracies which preclude a meaningful review, or does not adhere to the Governing

Regulations listed in section 8.1 of this document, the Department will advise the DBT of the

shortcomings and direct the DBT to revise and resubmit the plan. No time extension will be

granted as a result of such action. The Department will schedule a review meeting or issue

review comments as appropriate.

In the event the DBT believes that any review comment, or orders issued by the Department,

require a change to the scope of the agreed work, the DBT shall first contact the Department for

clarification and shall, within 10 days of receipt of the comments or orders, provide written notice

to the District Project Manager and Project Engineer concerning the reasons why the DBT

believes the scope has been changed.

18.3 Stage 1 Plan Review Submission:

Not applicable.

18.4 Major Design Decision:

Not applicable.

18.5 Stage 2 Plan Review Submission: For each Buildable Unit the Consultant shall submit Stage 2

detailed design plans as per Location & Design Manual, Volume 3, and a load rating report and

summary for review by ODOT. All submissions must be shown on the required Progress

Schedule.

The Department shall have 14 calendar days from receipt to review complete submissions. This

review time must be shown on the required Progress Schedule.

Page 26: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

26

Following the review the Department will return to the DBT marked plans noted ‘ACCEPTED’,

‘ACCEPTED AS NOTED’ or ‘NOT ACCEPTED’ as described in section 105.02 of the

Construction and Material Specifications. The DBT shall correct errors, incorporate changes,

perform investigations and make related changes to the plans and supporting documents prior to

submitting construction plans.

Plan Review Distribution Table: The DBT shall supply half size (11" x 17") paper prints

simultaneously to the parties indicated below except that each affected utility company shall

receive one full size (22"x34") plans:

Number of half size Sets

ODOT District Production TIFF Images on Electronic Media [i.e. CD, DVD, etc] or PDF

ODOT District Construction TIFF Images on Electronic Media [i.e. CD, DVD, etc] or PDF

ODOT Central Office of Local

Programs

TIFF Images on Electronic Media [i.e. CD, DVD, etc] or PDF

ODOT Central Office, Office of

Structural Engineering

TIFF Images on Electronic Media [i.e. CD, DVD, etc] or PDF

County Engineer 3 paper half size sets + 1 emailed PDF

Each affected utility company 2

18.6 Construction Plans: After the review comments for the final plan review submission have been

complied with, and following approval of the design documentation, the DBT shall prepare plan

sets for use during construction. All review comments shall be resolved in writing by the DBT to

the satisfaction of the Department before the DBT submits the construction plans. Each plan

sheet shall have its last revised date noted on the sheet and clearly marked ‘Approved For

Construction’. The ‘Approved For Construction’ plan set shall be signed, dated and sealed

by a Professional Engineer. Physical construction shall not begin until the plans marked

‘Approved For Construction’ are delivered to each party on the Plan Distribution Table below.

No time extensions will be approved by the District Construction Engineer if the plan distribution

is not completed and project delays occur as a result.

Plans Distribution Table : The DBT shall supply full size (22" x 34") and/or half size (11" x 17") paper

prints of the each plan submission simultaneously to the parties indicated below:

Electronic

PDFFull Sets

Half Sets

ODOT District Production 1 3

ODOT District Construction 1 2

ODOT Central Office of Local Programs 1 0

ODOT Central Office, Division of Construction

Management

Notification

Only

Page 27: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

27

ODOT Central Office, Office of Environmental Services 1 1

ODOT Central Office, Office of Structural Engineering 1 0

Oregon City Engineer 1 3

Each affected utility or railroad company 1

18.7 Plan Distribution Addresses:

City of Oregon, Engineering Department

Paul Roman, PE

5330 Seaman Rd

Oregon OH 43616

[email protected]

Ohio Department of Transportation

District 02 Office

317 East Poe Rd

Bowling Green, OH 43402

Attn: Natina Ariss

[email protected]

Ohio Department of Transportation Central Office

Office of Local Programs

1980 West Broad Street

Columbus, Ohio 43223

Attn: Jeff Peyton

[email protected]

Ohio Department of Transportation Central Office

Division of Construction Management

1980 West Broad Street

Columbus, Ohio 43223

Attn: Eric Kahlig

[email protected]

