Activity ID Activity Name Original Duration Early Start Early Finish Late Start Late Finish Total Float PACKAGE B : FOURTH LANE WIDENING 593 06-Jul-12 05-Jul-14 06-Jul-12 05-Jul-14 0 Milestones 593 06-Jul-12 05-Jul-14 06-Jul-12 05-Jul-14 0 BA1000 Letter of Award 0 06-Jul-12 06-Jul-12 0 BA1010 Site Possession 0 06-Jul-12 06-Jul-12 0 BA1060 Section Completion of Package B Section 1 (East Bound) Work 0 05-Oct-13 05-Jul-14 221 BA1150 Section Completion of Package B Section 2 (West Bound) Work 0 05-Jul-14 05-Jul-14 0 BA2000 Completion of PLUS Package B 0 05-Jul-14 05-Jul-14 0 Section 2 (West Bound) 375 01-Apr-13 05-Jul-14 05-Jul-14 05-Jul-14 0 BA4000 Commencement Stage 1 0 01-Apr-13 05-Jul-14 375 BA4010 Completion Stage 1 0 14-Apr-14 05-Jul-14 68 BA4020 Commencement Stage 2 0 15-Apr-14 05-Jul-14 68 BA4030 Completion Stage 2 0 05-Jul-14 05-Jul-14 0 Section 1 (East Bound) 372 06-Jul-12 05-Oct-13 05-Jul-14 05-Jul-14 221 BA3000 Commencement Stage 1 0 06-Jul-12 05-Jul-14 593 BA3010 Completion Stage 1 0 05-Jun-13 05-Jul-14 321 BA3020 Commencement Stage 2 0 06-Jun-13 05-Jul-14 321 BA3030 Completion Stage 2 0 05-Oct-13 05-Jul-14 221 General Items 588 06-Jul-12 30-Jun-14 06-Jul-12 05-Jul-14 5 BB1000 Preliminaries Start 0 06-Jul-12 06-Jul-12 0 BB1010 Initial Site Survey 50 06-Jul-12 06-Sep-12 06-Jul-12 06-Sep-12 0 BB1020 Mobilisation 50 06-Jul-12 06-Sep-12 12-Jul-12 12-Sep-12 5 BB1030 Preliminaries Finish 0 30-Jun-14 05-Jul-14 5 BB4000 Testing of Materials and Works 542 03-Sep-12 30-Jun-14 06-Sep-12 03-Jul-14 3 Method Related Items 578 18-Jul-12 30-Jun-14 24-Jul-12 05-Jul-14 5 BB3030 Construction Plant 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8 Contractor's Accommodation and Buildings 578 18-Jul-12 30-Jun-14 24-Jul-12 05-Jul-14 5 BB3000 Establishment of the Contractor's Offices 35 18-Jul-12 30-Aug-12 24-Jul-12 06-Sep-12 5 BB3010 Removal of the Contractor's Offices 24 03-Jun-14 30-Jun-14 09-Jun-14 05-Jul-14 5 BB3020 Maintenance of the Contractor's Offices 575 18-Jul-12 26-Jun-14 24-Jul-12 02-Jul-14 5 Temporary Works 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8 BB3100 Temporary Access and Haul Roads 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8 BB3110 Temporary Facilities 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8 BB3120 Project Signboard 6 18-Jul-12 24-Jul-12 27-Jul-12 02-Aug-12 8 BB3130 Metal Deck Hoardings 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8 Specified Requirements 578 18-Jul-12 30-Jun-14 24-Jul-12 05-Jul-14 5 BB2000 Progress Reports 575 18-Jul-12 26-Jun-14 24-Jul-12 02-Jul-14 5 BB2010 Progress Photographs 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8 BB2020 Progress Videos 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8 BB2030 As-Built Drawings 46 06-May-14 30-Jun-14 12-May-14 05-Jul-14 5 BB2040 Operation & Maintenance Manual (O&M) 46 06-May-14 30-Jun-14 12-May-14 05-Jul-14 5 BB2050 Occupational, Safety adn Health Requirements 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8 BB2060 Setting Out 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8 Land Acquisition 52 06-Jul-12 08-Sep-12 18-Sep-12 04-Dec-12 70 BB5000 Access from Desa Park City to Edinburgh Estate CH.3380 52 06-Jul-12 08-Sep-12 02-Oct-12 04-Dec-12 70 BB5010 Segambut Dalam Encumbrances at CH.5480 52 06-Jul-12 08-Sep-12 18-Sep-12 20-Nov-12 58 Phase 1 (East Bound) 320 03-Sep-12 28-Sep-13 03-Sep-12 05-Jul-14 227 Site Clearance and Fencing (EB) 317 03-Sep-12 25-Sep-13 03-Sep-12 05-Jul-14 230 BC1005 Site Clearance and Fencing Start (EB) 0 03-Sep-12 03-Sep-12 0 BC1015 Site Clearance and Fencing Finish (EB) 0 25-Sep-13 05-Jul-14 230 Site Clearing and Fencing (CH.0-CH.1400) 206 03-Sep-12 10-May-13 03-Sep-12 12-Aug-13 75 BC1000 Site Clearing & Demolition Works 38 03-Sep-12 17-Oct-12 03-Sep-12 17-Oct-12 0 BC1010 Demolition Works 38 03-Sep-12 17-Oct-12 26-Jun-13 12-Aug-13 243 BC1020 Relocation & Installation of Temporary Signage & Gantry 38 03-Sep-12 17-Oct-12 26-Jun-13 12-Aug-13 243 BC1030 Fencing and Gate 37 28-Mar-13 10-May-13 03-Apr-13 16-May-13 5 BC1040 Miscellaneous Dismantling, Demolition and Excavation 38 03-Sep-12 17-Oct-12 26-Jun-13 12-Aug-13 243 Site Clearing and Fencing (CH.1400-CH.2800) 205 18-Oct-12 25-Jun-13 18-Oct-12 27-Sep-13 76 BC1100 Site Clearing & Demolition Works 38 18-Oct-12 04-Dec-12 18-Oct-12 04-Dec-12 0 BC1110 Demolition Works 38 18-Oct-12 04-Dec-12 13-Aug-13 27-Sep-13 243 BC1120 Relocation & Installation of Temporary Signage & Gantry 38 18-Oct-12 04-Dec-12 13-Aug-13 27-Sep-13 243 BC1130 Fencing and Gate 37 11-May-13 25-Jun-13 17-May-13 01-Jul-13 5 BC1140 Miscellaneous Dismantling, Demolition and Excavation 38 18-Oct-12 04-Dec-12 13-Aug-13 27-Sep-13 243 Site Clearing and Fencing (CH.2800-CH.4200) 204 05-Dec-12 10-Aug-13 05-Dec-12 14-Nov-13 77 BC1200 Site Clearing & Demolition Works 38 05-Dec-12 19-Jan-13 05-Dec-12 19-Jan-13 0 BC1210 Demolition Works 38 05-Dec-12 19-Jan-13 28-Sep-13 14-Nov-13 243 BC1220 Relocation & Installation of Temporary Signage & Gantry 38 05-Dec-12 19-Jan-13 28-Sep-13 14-Nov-13 243 BC1230 Fencing and Gate 37 26-Jun-13 10-Aug-13 02-Jul-13 16-Aug-13 5 BC1240 Miscellaneous Dismantling, Demolition and Excavation 38 05-Dec-12 19-Jan-13 28-Sep-13 14-Nov-13 243 Site Clearing and Fencing (CH.4200-CH.5600) 203 21-Jan-13 25-Sep-13 21-Jan-13 31-Dec-13 78 BC1300 Site Clearing & Demolition Works 38 21-Jan-13 07-Mar-13 21-Jan-13 07-Mar-13 0 BC1310 Demolition Works 38 21-Jan-13 07-Mar-13 28-Jan-13 13-Mar-13 5 BC1320 Relocation & Installation of Temporary Signage & Gantry 38 21-Jan-13 07-Mar-13 28-Jan-13 13-Mar-13 5 BC1330 Fencing and Gate 37 12-Aug-13 25-Sep-13 17-Aug-13 01-Oct-13 5 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2012 2013 2014 05-Jul-14, PA 05-Jul-14, Mi Letter of Award Site Possession Section Completion of Package B Section 1 (East Bound) Work Section Com Completion o 05-Jul-14, Se Commencement Stage 1 Completion Stage 1 Commencement Stage 2 Completion S 05-Oct-13, Section 1 (East Bound) Commencement Stage 1 Completion Stage 1 Commencement Stage 2 Completion Stage 2 30-Jun-14, Ge Preliminaries Start Initial Site Survey Mobilisation Preliminaries F Testing of Mat 30-Jun-14, Me Construction Pla 30-Jun-14, Co Establishment of the Contractor's Offices Removal of the Maintenance of 26-Jun-14, Tem Temporary Acce Temporary Faci Project Signboard Metal Deck Hoa 30-Jun-14, Sp Progress Repor Progress Photo Progress Videos As-Built Drawin Operation & M Occupational, S Setting Out 08-Sep-12, Land Acquisition Access from Desa Park City to Edinburgh Estate CH.3380 Segambut Dalam Encumbrances at CH.5480 28-Sep-13, Phase 1 (East Bound) 25-Sep-13, Site Clearance and Fencing (EB) Site Clearance and Fencing Start (EB) Site Clearance and Fencing Finish (EB) 10-May-13, Site Clearing and Fencing (CH.0-CH.1400) Site Clearing & Demolition Works Demolition Works Relocation & Installation of Temporary Signage & Gantry Fencing and Gate Miscellaneous Dismantling, Demolition and Excavation 25-Jun-13, Site Clearing and Fencing (CH.1400-CH.2800) Site Clearing & Demolition Works Demolition Works Relocation & Installation of Temporary Signage & Gantry Fencing and Gate Miscellaneous Dismantling, Demolition and Excavation 10-Aug-13, Site Clearing and Fencing (CH.2800-CH.4200) Site Clearing & Demolition Works Demolition Works Relocation & Installation of Temporary Signage & Gantry Fencing and Gate Miscellaneous Dismantling, Demolition and Excavation 25-Sep-13, Site Clearing and Fencing (CH.4200-CH.5600) Site Clearing & Demolition Works Demolition Works Relocation & Installation of Temporary Signage & Gantry Fencing and Gate NORTH-SOUTH EXPRESSWAY (PLUS) PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B Remaining Work Critical Remaining Work Milestone Summary 1 of 13 WORK PROGRAMME Date Revision Checked Approved 30-Jul-12 Rev.0 11-Sep-12 Rev.1

Package B - Fourth Lane Widening

Embed Size (px)

DESCRIPTION

proposed work program for fourth lane widening project - package b

Citation preview

Page 1: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

PACKAGE B : FOURTH LANE WIDENINGPACKAGE B : FOURTH LANE WIDENING 593 06-Jul-12 05-Jul-14 06-Jul-12 05-Jul-14 0

MilestonesMilestones 593 06-Jul-12 05-Jul-14 06-Jul-12 05-Jul-14 0

BA1000 Letter of Award 0 06-Jul-12 06-Jul-12 0

BA1010 Site Possession 0 06-Jul-12 06-Jul-12 0

BA1060 Section Completion of Package B Section 1 (East Bound) Work 0 05-Oct-13 05-Jul-14 221

BA1150 Section Completion of Package B Section 2 (West Bound) Work 0 05-Jul-14 05-Jul-14 0

BA2000 Completion of PLUS Package B 0 05-Jul-14 05-Jul-14 0

Section 2 (West Bound)Section 2 (West Bound) 375 01-Apr-13 05-Jul-14 05-Jul-14 05-Jul-14 0

