Upload
gaurav-anand
View
220
Download
0
Embed Size (px)
Citation preview
7/30/2019 P1-GIPL-003
1/15
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
PROCEDURE FOR MAINTENANCE OF SWITCHED
MODE POWER SUPPLIES
PROCEDURE NO.: P1-GIPL-003
7/30/2019 P1-GIPL-003
2/15
2
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
1. Purpose
This document provides instructions for carrying out Periodic Maintenance of
Switched Mode Power Supply and its parts like Rectifiers, Alarm Control Module,
AC distribution unit & DC distribution unit and metal clad enclosure housing these
components. The AC & DC distribution unit mainly consists of components like
contactors, moulded Case Circuit Breakers (MCCB), Miniature Circuit Breakers
(MCB) & HRC fuses.
2. Scope
This procedure will outline the maintenance routines and responsibilities for the
Switched Mode Power Supplies (SMPS) in BTS sites. This procedure provides
general guidelines as applicable for different types of SMPS. The users of this
procedure are advised to refer the corresponding OEM (O&M) manual for
carrying out specific O&M activities.
3. Responsibilities
3.1 National Head
Based at Corporate office New Delhi is responsible for the technical integrity of
this procedure. The National Head or his nominated Deputy shall be authorised
for any changes with this procedure.
3.2 Circle Manager
The Circle Manager or In-charge is responsible for ensuring that all activities
related to this procedure are complied with and recorded as described in this
document.
7/30/2019 P1-GIPL-003
3/15
3
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
4.4 Maintenance Process
4.1 Background
The rectifiers in SMPS are in modular fashion. The rating of the rack depends on
the total number of rectifier modules. All the rectifier modules provide active load
current sharing.
The AC distribution unit consists of MCBs for protection, contactors for mains
supply to the power rack terminal and surge protection device to prevent damage
to rectifier modules due to surges & spikes present in AC mains.
The DC distribution unit consists of a number of miniature circuit breakers,
battery fuse, terminal blocks for loads & battery distribution and protection like
BLVD, LLVD. It also has the functions of detecting the signal of DC and AC power
distribution units, fault alarm, and communicating with host and monitoring
module.The alarm control module receives the operation information of AC & DC
distribution units and rectifiers and performs the corresponding controls.
When the battery voltage drops to the terminating voltage 42.5V, in order to
prevent battery over-discharge, the system activates the BLVD contactor to
disconnect and thoroughly protect the battery.
In normal conditions, the system operates in parallel float charge state, i.e. the
rectifiers and batteries operate in parallel. The rectifiers supply power to the
telecom equipments & security systems and float charge current to the battery.When an AC main fails, the rectifiers stop working, the battery to maintain normal
operation powers the equipment. When the AC main is recovered, the rectifiers
resume powering the equipment and charging the battery to compensate for the
consumed energy.
4.4.2 Maintenance Frequency and Records
7/30/2019 P1-GIPL-003
4/15
4
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
Format No. Frequency Location Period to be maintained
OEM/002 Yearly BTS 3 Years
OEM/0013 Fortnightly BTS 3 Months
Contact the vendor for any manufacturing defects or discrepancies found during
the maintenance.
4.4.3 Safety Precautions
The following safety precautions need to be followed for carrying out any work on
the SMPS:
4.4.3.1 Inspections SMPS in energised condition
Inform the concerned authority and start
The SMPS and the components therein are LIVE and in energised state. Do
NOT touch any components with bare hands as this may lead to
electrocution.
Maintain a safe distance while working near LIVE terminals.
When the rectifier is working, the temperature of the heat sink is very high.
When the working rectifier is extracted out, never directly touch the
radiator of the rectifier to avoid any scald.
Wear safety shoes while working.
Stand on dry and insulated objects like Rubber Matt during working.
Do not touch any live conductors/cables without verifying that they are
dead. Use only insulated tools while working on DC circuits.
