One Year of Commercial Operation in Irsching.pdf

  • Upload
    myegnr

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    1/33

      1

     

    Update on Siemens 8000H CCPP Technology and Operational

    Experience

     Authors: 

    Dr. Kais Sfar

    Siemens Energy, Head of Product Line Marketing Plant Solutions

     Armin Staedtler

    Siemens Energy, Head of 8000H R&D Program

    PowerGen Asia

    Bangkok, October 3 – 5, 2012

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    2/33

      2

     Abstract

    More than one year ago, the start of commercial operation of “Ulrich Hartmann” power

    plant in Irsching (unit #4, Germany) marked the dawn of a new era in combined cyclepower plant construction. For the first time the magic figure of 60% efficiency was

    topped. However, not only this world-record efficiency level sparked the interest of the

    power generation community, but also the successful optimization of the plant’s

    operational flexibility. The high level of plant flexibility is setting benchmarks and

    enabling an operating regime, which today already meets the rising demand of the future.

    Rapidly increasing share of renewables-based power generation and high fluctuating load

    demand – especially in small grids – will require combined cycle power plants able to

    provide highest performance at base and part load and at the same capacity for fast

    cycling and grid support. Initial tests already demonstrated that the plant exhibits

    excellent characteristics in terms of grid stabilization. It was also demonstrated that the

    FACY ™ package developed by Siemens enables startup times of less than 30 minutes.

     This paper describes Siemens answer to the different regional market requirements and

    focus on both the SGT-8000H gas turbine series and the corresponding combined cycle

    power plant solutions for the 50Hz and 60Hz regions. The market introduction of the

    8000H class technology was based on an extensive validation and test strategy first in

    Irsching for the 50Hz frame under real field conditions and later for the 60Hz frame,

     which is a direct scale of the SGT5-8000H, in the Berlin test facility. This paper will

    further summarize all field validation activities and results, showing how Siemens is

    bringing the 8000H to the market based on a comprehensive approach to ensure a risk

    minimized market introduction. Finally this paper will describe the current commercial

    experience and the first references within the 50Hz and 60Hz markets.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    3/33

      3

     Table of contents 

    1.   The challenge – Fluctuating power demand at raising

    fuel costs 4 

    2.  Siemens 8000H combined cycle power plant solutions 8 

    2.1.  SGT-8000H gas turbine: Proven design with highest efficiency & flexibility 8 

    2.2.  SCC-8000H combined cycle power plant solutions 13 

    3.  Operational experience 19 

    3.1.   Test and validation of the SGT5-8000H and SCC5-8000H 19 

    3.2.   Test and validation of the SGT6-8000H 23 

    4. 

    Market launch and first commercial references 27 

    5.  Conclusion 29 

    6.  References 31 

    7.  Copyright 33 

    8.  Disclaimer 33 

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    4/33

      4

    1.  The challenge – Fluctuating power demand at raising fuel

    costs

    Considering the worldwide trend of increasing demand for eco-friendly power

    generation, a major concern to power producers aiming to build new plants is to

    understand the impact of the long-term CO2 reduction targets on the power generation

    market of today and the future. Despite all uncertainties related to the potential future

    changes in regional environmental policies and CO2 reduction targets, today’s power

    plant solutions must be capable of running profitably throughout the whole service life,

     which in the case of combined cycle power plants is typically more than 20 years.

    Customers expect environmentally-compatible and economical state-of-the-art solutions, which offer a maximum value and long-term investment security, even in a volatile

    market environment.

    Driven by stringent CO2 reduction targets, the share of renewable energy resources is

    rapidly growing. The analysis of the predicted residual load, which is the difference

    between incoming renewables-based power supply and power consumption, shows an

    extremely fluctuating course over the year. Based on further statistical analysis a clear

    shift of the fossil power plants' operating regime from base load towards intermediate

    and peak load is predicted. Also, the remaining conventional power plant fleet has to be

    able to cope with much higher load ramps and therefore partly serve as backup, e.g. in

    case renewables feed-in is interrupted, on short notice.

    Considering the ASEAN region, which is characterized by strong economic growth, a

    continuous increase of power demand of approx. 6% per annum is anticipated over the

    upcoming years. Accordingly, new generating capacities will have to be built to meet thisincrease in the years ahead. Inversely to Europe, renewable energy power generation in

    the ASEAN region is still limited and plays a secondarily role within today’s energy mix.

    Nevertheless, it is clearly expected that in future the renewable power generation share

     will increase. Therefore new future power plant investments have to consider renewable’s

    impact at a very early stage of the planning process.

    Since natural gas availability in the region is growing, e.g. through the continuous

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    5/33

      5

    extension of the LNG terminals network around the South Pacific Rim, gas fired power

    generation plays a key role in securing the energy supply of the region.

     Thanks to their outstanding dynamic characteristics, combined cycle power plants are

    able to offer highly flexible solutions that can accommodate sharp daily fluctuations in

    power consumption. Operational flexibility is based mainly on three major aspects:

     –   Operational efficiency comprising highest efficiency throughout the whole loadrange and optimized start-up and shut-down operation

     –   Power on demand comprising rapid availability by fast starts and load ramps

     –  

    Grid support, also comprising load ramps, stable operation in case of gridincidents and backup power

    Since gas fired power plants represent a major portion of the energy mix, it is clear that

    this type of plant is used to cover a certain portion of the base load needed in the region.