BA4000 Commencement Stage 1 0 01-Apr-13 05-Jul-14 375

BA4010 Completion Stage 1 0 14-Apr-14 05-Jul-14 68

BA4020 Commencement Stage 2 0 15-Apr-14 05-Jul-14 68

BA4030 Completion Stage 2 0 05-Jul-14 05-Jul-14 0

Section 1 (East Bound)Section 1 (East Bound) 372 06-Jul-12 05-Oct-13 05-Jul-14 05-Jul-14 221

BA3000 Commencement Stage 1 0 06-Jul-12 05-Jul-14 593

BA3010 Completion Stage 1 0 05-Jun-13 05-Jul-14 321

BA3020 Commencement Stage 2 0 06-Jun-13 05-Jul-14 321

BA3030 Completion Stage 2 0 05-Oct-13 05-Jul-14 221

General ItemsGeneral Items 588 06-Jul-12 30-Jun-14 06-Jul-12 05-Jul-14 5

BB1000 Preliminaries Start 0 06-Jul-12 06-Jul-12 0

BB1010 Initial Site Survey 50 06-Jul-12 06-Sep-12 06-Jul-12 06-Sep-12 0

BB1020 Mobilisation 50 06-Jul-12 06-Sep-12 12-Jul-12 12-Sep-12 5

BB1030 Preliminaries Finish 0 30-Jun-14 05-Jul-14 5

BB4000 Testing of Materials and Works 542 03-Sep-12 30-Jun-14 06-Sep-12 03-Jul-14 3

Method Related ItemsMethod Related Items 578 18-Jul-12 30-Jun-14 24-Jul-12 05-Jul-14 5

BB3030 Construction Plant 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8

Contractor's Accommodation and BuildingsContractor's Accommodation and Buildings 578 18-Jul-12 30-Jun-14 24-Jul-12 05-Jul-14 5

BB3000 Establishment of the Contractor's Offices 35 18-Jul-12 30-Aug-12 24-Jul-12 06-Sep-12 5

BB3010 Removal of the Contractor's Offices 24 03-Jun-14 30-Jun-14 09-Jun-14 05-Jul-14 5

BB3020 Maintenance of the Contractor's Offices 575 18-Jul-12 26-Jun-14 24-Jul-12 02-Jul-14 5

Temporary WorksTemporary Works 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8

BB3100 Temporary Access and Haul Roads 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8

BB3110 Temporary Facilities 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8

BB3120 Project Signboard 6 18-Jul-12 24-Jul-12 27-Jul-12 02-Aug-12 8

BB3130 Metal Deck Hoardings 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8

Specified RequirementsSpecified Requirements 578 18-Jul-12 30-Jun-14 24-Jul-12 05-Jul-14 5

BB2000 Progress Reports 575 18-Jul-12 26-Jun-14 24-Jul-12 02-Jul-14 5

BB2010 Progress Photographs 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8

BB2020 Progress Videos 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8

BB2030 As-Built Drawings 46 06-May-14 30-Jun-14 12-May-14 05-Jul-14 5

BB2040 Operation & Maintenance Manual (O&M) 46 06-May-14 30-Jun-14 12-May-14 05-Jul-14 5

BB2050 Occupational, Safety adn Health Requirements 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8

BB2060 Setting Out 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8

Land AcquisitionLand Acquisition 52 06-Jul-12 08-Sep-12 18-Sep-12 04-Dec-12 70

BB5000 Access from Desa Park City to Edinburgh Estate CH.3380 52 06-Jul-12 08-Sep-12 02-Oct-12 04-Dec-12 70

BB5010 Segambut Dalam Encumbrances at CH.5480 52 06-Jul-12 08-Sep-12 18-Sep-12 20-Nov-12 58

Phase 1 (East Bound)Phase 1 (East Bound) 320 03-Sep-12 28-Sep-13 03-Sep-12 05-Jul-14 227

Site Clearance and Fencing (EB)Site Clearance and Fencing (EB) 317 03-Sep-12 25-Sep-13 03-Sep-12 05-Jul-14 230

BC1005 Site Clearance and Fencing Start (EB) 0 03-Sep-12 03-Sep-12 0

BC1015 Site Clearance and Fencing Finish (EB) 0 25-Sep-13 05-Jul-14 230

Site Clearing and Fencing (CH.0-CH.1400)Site Clearing and Fencing (CH.0-CH.1400) 206 03-Sep-12 10-May-13 03-Sep-12 12-Aug-13 75

BC1000 Site Clearing & Demolition Works 38 03-Sep-12 17-Oct-12 03-Sep-12 17-Oct-12 0

BC1010 Demolition Works 38 03-Sep-12 17-Oct-12 26-Jun-13 12-Aug-13 243

BC1020 Relocation & Installation of Temporary Signage & Gantry 38 03-Sep-12 17-Oct-12 26-Jun-13 12-Aug-13 243

BC1030 Fencing and Gate 37 28-Mar-13 10-May-13 03-Apr-13 16-May-13 5

BC1040 Miscellaneous Dismantling, Demolition and Excavation 38 03-Sep-12 17-Oct-12 26-Jun-13 12-Aug-13 243

Site Clearing and Fencing (CH.1400-CH.2800)Site Clearing and Fencing (CH.1400-CH.2800) 205 18-Oct-12 25-Jun-13 18-Oct-12 27-Sep-13 76

BC1100 Site Clearing & Demolition Works 38 18-Oct-12 04-Dec-12 18-Oct-12 04-Dec-12 0

BC1110 Demolition Works 38 18-Oct-12 04-Dec-12 13-Aug-13 27-Sep-13 243

BC1120 Relocation & Installation of Temporary Signage & Gantry 38 18-Oct-12 04-Dec-12 13-Aug-13 27-Sep-13 243

BC1130 Fencing and Gate 37 11-May-13 25-Jun-13 17-May-13 01-Jul-13 5

BC1140 Miscellaneous Dismantling, Demolition and Excavation 38 18-Oct-12 04-Dec-12 13-Aug-13 27-Sep-13 243

Site Clearing and Fencing (CH.2800-CH.4200)Site Clearing and Fencing (CH.2800-CH.4200) 204 05-Dec-12 10-Aug-13 05-Dec-12 14-Nov-13 77

BC1200 Site Clearing & Demolition Works 38 05-Dec-12 19-Jan-13 05-Dec-12 19-Jan-13 0

BC1210 Demolition Works 38 05-Dec-12 19-Jan-13 28-Sep-13 14-Nov-13 243

BC1220 Relocation & Installation of Temporary Signage & Gantry 38 05-Dec-12 19-Jan-13 28-Sep-13 14-Nov-13 243

BC1230 Fencing and Gate 37 26-Jun-13 10-Aug-13 02-Jul-13 16-Aug-13 5

BC1240 Miscellaneous Dismantling, Demolition and Excavation 38 05-Dec-12 19-Jan-13 28-Sep-13 14-Nov-13 243

Site Clearing and Fencing (CH.4200-CH.5600)Site Clearing and Fencing (CH.4200-CH.5600) 203 21-Jan-13 25-Sep-13 21-Jan-13 31-Dec-13 78

BC1300 Site Clearing & Demolition Works 38 21-Jan-13 07-Mar-13 21-Jan-13 07-Mar-13 0

BC1310 Demolition Works 38 21-Jan-13 07-Mar-13 28-Jan-13 13-Mar-13 5

BC1320 Relocation & Installation of Temporary Signage & Gantry 38 21-Jan-13 07-Mar-13 28-Jan-13 13-Mar-13 5

BC1330 Fencing and Gate 37 12-Aug-13 25-Sep-13 17-Aug-13 01-Oct-13 5

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

05-Jul-14, PACKAGE B : FOURTH LANE WIDENING

05-Jul-14, Milestones

Letter of Award

Site Possession

Section Completion of Package B Section 1 (East Bound) Work

Section Completion of Package B Section 2 (West Bound) Work

Completion of PLUS Package B

05-Jul-14, Section 2 (West Bound)

Commencement Stage 1

Completion Stage 1

Commencement Stage 2

Completion Stage 2

05-Oct-13, Section 1 (East Bound)

Commencement Stage 1

Completion Stage 1

Commencement Stage 2

Completion Stage 2

30-Jun-14, General Items

Preliminaries Start

Initial Site Survey

Mobilisation

Preliminaries Finish

Testing of Materials and Works

30-Jun-14, Method Related Items

Construction Plant

30-Jun-14, Contractor's Accommodation and Buildings

Establishment of the Contractor's Offices

Removal of the Contractor's Offices

Maintenance of the Contractor's Offices

26-Jun-14, Temporary Works

Temporary Access and Haul Roads

Temporary Facilities

Project Signboard

Metal Deck Hoardings

30-Jun-14, Specified Requirements

Progress Reports

Progress Photographs

Progress Videos

As-Built Drawings

Operation & Maintenance Manual (O&M)

Occupational, Safety adn Health Requirements

Setting Out

08-Sep-12, Land Acquisition

Access from Desa Park City to Edinburgh Estate CH.3380

Segambut Dalam Encumbrances at CH.5480

28-Sep-13, Phase 1 (East Bound)

25-Sep-13, Site Clearance and Fencing (EB)

Site Clearance and Fencing Start (EB)

Site Clearance and Fencing Finish (EB)

10-May-13, Site Clearing and Fencing (CH.0-CH.1400)

Site Clearing & Demolition Works

Demolition Works

Relocation & Installation of Temporary Signage & Gantry

Fencing and Gate

Miscellaneous Dismantling, Demolition and Excavation

25-Jun-13, Site Clearing and Fencing (CH.1400-CH.2800)

Site Clearing & Demolition Works

Demolition Works

Relocation & Installation of Temporary Signage & Gantry

Fencing and Gate

Miscellaneous Dismantling, Demolition and Excavation

10-Aug-13, Site Clearing and Fencing (CH.2800-CH.4200)

Site Clearing & Demolition Works

Demolition Works

Relocation & Installation of Temporary Signage & Gantry

Fencing and Gate

Miscellaneous Dismantling, Demolition and Excavation

25-Sep-13, Site Clearing and Fencing (CH.4200-CH.5600)

Site Clearing & Demolition Works

Demolition Works

Relocation & Installation of Temporary Signage & Gantry

Fencing and Gate

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 1 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1

Page 2: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

BC1340 Miscellaneous Dismantling, Demolition and Excavation 38 21-Jan-13 07-Mar-13 15-Nov-13 31-Dec-13 243

Earthworks (EB)Earthworks (EB) 309 15-Sep-12 28-Sep-13 22-Sep-12 05-Jul-14 227

BD0010 Earthwork Start (EB) 0 15-Sep-12 08-Nov-12 44

BD0020 Earthwork Finish (EB) 0 28-Sep-13 05-Jul-14 227

Stage 1Stage 1 175 15-Sep-12 16-Apr-13 22-Sep-12 14-Oct-13 147

CH.2800-CH.4200CH.2800-CH.4200 61 18-Dec-12 02-Mar-13 12-Jan-13 28-Aug-13 147

BD1200 Excavate to Toe of Slope (CH.2800-CH.4200) 38 18-Dec-12 02-Feb-13 05-Jul-13 21-Aug-13 164

BD1210 Fill to Formation Level (CH.2800-CH.4200) 38 07-Jan-13 21-Feb-13 12-Jan-13 27-Feb-13 5

BD1220 Turf ing 38 16-Jan-13 02-Mar-13 18-Mar-13 30-Apr-13 50

BD1230 Instrumentation and Monitoring 44 07-Jan-13 28-Feb-13 05-Jul-13 28-Aug-13 149