4.4.3.2 Maintenance SMPS in de-energised condition
Ensure that all supplies to the panel are switched OFF and the respective
switch locked and red tags placed on them.
7/30/2019 P1-GIPL-003
5/15
5
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
In case the maintenance is to be done on part of the SMPS and where the
other part is LIVE then appropriate care should be taken to mark its LIVEportion.
Temporary stickers have to be placed to discourage working personnel
from operating at the LIVE parts.
To protect the system against the rise in potential of metal structures, keep
the earth connections continuously on the bus-bars.
Discharge the circuits using proper discharge wire. Care should be taken tofirst connect the discharge wire to ground bus and then connect it to the
circuit.
Use personal protective equipment like safety shoes and hand gloves while
working on SMPS.
Access to working space and escape passages shall be kept clear and
unobstructed.
Warning signs, if required shall be placed at appropriate places.
Follow all precautions while using hand held tools like blowers, drill
machines etc. Use hand held tools with ELCB boards only. Use only insulated tools while working on DC circuits.
4.4.4 Tools Required
Calibrated Digital Multimeter
Spanner set
Cloth, Cotton rags
Nylon Brush
Normal hand gloves
Megger 500 V
Discharge wire
First aid kit
Vacuum cleaner
4.4.5 Fortnightly Maintenance Tasks
7/30/2019 P1-GIPL-003
6/15
6
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
Ref the data sheet OEM/0013
4.4.6.1 Purpose of Inspection
The purpose of the fortnightly inspection is to assess the general condition of the
SMPS including the condition monitoring check of its various parameters. This
fortnightly inspection is intended to be a general quick check for the moreconspicuous problems that can be encountered. Proper maintenance of SMPS
ensures continuous power availability to loads. The following types of problems
can be detected during the fortnightly inspection:
Overheating of components like MCB, MCCB, Contactors, Relays.
Oxidation of connections at terminals.
Non-working or missing indicating lamps and meters.
Overheating or chaffing of cables inside the panel.
High amount of dust and dirt inside the SMPS. Unbalance or overloading of the circuits.
Improper voltages from the supply side.
Possible source of entry for vermin entry
4.4.6.2 Inspection Procedure
Refer the manufacturers manual for the maintenance guidelines and record the
observations. Intention of this inspection as described above is to find out thevisible abnormalities, which could lead to failures. Extreme care should be
exercised while opening the door and working near or close to LIVE parts.
NOTE: Whenever performing maintenance inspections ensure that the
manufacturers instruction manual for the SMPS is available for review.
The general steps for inspection are as outlined below:
7/30/2019 P1-GIPL-003
7/15
7
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
Follow all safety precautions as mentioned in section.4.4.3
Check whether all indicating lamps/alarm control module are in working
condition and are as per logic designed. Check normal display parameters
as per OEM.
Check all the three-phase or single-phase voltage(s) from the Monitoring
Module. In case of doubt check the voltage using a multimeter on the
incomer switch/MCB/MCCB. Do not try to rectify the switch or meter inLIVE state as this may lead to short circuit.
Check the three phase or single-phase current(s) from the Monitoring
Module. Do not disconnect the secondary connections of the CT as this may
lead to high voltage on the secondary side and damage the CT and as well
as create a hazard for the working personnel.
Check the load current and compare the same with the ratings of the
breaker, MCB, MCCB etc.
Check that the frequency of supply is within the range i.e. 50Hz 5%
Check that the output voltage and current of rectifier is normal. Thedifference between the system voltage displayed by the monitoring module
and that displayed by the rectifier should not exceed 0.2V. Check the
output current of each rectifier.
Check the normal condition of the surge protection device (SPD) and its
breaker. Check that the SPD is not discoloured, deformed or torn up.
Check the earthing bonding between surge arrestor ground and main
earthing bus.
Check the battery float voltage with the batteries in fully charged condition
(for VRLA battery, it should be 2.25 + 0.02 x 24 =54.2 to 54.4 V).