    During this load regime highest efficiency is a key requirement to drastically reduce fuel

    consumption and, of course, reduce CO2 emissions.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    6/33

      6

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    Siemens combined cycle power plants are addressing

    the major environmental and economical market drivers

    Steep load ramps

    and fluctuating

    power demand

    Gas prices Ecologicalawareness

    Lowest investment Highest efficiency Operational flexibility

    + +

     

    Figure 1 Major power plant requirements

     The evaluation of the different regional requirements (Figure 1) as discussed earlier leads

    to the following key drivers:

     –   Investment: lower specific investment (EUR/kW) resulting from economies ofscale, while achieving highest reliability and availability.

     –   Performance: increase combined cycle net efficiency to over 60% with a poweroutput over 550 MW in a 1 on 1, while drastically reducing emissions.

     –  

    Operational flexibility: reduce startup and shutdown times, increase load rampsfor fast load-following ability, improve turn down capability, part-load efficiencyand startup reliability.

     These factors have been considered by Siemens Energy in the development of the new

    H-Class gas turbine SGT-8000H series and the combined cycle power plant, the SCC-

    8000H series, taking both environmental protection as well as economical focus into

    consideration. The 8000H program was started in 2000. It was dedicated to consistently

    implementing our engineering know-how not only for the gas turbine but also for the

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    7/33

      7

    overall plant solution. Thus, Siemens Energy can provide the right answer to tomorrows’

    energy supply needs already today.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    8/33

      8

    2. Siemens 8000H combined cycle power plant solutions

    2.1.  SGT-8000H gas turbine: Proven design with highest efficiency &

    flexibility

    Following the merger of Westinghouse Power Generation with Siemens in 1998, the

    decision was made to develop a Next Generation Family of Gas Turbines and therewith

     widen the existing product portfolio based on the H class frames for 50Hz and 60Hz

    markets (Figure 2). The SGT-8000H series addresses the major market requirements in

    terms of efficiency, environmental protection, operational flexibility and economical

     value.

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    SGT6-2000E

    SGT5-2000E

    SGT6-5000F

    SGT5-4000F

    Output in MW @ ISO conditions

    292

    200

    168

    113

    375SGT5-8000H

    Siemens Large Scale Gas Turbines:

    Product Portfolio for 50 Hz and 60 Hz

    SGT6-8000H   274

     

    Figure 2 Siemens Energy large scale gas turbine product portfolio

     The SGT-8000H gas turbine series combines the best design features and technologies of

    the established product lines with some technology innovations and enhancements and is

    the result of a continuous optimization and harmonization development activities. The

    functional and mechanical design of the engine was built on the extensive experience

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    9/33

      9

    gathered over decades with the predecessor 50Hz and 60Hz engines of both companies

    Siemens and former Westinghouse. Proven design features were applied wherever

    possible, and “Design for Six Sigma” tools were used throughout the process, to deliver a

    robust product which meets all requirements (Figure 3). The results of the 8000H

    development, testing and validation activities were also used as an enabler for the

    different F class engines upgrades.

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    SGT-8000H engine concept

    based on harmonization and new technology

    Siemens V Design Siemens W Design

    Turbine cylinder 

    Turbine vane carrier 

    Exit housing

    Front hollow shaft

    Bearings

    Compressor cylinder 

    Turbine features

    Turbine diffuser 

    Single tie bolt

    Compr. stat. design

    Secondary Air

    System

    ULN can-annular

    combustion systemHarmonized

    Compressor 

    The SGT-8000H concept uses proven features from Siemens and (former)

    Westinghouse engines and introduces new technology

     

    Figure 3 Concept of the SGT-8000H series

    Based on the SGT-8000H frames different packages and plant product configurationsfor both 50Hz and 60Hz markets were developed (Figure 4). A detailed plant solution

     view will be discussed in the next chapter.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    10/33

      10

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    Configuration and Performance Overview

    50 Hz 60 Hz

    SGT-PAC 8000H 375 MW 274 MW40 % 40 %

    SCC-PAC 8000H 1S 570 MW 410 MW60 % 60 %

    SCC-PAC 8000H 2x1 1.145 MW 824 MW60 % 60 %

    SCC-PAC 8000H 3x1 - - 1.236 MW- - 60 %

    at ISO conditions

    SGT5/6-8000H

    SCC5/6-8000H 1S

    SCC5/6-8000H 2x1

     

    Figure 4 Configuration and performance overview

     The basic engine design is summarized in Figure 5 and has the following features, which

    account for the high efficiency and the increased operational flexibility: The SGT-8000H

    series is an integrated product line with common features and an evolutionary design.

     –    The engine uses the well known SGT5-4000F disc-type hollow-shaft rotor with a

    single tie bolt. The discs are interlocked and centered using Hirth couplings. This

    shaft design has smooth and stable running behavior due to the low weight with

    high stiffness and uniform thermal expansion under all operating conditions.Siemens has over 16 Million EOHs and more than 750 gas turbines operating

     with this type of rotor.

     –    The 13 stages high efficiency axial compressor is Siemens harmonized design,

     which is offered on the SGT6-5000F as well as the SGT-8000H engines. This

    design has four variable guide vanes to maintain high part load efficiency and low

    emissions. This design continues to offer the ability to replace blades without a

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    11/33

      11

    rotor lift. The 50Hz and 60Hz versions are conceptually identical and are

    geometrically scaled.

     –    The can annular combustion system design is based on the SGT6-5000F and is

    purely air-cooled. The existing Siemens fleet with over 400 operating units offers

    more than 8,500,000 EOHs of extensive experience with this type of combustion

    system. Both 50Hz and 60Hz SGT-8000H engines have a common combustor

    assembly.

