Opencast Quarries

Embed Size (px)

Citation preview

  • 5/28/2018 Opencast Quarries

    1/6

    Opencast Quarries:

    Vibration Assessing MethodsGuido Alfaro Degan, Dario Lippiello, and Mario PinzariDepartment of EngineeringUniversity ROMA TRE, Roma, Italy

    Abstract. The proposed work is a prediction of the propagation of seismic waves

    induced by the cultivation of quarries through the use of explosives. The paper is

    divided in two different stages: first of all it is necessary to choose, among the

    various explosives for industrial use and all possible blasting designs, the one with

    which it would be possible to get an embraceable result from the industrial point

    of view and with the minimal possible forecasted disturbance for the buildings

    present in the surrounding areas (receptors); as a second step it was found, with

    the simulations, the indicative values (for different distances) for the peak particle

    velocity (PPV - peak particle velocity). In order to work with the values as real as

    possible, we used the data contained in a draft E.I.A. (Environmental Impact

    Assessment) of the Lazio Region, regarding the project of a quarry. The optimal

    blasting design choice was made considering that a substantial amount of the work

    has to be spent at thefoot of each blastholes; therefore, we considered two

    different types of plughole, one obtained with two different diameters of drilling

    (the larger for the lower portion of the blasthole) containing only one type ofexplosive, and another one having the same diameter along its entire length, but

    containing two different types of explosives.

    Obtained the mine parameters (blasting design), the peak particle velocity

    (PPV) and its trend was determined, assuming an exponential decaying of the

    mathematical functionf = PPV(t). At the conclusion of the paper "iso-PPV"

    maps were created regarding the quarry adjacent area.

    Keywords: Vibration assessment, blasting design, PPV forecasting methods.

    1 ForewordQuarrys Drill and Blast planning consists first of all, in creating the right blast

    pattern in order to obtain a prefixed value of productivity. According to data

    contained in a Lazio Region E.I.A. draft, it was possible to arrange the optimal

    design choice, purposed to minimize the forecasted PPV values in an adjacent

    amenable area (figure 1 below shows a particular of the Technical Regional Chartn. 364040, Lazio, Italy).254Fig. 1 The quarry location an

    Once obtained the bla

    assumed to achieve the e

    working with parallel pa

    choice, it was calculated t

    trend as a mathematical ti

    2 The Quarry PrThe present work refers a

    (Viterbo, Italy), where th

    stone. As for its lithology

    alternation of pyroclasticWhinstone quarries gen

    1) Hill-side quarries

    excavated material fr

    (lower down the slope

    2) Open-pit quarries

    of the processing plan

    Hill-side quarries ma

    excavation has reached, a

    The choice of whethe

  • 5/28/2018 Opencast Quarries

    2/6

    usually dictated by the

    structure and environmen

    features and have a high v

    It is assumed that, for t

    identified and is consider

    technological, environmeG. Alfaro Degan, D. Lippiello, and M. Pinza

    nd the adjacent protected area (right side)

    asting parameters with specific computer codes, it wa

    nforced productivity value (817 m3 of ore per day) bot

    anels and with serial ones; according with the differen

    the provisional peak particle velocity (PPV) value and i

    ime depending function.

    rojectabout a whinstone quarry project, located near Setteven

    hey will extract whinstone for the production of crushe

    y the area is made up of major volcanic complexes wit

    products and lava flows.

    nerally take one of two forms:

    characterized by a general downward haulage o

    rom the quarry area (up slope) to the processing plane);

    where quarrying workings are generally below the lev

    t and excavated material is hauled up and out of the pit.

    ay often become open-pit quarries once the level o

    nd subsequently extends below, the quarry plant area.

    er a hill-side or open-pit operation is contemplated

    e site topography, ownership boundaries, geologic

    ntal considerations (hill-side quarries can be very obviou

    visual impact).

    the purposes of this paper, a hard-rock resource has bee

    red suitable for quarrying subject to the usual economi

    ental and legislative matters being satisfied. From th

    arias

    th

    nt

    its

    ne

    ed

    th

    of

    nt

    el

    of

    is

    alus

    en

    ic,

    hisOpencast Quarries: Vi bration Assessing Methods 255

    point of view, quarry management planning will be assumed, according with a

    simple scheme in which the whinstone is extracted using explosives. Loose

    materials are captured with diggers and sent to a crushing and sifting plant. In this

    phase materials are processed and then loaded into trucks for road transportation.

  • 5/28/2018 Opencast Quarries

    3/6

    3 Ore Description: The WhinstoneWhinstone is a term used in the quarrying industry to describe any hard darkcoloured

    rock. Examples include the igneous rocks basalt and dolerite as well as

    the sedimentary rock chert. The name 'whin' derives from the sound it makes when

    struck with a hammer. It is used for road chippings and dry stone walls, but its

    natural angular shapes do not fit together well and are not easy to build with, and

    its hardness makes it a difficult material to work.Whinstone is an igneous rock, which formed as the volcanic molten magma

    cooled. Being such hard, resistant rock, dolerite stands out as prominent cliffs or

    crags.