BD1240 Soil Investigation 38 18-Dec-12 02-Feb-13 05-Jul-13 21-Aug-13 164

CH.0-CH.1400CH.0-CH.1400 61 15-Sep-12 29-Nov-12 22-Sep-12 27-May-13 147

BD1000 Excavate to Toe of Slope (CH.0-CH.1400) 38 15-Sep-12 31-Oct-12 22-Sep-12 06-Nov-12 5

BD1010 Fill to Formation Level (CH.0-CH.1400) 38 04-Oct-12 20-Nov-12 10-Oct-12 26-Nov-12 5

BD1020 Turf ing 38 13-Oct-12 29-Nov-12 14-Dec-12 30-Jan-13 50

BD1030 Instrumentation and Monitoring 44 04-Oct-12 27-Nov-12 04-Apr-13 27-May-13 149

BD1040 Soil Investigation 38 15-Sep-12 31-Oct-12 04-Apr-13 18-May-13 164

CH.1400-CH.2800CH.1400-CH.2800 61 01-Nov-12 15-Jan-13 27-Nov-12 11-Jul-13 147

BD1100 Excavate to Toe of Slope (CH.1400-CH.2800) 38 01-Nov-12 17-Dec-12 20-May-13 04-Jul-13 164

BD1110 Fill to Formation Level (CH.1400-CH.2800) 38 21-Nov-12 05-Jan-13 27-Nov-12 11-Jan-13 5

BD1120 Turf ing 38 30-Nov-12 15-Jan-13 31-Jan-13 16-Mar-13 50

BD1130 Instrumentation and Monitoring 44 21-Nov-12 12-Jan-13 20-May-13 11-Jul-13 149

BD1140 Soil Investigation 38 01-Nov-12 17-Dec-12 20-May-13 04-Jul-13 164

CH.4200-CH.5600CH.4200-CH.5600 61 04-Feb-13 16-Apr-13 28-Feb-13 14-Oct-13 147

BD1300 Excavate to Toe of Slope (CH.4200-CH.5600) 38 04-Feb-13 20-Mar-13 22-Aug-13 07-Oct-13 164

BD1310 Fill to Formation Level (CH.4200-CH.5600) 38 22-Feb-13 06-Apr-13 28-Feb-13 12-Apr-13 5

BD1320 Turf ing 38 04-Mar-13 16-Apr-13 02-May-13 17-Jun-13 50

BD1330 Instrumentation and Monitoring 44 22-Feb-13 13-Apr-13 22-Aug-13 14-Oct-13 149

BD1340 Soil Investigation 38 04-Feb-13 20-Mar-13 22-Aug-13 07-Oct-13 164

Stage 2Stage 2 142 08-Apr-13 28-Sep-13 30-Apr-13 07-Feb-14 104

CH.4200-CH.5600CH.4200-CH.5600 46 02-Aug-13 28-Sep-13 27-Aug-13 07-Feb-14 104

BD2300 Removal of Existing Pavement 32 02-Aug-13 11-Sep-13 27-Aug-13 04-Oct-13 19

BD2310 Turf ing (Remaining Works) 32 21-Aug-13 28-Sep-13 28-Dec-13 07-Feb-14 104

BD2320 Treatment of Existing Subsoil Drain 32 13-Aug-13 20-Sep-13 19-Dec-13 28-Jan-14 104

CH.1400-CH.2800CH.1400-CH.2800 46 16-May-13 10-Jul-13 10-Jun-13 18-Nov-13 104

BD2100 Removal of Existing Pavement 32 16-May-13 24-Jun-13 10-Jun-13 16-Jul-13 19

BD2110 Turf ing (Remaining Works) 32 04-Jun-13 10-Jul-13 09-Oct-13 18-Nov-13 104

BD2120 Treatment of Existing Subsoil Drain 32 25-May-13 02-Jul-13 01-Oct-13 09-Nov-13 104

CH.2800-CH.4200CH.2800-CH.4200 46 25-Jun-13 20-Aug-13 17-Jul-13 27-Dec-13 104

BD2200 Removal of Existing Pavement 32 25-Jun-13 01-Aug-13 17-Jul-13 26-Aug-13 19

BD2210 Turf ing (Remaining Works) 32 11-Jul-13 20-Aug-13 19-Nov-13 27-Dec-13 104

BD2220 Treatment of Existing Subsoil Drain 32 03-Jul-13 12-Aug-13 11-Nov-13 18-Dec-13 104

CH.0-CH.1400CH.0-CH.1400 46 08-Apr-13 03-Jun-13 30-Apr-13 08-Oct-13 104

BD2000 Removal of Existing Pavement 32 08-Apr-13 15-May-13 30-Apr-13 08-Jun-13 19

BD2010 Turf ing (Remaining Works) 32 24-Apr-13 03-Jun-13 30-Aug-13 08-Oct-13 104

BD2020 Treatment of Existing Subsoil Drain 32 16-Apr-13 23-May-13 22-Aug-13 30-Sep-13 104

Drainage Works (EB)Drainage Works (EB) 309 15-Sep-12 28-Sep-13 10-Nov-12 05-Jul-14 227

BE0010 Drainage Works Start (EB) 0 15-Sep-12 10-Nov-12 46

BE0030 Drainage Works Finish (EB) 0 28-Sep-13 05-Jul-14 227

Stage 1Stage 1 309 15-Sep-12 28-Sep-13 10-Nov-12 05-Jul-14 227

Pipe Culverts ExtensionsPipe Culverts Extensions 250 28-Nov-12 28-Sep-13 02-Sep-13 05-Jul-14 227

Culvert 4 (CH.1293)Culvert 4 (CH.1293) 25 28-Feb-13 28-Mar-13 03-Dec-13 03-Jan-14 227

BE3300 Pipe Culvert Extension 11 28-Feb-13 12-Mar-13 03-Dec-13 16-Dec-13 227

BE3310 RC Box Joints 3 13-Mar-13 15-Mar-13 17-Dec-13 19-Dec-13 227

BE3320 Inlet/Outlet Structures 11 16-Mar-13 28-Mar-13 20-Dec-13 03-Jan-14 227

Culvert 1 (CH.94)Culvert 1 (CH.94) 25 28-Nov-12 27-Dec-12 02-Sep-13 01-Oct-13 227

BE3000 Pipe Culvert Extension 11 28-Nov-12 10-Dec-12 02-Sep-13 13-Sep-13 227

BE3010 RC Box Joints 3 11-Dec-12 13-Dec-12 14-Sep-13 18-Sep-13 227

BE3020 Inlet/Outlet Structures 11 14-Dec-12 27-Dec-12 19-Sep-13 01-Oct-13 227

Culvert 2 (CH.625)Culvert 2 (CH.625) 25 28-Dec-12 28-Jan-13 02-Oct-13 31-Oct-13 227

BE3100 Pipe Culvert Extension 11 28-Dec-12 10-Jan-13 02-Oct-13 14-Oct-13 227

BE3110 RC Box Joints 3 11-Jan-13 14-Jan-13 16-Oct-13 18-Oct-13 227

BE3120 Inlet/Outlet Structures 11 15-Jan-13 28-Jan-13 19-Oct-13 31-Oct-13 227

Culvert 3 (CH.927)Culvert 3 (CH.927) 25 29-Jan-13 27-Feb-13 01-Nov-13 02-Dec-13 227

BE3200 Pipe Culvert Extension 11 29-Jan-13 09-Feb-13 01-Nov-13 15-Nov-13 227

BE3210 RC Box Joints 3 12-Feb-13 14-Feb-13 16-Nov-13 19-Nov-13 227

BE3220 Inlet/Outlet Structures 11 15-Feb-13 27-Feb-13 20-Nov-13 02-Dec-13 227

Culvert 5 (CH.2365)Culvert 5 (CH.2365) 25 29-Mar-13 26-Apr-13 04-Jan-14 05-Feb-14 227

BE3400 Pipe Culvert Extension 11 29-Mar-13 10-Apr-13 04-Jan-14 17-Jan-14 227

BE3410 RC Box Joints 3 11-Apr-13 13-Apr-13 18-Jan-14 21-Jan-14 227

BE3420 Inlet/Outlet Structures 11 15-Apr-13 26-Apr-13 22-Jan-14 05-Feb-14 227

Culvert 6 (CH.2926)Culvert 6 (CH.2926) 25 27-Apr-13 28-May-13 06-Feb-14 07-Mar-14 227

BE3500 Pipe Culvert Extension 11 27-Apr-13 10-May-13 06-Feb-14 19-Feb-14 227

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

Miscellaneous Dismantling, Demolition and Excavation

28-Sep-13, Earthworks (EB)

Earthwork Start (EB)

Earthwork Finish (EB)

16-Apr-13, Stage 1

02-Mar-13, CH.2800-CH.4200

Excavate to Toe of Slope (CH.2800-CH.4200)

Fill to Formation Level (CH.2800-CH.4200)

Turfing

Instrumentation and Monitoring

Soil Investigation

29-Nov-12, CH.0-CH.1400

Excavate to Toe of Slope (CH.0-CH.1400)

Fill to Formation Level (CH.0-CH.1400)

Turf ing

Instrumentation and Monitoring

Soil Investigation

15-Jan-13, CH.1400-CH.2800

Excavate to Toe of Slope (CH.1400-CH.2800)

Fill to Formation Level (CH.1400-CH.2800)

Turf ing

Instrumentation and Monitoring

Soil Investigation

16-Apr-13, CH.4200-CH.5600

Excavate to Toe of Slope (CH.4200-CH.5600)

Fill to Formation Level (CH.4200-CH.5600)

Turf ing

Instrumentation and Monitoring

Soil Investigation

28-Sep-13, Stage 2

28-Sep-13, CH.4200-CH.5600

Removal of Existing Pavement

Turf ing (Remaining Works)

Treatment of Existing Subsoil Drain

10-Jul-13, CH.1400-CH.2800

Removal of Existing Pavement

Turf ing (Remaining Works)

Treatment of Existing Subsoil Drain

20-Aug-13, CH.2800-CH.4200

Removal of Existing Pavement

Turf ing (Remaining Works)

Treatment of Existing Subsoil Drain

03-Jun-13, CH.0-CH.1400

Removal of Existing Pavement

Turf ing (Remaining Works)

Treatment of Existing Subsoil Drain

28-Sep-13, Drainage Works (EB)

Drainage Works Start (EB)

Drainage Works Finish (EB)

28-Sep-13, Stage 1

28-Sep-13, Pipe Culverts Extensions

28-Mar-13, Culvert 4 (CH.1293)

Pipe Culvert Extension

RC Box Joints

Inlet/Outlet Structures

27-Dec-12, Culvert 1 (CH.94)

Pipe Culvert Extension

RC Box Joints

Inlet/Outlet Structures

28-Jan-13, Culvert 2 (CH.625)

Pipe Culvert Extension

RC Box Joints

Inlet/Outlet Structures

27-Feb-13, Culvert 3 (CH.927)

Pipe Culvert Extension

RC Box Joints

Inlet/Outlet Structures

26-Apr-13, Culvert 5 (CH.2365)

Pipe Culvert Extension

RC Box Joints

Inlet/Outlet Structures

28-May-13, Culvert 6 (CH.2926)

Pipe Culvert Extension

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 2 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1