     –    The turbine part of the engine consists of four high efficiency stages with air-

    cooled turbine blades. Blade R1 uses directionally solidified material and

    enhanced TBC system. There is no need for single crystals use and steam cooling. The first stage blade and vane are removable through the combustor without

    cover lift. Further measure for improved serviceability and shorter outages is the

    use of a single turbine vane carrier. Similar the SGT5-4000F the turbine has a

    conical flow path, which allows for hydraulic clearance optimization.

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    > 60% combined

    cycle efficiency

    Designed for >60% efficiency in combined cycleand best in class operational flexibility

    SGT5-8000H

    Efficient & Flexible

    4 stages of fast acting variable-

    pitch guide vanes (VGV) allowing

    for improved part load efficiency

    and high load transients

    Proven rotor design

    (Hirth serration,

    central tie rod, internal

    cooling air passages)

    for world class fast

    (cold) start and hot

    restart capability

    High cycling capability due

    to fully internally air cooled

    turbine section

    Evolutionary 3D blading

    3D Four stage turbine with

    advanced materials and

    thermal barrier coating

    HCO for reduced

    clearance losses

    Transient protection of clearances

    for reduced degradation with

    hydraulic clearance optimization

    (HCO) active clearance control

     Advanced Can Annular

    combustion system

    Performance features

    Flexibility features

     

    Figure 5 Main design features of the SGT-8000H series

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    12/33

      12

     A key design feature towards operational flexibility and a major concept decision which

    had to be made early in the SGT-8000H program, was the selection of the engine cooling

    method. Siemens Energy gas turbine portfolio has both types of the major cooling

    technologies: The SGT5-4000F and the SGT6-5000F are both based on purely air-cooled

    engine concepts, while the SGT6-6000G had a combined air and steam cooled approach.

     This experience offered a wide information and experience basis, showing the benefits

    and disadvantages of both technologies. Due to the heavy impact of the steam cooling

    on the engine operational flexibility and design complexity, the internally fully air-cooled

    design was selected for the SGT-8000H. This design feature enables faster starts, since

    there is no need to wait for steam from the water/steam cycle. The avoidance of steam

    cooling and external coolers enable easier simple cycle and bypass operation, faster load

    following and part load operation. Design simplicity especially in terms of sealing designs

    provides higher engine robustness. SGT-8000H proven design allows achieving

    outstanding performance and operational flexibility without the higher risk associated to

    the steam cooling.

     A further key aspect which was incorporated in the SGT-8000H was the special focus on

    design features to enable easy and quick serviceability:

     –   Replacement of compressor blades without rotor de-stack or lift

     –   Roll out/in capability of the turbine vane carrier enables exchange of stationary

    turbine hardware without rotor lift

     –    All turbine blades removable without rotor lift

     –  

     Turbine vane 1 and blade 1 removable without cover lift (access throughcombustion chamber)

     –    Turbine blade 4 removable without cover lift (towards the exhaust end)

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    13/33

      13

    2.2.  SCC-8000H combined cycle power plant solutions

     As shown in Figure 4 Siemens Energy offers different combined cycle power plant

    configurations based on single- and multi-shaft arrangements. Additionally Siemens is

    unique in offering a flexible scope of supply varying between entire power plant (turnkey

    scope) over power block / power island and up to an extended power train. This enables

    Siemens to add – depending on the project specific setup– the regional partners and local

    knowledge (Figure 6). The portfolio flexibility with regards to different arrangements and

    scope of supply allows a wide range of technical and commercial (risk and cost)

    optimizations, allowing best fit to customer’ requirements.

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    Different scope variations for Siemens combined cycle power plants

    Extended

    Power TrainPower Island Power Block Entire Power Plant

     

    Figure 6 Siemens offers various scopes to customers adding regional partners & local knowledge

     A major solution within the product portfolio is the proven single-shaft design that was

    developed in the early 90s. Since then, it has since been successfully implemented in the

    F-class (SCC5-4000F 1S) with about 100 units in commercial operation. The power plant

    SCC-8000H series was developed based on the SGT-8000H as prime mover, the Irsching

    4 test plant and the large F class experience as mentioned above. The design principle

    comprising the gas turbine, the generator, the coupling and the steam turbine on a single-

    shaft has remained the same, as this continues to offer the customer the greatest

    economy and at the same time supreme operational and financial flexibility. The SCC-

    8000H series is also characterized by its high degree of harmonization, modularization

    and compact design towards footprint and space requirements. Both solutions for 50Hz

    and 60Hz markets are based on the same design principles.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    14/33

      14

     The overall plant design was optimized to provide over 570 MW net power output at

    ISO conditions and a net efficiency greater than 60%, while keeping the emissions

    extremely low, in this case 25 ppm NOx emissions or less at gas turbine base load (Figure

    7). Further performance figures for single and multi-shaft configurations for both 50Hz

    and 60Hz are shown in Figure 4.

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    SCC5-8000H 1S designed for η > 60% and highest

    operational flexibility

    HRSG: BensonTM3Pr/RH 600 °C/170 bar 

    Steam Turb.:SST5-5000Combined HP/IP

    Dual flow LPHP: 170 bar / 600 °CIP: 35 bar / 600 °CLP: 5 bar / 300 °C

    Generator: SGen5-3000WWater cooled stator winding

    Hydrogen cooled rotor windingMICALASTIC® Stator insulation

    World class efficiency

    Published DesignTargets:

    Performance (net, ISO)Power: >570 MWEfficiency: > 60%

    Emissions (Base load)NOx < 25 ppmCO < 10 ppm

    Gas Turbine: SGT5-8000H

     

    Figure 7 SCC5-8000H 1S designed for highest efficiency and operational flexibility

    Siemens Energy solutions single shaft design is also optimized for CHP applications.Despite the compact design with the floor mounted turbine generator train, it’s possible

    to provide up to a three stage steam extraction for heating purposes or process steam.