    In modern times whinstone has been extensively quarried to be used in the

    construction of roads.

    Whinstone is an extrusive igneous volcanic formed from the rapid cooling of

    basaltic lava. By definition, it is an aphanitic igneous rock with less than 20%

    quartz and less than 10% feldspathoid by volume, and where at least 65% of the

    feldspar is in the form of plagioclase. Whinstone is usually grey to black in colour,

    but rapidly weathers to brown or rust-red due to oxidation of its mafic (iron-rich)

    minerals into rust. It almost always has a fine-grained mineral texture due to the

    molten rock cooling too quickly for large mineral crystals to grow, although it can

    sometimes be porphyritic, containing the larger crystals formed prior to the

    extrusion that brought the lava to the surface, embedded in a finer-grained matrix.

    Whinstone with a vesicular or frothy texture is called scoria, and forms when

    dissolved gases are forced out of solution and form vesicles as the lava

    decompresses as it reaches the surface.

    4 Drill and Blast Design and the Forecasting ModelThe purpose of blasting operations is rock fragmentation. It provides appropriate

    rock material granulation or size that is suitable for loading and transportation.

    The blasting process and usage of explosives, however, remain a potential source

    of numerous human and environmental hazards. Several studies indicate that

    fragmentation accounts for only 20-30% of the total amount of explosive energy

    used. The remainder of the energy is wasted away in the form of ground

    vibrations, air-overpressure and flyrock. All of them can, under some

    circumstances, cause damage to structures nearby and, apart from this, be the

    source of permanent conflict with inhabitants who live close to the operation.256 G. Alfaro Degan, D. Lippiello, and M. Pinzari

    Ground vibrations can be considered as acoustic waves that propagate through

    the rocks. They differ from the round vibrations caused by earthquakes in terms of

    seismic source, amount of available energy and travelled distances. Usually,

    parameters such as velocity, displacement and acceleration of particles are

    recorded during the vibration measurements, but several studies achieved that the

    most important parameter, that has to be studied, is the Particle velocity. Many

    scientists and engineers investigated on PPV prediction considered to be the

    maximum velocity in any of the components and also on the peak vector sum

    (PVS) that is the true vector sum of the three components. The first significant

    PPV predictor equation was proposed by the United States Bureau of Mines.

    There are also modified predictors from other researchers or institutions such as

    Langefors and Kihlstrom, Ambraseys, Indian Standard, Ghosh and Daemen, PalRoy of CMRI, etc. However, the PPV predictor established by USBM is still the

    most widely used equation in the literature. To the knowledge of the author, no

    work has been reported in the literature that addresses the application of

    geostatistical approach for the estimation of ground vibration.

    4.1 Frequency of Ground VibrationThe dominant frequency of ground vibration was determined through the

    developed forecasting software. The range of observed frequencies for different

    mines and blasting projects varies between 5 and 40 Hz.

    The provisional adopted formula assumes frequency decreases with distance:

  • 5/28/2018 Opencast Quarries

    4/6

    f = (Kf logR)-1 (1)

    Where f is the frequency, R is the distance from the blasting hole (m), Kf is a

    constant that takes into account the ground characteristics (tab.1).Table 1 Values of Kf in function of the ground characteristics

    Ground KfSands and waterlogged soils 0,110,13

    Middle hardness 0,060,09

    Hard rocks 0,010,03

    Studies [1] refer that the frequency is confined within 5-60 Hz in spite of

    differing blast geometries and used explosives. In spite of the differing blast

    geometries and the explosives used, blasts in coal, lignite and iron ore mines

    produced low frequency. Relatively higher frequencies were found in case of

    limestone quarries and construction projects. It is therefore inferred that large

    blasts using higher bench heights and larger diameter blastholes are more likely to

    produce lower frequency of ground vibration.Opencast Quarries: Vi bration Assessing Methods 257

    The lowest frequencies were associated with coal mine blasting, intermediate

    with quarry blasting and high frequencies with construction blasting.

