Open Access in power

Embed Size (px)

DESCRIPTION

Consumers ProspectiveInOpen Access of power

Citation preview

PowerPoint Presentation

P.S. ShekawatSuperintending Engineer(Power),Rajasthan State Industrial Development & Investment Co. Ltd.

Consumers ProspectiveInOpen Access of power Is consumers choice through open access an enforceable right?Impact of directive of PSERC on short term Open AccessCan Open Access and Competitive power generation bring down power cost for discoms and consumersWill there be standby charges and cross subsidy surcharge if MoP directives on Open Access are implemented (30-11-2011)Operational constraints and roles of SLDCs and STUs

Open Access of Power

Powered Consumer to choose Power

Is consumers choice through open access an enforceable right?

The Government of India (Ministry of Power and Ministry of Law) in its latest interpretation on 30.11.2011 has articulated that Section 42 of the Act makes it mandatory for all consumers with load exceeding 1 MW to be open access consumers and that the tariffs for such consumers shall not be regulated by SERCs.

Cont

Is consumers choice through open access an enforceable right?

Section 42 of the Act deals with the provision of open access to distribution and reads as follows: ((2) The State Commission shall introduce open access in such phases and subject to such conditions, (including the cross subsidies, and other operational constraints) as may be specified within one year of the appointed date by it and in specifying the extent of open access in successive phases and in determining the charges for wheeling, it shall have due regard to all relevant factors including such cross subsidies, and other operational constraints: Provided that such open access shall be allowed on payment of a surcharge in addition to the charges for wheeling as may be determined by the State Commission: Provided further that such surcharge shall be utilised to meet the requirements of current level of cross subsidy within the area of supply of the distribution licensee: Provided also that such surcharge and cross subsidies shall be progressively reduced in the manner as may be specified by the State Commission: Provided also that such surcharge shall not be liveable in case open access is provided to a person who has established a captive generating plant for carrying the electricity to the destination of his own use: Provided also that the State Commission shall, not later than five years from the date of commencement of the Electricity (Amendment) Act, 2003, by regulations, provide such open access to all consumers who require a supply of electricity where the maximum power to be made available at any time exceeds one megawatt. Cont

Benefits to Consumer

Buy power from anywhere- could explore cheaper sources; Specially useful for high demand industrial /commercial consumer.Industrial houses could consolidate power supply to plant at various locations and build captive power plant to achieve economy.Give choice to consumer option to switch.Cheaper power.Improved Efficiency .Better Reliability.

Impact of directive of PSERC on short term Open AccessPower requirement varying unpredictable; which jeopardizes the system reliability.No alternative for arranging excess power or surrendering the power; thus PSPCL is financially affected.The frequent shifting of OA consumers from PSPCL to Open Access and again to PSPCL is affecting the quality of power to other consumers.The OA consumers being the cross subsidizing category for other consumer groups, this reduction of power off-take by them from PSPCL power pool has adverse impact on the tariff of other categories.Due to Open Access, the LS consumption is likely to reduce which will hit the revenue and T&D losses of PSPCL adversely. In order to prevent financial collapse of PSPCL, appropriate safeguards e.g. cross subsidy surcharge and additional surcharge as provided in the National Tariff Policy be levied on OA consumers.

Cont..

Impact of directive of PSERC on short term Open AccessWith the high end consumers migrating to Open Access without paying any surcharge, the burden on distribution licensee increases which ultimately results in increase in tariff of remaining about 70 lac consumers. The PSPCL has intimated that due to 2513 MUs availed by the Open Access consumers during 2010-11, it has suffered a loss of Rs.371 crore and this loss is likely to increase to around Rs.1000 crore during 2011-12. If this loss is passed on to the remaining consumers it will result in an unjustified hike in the tariff for these consumers.

Can Open Access and Competitive power generation bring down power cost for Discom and consumersElectricity Act 2003 has mandated that with immediate effect open access should be implemented. While everyone accepts that it may serve the consumer interests, there are two contradicting views regarding the implications of the open access system on the electricity entities especially the DISCOMs. The first view is that competitive power generation will bring down the ultimate costs to the consumers. Cost reduction is possible only by reducing the T&D losses, keeping under control the operating costs and keeping the additional power purchase costs low. Given the facts that power purchase costs keep increasing and the HT tariff has been mandated to be brought down closer to the average costs (thereby reducing the cross-subsidy) according to a fixed time schedule to be set by the regulator, the first group argues that taking up additional liabilty by way of HT consumers at such high marginal costs of power purchase would be financially imprudent for the electricity entities.