    Figure 8 shows the possible heat extraction of both SCC-8000H product lines. In chapter

    4 of this paper a commercial reference of the SCC5-8000H 1S with CHP will be

    discussed.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    15/33

      15

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    SCC-8000H

    Possible heat extraction in large CHP combined cycles

    SGT5-8000H

    50 100 150 200 250 300 3500 400

    SCC6-8000H 1S

    SCC5-8000H 1S 570MW

    410MW

    Possible heat extraction [MWth]

    SGT6-8000H

     

    Figure 8 SCC-8000H with combined heat & power (CHP) application

     The selected steam turbine type used for SCC-8000H series comprises one combined

    HP/IP casing and one double-flow low-pressure casing. The advanced steam turbine

    design is optimized for combined cycle applications, providing enhanced transient

    thermal behavior for fast loading and fast cycling. For the single shaft configuration the

    synchronous self shifting (SSS) clutch allows a self-contained individual turning mode of

    the gas turbine and the steam turbine increases the operation flexibility and allows also a

    faster start-up of the power plant.

    Depending on the frequency and plant configuration different generators within the H2 

    and H2O cooled product lines are used. Both types are contributing to the overall plant

    efficiency increase based on its outstanding performance. Due to the large plant output

    the 50Hz single-shaft solution is using – as a unique configuration – a generator with

    direct radial hydrogen cooling for the rotor winding and water cooling for the stator

     winding. This frame is mainly characterized by its high efficiency and reliability beyond

    99%. A start-up frequency converter is used for start-up of the turbine generator unit.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    16/33

      16

     The generator acts as a motor in the converter mode to start the gas turbine set without

    an additional rotating device.

     As the SGT5-8000H provides a high exhaust temperature of approximately 625 °C, a

    further efficiency increase was achieved based on an advanced three pressure reheat

     water steam cycle (up to 600°C inlet temperature and 170 bars inlet pressure) with a

    BENSON type heat recovery steam generator (HRSG) and condensate polishing.

    Further efficiency improvement measures were based on the use of fuel preheating at

    215°C, reduction of pressure losses in the HRSG and piping, feed water pumps with

     variable speed drives, etc. The combination of all efficiency improvement measures

    enables the major step over 60% efficiency at base load and an efficiency increase of up

    to 1,7%-Pt. compared to typical F class over the main operation range.

     The Benson-type HRSG for high steam parameters is an essential component in addition

    to the "rotating equipment". The HRSG is designed and built by Siemens (Figure 9). As

    this component is of major importance for boosting efficiency and flexibility, the

    decision was taken to develop and build it in-house on the basis of the available

    experience with previous Benson boilers, such as in the projects Karstoe, Simmering and

     Timelkam. Due to the increased thermal cycle parameters, advanced high temperature

    materials known from the 600 °C steam power plant technology were used for the

    HRSG design. For both design standards DIN and ASME Siemens Energy provides

    solutions with proven materials for up to 600°C water / steam cycles. Depending on the

    plant configuration economics main steam parameters for 50Hz and 60Hz may be

    decreased to 150bar and 585°C to enable e.g. the use of a drum type HRSG.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    17/33

      17

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    Siemens Benson HRSG

    design, 19 units built, e.g.

    Malzenice, Gönyü, Severn

    Power, Sloe Centrale…

    Based on F-class

    technology as executed

    in e.g. Karstoe,

    Simmering, Timelkam

    Based on Siemens

    BensonTM Technology*

    (Elimination of HP drum)

    Utilization of high

    temperature materials

    applied for 600 °C

    Steam Power Plants

    Proven

    Benson

    Design

    Concept

    Benson

    Evaporator

    Design

    HRSG + Plant

    Development

    in one Hand

    =

    Innovation based

    on proven

    technology andmaterials

    HRSG with Siemens BensonTM HP section

    designed for 600 °C steam temperature

    600 °C

    Technology

    Siemens

    Design

    Principles

    HP pressure/Temp.: 170 bar/600 °C RH pressure/Temp: 35 bar/600 °C

    Mass flow: 100 kg/s

    Weight: ~ 7000 tons

    Heating surface: > 500.000 m²

    Irsching 4 BensonTM* HRSG is designed and delivered by Siemens

    (*) Siemens is owner of the BensonTM patent

     

    Figure 9 BENSON HRSG designed for 600 °C steam temperature

     All flexibility features – well known from our SCC5-4000F series – were implemented in

    SCC5-8000H. The FACY (FAst CYcling) concept with its key components is

    summarized in Figure 10.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    18/33

      18

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    SCC5-8000H 1S – a proven concept optimized for

    highest operational flexibility

    Proven cycleconcept

    Triple pressurereheat cycle

    Advanced

    steam parameter 

    Up to 600 °C 

    Low complexity(No GT external

    cooling interface)

    FACYFast Cycling 

    Stack damper 

    ST stress

    controller 

    HRSG stand-by heating

    Condensatepolishing plant

    High-capacity

    de-superheater 

    BensonTM

    technology

    Optimized GT

    load ramp

    Specific features included in our advanced 8000H plant cycle design for

    most flexible and reliable operation

     