Page 3: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

BE3510 RC Box Joints 3 11-May-13 14-May-13 20-Feb-14 22-Feb-14 227

BE3520 Inlet/Outlet Structures 11 15-May-13 28-May-13 24-Feb-14 07-Mar-14 227

Culvert 7 (CH.3640)Culvert 7 (CH.3640) 25 29-May-13 27-Jun-13 08-Mar-14 05-Apr-14 227

BE3600 Pipe Culvert Extension 11 29-May-13 11-Jun-13 08-Mar-14 20-Mar-14 227

BE3610 RC Box Joints 3 12-Jun-13 14-Jun-13 21-Mar-14 24-Mar-14 227

BE3620 Inlet/Outlet Structures 11 15-Jun-13 27-Jun-13 25-Mar-14 05-Apr-14 227

Culvert 8 (CH.4196)Culvert 8 (CH.4196) 25 28-Jun-13 27-Jul-13 07-Apr-14 06-May-14 227

BE3700 Pipe Culvert Extension 11 28-Jun-13 10-Jul-13 07-Apr-14 18-Apr-14 227

BE3710 RC Box Joints 3 11-Jul-13 13-Jul-13 19-Apr-14 22-Apr-14 227

BE3720 Inlet/Outlet Structures 11 15-Jul-13 27-Jul-13 23-Apr-14 06-May-14 227

Culvert 9 (CH.4628)Culvert 9 (CH.4628) 25 29-Jul-13 28-Aug-13 07-May-14 06-Jun-14 227

BE3800 Pipe Culvert Extension 11 29-Jul-13 12-Aug-13 07-May-14 20-May-14 227

BE3810 RC Box Joints 3 13-Aug-13 15-Aug-13 21-May-14 23-May-14 227

BE3820 Inlet/Outlet Structures 11 16-Aug-13 28-Aug-13 24-May-14 06-Jun-14 227

Culvert 10 (CH.4906)Culvert 10 (CH.4906) 25 29-Aug-13 28-Sep-13 07-Jun-14 05-Jul-14 227

BE3900 Pipe Culvert Extension 11 29-Aug-13 11-Sep-13 07-Jun-14 19-Jun-14 227

BE3910 RC Box Joints 3 12-Sep-13 14-Sep-13 20-Jun-14 23-Jun-14 227

BE3920 Inlet/Outlet Structures 11 17-Sep-13 28-Sep-13 24-Jun-14 05-Jul-14 227

Drainage (CH.0-CH.1400)Drainage (CH.0-CH.1400) 43 15-Sep-12 06-Nov-12 10-Nov-12 03-Jan-13 46

BE1000 Excavation 33 15-Sep-12 24-Oct-12 10-Nov-12 20-Dec-12 46

BE1010 Laying of Drain 33 22-Sep-12 31-Oct-12 19-Nov-12 27-Dec-12 46

BE1020 Backfilling 33 28-Sep-12 06-Nov-12 24-Nov-12 03-Jan-13 46

Drainage (CH.1400-CH.2800)Drainage (CH.1400-CH.2800) 43 07-Nov-12 29-Dec-12 04-Jan-13 25-Feb-13 46

BE1100 Excavation 33 07-Nov-12 17-Dec-12 04-Jan-13 13-Feb-13 46

BE1110 Laying of Drain 33 14-Nov-12 22-Dec-12 10-Jan-13 19-Feb-13 46

BE1120 Backfilling 33 21-Nov-12 29-Dec-12 16-Jan-13 25-Feb-13 46

Drainage (CH.2800-CH.4200)Drainage (CH.2800-CH.4200) 43 31-Dec-12 21-Feb-13 26-Feb-13 16-Apr-13 46

BE1200 Excavation 33 31-Dec-12 08-Feb-13 26-Feb-13 04-Apr-13 46

BE1210 Laying of Drain 33 07-Jan-13 15-Feb-13 04-Mar-13 10-Apr-13 46

BE1220 Backfilling 33 12-Jan-13 21-Feb-13 09-Mar-13 16-Apr-13 46

Drainage (CH.4200-CH.5600)Drainage (CH.4200-CH.5600) 43 22-Feb-13 12-Apr-13 17-Apr-13 08-Jun-13 46

BE1300 Excavation 33 22-Feb-13 01-Apr-13 17-Apr-13 27-May-13 46

BE1310 Laying of Drain 33 28-Feb-13 06-Apr-13 23-Apr-13 03-Jun-13 46

BE1320 Backfilling 33 06-Mar-13 12-Apr-13 29-Apr-13 08-Jun-13 46

Stage 2Stage 2 128 13-Apr-13 18-Sep-13 03-Feb-14 05-Jul-14 236

Drains (Remaining Works) and KerbsDrains (Remaining Works) and Kerbs 128 13-Apr-13 18-Sep-13 03-Feb-14 05-Jul-14 236

BE1500 CH.0-CH.1400 32 13-Apr-13 21-May-13 03-Feb-14 12-Mar-14 236

BE1510 CH.1400-CH.2800 32 22-May-13 29-Jun-13 13-Mar-14 18-Apr-14 236

BE1520 CH.2800-CH.4200 32 01-Jul-13 07-Aug-13 19-Apr-14 28-May-14 236

BE1530 CH.4200-CH.5600 32 10-Aug-13 18-Sep-13 29-May-14 05-Jul-14 236

Sub-Base, Roadbase and Pavement (EB)Sub-Base, Roadbase and Pavement (EB) 158 20-Mar-13 28-Sep-13 11-May-13 05-Jul-14 227

BF0010 Sub-Base, Roadbase and Pavement Start (EB) 0 20-Mar-13 11-May-13 44

BF0020 Sub-Base, Roadbase and Pavement Finish (EB) 0 28-Sep-13 05-Jul-14 227

Stage 1Stage 1 96 20-Mar-13 12-Jul-13 13-Mar-14 05-Jul-14 289

BF0500 Saw Cut of CRCP - CH.0-CH.1400 24 20-Mar-13 16-Apr-13 13-Mar-14 09-Apr-14 289

BF0510 Saw Cut of CRCP - CH.1400-CH.2800 24 17-Apr-13 15-May-13 10-Apr-14 08-May-14 289

BF0520 Saw Cut of CRCP - CH.2800-CH.4200 24 16-May-13 14-Jun-13 09-May-14 07-Jun-14 289

BF0530 Saw Cut of CRCP - CH.4200-CH.5600 24 15-Jun-13 12-Jul-13 09-Jun-14 05-Jul-14 289

Stage 2Stage 2 158 20-Mar-13 28-Sep-13 11-May-13 05-Jul-14 227

BF3000 Sub-surface Drainage Improvement (East Bound) 140 20-Mar-13 06-Sep-13 11-May-13 30-Oct-13 44

Sub-Base upto Pavement (CH.0-CH.1400)Sub-Base upto Pavement (CH.0-CH.1400) 38 18-Apr-13 04-Jun-13 11-May-13 16-Apr-14 256

BF1010 Sub-Grade and Prepare Formation 24 18-Apr-13 16-May-13 11-May-13 10-Jun-13 19

BF1020 Laying of Lower Sub-Base 24 20-Apr-13 18-May-13 14-May-13 12-Jun-13 19

BF1030 Laying of Lower Upper-Base 24 23-Apr-13 21-May-13 16-May-13 14-Jun-13 19

BF1040 Laying of CBM 22 25-Apr-13 21-May-13 18-May-13 14-Jun-13 19

BF1050 Laying of WMM 22 27-Apr-13 23-May-13 01-Nov-13 28-Nov-13 152

BF1060 Laying of DBM 22 30-Apr-13 27-May-13 06-Nov-13 30-Nov-13 152

BF1070 Laying of ACBC 22 03-May-13 29-May-13 08-Nov-13 03-Dec-13 152

BF1075 Regulating 22 04-May-13 30-May-13 22-Mar-14 16-Apr-14 259

BF1080 Laying of ACWC 22 06-May-13 31-May-13 11-Nov-13 05-Dec-13 152

BF1090 Laying of SMA 22 08-May-13 04-Jun-13 13-Nov-13 07-Dec-13 152

BF1100 Dismantle Guardrail, NJB Installation & Misc. Works 32 25-Apr-13 04-Jun-13 18-May-13 26-Jun-13 19

BF1110 Temporay Road Marking & Traffic Diversion/Contra Flow 32 25-Apr-13 04-Jun-13 04-Feb-14 13-Mar-14 227

Sub-Base upto Pavement (CH.2800-CH.4200)Sub-Base upto Pavement (CH.2800-CH.4200) 38 05-Jul-13 21-Aug-13 29-Jul-13 05-Jul-14 258

BF1410 Sub-Grade and Prepare Formation 24 05-Jul-13 02-Aug-13 29-Jul-13 27-Aug-13 19

BF1420 Laying of Lower Sub-Base 24 08-Jul-13 05-Aug-13 31-Jul-13 29-Aug-13 19

BF1430 Laying of Lower Upper-Base 24 10-Jul-13 07-Aug-13 02-Aug-13 02-Sep-13 19

BF1440 Laying of CBM 22 12-Jul-13 07-Aug-13 05-Aug-13 02-Sep-13 19

BF1450 Laying of WMM 22 15-Jul-13 12-Aug-13 08-May-14 04-Jun-14 239

BF1460 Laying of DBM 22 17-Jul-13 14-Aug-13 10-May-14 06-Jun-14 239

BF1470 Laying of ACBC 22 19-Jul-13 16-Aug-13 14-May-14 09-Jun-14 239

BF1475 Regulating 22 20-Jul-13 17-Aug-13 15-May-14 10-Jun-14 239

BF1480 Laying of ACWC 22 22-Jul-13 19-Aug-13 09-Jun-14 03-Jul-14 258

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

RC Box Joints

Inlet/Outlet Structures

27-Jun-13, Culvert 7 (CH.3640)

Pipe Culvert Extension

RC Box Joints

Inlet/Outlet Structures

27-Jul-13, Culvert 8 (CH.4196)

Pipe Culvert Extension

RC Box Joints

Inlet/Outlet Structures

28-Aug-13, Culvert 9 (CH.4628)

Pipe Culvert Extension

RC Box Joints

Inlet/Outlet Structures

28-Sep-13, Culvert 10 (CH.4906)

Pipe Culvert Extension

RC Box Joints

Inlet/Outlet Structures

06-Nov-12, Drainage (CH.0-CH.1400)

Excavation

Laying of Drain

Backfilling

29-Dec-12, Drainage (CH.1400-CH.2800)

Excavation

Laying of Drain

Backfilling

21-Feb-13, Drainage (CH.2800-CH.4200)

Excavation

Laying of Drain

Backfilling

12-Apr-13, Drainage (CH.4200-CH.5600)

Excavation

Laying of Drain

Backfilling

18-Sep-13, Stage 2

18-Sep-13, Drains (Remaining Works) and Kerbs

CH.0-CH.1400

CH.1400-CH.2800

CH.2800-CH.4200

CH.4200-CH.5600

28-Sep-13, Sub-Base, Roadbase and Pavement (EB)

Sub-Base, Roadbase and Pavement Start (EB)

Sub-Base, Roadbase and Pavement Finish (EB)

12-Jul-13, Stage 1

Saw Cut of CRCP - CH.0-CH.1400

Saw Cut of CRCP - CH.1400-CH.2800

Saw Cut of CRCP - CH.2800-CH.4200

Saw Cut of CRCP - CH.4200-CH.5600

28-Sep-13, Stage 2

Sub-surface Drainage Improvement (East Bound)

04-Jun-13, Sub-Base upto Pavement (CH.0-CH.1400)