Check that the output current imbalance between rectifiers is less than 5%.
7/30/2019 P1-GIPL-003
8/15
8
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
Check the individual general parameters of the SMPS available from the
panel display. Use of Laptop to check all parameter is not necessary.
Check that there is no blockage in equipment radiation passage.
Check that the rectifiers fan and airway, dust net and cabinet ventilation
are not obstructed by objects and no dust is accumulated. If dust is
observed then clear the same using a vacuum cleaner or a blower or brush.
Observe for any leaks over the top of SMPS. If water leaks are observedthen cover the panel with plastic sheet as a temporary measure.
Subsequently attend the water leak.
Observe for any unwanted cable openings. This can be source for
rodent/reptile entry. Plug such opening with proper material. Temporary
measure can be adopted to cover the openings till permanent arrangement
is made.
Feel the SMPS with bare hands. As a general rule, during operation, any
temperature that the palm of the hand cannot stand for about 3 secondsmay indicate trouble. If found abnormally hot then switch off the
concerned circuit and observe for any abnormalities. In case the circuit
cannot be de-energised because of operational criticality then arrange for a
planned event at the earliest.
Wherever feasible observe the cable terminations and connections.
Observe for insulation chaffing, frayed sheath, improper glanding, wrong
sizes of glands and terminals. Take corrective actions if possible or else
arrange for planned event.
Check that the sockets are connected firmly. Check that the cables are
routed in order and firmly and that no cables are distorted due to the
pressure imposed by metallic parts.
Check the neutral conductor condition for any visible signs of over-heat.
7/30/2019 P1-GIPL-003
9/15
9
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
Check the individual component like MCB, MCCB, contactors, relays and
fuses for any abnormality like overheating, broken condition, discoloration,
unusual noises etc. Replace if it is possible without affecting the operations
else arrange a planed event for replacement.
Check the grounding connections for the SMPS. Check the continuity of
earthing point up-to earth pit physically. Repair if found loose, corroded or
broken.
4.4.7 Yearly Maintenance & Inspection
4.4.7.1 Purpose of Inspection
The purpose of yearly inspection is to assess the overall condition of the SMPS.
This is normally performed with the SMPS in OFF and DEAD condition. However,
the maintenance of SMPS in fully de-energised state would lead to outage of DC
power and thus outage of network. In order to avoid such a scenario, it is
proposed to carry this maintenance procedure with only AC input & rectifiers in
OFF condition. The load (telecom) will continue to be fed through the battery
bank and the respective load MCBs.
The normal course of maintenance of the SMPS shall be in PARTIALLY DE-
ENERGISED CONDITION only. In case of any critical/pending jobs that warrants
shutdown of the complete SMPS, then this job has to be done under PE window.
Generally it is recommended to conduct annual inspection during the first three
years of operation. Inspection and maintenance frequency can then be increased
or decreased depending upon the observations and experience.
The inspection followed by subsequent maintenance during the annual shutdown
(Partially & fully de-energised) is quite detailed. The following repair
work/maintenance jobs are taken up during the annual maintenance plan:
Replacement of all missing meters and indication lamps.
7/30/2019 P1-GIPL-003
10/15
10
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
Rectification of faults observed during the normal energised state
inspection
Cleaning of SMPS interiors
Meggering of bus ducts and bus-bars
Checking of trips and alarms.
4.4.7.2 Inspection/Maintenance Procedure
Refer Format No.: OEM/0002 for annual maintenance of SMPS in partially de-
energised and fully de-energised condition. The general parameters of the SMPS
shall be recorded in Format OEM/0003. The maintenance procedure for SMPS in
partially de-energised condition includes shifting the DC load onto the batteries.
Prolonged outage of SMPS panel may lead to site failure due to battery discharge
Hence the shutdown work should be completed in stipulated hours of battery
backup.
NOTE: Whenever performing maintenance inspections ensure that the
manufacturers instruction manual for the SMPS is available for review.