Ohio Department of Transportation Central Office

Office of Environmental Services

1980 West Broad Street

Columbus, Ohio 43223

Attn: Tim Hill

[email protected]

Ohio Department of Transportation Central Office

Office of Structural Engineering

1980 West Broad Street

Columbus, OH 43223

Attn: Tim Keller

[email protected]

Page 28: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

28

District LPA coordinator:

Imad Bdeiri

[email protected]

District Construction Administrator:

Dennis Charvat

[email protected]

19 BUILDABLE UNITS (BU)

Definition: Buildable Units are portions of the projects which can be designed, reviewed and

built with only limited controls and assumptions coming from the design of other portions of the

project. Often a Buildable Unit will be defined by a geographic area within the plan, but it may

also be defined by types of work or construction stages which may require or permit similar,

nearby work to be divided into separate Buildable Units.

All Buildable Units shall summarize the materials required to construct that portion of the project.

The summary shall include the Construction and Material Specifications Item Number, and a

description of the materials to be used.

General: For the Stage 2 submittals, the DBT may break the project work into two or more

separate BU which can be progressed through design and construction with minimal or known

effect on each other and/or which can be dealt with sequentially such that sufficient data is

available for design and review of each BU. In order that the design and construction of one BU

may proceed without significant approved information from an associated BU, the DBT may

develop and propose assumptions which will allow for the first BU to proceed through design

and/or construction. These assumptions shall be submitted for review and comment but their

accuracy and effort upon the final design are the sole responsibility of the DBT. Should error in

these assumptions result in additional work, remedial work or other changes to assure an

acceptable design or should they result in the need to remove work and substitute additional

work, the Contractor shall be responsible for all such costs including, removal of unacceptable

materials from the site, modification, additional work, repairs, etc. as necessary to produce an

acceptable result.

If the DBT elects to develop Buildable Units, the DBT shall prepare, for review by the

Department, a table of Buildable Units for the project with each BU described in detail. If the

table is approved, the DBT shall modify the Progress Schedule to show a separate group of

activities for BU and these activities shall encompass all of the design and construction work in

each BU. Work activities shall be further separated in the Progress Schedule to show a

meaningful completion status (i.e. separate activities comprising the placement of a bridge deck

on steel beams shall describe; shoring, form building, steel placement, placement of conduit &

joints, pouring concrete, forming parapets, pouring or slip forming parapets, provision of

membranes, provision of wearing surfaces, curing, repair, form removal, cleaning, etc.).

The Final Review Submission and construction plans shall specifically be identified by the

Buildable Unit code. If the design of a BU requires input information from an adjacent or related

BU, the source for that information in previously approved plans shall be cited or the DBT shall

provide an estimated value of the data. The input data shall also be carefully identified. In the

same way any assumption, calculations or results from the stage and BU which are used as input

to another BU shall be similarly identified, and where appropriate, compared back to that BU to

Page 29: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

29

verify previous assumptions. Should assumptions not match values calculated later, the DBT

shall re-analyze all affected components and determine appropriate changes. Should those

elements have already been constructed, the DBT shall recommend repairs, adjustments,

modifications or replacement of the existing work as necessary to comply with the Scope of

Work. All costs for re-design, re-submissions, modifications, removals, disposal of materials and

new work needed to remedy the project and bring it to compliance shall be borne by the

Contractor and no time extensions shall be approved for this.

Page 30: ODOT DESIGN BUILD SCOPE OF SERVICES OHIO BRIDGE ... C… · OHIO BRIDGE PARTNERSHIP PROGRAM PID # 97648 Package # LUC Taylor Rd Gp4 Muni FY15 ... 19 Buildable Units 27 20 Index of

30

20 INDEX OF ATTACHMENTS

ATTACHMENT A – Location Map

ATTACHMENT B – Existing Plans and Photos

ATTACHMENT C – Preliminary Plan

ATTACHMENT D – Nationwide Permit (NWP) or Regional General Permit (RGP)

ATTACHMENT E – Preliminary Subsurface Explorations.

ATTACHMENT F – Integral and Semi-Integral Box Beam Abutment Details