Sub-Grade and Prepare Formation

Laying of Lower Sub-Base

Laying of Lower Upper-Base

Laying of CBM

Laying of WMM

Laying of DBM

Laying of ACBC

Regulating

Laying of ACWC

Laying of SMA

Dismantle Guardrail, NJB Installation & Misc. Works

Temporay Road Marking & Traffic Diversion/Contra Flow

21-Aug-13, Sub-Base upto Pavement (CH.2800-CH.4200)

Sub-Grade and Prepare Formation

Laying of Lower Sub-Base

Laying of Lower Upper-Base

Laying of CBM

Laying of WMM

Laying of DBM

Laying of ACBC

Regulating

Laying of ACWC

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 3 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1

Page 4: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

BF1490 Laying of SMA 22 24-Jul-13 21-Aug-13 11-Jun-14 05-Jul-14 258

BF1500 Dismantle Guardrail, NJB Installation & Misc. Works 32 12-Jul-13 21-Aug-13 05-Aug-13 13-Sep-13 19

BF1510 Temporay Road Marking & Traffic Diversion/Contra Flow 32 12-Jul-13 21-Aug-13 21-Apr-14 29-May-14 227

Sub-Base upto Pavement (CH.4200-CH.5600)Sub-Base upto Pavement (CH.4200-CH.5600) 37 15-Aug-13 28-Sep-13 07-Sep-13 05-Jul-14 227

BF1610 Sub-Grade and Prepare Formation 24 15-Aug-13 12-Sep-13 07-Sep-13 05-Oct-13 19

BF1620 Laying of Lower Sub-Base 24 17-Aug-13 14-Sep-13 10-Sep-13 08-Oct-13 19

BF1630 Laying of Lower Upper-Base 24 20-Aug-13 18-Sep-13 12-Sep-13 10-Oct-13 19

BF1640 Laying of CBM 22 22-Aug-13 18-Sep-13 14-Sep-13 10-Oct-13 19

BF1650 Laying of WMM 22 24-Aug-13 20-Sep-13 04-Jun-14 28-Jun-14 228

BF1660 Laying of DBM 22 27-Aug-13 23-Sep-13 06-Jun-14 01-Jul-14 228

BF1670 Laying of ACBC 22 29-Aug-13 25-Sep-13 09-Jun-14 03-Jul-14 228

BF1675 Regulating 22 30-Aug-13 26-Sep-13 11-Jun-14 05-Jul-14 229

BF1680 Laying of ACWC 22 30-Aug-13 26-Sep-13 10-Jun-14 04-Jul-14 228

BF1690 Laying of SMA 22 02-Sep-13 27-Sep-13 11-Jun-14 05-Jul-14 228

BF1700 Dismantle Guardrail, NJB Installation & Misc. Works 31 22-Aug-13 28-Sep-13 14-Sep-13 22-Oct-13 19

BF1710 Temporay Road Marking & Traffic Diversion/Contra Flow 31 22-Aug-13 28-Sep-13 30-May-14 05-Jul-14 227

Sub-Base upto Pavement (CH.1400-CH.2800)Sub-Base upto Pavement (CH.1400-CH.2800) 38 28-May-13 11-Jul-13 20-Jun-13 05-Jul-14 290

BF1210 Sub-Grade and Prepare Formation 24 28-May-13 25-Jun-13 20-Jun-13 17-Jul-13 19

BF1220 Laying of Lower Sub-Base 24 30-May-13 27-Jun-13 22-Jun-13 19-Jul-13 19

BF1230 Laying of Lower Upper-Base 24 03-Jun-13 29-Jun-13 25-Jun-13 22-Jul-13 19

BF1240 Laying of CBM 22 05-Jun-13 29-Jun-13 27-Jun-13 22-Jul-13 19

BF1250 Laying of WMM 22 07-Jun-13 02-Jul-13 11-Apr-14 07-May-14 249

BF1260 Laying of DBM 22 10-Jun-13 04-Jul-13 14-Apr-14 09-May-14 249

BF1270 Laying of ACBC 22 12-Jun-13 06-Jul-13 16-Apr-14 12-May-14 249

BF1275 Regulating 22 13-Jun-13 08-Jul-13 17-Apr-14 14-May-14 249

BF1280 Laying of ACWC 22 14-Jun-13 09-Jul-13 09-Jun-14 03-Jul-14 290

BF1290 Laying of SMA 22 17-Jun-13 11-Jul-13 11-Jun-14 05-Jul-14 290

BF1300 Dismantle Guardrail, NJB Installation & Misc. Works 32 05-Jun-13 11-Jul-13 27-Jun-13 03-Aug-13 19

BF1310 Temporay Road Marking & Traffic Diversion/Contra Flow 32 05-Jun-13 11-Jul-13 14-Mar-14 19-Apr-14 227

Road Furniture (EB)Road Furniture (EB) 73 01-Jul-13 28-Sep-13 07-Jan-14 05-Jul-14 227

BG0010 Road Furniture Start (EB) 0 01-Jul-13 07-Jan-14 152

BG0020 Road Furniture Finish (EB) 0 28-Sep-13 05-Jul-14 227

Stage 2Stage 2 73 01-Jul-13 28-Sep-13 07-Jan-14 05-Apr-14 152

CH.4200-CH.5600CH.4200-CH.5600 18 07-Sep-13 28-Sep-13 17-Mar-14 05-Apr-14 152

BG1300 Traffic Signs 18 07-Sep-13 28-Sep-13 17-Mar-14 05-Apr-14 152

BG1310 Road Markings 18 07-Sep-13 28-Sep-13 17-Mar-14 05-Apr-14 152

BG1320 Ancillary Finishings 18 07-Sep-13 28-Sep-13 17-Mar-14 05-Apr-14 152

CH.1400-CH.2800CH.1400-CH.2800 18 23-Jul-13 15-Aug-13 30-Jan-14 22-Feb-14 152

BG1100 Traffic Signs 18 23-Jul-13 15-Aug-13 30-Jan-14 22-Feb-14 152

BG1110 Road Markings 18 23-Jul-13 15-Aug-13 30-Jan-14 22-Feb-14 152

BG1120 Ancillary Finishings 18 23-Jul-13 15-Aug-13 30-Jan-14 22-Feb-14 152

CH.2800-CH.4200CH.2800-CH.4200 18 16-Aug-13 06-Sep-13 24-Feb-14 15-Mar-14 152

BG1200 Traffic Signs 18 16-Aug-13 06-Sep-13 24-Feb-14 15-Mar-14 152

BG1210 Road Markings 18 16-Aug-13 06-Sep-13 24-Feb-14 15-Mar-14 152

BG1220 Ancillary Finishings 18 16-Aug-13 06-Sep-13 24-Feb-14 15-Mar-14 152

CH.0-CH.1400CH.0-CH.1400 19 01-Jul-13 22-Jul-13 07-Jan-14 29-Jan-14 152

BG1000 Traffic Signs 19 01-Jul-13 22-Jul-13 07-Jan-14 29-Jan-14 152

BG1010 Road Markings 19 01-Jul-13 22-Jul-13 07-Jan-14 29-Jan-14 152

BG1020 Ancillary Finishings 19 01-Jul-13 22-Jul-13 07-Jan-14 29-Jan-14 152

Utilities and Services (EB)Utilities and Services (EB) 222 02-Jan-13 28-Sep-13 10-Jan-13 05-Jul-14 227

BH0100 Utilities and Services Start (EB) 0 02-Jan-13 10-Jan-13 7

BH0110 Utilities and Services Finish (EB) 0 28-Sep-13 05-Jul-14 227

Overall Stage 1Overall Stage 1 222 02-Jan-13 28-Sep-13 10-Jan-13 05-Jul-14 227

BH0020 Testing and Commissioning 94 06-Jun-13 28-Sep-13 12-Jun-13 04-Oct-13 5

CH.0-CH.1400CH.0-CH.1400 122 02-Jan-13 28-May-13 10-Jan-13 05-Jul-14 327

BH1030 Temporary Works for Exist ing Utilities 104 23-Jan-13 28-May-13 04-Mar-14 05-Jul-14 327

Telecommunication SystemTelecommunication System 36 02-Jan-13 14-Feb-13 10-Jan-13 22-Feb-13 7

BH1000 Lay Duct 36 02-Jan-13 14-Feb-13 10-Jan-13 22-Feb-13 7

CH.1400-CH.2800CH.1400-CH.2800 108 02-Feb-13 12-Jun-13 12-Feb-13 05-Jul-14 315

BH2030 Temporary Works for Exist ing Utilities 90 25-Feb-13 12-Jun-13 20-Mar-14 05-Jul-14 315

Telecommunication SystemTelecommunication System 60 02-Feb-13 13-Apr-13 12-Feb-13 11-Jun-13 47

BH2000 Lay Duct 36 02-Feb-13 16-Mar-13 12-Feb-13 25-Mar-13 7

BH2010 Relocation of OFC 36 18-Feb-13 30-Mar-13 13-Apr-13 27-May-13 47

BH2020 ITS System 36 04-Mar-13 13-Apr-13 27-Apr-13 11-Jun-13 47

CH.2800-CH.4200CH.2800-CH.4200 108 06-Mar-13 12-Jul-13 14-Mar-13 05-Jul-14 289

BH3030 Temporary Works for Exist ing Utilities 90 27-Mar-13 12-Jul-13 20-Mar-14 05-Jul-14 289

Telecommunication SystemTelecommunication System 60 06-Mar-13 15-May-13 14-Mar-13 11-Jun-13 21

BH3000 Lay Duct 36 06-Mar-13 16-Apr-13 14-Mar-13 24-Apr-13 7

BH3010 Relocation of OFC 36 20-Mar-13 30-Apr-13 13-Apr-13 27-May-13 21

BH3020 ITS System 36 03-Apr-13 15-May-13 27-Apr-13 11-Jun-13 21

CH.4200-CH.5600CH.4200-CH.5600 202 02-Jan-13 04-Sep-13 13-Apr-13 05-Jul-14 247

BH4030 Temporary Works for Exist ing Utilities 104 29-Apr-13 04-Sep-13 04-Mar-14 05-Jul-14 247

BH4040 Waterworks, Relocation of Water Mains (CH.5450) 70 02-Jan-13 26-Mar-13 09-Oct-13 04-Jan-14 230

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

Laying of SMA

Dismantle Guardrail, NJB Installation & Misc. Works

Temporay Road Marking & Traffic Diversion/Contra Flow

28-Sep-13, Sub-Base upto Pavement (CH.4200-CH.5600)

Sub-Grade and Prepare Formation

Laying of Lower Sub-Base

Laying of Lower Upper-Base

Laying of CBM

Laying of WMM

Laying of DBM

Laying of ACBC

Regulating

Laying of ACWC

Laying of SMA

Dismantle Guardrail, NJB Installation & Misc. Works

Temporay Road Marking & Traffic Diversion/Contra Flow

11-Jul-13, Sub-Base upto Pavement (CH.1400-CH.2800)

Sub-Grade and Prepare Formation

Laying of Lower Sub-Base

Laying of Lower Upper-Base

Laying of CBM

Laying of WMM

Laying of DBM

Laying of ACBC

Regulating

Laying of ACWC

Laying of SMA

Dismantle Guardrail, NJB Installation & Misc. Works

Temporay Road Marking & Traffic Diversion/Contra Flow

28-Sep-13, Road Furniture (EB)

Road Furniture Start (EB)

Road Furniture Finish (EB)