MAINTENANCE OF SMPS IN PARTIALLY DE-ENERGISED CONDITION
The following activities shall be carried out during the annual maintenance in
partially de-energised condition:
Identify the section that will be shut down for maintenance.
Identify the switches, MCCB, breakers that need to be isolated for de-
energizing the section of SMPS. Inform the NNOC about the work.
Follow all safety precautions as mentioned in section 4.4.3
Switch OFF the input MCB on the AC side. This will shift the load on to the
batteries. In case of two sources of power shut OFF both the power
sources. Ensure that the upstream MCB/SFU in the LT panel is also switched
OFF. Place a red tag on the LT panel to indicate that the circuit is de-
energised.
7/30/2019 P1-GIPL-003
11/15
11
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
Isolate the section planned for maintenance.
Ensure that the load is transferred to the battery backup.
Switch OFF individual rectifiers by switching OFF the corresponding MCBs.
Ensure that proper red tags are placed at appropriate places.
Open the SMPS door and check the enclosure door gasket for proper
placement & replace if damaged.
Check for AC loose connections. Loose connections or bad terminations will
cause heat buildup. If any signs of heat are noticed at any termination
point, that connection should be disconnected, inspected & replaced, if
necessary, before resuming operation.
Check that all the nuts & bolts are tightened properly, being careful not to
overstress the bolts.
Clean the air filter to provide filtered air. Do not install a wet filter in the
unit.
Observe the AC cable terminations and connections. Observe for cracked
insulation, frayed sheath, improper glanding, wrong sizes of glands and
terminals and take corrective actions if required.
Check the cables for evidence of overheating.
Check the SMPS earthing continuity.
Check the normal operation of the surge protection device. Check that it is
not damaged and replace if necessary. Check that there is no fault
indication displayed on surge protector.
Check the wiring between SMPS and the remote alarm management
system (either at DDF or SCADA system).
All the switches and breakers (AC input MCCB and rectifiers circuit breaker)should be in OFF position and the lightning protection circuit breaker is
closed before switching on the AC power.
Switch on the MCCB corresponding to the SMPS at the ACDB
Switch ON the AC input MCCB of the SMPS. At this time, the AC contactor
closes. Check that the AC operation indicator turns ON.
Switch on the rectifiers circuit breakers in front of the AC distribution
Module one by one.
7/30/2019 P1-GIPL-003
12/15
12
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
Measure the mains voltage.
Check the output voltage displayed on the monitoring module.
Using a digital voltmeter verify that the output voltage is in accordance
with the systems voltage.
Verify that all the rectifier modules are ON and without any fault alarms. If
any alarm is observed then it should be checked & rectified.
Ensure that the load is transferred to the normal power supply.
Note down the load currents. Check the parameters of the alarm simulation and check the alarms
accordingly.
Follow the OEM manual for the procedure of checking of alarms.
MAINTENANCE OF SMPS IN FULLLY DE-ENERGISED CONDITION
In addition to the above-mentioned procedures for SMPS maintenance in partially
de-energised condition, the following activities shall be carried out during fully-
de-energised maintenance: Switch OFF the input MCB on the AC side. In case of two sources of power
shut OFF both the power sources. Ensure that the upstream MCB/SFU in
the LT panel is also switched OFF. Place a red tag on the LT panel to indicate
that the circuit is de-energised.
Remove the HRC battery fuse ensuring the battery is not connected to the
system. Use an insulated fuse puller.
Ensure that the power has been properly locked out i.e. verify that no parts
of the power or control circuitry are energized by back feed from alternate
power or control sources and proper red tags are placed at appropriateplaces.
Check for AC & DC loose connections.
Inspect inside the enclosures for damage & corrosion of metallic objects.
Repair & paint as required.
Completely clean the SMPS interiors if dust is observed using vacuum
cleaner or blower. Be careful to use insulated tools.