The other view is that electricity entities have heavy responsibility to meet the needs of agricultural consumers and small domestic consumers at a lower rate than the average cost. Consumers who are currently the HT consumers and commercial consumers paying a higher tariff are providing the means to do this. If such consumers walk away from Grid supply subsidy from Government will have to increase. The correct position would depend on the statewise situation regarding relative tariff of the different consumers, the possible rates of growth of category wise consumption and the potential for purchasing additional power at low rates in the future Can Open Access and Competitive power generation bring down power cost for Discom and consumersIn open access consumers of 1 MW and above are deemed OA consumer and shall have choice of purchase power cheaper sources including Discom.Discom/Transmission licensee shall be benefited by collecting wheeling and transmission charges as additional income over and above the income from retails sale of power to the consumers below 1 MW.Power purchase quantum of discom shall reduce and shall be limited only equivalent to supplying power to consumers below 1 mw and commission shall decide the tariff only for consumers below 1 MW hence ARR of Discoms shall be substantially reduce.Sufficient power shall be available to discom from Genco plants at chaper rate to supply power consumers below 1 MW and total load shedding shall be withdrawn to such consumres.Expenditure account of discoms shall reduce because of reduced employees strength and reduced working capital requirment hence tariff for consumers below 1 MW shall reduce.Tariff will change slowly to reflect the cost to serve and cross subsidy will get reduced and may finally disappear. State government may give subsidy in advance if it wants to lower the tariff for some consumers.Large consumers: They would be allowed to access new generation or put up their own captive plants. These consumers would see a major reduction in their tariff and be allowed to shrug off or reduce burden of the historical costs (stranded costs).

Will there be standby charges and cross subsidy surcharge if MoP directives on Open Access are implemented (30-11-2011)The Ministry of Power in its letter dated 30.11.2011 say that:

once a consumer becomes an Open Access consumer, the State Commission shall no longer fix the energy charges to be paid by him but will continue to fix the wheeling charges and surcharges in accordance with the provisions of the Act.

Will there be standby charges and cross subsidy surcharge if MoP directives on Open Access are implemented (30-11-2011)Electricity entities have heavy responsibility to meet the needs of agricultural consumers and small domestic consumers at a lower rate than the average cost. Consumers who are currently the HT consumers and commercial consumers paying a higher tariff are providing the means to do this. If such consumers walk away from Grid supply subsidy from Government will have to increase

Will there be standby charges and cross subsidy surcharge if MoP directives on Open Access are implemented (30-11-2011)The tariff of OA consumers shall not be regulated by state commission and the heavy burden of cross subsidies shall not be loaded to such consumers.The OA consumers shall not be consumers of discoms the power requirement shall not be the part of ARR of discom.According to national tariff policies the cross subsidy is linked with tariff for the category of consumers decided by the commission who are going out of net of Discom because of open access hence discom to be compensated by cross subsidy surcharge but there shall no such requirement in the change scenario hence such consumers will have not to pay CSS on the power wheeled through Open access.

Operational constraints of SLDC and STUsThe operations of the STU and SLDC are closely linked, and the organisational separation of these two functions should be undertaken only after robust systems and processes are established for interaction between the two.Transition RiskSettlement of imbalances in power injected and drawls.Effective Metering.Efficient pricing of transmission.Management of congestion .

Roles of SLDC and STUsensure integrated operation of the power system in a State.optimum scheduling and despatch of electricity within a State in accordance with the contracts entered into with the licensees or the generating Companies operating in that Statemonitor grid operation. keep accounts of the quantity of electricity transmittedsupervision and control over the inter-State transmission system.be responsible for carrying out real time operation for grid control and despatch of electricity within the State through secure and economic operation of the State Grid in accordance with the Grid standards and State Grid Code. Creating a system of monitoring the grant of open access by SLDC in an expeditious and non-discriminator manner.Cont

Roles of SLDC and STUsTo build, maintain and operate an efficient, co-ordinated and economical inter-State transmission system or intra-State transmission system, as the case may be; (b) to comply with the directions of the Regional Load Despatch Centre and the State Load Despatch Centre as the case may be;. (c) to provide non-discriminatory open access to its transmission system for use by- (i) any licensee or generating company on payment of the transmission charges; or (ii) any consumer as and when such open access is provided by the State Commission under sub-section (2) of section 42, on payment of the transmission charges and a surcharge thereon, as may be specified by the State Commission: Provided that such surcharge shall be utilised for the purpose of meeting the requirement of current level cross-subsidy: Provided further that such surcharge and cross subsidies shall be progressively reduced in the manner as may be specified by the Appropriate Commission:Provided also that the manner of payment and utilisation of the surcharge shall be specified by the Appropriate Commission: Provided also that such surcharge shall not be leviable in case open access is provided to a person who has established a captive generating plant for carrying the electricity to the destination of his own use.

Roles of SLDC and STUsto undertake transmission of electricity through intra-State transmission system . to provide non-discriminatory open access to its transmission system for use by- (i) any licensee or generating company on payment of the transmission charges; or (ii) any consumer as and when such open access is provided by the State Commission under sub-section (2) of section 42, on payment of the transmission charges and a surcharge thereon, as may be specified by the Central Commission: Provided that such surcharge shall be utilised for the purpose of meeting the requirement of current level cross-subsidy: Provided further that such surcharge and cross subsidies shall be progressively reduced in the manner as may be specified by the State Commission: Provided also that the manner of payment and utilisation of the surcharge shall be specified by the State Commission: Provided also that such surcharge shall not be leviable in case open access is provided to a person who has established a captive generating plant for carrying the electricity to the destination of his own use.

Conclusions Open access of power is in its ground stage and has high potential for growthIt is a step towards commercialization of power market with high growth potential. Removal of cross subsidy and surcharge need to be done with a time bound program.Open Access charges / losses based on commercial principles to optimize use of existing assets and to encourage investment.Open access process, charges and priorities need to be non-discriminatory