28-Sep-13, Stage 2

28-Sep-13, CH.4200-CH.5600

Traffic Signs

Road Markings

Ancillary Finishings

15-Aug-13, CH.1400-CH.2800

Traffic Signs

Road Markings

Ancillary Finishings

06-Sep-13, CH.2800-CH.4200

Traffic Signs

Road Markings

Ancillary Finishings

22-Jul-13, CH.0-CH.1400

Traffic Signs

Road Markings

Ancillary Finishings

28-Sep-13, Utilities and Services (EB)

Utilities and Services Start (EB)

Utilities and Services Finish (EB)

28-Sep-13, Overall Stage 1

Testing and Commissioning

28-May-13, CH.0-CH.1400

Temporary Works for Exist ing Utilities

14-Feb-13, Telecommunication System

Lay Duct

12-Jun-13, CH.1400-CH.2800

Temporary Works for Existing Utilities

13-Apr-13, Telecommunication System

Lay Duct

Relocation of OFC

ITS System

12-Jul-13, CH.2800-CH.4200

Temporary Works for Exist ing Utilities

15-May-13, Telecommunication System

Lay Duct

Relocation of OFC

ITS System

04-Sep-13, CH.4200-CH.5600

Temporary Works for Exist ing Utilities

Waterworks, Relocation of Water Mains (CH.5450)

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 4 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1

Page 5: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

Telecommunication SystemTelecommunication System 48 08-Apr-13 05-Jun-13 13-Apr-13 11-Jun-13 5

BH4000 Lay Duct 36 08-Apr-13 20-May-13 13-Apr-13 27-May-13 5

BH4010 Relocation of OFC 36 15-Apr-13 28-May-13 20-Apr-13 04-Jun-13 5

BH4020 ITS System 36 22-Apr-13 05-Jun-13 27-Apr-13 11-Jun-13 5

Bridge Widening (EB)Bridge Widening (EB) 286 15-Sep-12 30-Aug-13 20-Oct-12 05-Jul-14 250

BJ1000 Bridge Widening Start (EB) 0 15-Sep-12 20-Oct-12 29

BJ1010 Bridge Widening Finish (EB) 0 30-Aug-13 05-Jul-14 250

Bridge Extension Over Jalan Damansara (BR B.1)Bridge Extension Over Jalan Damansara (BR B.1) 238 14-Nov-12 30-Aug-13 19-Dec-12 21-Jun-14 238

Section 1 - East BoundSection 1 - East Bound 238 14-Nov-12 30-Aug-13 19-Dec-12 21-Jun-14 238

East AbutmentEast Abutment 52 03-Jan-13 06-Mar-13 29-Apr-13 01-Jul-13 97

BJ2140 Pile Cap Construction 18 03-Jan-13 23-Jan-13 29-Apr-13 20-May-13 97

BJ2150 Abutment Wall 16 25-Jan-13 13-Feb-13 21-May-13 10-Jun-13 97

BJ2160 Wing Wall & Curtail Wall 10 14-Feb-13 25-Feb-13 11-Jun-13 21-Jun-13 97

BJ2170 Approach Slab 8 26-Feb-13 06-Mar-13 22-Jun-13 01-Jul-13 97

Bridge DeckBridge Deck 40 21-Mar-13 07-May-13 16-Jul-13 04-Sep-13 97

BJ2410 Bridge Deck Construction 40 21-Mar-13 07-May-13 16-Jul-13 04-Sep-13 97

MiscellaneousMiscellaneous 106 23-Apr-13 30-Aug-13 21-Aug-13 21-Jun-14 238

BJ2420 Bridge Parapet, Lining to Abutment and Service Ducts 26 23-Apr-13 23-May-13 21-Aug-13 21-Sep-13 97

BJ2430 Installation of Movement Joints in Bridge Deck and Approach Slab 12 17-Aug-13 30-Aug-13 09-Jun-14 21-Jun-14 238

Precast BeamsPrecast Beams 12 07-Mar-13 20-Mar-13 02-Jul-13 15-Jul-13 97

BJ2400 Launching of Pre-tensioned Concrete Beams 12 07-Mar-13 20-Mar-13 02-Jul-13 15-Jul-13 97

PilingPiling 40 14-Nov-12 02-Jan-13 19-Dec-12 27-Apr-13 97

BJ2000 Temporary Sheet Piling 6 14-Nov-12 21-Nov-12 19-Dec-12 26-Dec-12 29

BJ2005 Bored Piling 26 01-Dec-12 02-Jan-13 29-Mar-13 27-Apr-13 97

West AbutmentWest Abutment 52 08-Dec-12 09-Feb-13 24-Apr-13 01-Jul-13 117

BJ2100 Pile Cap Construction 18 08-Dec-12 29-Dec-12 24-Apr-13 15-May-13 113

BJ2110 Abutment Wall 16 31-Dec-12 18-Jan-13 21-May-13 10-Jun-13 117

BJ2120 Wing Wall & Curtail Wall 10 19-Jan-13 31-Jan-13 11-Jun-13 21-Jun-13 117

BJ2130 Approach Slab 8 01-Feb-13 09-Feb-13 22-Jun-13 01-Jul-13 117

Pier 1Pier 1 48 11-Dec-12 07-Feb-13 04-May-13 01-Jul-13 119

BJ2200 Pile Cap Construction 22 11-Dec-12 07-Jan-13 04-May-13 30-May-13 119

BJ2210 Column Construction 26 08-Jan-13 07-Feb-13 31-May-13 01-Jul-13 119

Pier 2Pier 2 54 11-Dec-12 15-Feb-13 26-Apr-13 01-Jul-13 113

BJ2220 Pile Cap Construction 22 11-Dec-12 07-Jan-13 26-Apr-13 22-May-13 113

BJ2230 Column Construction 32 08-Jan-13 15-Feb-13 23-May-13 01-Jul-13 113

Pier 3Pier 3 62 15-Dec-12 01-Mar-13 17-Apr-13 01-Jul-13 101

BJ2240 Pile Cap Construction 22 15-Dec-12 11-Jan-13 17-Apr-13 13-May-13 101

BJ2250 Column Construction 40 12-Jan-13 01-Mar-13 14-May-13 01-Jul-13 101

Pier 4Pier 4 26 18-Dec-12 18-Jan-13 31-May-13 01-Jul-13 135

BJ2260 Pile Cap Construction 22 18-Dec-12 14-Jan-13 31-May-13 26-Jun-13 135

BJ2270 Column Construction 4 15-Jan-13 18-Jan-13 27-Jun-13 01-Jul-13 135

Pier 5Pier 5 48 20-Dec-12 18-Feb-13 04-May-13 01-Jul-13 111

BJ2280 Pile Cap Construction 22 20-Dec-12 16-Jan-13 04-May-13 30-May-13 111

BJ2290 Column Construction 26 17-Jan-13 18-Feb-13 31-May-13 01-Jul-13 111

Bridge Extension Over Segambut Dalam (BR B.2)Bridge Extension Over Segambut Dalam (BR B.2) 236 15-Oct-12 29-Jul-13 21-Nov-12 21-Jun-14 264

Section 1 - East BoundSection 1 - East Bound 236 15-Oct-12 29-Jul-13 21-Nov-12 21-Jun-14 264

PilingPiling 38 15-Oct-12 30-Nov-12 21-Nov-12 28-Mar-13 97

BJ3000 Temporary Sheet Piling 6 15-Oct-12 20-Oct-12 21-Nov-12 27-Nov-12 29

BJ3005 Bored Piling 26 30-Oct-12 30-Nov-12 27-Feb-13 28-Mar-13 97

West AbutmentWest Abutment 52 03-Nov-12 07-Jan-13 16-Apr-13 18-Jun-13 134

BJ3100 Pile Cap Construction 18 03-Nov-12 26-Nov-12 16-Apr-13 07-May-13 134

BJ3110 Abutment Wall 16 27-Nov-12 14-Dec-12 08-May-13 27-May-13 134

BJ3120 Wing Wall & Curtail Wall 10 15-Dec-12 27-Dec-12 28-May-13 08-Jun-13 134

BJ3130 Approach Slab 8 28-Dec-12 07-Jan-13 10-Jun-13 18-Jun-13 134

Pier 1Pier 1 48 08-Nov-12 07-Jan-13 20-Apr-13 18-Jun-13 134

BJ3180 Pile Cap Construction 22 08-Nov-12 05-Dec-12 20-Apr-13 16-May-13 134

BJ3190 Column Construction 26 06-Dec-12 07-Jan-13 17-May-13 18-Jun-13 134

Pier 2Pier 2 62 14-Nov-12 29-Jan-13 04-Apr-13 18-Jun-13 116

BJ3200 Pile Cap Construction 22 14-Nov-12 10-Dec-12 04-Apr-13 29-Apr-13 116

BJ3210 Column Construction 40 11-Dec-12 29-Jan-13 30-Apr-13 18-Jun-13 116

Pier 3Pier 3 62 20-Nov-12 02-Feb-13 04-Apr-13 18-Jun-13 112

BJ3220 Pile Cap Construction 22 20-Nov-12 14-Dec-12 04-Apr-13 29-Apr-13 112

BJ3230 Column Construction 40 15-Dec-12 02-Feb-13 30-Apr-13 18-Jun-13 112

Pier 4Pier 4 56 24-Nov-12 31-Jan-13 11-Apr-13 18-Jun-13 114

BJ3240 Pile Cap Construction 22 24-Nov-12 19-Dec-12 11-Apr-13 07-May-13 114

BJ3250 Column Construction 34 20-Dec-12 31-Jan-13 08-May-13 18-Jun-13 114

East AbutmentEast Abutment 52 01-Dec-12 02-Feb-13 16-Apr-13 18-Jun-13 112

BJ3140 Pile Cap Construction 18 01-Dec-12 21-Dec-12 16-Apr-13 07-May-13 112

BJ3150 Abutment Wall 16 22-Dec-12 11-Jan-13 08-May-13 27-May-13 112

BJ3160 Wing Wall & Curtail Wall 10 12-Jan-13 23-Jan-13 28-May-13 08-Jun-13 112

BJ3170 Approach Slab 8 25-Jan-13 02-Feb-13 10-Jun-13 18-Jun-13 112

Precast BeamsPrecast Beams 12 04-Feb-13 18-Feb-13 19-Jun-13 02-Jul-13 112

BJ3410 Launching of Post-tensioned Concrete Beams 12 04-Feb-13 18-Feb-13 19-Jun-13 02-Jul-13 112

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

05-Jun-13, Telecommunication System

Lay Duct

Relocation of OFC

ITS System

30-Aug-13, Bridge Widening (EB)

Bridge Widening Start (EB)

Bridge Widening Finish (EB)

30-Aug-13, Bridge Extension Over Jalan Damansara (BR B.1)

30-Aug-13, Section 1 - East Bound

06-Mar-13, East Abutment

Pile Cap Construction

Abutment Wall

Wing Wall & Curtail Wall

Approach Slab

07-May-13, Bridge Deck

Bridge Deck Construction

30-Aug-13, Miscellaneous

Bridge Parapet, Lining to Abutment and Service Ducts

Installation of Movement Joints in Bridge Deck and Approach Slab

20-Mar-13, Precast Beams

Launching of Pre-tensioned Concrete Beams

02-Jan-13, Piling

Temporary Sheet Piling

Bored Piling

09-Feb-13, West Abutment

Pile Cap Construction

Abutment Wall

Wing Wall & Curtail Wall

Approach Slab

07-Feb-13, Pier 1

Pile Cap Construction

Column Construction

15-Feb-13, Pier 2

Pile Cap Construction

Column Construction

01-Mar-13, Pier 3

Pile Cap Construction

Column Construction

18-Jan-13, Pier 4

Pile Cap Construction

Column Construction

18-Feb-13, Pier 5

Pile Cap Construction

Column Construction

29-Jul-13, Bridge Extension Over Segambut Dalam (BR B.2)