    4.2 PPV ForecastingTo assess the PPV it has been used the arrangement of an important Italian

    theoretical model [2]. This model considers that the seismic energy transmitted tothe rock by the explosive can be evaluated with the two following equations:

    Es = 2 2 f2 2 Ds2 r Vc Tv 10-6 (2)Es = nt n1 n2 ET Q (3)Where:

    A = displacement (m), f = Frequency (Hz), D S = Distance from the blasting

    point (m), r = Density of the rock(kg/m), VC = Seismic velocity (m/s), TV =Duration of the vibration (s), n= Breaking factor (charges laid on the ground

    n0.4), ET =Energy per unit of mass, Q =

    amount of explosive. nand nare respectively the impedance factor and coupling

    factor, represented by the following formulas:

    n1 = 1 - [(ZeZr (Ze + Zr ] (4)n2 = 1 / (ED/d (5)Where:

    Ze = impedance of explosive (kgms), Zr = impedance of rock (kg ms),

    D = blasthole diameter (mm), d = charge diameter (mm). From previous equations

    the following is obtained:

    A(m/s2) = [(nt n1 n2 ET Q 10-6 4 f2 Ds2 r Vc Tv] (6)As the significative duration of vibrations is considered to be five times the

    period:

    TV = 5 TS = 5 / f (7)

    According to the equation (1),f = (Kf logR)-1, the equation (6) can be written

    as follows:

    A(m/s2) = [(nt n1 n2 ET Q Kf logDS 6 Ds2 r Vc Tv] (8)And integrating,

    V(m/s) = (Q/DS) [(nt n1 n2 106 Kf logDS r Vc] (9)258 G. Alfaro Degan, D. Lippiello, and M. Pinzari

    5 Blasting DesignIt has been found that the type of explosives has significant influence on ground

    vibration [1]. Hossaini and Sen [3] have found that ANFO generates lesser

    vibration than slurry explosives. Among the different blends tested, it was found

  • 5/28/2018 Opencast Quarries

    5/6

    that the explosive with lower density and lower detonation velocity produced

    lower level of ground vibration.

    As the shock energy component of an explosive gives rise to unwanted

    vibrations [4], explosives having larger portion of gaseous energy should be

    preferred.Table 2 Explosives technical characteristics

    Explosive [Kg/m3]

    Impedance

    Ie

    Energy per kg

    [MJ/kg]

    GOMMA A 1550 11,63 6,74

    GELATINA 1 1450 9,50 4,52

    GELATINA 2 1420 8,66 4,44

    SISMIC 2 1550 10,23 4,00

    IDROPENT D 1550 12,25 7,47

    PROFIL X 1200 3,89 2,66

    TUTAGEX 210 1150 4,83 3,52

    TUTAGEX 110 1150 4,60 2,79

    VULCAN 3 1050 4,73 3,90

    CAVA EXTRA 2 1050 4,78 4,31CAVA 1 1000 3,80 4,16

    ANFO 5 800 1,84 3,66

    5.1 Bl asthole DesignAccording to results obtained, it was found that the best issue can be reached

    using two different quantity of explosives. The first explosive should be used to

    charge the upper part of the blasthole (column area) and the second one to charge

    the lower portion of the hole (foot area).

    The lower portion of the blasthole, indeed, will be charged with a greater

    quantity (kg) of explosives according to the equations (8) and (9):

    QFoot = ( / 2)2 V e (10)QColumn = (c/ 2)2 H - V - b) e (11)Opencast Quarries: Vi bration Assessing Methods 259

    This design choice (two different quantity of explosives) is coerced, according

    to the occurrence that it is necessary develop a different amount of energy in the

    lower part of the blasthole (foot portion), especially in case of sub-drilling

    perforation.

    The same result, indeed, can be obtained even using two different explosives

    with different specific characteristics (density, detonation velocity, energy per kg

    etc.).

    5.2 Inf luence of Delay In terval on PPVUsing a combination of single hole waveforms and computer simulation, the

    influence of delay interval was investigated. It is found that the delay of 25-35 ms

    produces the lowest vibration in term of PPV propagation. We can say that this

    agrees with the mines practice [5].

    6 ConclusionIn order to respect the daily imposed productivity (817 m3) it was calculated (even

    on the base of the geological site characteristics) that it is necessary to drill at least

    56 blastholes. Those holes can be subdivided in two different blasting (benchs) of

    28 holes each (single panel case study) or in 5 different blasting of 11 holes (case

    of parallel panels).

    Figure 2 and 3 show the PPV forecasting for the two cases (single panel,

    parallel panels).Fig. 2 PPV Forecastingsingle panel case

  • 5/28/2018 Opencast Quarries

    6/6

    260 G. Alfaro Degan, D. Lippiello, and M. Pinzari

    Fig. 3 PPV Forecastingparallel panels case

    7 Discussion: Most Significant Study Findings1) This study identifies the blast design parameters that can be suitably modified

    to control peak particle velocity (PPV).

    2) When predicted or monitored vibrations exceed the statutory limits, ground

    vibrations are to be controlled by modifying the blast design parameters.

    Digging trenchs between the blast and the structure can further reduce ground

    vibration seems to be a feasible solution. Numerical simulations show that the

    percentage of reduction obviously depends on the trench depth to blasthole

    depth ratio (at a ratio of 1.2, PPV value was reduced by 53%).

    3) The PPV forecasting method shows its always preferable the productivity

    process with parallel panels.