    Figure 10 SCC5-8000H 1S optimized design to allow highest operational flexibility

     The implementation of the FACY concept in combination with the hot start on-the-fly

    allows a hot start-up time reduction down to less than 30 minutes in comparison to

    “conventional” hot starts. The concept is based on a procedure for parallel start-up of

    gas and steam turbines, while monitoring and controlling the temperature gradients

     within limits acceptable for all critical plant components and long term operation

    experience with different steam conditions in the Siemens turbine design. A new start-up

    sequence, which avoids gas turbine load hold points, was implemented. The main

    innovation here is the early steam turbine starting point with earlier acceleration andloading of the turbine. The FACY technology allows for higher number of starts and

    faster cycling without compromising plant lifetime consumption.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    19/33

      19

    3. Operational experience

    3.1.  Test and validation of the SGT5-8000H and SCC5-8000H

     The 8000H program was started in 2000, and after thorough development and

    engineering successful component testing paved the way to the first field installation in a

    simple cycle configuration built by Siemens for E.ON Kraftwerke in the Irsching site

    (Figure 11).

    PowerGen Asia 2012© Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    Irsching Units 1 - 5, as of June 2011Owned by E.ON Kraftwerke

    Block #4 – SCC5-8000H 1S

    Ulrich Hartmann

    Block #5 – SCC5-4000F 2x1

     

    Figure 11 Irsching power plants – Unit 4 built based on SCC5-8000H 1S and the first commercial

    SGT5-8000H

    First firing took place in December 2007. First synchronization to the grid occurred on

    March 7, gas turbine base load was achieved on April 24, 2008, and the field validation

    program was successfully completed in August 2009, after over one and a half years in

    simple cycle operation. The total 18-month validation program consisted of multiple

    measurement campaigns, covering the full operating range starting from hot

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    20/33

      20

    commissioning to a final endurance test in open cycle configuration. This validation

    phase confirmed its functionality, operational capability, performance, serviceability,

    integrity and stability limits.

    Following completion of GT field validation in August 2009, extension and conversion

    to a combined cycle power plant started at Irsching and was completed on schedule in

    December 2010. The conversion to a complete combined cycle power plant went off

     without hitch within a very tight time frame of only 16 months. With the re-ignition of

    the gas turbine in its new configuration for the first time in January 2011 and steam

    admission just few weeks later, the commissioning phase, including the final test and

     validation of the entire combined cycle power plant, was begun. Only few days after this,

    in March 2011, it was possible to run the plant at combined cycle base load for the first

    time. The further commissioning activities up to June 2011 were marked by tests to

     validate the performance of the components and the overall thermal cycle and to

    demonstrate the plant's high operational flexibility and capability in meeting the most

    stringent grid requirements, to optimize the startup times and load rejections, and to

     verify its output and efficiency.

    Once all tests were completed, the plant was adjusted to the guarantee conditions, which

     were agreed with E.ON in 2005 and increased in 2008 (in terms of output, efficiency,

    emissions and startup times). During the customer performance test the plant achieved

    for the first time in the history of power plant engineering a net electrical efficiency of

    60.4% while producing at the same time a unit net output of 561 MW complying with all

    contractually defined emission limits. The achieved efficiency level and the low emissions

    (NOx below 25 ppm and CO below 10 ppm) make Irsching 4 – SCC5-8000H 1S a

    milestone in environmentally friendly fossil power generation

    In terms of operational flexibility following results were achieved under combined cycle

    operation conditions:

     –   Fast hot start-up using FACY  TM technology and hot start on the fly: the overall

    plant can be very reliably run up to full load in less than 30 minutes, putting over

    500 MW in to the grid at combined cycle load ramps up to 50MW/min. It should

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    21/33

      21

    be mentioned that under simple cycle operation conditions, GT full load can be

    achieved within 10 minutes at GT load ramps of 35MW/min.

     –   Plant fast shut down was achieved in less than 30 minutes. During the combined

    cycle operation fast plant de-loading was also tested to demonstrate its ability to

    run under stable conditions at minimum load (combined cycle load of approx.

    100MW or less than 20% of rated output with both GT and steam turbine in

    operation).

     –   Fast cycling dynamic load tests showed excellent capability to effectively

    contribute to grid stabilization and to run in a fast load following mode. Load

    gradients up to 35 MW/min. were demonstrated and the plant achieved over 200MW load increase and decrease in less than 7 minutes, while all systems were

    running under perfectly stable conditions.

     –   Grid support capability: The UK grid code is the most stringent in the world.

     Two major aspects of the UK grid code define the requirements for frequency

    response and load stabilization in case of island grid formation. In terms of

    primary and secondary frequency response, the Irsching 4 plant surpassed the

    UK grid code target as a 12% load increase initiated by a simulated frequency

    drop was demonstrated in less than 10 seconds. In order to fulfill the island

    formation requirement a load reduction of 45% within 6 seconds as an

    instantaneous answer to the detected frequency deviation in the gas turbine

    controller was achieved. Such capabilities are indispensable to allow effective grid

    stabilization and avoidance of grid blackouts, especially within small grids.

    Prior to customer handover world record performance test runs were done. The plant

     was operated and tested according to its design conditions. These runs have

    demonstrated, also under the supervision and verification of the independent certified

    body TÜV, the potential that this plant harbors in this configuration for further planned

    commercial projects. The achieved performance at Irsching 4 reference site conditions

     were:

     –   Power output of 578 MW

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    22/33

      22

     –   Efficiency of 60.75% (net) with compliance to the emission limits.