29-Jul-13, Section 1 - East Bound

30-Nov-12, Piling

Temporary Sheet Piling

Bored Piling

07-Jan-13, West Abutment

Pile Cap Construction

Abutment Wall

Wing Wall & Curtail Wall

Approach Slab

07-Jan-13, Pier 1

Pile Cap Construction

Column Construction

29-Jan-13, Pier 2

Pile Cap Construction

Column Construction

02-Feb-13, Pier 3

Pile Cap Construction

Column Construction

31-Jan-13, Pier 4

Pile Cap Construction

Column Construction

02-Feb-13, East Abutment

Pile Cap Construction

Abutment Wall

Wing Wall & Curtail Wall

Approach Slab

18-Feb-13, Precast Beams

Launching of Post-tensioned Concrete Beams

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 5 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1

Page 6: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

Bridge DeckBridge Deck 40 19-Feb-13 05-Apr-13 03-Jul-13 21-Aug-13 112

BJ3420 Bridge Deck Construction 40 19-Feb-13 05-Apr-13 03-Jul-13 21-Aug-13 112

MiscellaneousMiscellaneous 106 23-Mar-13 29-Jul-13 06-Aug-13 21-Jun-14 264

BJ3430 Bridge Parapet, Lining to Abutment and Service Ducts 26 23-Mar-13 22-Apr-13 06-Aug-13 07-Sep-13 112

BJ3440 Installation of Movement Joints in Bridge Deck and Approach Slab 12 15-Jul-13 29-Jul-13 09-Jun-14 21-Jun-14 264

Extension of Viaduct at Edinburgh Estate (BR B.3)Extension of Viaduct at Edinburgh Estate (BR B.3) 268 15-Sep-12 07-Aug-13 20-Oct-12 14-Jun-14 250

Section 1 - East BoundSection 1 - East Bound 268 15-Sep-12 07-Aug-13 20-Oct-12 14-Jun-14 250

PilingPiling 36 15-Sep-12 29-Oct-12 20-Oct-12 26-Feb-13 97

BJ4000 Temporary Sheet Piling 6 15-Sep-12 22-Sep-12 20-Oct-12 27-Oct-12 29

BJ4005 Bored Piling 30 24-Sep-12 29-Oct-12 21-Jan-13 26-Feb-13 97

West AbutmentWest Abutment 58 01-Oct-12 10-Dec-12 13-Apr-13 22-Jun-13 160

BJ4100 Pile Cap Construction 22 01-Oct-12 25-Oct-12 13-Apr-13 09-May-13 160

BJ4110 Abutment Wall 18 27-Oct-12 19-Nov-12 10-May-13 31-May-13 160

BJ4120 Wing Wall & Curtail Wall 12 14-Nov-12 28-Nov-12 28-May-13 11-Jun-13 160

BJ4130 Approach Slab 10 29-Nov-12 10-Dec-12 12-Jun-13 22-Jun-13 160

Pier 1Pier 1 40 03-Oct-12 21-Nov-12 06-May-13 22-Jun-13 176

BJ4200 Pile Cap Construction 22 03-Oct-12 29-Oct-12 06-May-13 31-May-13 176

BJ4210 Column Construction 18 30-Oct-12 21-Nov-12 03-Jun-13 22-Jun-13 176

Pier 2Pier 2 48 05-Oct-12 03-Dec-12 25-Apr-13 22-Jun-13 166

BJ4220 Pile Cap Construction 22 05-Oct-12 31-Oct-12 25-Apr-13 21-May-13 166

BJ4230 Column Construction 26 01-Nov-12 03-Dec-12 22-May-13 22-Jun-13 166

Pier 3Pier 3 58 08-Oct-12 17-Dec-12 13-Apr-13 22-Jun-13 154

BJ4240 Pile Cap Construction 22 08-Oct-12 02-Nov-12 13-Apr-13 09-May-13 154

BJ4250 Column Construction 36 03-Nov-12 17-Dec-12 10-May-13 22-Jun-13 154

Pier 4Pier 4 68 10-Oct-12 02-Jan-13 02-Apr-13 22-Jun-13 142

BJ4260 Pile Cap Construction 22 10-Oct-12 05-Nov-12 02-Apr-13 26-Apr-13 142

BJ4270 Column Construction 46 06-Nov-12 02-Jan-13 27-Apr-13 22-Jun-13 142

Pier 5Pier 5 68 12-Oct-12 04-Jan-13 02-Apr-13 22-Jun-13 140

BJ4280 Pile Cap Construction 22 12-Oct-12 07-Nov-12 02-Apr-13 26-Apr-13 140

BJ4290 Column Construction 46 08-Nov-12 04-Jan-13 27-Apr-13 22-Jun-13 140

Pier 6Pier 6 68 15-Oct-12 07-Jan-13 02-Apr-13 22-Jun-13 138

BJ4300 Pile Cap Construction 22 15-Oct-12 09-Nov-12 02-Apr-13 26-Apr-13 138

BJ4310 Column Construction 46 10-Nov-12 07-Jan-13 27-Apr-13 22-Jun-13 138

Pier 7Pier 7 72 17-Oct-12 14-Jan-13 28-Mar-13 22-Jun-13 132

BJ4320 Pile Cap Construction 22 17-Oct-12 12-Nov-12 28-Mar-13 22-Apr-13 132

BJ4330 Column Construction 50 14-Nov-12 14-Jan-13 23-Apr-13 22-Jun-13 132

Pier 8Pier 8 72 19-Oct-12 16-Jan-13 28-Mar-13 22-Jun-13 130

BJ4340 Pile Cap Construction 22 19-Oct-12 16-Nov-12 28-Mar-13 22-Apr-13 130

BJ4350 Column Construction 50 17-Nov-12 16-Jan-13 23-Apr-13 22-Jun-13 130

Pier 9Pier 9 58 22-Oct-12 02-Jan-13 13-Apr-13 22-Jun-13 142

BJ4360 Pile Cap Construction 22 22-Oct-12 19-Nov-12 13-Apr-13 09-May-13 142

BJ4370 Column Construction 36 20-Nov-12 02-Jan-13 10-May-13 22-Jun-13 142

Pier 10Pier 10 48 24-Oct-12 21-Dec-12 25-Apr-13 22-Jun-13 150

BJ4380 Pile Cap Construction 22 24-Oct-12 21-Nov-12 25-Apr-13 21-May-13 150

BJ4390 Column Construction 26 22-Nov-12 21-Dec-12 22-May-13 22-Jun-13 150

East AbutmentEast Abutment 58 30-Oct-12 09-Jan-13 13-Apr-13 22-Jun-13 136

BJ4150 Pile Cap Construction 22 30-Oct-12 26-Nov-12 13-Apr-13 09-May-13 136

BJ4160 Abutment Wall 18 27-Nov-12 17-Dec-12 10-May-13 31-May-13 136

BJ4170 Wing Wall & Curtail Wall 12 13-Dec-12 27-Dec-12 28-May-13 11-Jun-13 136

BJ4180 Approach Slab 10 28-Dec-12 09-Jan-13 12-Jun-13 22-Jun-13 136

Precast BeamsPrecast Beams 16 17-Jan-13 05-Feb-13 24-Jun-13 11-Jul-13 130

BJ4400 Launching of Post-tensioned Concrete Beams 16 17-Jan-13 05-Feb-13 24-Jun-13 11-Jul-13 130

Bridge DeckBridge Deck 46 06-Feb-13 01-Apr-13 12-Jul-13 07-Sep-13 130

BJ4410 Bridge Deck Construction 46 06-Feb-13 01-Apr-13 12-Jul-13 07-Sep-13 130

MiscellaneousMiscellaneous 118 19-Mar-13 07-Aug-13 24-Aug-13 14-Jun-14 250

BJ4420 Bridge Parapet, Lining to Abutment and Service Ducts 32 19-Mar-13 24-Apr-13 24-Aug-13 02-Oct-13 130

BJ4430 Installation of Movement Joints in Bridge Deck and Approach Slab 18 17-Jul-13 07-Aug-13 24-May-14 14-Jun-14 250

Slope Improvement Works (EB)Slope Improvement Works (EB) 173 01-Oct-12 27-Apr-13 08-Dec-12 05-Jul-14 351

BL0010 Slope Improvement Works Start (EB) 0 01-Oct-12 08-Dec-12 56

BL0020 Slope Improvement Works Finish (EB) 0 27-Apr-13 05-Jul-14 351

Overall Stage 1Overall Stage 1 173 01-Oct-12 27-Apr-13 08-Dec-12 04-Apr-14 275

Fill AreaFill Area 40 13-Mar-13 27-Apr-13 18-Feb-14 04-Apr-14 275

Slope Improvement - Retaining Wall (CH.4300-CH.4540)Slope Improvement - Retaining Wall (CH.4300-CH.4540) 40 13-Mar-13 27-Apr-13 18-Feb-14 04-Apr-14 275

BL2300 Excavation 26 13-Mar-13 11-Apr-13 18-Feb-14 19-Mar-14 275

BL2320 Construction of Wall Base 26 20-Mar-13 18-Apr-13 25-Feb-14 26-Mar-14 275

BL2330 Construction of Retaining Wall 26 25-Mar-13 23-Apr-13 01-Mar-14 31-Mar-14 275

BL2340 Backfill 26 29-Mar-13 27-Apr-13 06-Mar-14 04-Apr-14 275

Cut AreaCut Area 172 01-Oct-12 26-Apr-13 08-Dec-12 04-Jul-13 56

Slope Improvement - Horizontal DrainSlope Improvement - Horizontal Drain 172 01-Oct-12 26-Apr-13 08-Dec-12 04-Jul-13 56

BL1000 Installation of Horizontal Drain (CH.0-CH.1400) 43 01-Oct-12 22-Nov-12 08-Dec-12 30-Jan-13 56

BL1010 Installation of Horizontal Drain (CH.1400-CH.2800) 43 23-Nov-12 14-Jan-13 31-Jan-13 22-Mar-13 56

BL1020 Installation of Horizontal Drain (CH.2800-CH.4200) 43 15-Jan-13 07-Mar-13 23-Mar-13 13-May-13 56

BL1030 Installation of Horizontal Drain (CH.4200-CH.5600) 43 08-Mar-13 26-Apr-13 14-May-13 04-Jul-13 56

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

05-Apr-13, Bridge Deck

Bridge Deck Construction

29-Jul-13, Miscellaneous

Bridge Parapet, Lining to Abutment and Service Ducts

Installation of Movement Joints in Bridge Deck and Approach Slab

07-Aug-13, Extension of Viaduct at Edinburgh Estate (BR B.3)

07-Aug-13, Section 1 - East Bound

29-Oct-12, Piling

Temporary Sheet Piling

Bored Piling

10-Dec-12, West Abutment

Pile Cap Construction

Abutment Wall

Wing Wall & Curtail Wall

Approach Slab

21-Nov-12, Pier 1

Pile Cap Construction

Column Construction

03-Dec-12, Pier 2

Pile Cap Construction

Column Construction

17-Dec-12, Pier 3

Pile Cap Construction

Column Construction

02-Jan-13, Pier 4

Pile Cap Construction

Column Construction

04-Jan-13, Pier 5

Pile Cap Construction

Column Construction

07-Jan-13, Pier 6

Pile Cap Construction

Column Construction

14-Jan-13, Pier 7

Pile Cap Construction

Column Construction

16-Jan-13, Pier 8

Pile Cap Construction

Column Construction

02-Jan-13, Pier 9

Pile Cap Construction

Column Construction

21-Dec-12, Pier 10

Pile Cap Construction

Column Construction

09-Jan-13, East Abutment

Pile Cap Construction

Abutment Wall

Wing Wall & Curtail Wall

Approach Slab

05-Feb-13, Precast Beams

Launching of Post-tensioned Concrete Beams

01-Apr-13, Bridge Deck

Bridge Deck Construction

07-Aug-13, Miscellaneous

Bridge Parapet, Lining to Abutment and Service Ducts

Installation of Movement Joints in Bridge Deck and Approach Slab

27-Apr-13, Slope Improvement Works (EB)