7/30/2019 P1-GIPL-003
13/15
13
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
Check that the fuses of appropriate ratings are completely inserted in the
clips. Check clips for adequate spring pressure.
Test the conductivity of DC cables by using micro-ohm meter or determine
voltage drop under test load conditions.
Perform insulation resistance test on each phase-to-phase and phase-to-
ground using a Megger on buses, breakers and cables. Insulation resistance
would be low if there is any dust or moisture in the interiors of the panel.
Before connecting the battery, confirm with a multimeter that the polarityof the battery cables, DC bus and battery terminals match. When
connecting the battery, careful attention is required to prevent short circuit
of the positive and negative poles of the battery. If two batteries are
connected at the same time, attention should be paid to prevent battery
mutual charging due to unequal end voltages of the two batteries.
Insert the HRC battery fuse thus connecting the battery to the system.
All the switches and breakers (AC input MCCB and rectifiers circuit breaker)
should be in OFF position and the lightning protection circuit breaker is
closed before switching on the AC power. Switch on the MCCB corresponding to the SMPS at the ACDB
Switch ON the AC input MCCB of the SMPS. At this time, the AC contactor
closes. Check that the AC operation indicator turns ON.
Switch on the rectifiers circuit breakers in front of the AC distribution
Module one by one.
Measure the mains voltage
Check the output voltage displayed on the monitoring module.
Using a digital voltmeter verify that the output voltage is in accordance
with the systems voltage.
Check and record the battery charging current.
Verify that all the rectifier modules are ON and without any fault alarms.
Check that all the rectifiers communicate properly with the alarm module
by observing the LED indications. If any alarm is observed then it should be
checked & rectified.
Check that the rectifier cooling fans are working properly.
Turn ON the load MCBs to put the load on the system
7/30/2019 P1-GIPL-003
14/15
14
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
Ensure that the load is transferred to the normal power supply.
Note down the load currents.
4.4.8 Alarm Simulation
The alarm module in the SMPS facilitates Potential Free Contacts (PFC) for remote
monitoring of alarms. All alarms are potential free and may be connected to
external displays/equipment as closed or open circuit when alarm is reported.Simulation can be done by shorting these terminals at the output relays or by
actual operation of relays through keypads. The output alarms of SMPS in case of
Avansys make are grouped and these can also be checked either through keypad
or shorting the terminals. Various alarms are configured to functional relays in
such a way that a single relay operates when one or more alarms configured to it
appear. These alarms are then extended to the OMCR.
The entire SMPS related alarms and electrical parameters need to be verified
after conjunction with OMCR. General alarms available in the SMPS are:
1. Battery On Line (BOL)
2. Fuse failure
3. Rectifier failure
4. Battery Low Voltage Disconnect (BLVD)
5. High and Low DC voltage
6. AC mains failure
For details of various alarms available for each model, please refer the OEM
manual.
7.Simulation of Alarms
1. By switching OFF the AC mains check that the BOL alarm (or/and AC mains
failure alarm) appears. Switch ON the AC mains and check that the alarm is
cleared.
7/30/2019 P1-GIPL-003
15/15
SECTION
PROCESS MANUALGIPL-OEM
Project and Operation & Maintenance
PROCEDURE
P1-GIPL-003
1. Either by shorting the terminals on DDF or SCADA or by operating the relay
through keypads check that the Fuse Failure alarm appears and the same is
cleared when resetted.
2. Pull out the redundant rectifier module and check that the Rectifier Failure
alarm appears. Refit the rectifier module back in its place and check that
the alarm clears.
3. Check the BLVD alarm only by shorting the terminals of the relay and NOT
through actuation.While carrying out the above alarm simulation, check that the alarms are
extended to the OMCR when they appear and the same are cleared when the
relays are resetted.
4.5 Formats, Records & Frequency
Format No. Frequency Location
Period to be
maintainedOEM/002 Yearly BTS 3 Years
OEM/0013 Fortnightly BTS 3 Months