    Since the customer handover in July 2011, the gas turbine SGT5-8000H has achieved in

    the Irsching 4 power plant in sum more than 17,000 equivalent operating hours (whereof

    more than 12,5000 EOH in combined cycle operation) and more than 400 starts (Figure

    12).

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    Phase I Phase II /

    GT Testing (open cycle) Combined cycle plant operation

    Starts 85 326

    Total EOH 4.365 12.689

    Grand Total GT > 17.054 EOH Combined Cycle > 12.689 EOH

    Operational Record Ulrich Hartmann CCPP

    Irsching unit #4 as of July 30, 2012 

    Irsching 4 is running with outstanding availability and startup reliability

     

    Figure 12 Operating experience gained in Irsching 4

    Since commercial operation two planned short time outages after 6,000 EOHs and 8,000

    EOHs were performed and allowed a visual inspection of the hot gas path and

    confirmed the anticipated excellent engine conditions. Based on these results the decision

     was made to potentially defer the combustor inspection to the 12,000 EOHs outage.

     After a further visual inspection at 10,000 EOH finally the combustor inspection took

    place during the outage in May 2012. The engine conditions and the hot gas path

    components were found to be in excellent conditions. Since then the unit was brought

    back in service successfully.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    23/33

      23

     With start of the commercial operation the combined cycle unit 4 in Irsching

    impressively showed its ability as a daily start/stop unit. Figure 13 shows the typical

    dispatch situation of Irsching unit 4. Although the plant was designed and sold as a base

    load unit, the current dispatch situation can be perfectly matched thanks to the plant’s

    capacity in terms of operational flexibility. The plant is typically starting up early in the

    morning with the increasing power demand. Over the day the unit is running in a load

    following mode with a cycling load profile between full load and 50 – 60% part load at

    the time same meeting the emission compliance and expected efficiency. Overnight shut

    downs enable our customer to save fuel cost and unnecessary emissions of NOx, CO

    and CO2. The intensive monitoring of Irsching 4 shows outstanding plant availability and

    starting reliability, which is necessary for a daily cycling operating regime.

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    Operation profile of Irsching 4

    Jun. 11 – Jun. 25, 2012

    Monday Monday

    GT speedPlant output

    Figure 13 Typical daily load profiles of Irsching unit #4

    3.2.  Test and validation of the SGT6-8000H

     The SGT6-8000H is a full scaled design (geometry factor 1.2) to the SGT5-8000H. The

    major difference is the number of burners (12 instead of 16) and the related design

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    24/33

      24

    adjustments (e.g. casing; transition from burner to turbine vane 1) in order to be able to

    use the same combustion system for 50 and 60Hz Version.

    Siemens has a vast and long lasting experience in scaling gas turbine design (e.g. SGT5-

    2000E/SGT6-2000E or SGT5-4000F/SGT6-4000F). This approach allowed Siemens to

    achieve a relative short design phase for the 6-8000H; in fact the design of the SGT6-

    8000H was initiated during the validation phase of the SGT5-8000H while the first

    commercial contract was signed only 2 years later. Of course the approach to start design

    after having already 50Hz validation results available significantly increased the

    confidence in achieving the desired design targets. There is still some remaining risk in

    scaling, especially for the non-scaled design parts. Examples are turbine inlet temperature

    profile; the specific transition-piece from combustor to turbine inlet and even production

    processes for the individual parts.

    Siemens experience in scaling allows for precise prediction of the items in question.

    However, in order to further limit the implementation risk of such a scaled prototype for

    both customer and Siemens, it was decided to perform a stringent test- and validation

    program also for the SGT6-8000H. Even if the risk for such an event is low, any

    unexpected prototype issue will cost both OEM and customer valuable time and money,

    if experienced during commissioning in a commercial project. Siemens policy is to avoid

    this. Therefore the 60Hz 8000H engine was implemented in the Berlin Test Facility

     within the Berlin gas turbine factory. Connected to a water brake instead of a grid

    connection via a generator, the engine can be operated at the design frequency of 60Hz

    as well as any desired under- and over-frequency despite being located in a 50Hz region.

     After a significant rebuilt of the test center in 2010/2011 the first SGT6-8000H was

    operated for a ca. 10 months test phase.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    25/33

      25

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    Test Bed in Berlin allowing up to 300 MW Testing at various

    speed conditions thanks to a water brake concept

     

    Figure 14 Berlin gas turbine test bed facility

    Focus of the validation phase was threefold. One target was to confirm the design of the

    scaled engine like hardware integrity, thermodynamical behavior, emission profile etc.

    Second target was to confirm the validation results of the SGT5-8000H. Third target was

    to add some additional test topics that were not conducted in Irsching like oil operation

    or sub-25ppm NOx operation. The test program was structured accordingly. The first

    test phase consisted of a baseline testing while oil operation or sub-25ppm NOx testing

     was conducted after corresponding outages.

     The targets of the SGT6-8000H test program were fully achieved. The data retrieved

    confirmed both performance prediction of SGT6-8000H and SGT5-8000H; all engine

    parameters (temperatures, pressures etc.) were as expected; predicted temperature

    profiles were confirmed via thermal paint testing; under- and over-frequency behavior of

    the engine was confirmed; operational behavior on both fuel gas and fuel oil did meet the

    requirements. Lessons learned from the validation phase are implemented in the

    production engines for the commercial projects; as a result any impact on the commercial

    projects could be avoided. So it can be concluded that the approach to validate also

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    26/33

      26

    the scaled SGT6-8000H did prove to be beneficial for both Siemens and the Siemens

    customers.

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    27/33

      27

    4. Market launch and first commercial references

     With the successful conclusion of Irsching 4 and the related validation and testing

    phases, Siemens Energy is the first OEM to operate a gas turbine engine and a combinedcycle plant with efficiency far beyond 60%. Siemens impressively demonstrated that

     world-record technology is commercially available to the customers and that the 8000H

    technology has a clear advance of years on the gas turbine and combined cycle market.

    Despite the direct scale approach, the full scale 60Hz engine was tested in the Berlin test

    facility, prior to shipment to first customer’s site. Indeed the next commercial success

     was achieved in Florida, USA, where 6 units of the SGT6-8000H were placed. Both

    Florida Power & Light sites in Riviera Beach and Cape Canaveral are equipped with the

    8000H gas turbine in a multi-shaft configuration (3 on 1) and provide approximately

    1200 MW electrical energy each. At the same time period the next order from South

    Korea for the supply of a complete combined cycle power plant equipped with the

    SGT6-8000H in a single shaft configuration was placed by the independent power

    producer GS Electric Power & Services, Ltd. As a consortium leader, Siemens is

    installing the 400MW class power plant Bugok 3 as a turnkey project. In 2012 further six

    units were successfully sold in South Korea, with ANSAN as a multi-shaft configurationand ANDONG, POSCO as a single shaft arrangement. The first 60Hz units will start the

    commercial operation already in summer 2013. Following the success in Asia Siemens

    Energy has received an order for turnkey erection of the Lausward combined cycle

    power plant with district heat extraction in Düsseldorf, Germany. The order was placed

    by Stadtwerke Düsseldorf AG (SWD). With an electrical unit output of around 595MW

    and a net efficiency of over 61% as a single shaft arrangement, the Lausward CCPP will

    set a new world record. In addition, the generated thermal energy will be used for the

    district heating system in the city of Düsseldorf. Never before has it been possible to

    extract 300 MWth of district heat from a single power plant unit in combined cycle

    operation. Thus, the overall efficiency of the natural gas fuel will be around 85 percent.

     The Lausward CCPP plant will be one of the most efficient and environmentally

    sustainable plants in the world. An overview of the references of the SGT-8000H and

    accordingly SCC-8000H is shown in Figure 15 SGT-8000H & SCC-8000H references

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    28/33

      28

    PowerGen Asia 2012

    © Siemens AG 2012

    Siemens Energy Sector Bangkok, Oct. 3 – 5

    SGT-8000H References

    Ulrich Hartmann – Irsching 4, Germany 1x SCC5-8000H 1S, >17.000 EOH

    Cape Canaveral / Riviera Beach, Florida, USA

    2x SCC6-8000H 3x1, COD 05/2013, COD 05/2014

    Bugok 3, South Korea

    1x SCC6-8000H 1S, COD 08/2013

    Status: August 2012

    15 SGT-8000H gas turbines sold

     Ansan, South Korea

    1x SCC6-8000H 2x1, COD 01/2015

     Andong, South Korea

    1x SCC6-8000H 1S, COD 04/2014

    Lausward, Germany 

    1x SCC5-8000H 1S CHP, COD 02/2016Düsseldorf,´Center 

    Düsseldorf,´Center 

    Posco Power 2, South Korea

    3x SCC6-8000H 1S, COD 11/2014, 02/2015, 05/2015

     

    Figure 15 SGT-8000H & SCC-8000H references

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    29/33

      29

     

    5. Conclusion

     This paper provides an overview regarding the Siemens SGT-8000H and the related

    SCC-8000H series product portfolio. The core engine of Siemens’ H Class is fully air

    cooled without having any external interfaces to external coolers. This key design feature

    is decisive for shifting the operational flexibility of the overall solution beyond the

    existing F Class limits, while providing a net performance far above 60%.

     The main elements of the different solutions for 50Hz and 60Hz were presented.

    Siemens’ H Class product portfolio is based on single shaft and multi shaft arrangements

     with optimized water / steam cycle and live steam parameters up to 600°C and 170 bars.

     The product portfolio offers several solutions with a flexible scope of supply, which

    drastically reduce life cycle costs and specific investment costs.

     The SGT-8000H is fully field tested and validated. An overview about all activities prior

    to market introduction was shown and which demonstrates Siemens’ approach in

    keeping the overall technology risk and hence customer’s risk at a low level. The Irschingunit #4 has already achieved more than 17,000 EOHs in commercial operation and has

    impressively demonstrated the high level of gas turbine and plant availability and starting

    reliability. In addition, the full scale 60Hz engine is tested and validated in the Berlin

    plant test facility prior to customer’s site shipment in order to limit remaining scaling

    risks. The operational records of our field validations and commercial operation have

    confirmed our expectations towards engine design reliability.

    Siemens 8000H product lines are the result of a long term development program with

    significant financial investments, demonstrating Siemens commitment to meet

    customer’s expectations and to durably improve customer’s value. Since commercial

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    30/33

      30

    availability 151 units were sold. This great success confirms the achievements in design,

    test and validation over more than a decade.

    1

     Status August 2012

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    31/33

      31

    6. References

    [1]  F. Eulitz, B. Kuesters, F. Mildner, M. Mittelbach, A. Peters, B. Van den Torn, U.

     Walke, P. Rimmington, D. Wasdell, “Design and Validation of a Compressor for aNew generation of Heavy-Duty Gas Turbines”, ASME Power Conference 2007,

    POWER2007-22100

    [2]  P. Ratliff, P. Garbett, W. Fischer, “SGT5-8000H Größerer Kundennutzen durch die

    neue Gasturbine von Siemens”, VGB PowerTech, September 2007

    [3]  U. Gruschka, B. Janus, J. Meisl, M. Huth, S. Wasif, “ULN System for the new SGT5-

    8000H gas turbine: Design and High Pressure Rig Test Results”, ASNME Turbo

    Expo GT2008-51208

    [4]  Dr. R. Fischer, P. Ratliff, W. Fischer, “SGT5-8000H – Product Validation at Irsching

     Test Center 4” Power-Gen Asia 2008

    [5]  R. Rudolph, R. Sunshine, M Woodhall, M. Haendler, “INNOVATIVE DESIGN

    FEATURES OF THE SGT5-8000H TURBINE AND SECONDARY AIR

    SYSTEM” ASME Turbo Expo, June 2009, Orlando, Florida, USA, GT2009-60137

    [6]  Dr. S. Abens, Dr. F. Eulitz, I. Harzdorf, M. Jeanchen, W. Fischer, R. Rudolph, P.

    Garbett, P. Ratliff, “Planning for Extensive Validation of the Siemens H-Class Gas

     Turbine SGT5-8000H at the Power Plant Irsching”, ASME Power Conference, July

    2009, POWER2009-81082

    [7] 

     W. Fischer, S. Abens, “SGT5-8000H Design and Product Validation at Irsching 4

     Test Center”, VGP Power Tec 09/2009

    [8]  Dr. M. Huth, U. Gruschka, Dr. B. Janus, J. Meisel, “Design of the Combustion

    System for the SGT5-8000H and First Experiences in the Irsching Power Plant”,

     VGP Power Tech 10/2009

    [9]   W. Fischer, “SGT5-8000H / IRSCHING 4: On The Way To 60% World Record

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    32/33

      32

    Efficiency And Path To 60 Hz SGT6-8000H”, 18th Conference of the Electric Power

    Supply Industry (CEPSI), Taipei, Taiwan, Oct. 2010

    [10]  Dr. S. Abens, W. Fischer, „SGT5-8000H / IRSCHING 4, On the way to 60 %

     World Record Efficiency And Path to 60 Hz SGT6-8000H”, PowerGen Asia,

    Singapore, Nov. 2010

    [11]  L. Balling, Dr. U. Tomschi, A. Pickard, G. Meinecke, “Fast Cycling and Grid Support

    Capability of Combined Cycle Power Plants to optimize the Integration of

    Renewable Generation into the European Grid: Live examples from projects in NL,

    F, UK, D”, PowerGen Europe, Amsterdam, June. 2010

    [12]  Dr. K. Sfar, T. Hagedorn, “Siemens H Class CCPP Technology: Implementation of

    the first 50Hz unit and update on latest 60Hz plant design standard”, PowerGen

     Asia, Kuala Lumpur, Sept. 2011

    [13]   W. Fischer, A. Städtler, “SGT5/6-8000H & SCC5/6-8000H Product Line: Advanced

    Generation of High Performance Gas Turbine and Combined Cycle System”, 6th

    IDGTE GT Conference, Milton Keynes, November 2011

    [14]   A. Städtler, “SGT5-8000H/SCC5-8000H 1S First experience of Commercial

    Operation at Irsching 4”, Russia Power, Moscow, March 2012

    [15]   W. Fischer, “SGT-8000H Product Line: Actual Update”, PowerGen Euorpe,

    Cologne, Jun. 2012

  • 8/16/2019 One Year of Commercial Operation in Irsching.pdf

    33/33

    7. Copyright

     The content of this paper is copyrighted by Siemens AG Energy Sector and is licensed

    only to PennWell for publication and distribution. Any inquiries regarding permission touse the content of this paper, in whole or in part, for any purpose must be addressed to

    Siemens AG Energy Sector directly.

    8. Disclaimer

     This document contains forward-looking statements and information – that is,

    statements related to future, not past, events. These statements may be identified either

    orally or in writing by words as “expects”, “anticipates”, “intends”, “plans”, “believes”,

    “seeks”, “estimates”, “will” or words of similar meaning. Such statements are based on

    our current expectations and certain assumptions, and are, therefore, subject to certain

    risks and uncertainties. A variety of factors, many of which are beyond Siemens’ control,

    affect its operations, performance, business strategy and results and could cause the

    actual results, performance or achievements of Siemens worldwide to be materially

    different from any future results, performance or achievements that may be expressed or

    implied by such forward-looking statements. For us, particular uncertainties arise, among

    others, from changes in general economic and business conditions, changes in currency

    exchange rates and interest rates, introduction of competing products or technologies by

    other companies, lack of acceptance of new products or services by customers targeted

    by Siemens worldwide, changes in business strategy and various other factors. More

    detailed information about certain of these factors is contained in Siemens’ filings with

    the SEC, which are available on the Siemens website, www.siemens.com and on the

    SEC’s website, www.sec.gov . Should one or more of these risks or uncertaintiesmaterialize, or should underlying assumptions prove incorrect, actual results may vary

    materially from those described in the relevant forward-looking statement as anticipated,

    believed, estimated, expected, intended, planned or projected. Siemens does not intend

    or assume any obligation to update or revise these forward-looking statements in light of

    developments which differ from those anticipated. Trademarks mentioned in this

    document are the property of Siemens AG, its affiliates or their respective owners.