Slope Improvement Works Start (EB)

Slope Improvement Works Finish (EB)

27-Apr-13, Overall Stage 1

27-Apr-13, Fill Area

27-Apr-13, Slope Improvement - Retaining Wall (CH.4300-CH.4540)

Excavation

Construction of Wall Base

Construction of Retaining Wall

Backfill

26-Apr-13, Cut Area

26-Apr-13, Slope Improvement - Horizontal Drain

Installation of Horizontal Drain (CH.0-CH.1400)

Installation of Horizontal Drain (CH.1400-CH.2800)

Installation of Horizontal Drain (CH.2800-CH.4200)

Installation of Horizontal Drain (CH.4200-CH.5600)

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 6 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1

Page 7: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

Ground Treatment Works (EB)Ground Treatment Works (EB) 168 07-Sep-12 30-Mar-13 13-Sep-12 05-Jul-14 375

BM0010 Ground Treatment Works Start (EB) 0 07-Sep-12 13-Sep-12 5

BM0020 Ground Treatment Works Finish (EB) 0 30-Mar-13 05-Jul-14 375

Stage 1Stage 1 168 07-Sep-12 30-Mar-13 13-Sep-12 20-May-13 42

Ground Treatment (CH.4200-CH.5600)Ground Treatment (CH.4200-CH.5600) 42 09-Feb-13 30-Mar-13 01-Apr-13 20-May-13 42

BM1300 Excavation of Unsuitable Material 30 09-Feb-13 16-Mar-13 01-Apr-13 06-May-13 42

BM1310 Laying of Geotextile Separator 30 15-Feb-13 21-Mar-13 05-Apr-13 10-May-13 42

BM1320 Laying of Outlet Drain 30 20-Feb-13 26-Mar-13 10-Apr-13 15-May-13 42

BM1330 Backfilling with Compacted Soil / hardcore Material 30 25-Feb-13 30-Mar-13 15-Apr-13 20-May-13 42

Ground Treatment (CH.1400-CH.2800)Ground Treatment (CH.1400-CH.2800) 42 29-Oct-12 18-Dec-12 19-Dec-12 08-Feb-13 42

BM1100 Excavation of Unsuitable Material 30 29-Oct-12 04-Dec-12 19-Dec-12 25-Jan-13 42

BM1110 Laying of Geotextile Separator 30 02-Nov-12 08-Dec-12 24-Dec-12 30-Jan-13 42

BM1120 Laying of Outlet Drain 30 07-Nov-12 13-Dec-12 29-Dec-12 04-Feb-13 42

BM1130 Backfilling with Compacted Soil / hardcore Material 30 12-Nov-12 18-Dec-12 04-Jan-13 08-Feb-13 42

Ground Treatment (CH.2800-CH.4200)Ground Treatment (CH.2800-CH.4200) 42 19-Dec-12 08-Feb-13 09-Feb-13 30-Mar-13 42

BM1200 Excavation of Unsuitable Material 30 19-Dec-12 25-Jan-13 09-Feb-13 16-Mar-13 42

BM1210 Laying of Geotextile Separator 30 24-Dec-12 30-Jan-13 15-Feb-13 21-Mar-13 42

BM1220 Laying of Outlet Drain 30 29-Dec-12 04-Feb-13 20-Feb-13 26-Mar-13 42

BM1230 Backfilling with Compacted Soil / hardcore Material 30 04-Jan-13 08-Feb-13 25-Feb-13 30-Mar-13 42

Ground Treatment (CH.0-CH.1400)Ground Treatment (CH.0-CH.1400) 42 07-Sep-12 27-Oct-12 13-Sep-12 02-Nov-12 5

BM1000 Excavation of Unsuitable Material 30 07-Sep-12 12-Oct-12 13-Sep-12 18-Oct-12 5

BM1010 Laying of Geotextile Separator 30 12-Sep-12 17-Oct-12 19-Sep-12 23-Oct-12 5

BM1020 Laying of Outlet Drain 30 18-Sep-12 22-Oct-12 24-Sep-12 29-Oct-12 5

BM1030 Backfilling with Compacted Soil / hardcore Material 30 22-Sep-12 27-Oct-12 28-Sep-12 02-Nov-12 5

Electrical Works for Street Lighting (EB)Electrical Works for Street Lighting (EB) 219 05-Jan-13 28-Sep-13 09-Oct-13 05-Jul-14 227

BN0010 Electrical Works for Street Lighting Start (EB) 0 05-Jan-13 09-Oct-13 227

BN0020 Electrical Works for Street Lighting Finish (EB) 0 28-Sep-13 05-Jul-14 227

Overall Stage 1Overall Stage 1 219 05-Jan-13 28-Sep-13 09-Oct-13 05-Jul-14 227

BN0100 Testing and Commissioning 60 16-Jul-13 28-Sep-13 24-Apr-14 05-Jul-14 227

CH.1400-CH.2800CH.1400-CH.2800 37 20-Feb-13 03-Apr-13 25-Nov-13 09-Jan-14 227

BN1100 High Mast 37 20-Feb-13 03-Apr-13 25-Nov-13 09-Jan-14 227

BN1110 Street Lighting 37 20-Feb-13 03-Apr-13 25-Nov-13 09-Jan-14 227

CH.0-CH.1400CH.0-CH.1400 37 05-Jan-13 19-Feb-13 09-Oct-13 23-Nov-13 227

BN1000 High Mast 37 05-Jan-13 19-Feb-13 09-Oct-13 23-Nov-13 227

BN1010 Street Lighting 37 05-Jan-13 19-Feb-13 09-Oct-13 23-Nov-13 227

CH.2800-CH.4200CH.2800-CH.4200 37 04-Apr-13 17-May-13 10-Jan-14 26-Feb-14 227

BN1200 High Mast 37 04-Apr-13 17-May-13 10-Jan-14 26-Feb-14 227

BN1210 Street Lighting 37 04-Apr-13 17-May-13 10-Jan-14 26-Feb-14 227

CH.4200-CH.5600CH.4200-CH.5600 37 18-May-13 02-Jul-13 27-Feb-14 10-Apr-14 227

BN1300 High Mast 37 18-May-13 02-Jul-13 27-Feb-14 10-Apr-14 227

BN1310 Street Lighting 37 18-May-13 02-Jul-13 27-Feb-14 10-Apr-14 227

Phase 2 (West Bound)Phase 2 (West Bound) 370 01-Apr-13 01-Jul-14 01-Apr-13 05-Jul-14 5

Site Clearance and Fencing (WB)Site Clearance and Fencing (WB) 370 01-Apr-13 01-Jul-14 01-Apr-13 05-Jul-14 5

BC3000 Site Clearance and Fencing Start (WB) 0 01-Apr-13 05-Jul-14 375

BC3010 Site Clearance and Fencing Finish (WB) 0 01-Jul-14 05-Jul-14 5

Site Clearing and Fencing (CH.4200-CH.2800)Site Clearing and Fencing (CH.4200-CH.2800) 242 04-Jun-13 29-Mar-14 21-Jun-13 04-Apr-14 5

BC2100 Site Clearing & Demolition Works 52 04-Jun-13 03-Aug-13 21-Jun-13 23-Aug-13 15

BC2110 Demolition Works 38 20-Jun-13 03-Aug-13 13-Aug-13 27-Sep-13 43

BC2120 Relocation & Installation of Temporary Signage & Gantry 38 20-Jun-13 03-Aug-13 20-Feb-14 04-Apr-14 195

BC2130 Fencing and Gate 38 13-Feb-14 29-Mar-14 20-Feb-14 04-Apr-14 5

BC2140 Miscellaneous Dismantling, Demolition and Excavation 38 20-Jun-13 03-Aug-13 20-Feb-14 04-Apr-14 195

Site Clearing and Fencing (CH.5600-CH.4200)Site Clearing and Fencing (CH.5600-CH.4200) 256 01-Apr-13 12-Feb-14 01-Apr-13 19-Feb-14 5

BC2000 Site Clearing & Demolition Works 52 01-Apr-13 03-Jun-13 01-Apr-13 03-Jun-13 0

BC2010 Demolition Works 38 17-Apr-13 03-Jun-13 26-Jun-13 12-Aug-13 57

BC2020 Relocation & Installation of Temporary Signage & Gantry 38 17-Apr-13 03-Jun-13 02-Jan-14 19-Feb-14 209

BC2030 Fencing and Gate 38 26-Dec-13 12-Feb-14 02-Jan-14 19-Feb-14 5

BC2040 Miscellaneous Dismantling, Demolition and Excavation 38 17-Apr-13 03-Jun-13 02-Jan-14 19-Feb-14 209

Site Clearing and Fencing (CH.2800-CH.1400)Site Clearing and Fencing (CH.2800-CH.1400) 228 05-Aug-13 15-May-14 24-Aug-13 21-May-14 5

BC2200 Site Clearing & Demolition Works 52 05-Aug-13 08-Oct-13 24-Aug-13 26-Oct-13 15

BC2210 Demolition Works 38 23-Aug-13 08-Oct-13 28-Sep-13 14-Nov-13 29

BC2220 Relocation & Installation of Temporary Signage & Gantry 38 23-Aug-13 08-Oct-13 05-Apr-14 21-May-14 181

BC2230 Fencing and Gate 38 31-Mar-14 15-May-14 05-Apr-14 21-May-14 5

BC2240 Miscellaneous Dismantling, Demolition and Excavation 38 23-Aug-13 08-Oct-13 05-Apr-14 21-May-14 181

Site Clearing and Fencing (CH.1400-CH.0)Site Clearing and Fencing (CH.1400-CH.0) 214 09-Oct-13 30-Jun-14 28-Oct-13 05-Jul-14 5

BC2300 Site Clearing & Demolition Works 52 09-Oct-13 12-Dec-13 28-Oct-13 31-Dec-13 15

BC2310 Demolition Works 38 26-Oct-13 12-Dec-13 15-Nov-13 31-Dec-13 15

BC2320 Relocation & Installation of Temporary Signage & Gantry 38 26-Oct-13 12-Dec-13 15-Nov-13 31-Dec-13 15

BC2330 Fencing and Gate 38 16-May-14 30-Jun-14 22-May-14 05-Jul-14 5

BC2340 Miscellaneous Dismantling, Demolition and Excavation 38 26-Oct-13 12-Dec-13 22-May-14 05-Jul-14 167

Earthworks (WB)Earthworks (WB) 341 02-May-13 26-Jun-14 02-May-13 05-Jul-14 8

BD6500 Earthwork Start (WB) 0 02-May-13 05-Jul-14 349

BD6510 Earthwork Finish (WB) 0 26-Jun-14 05-Jul-14 8

Stage 2Stage 2 133 16-Jan-14 26-Jun-14 16-Jan-14 05-Jul-14 8

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

30-Mar-13, Ground Treatment Works (EB)

Ground Treatment Works Start (EB)

Ground Treatment Works Finish (EB)

30-Mar-13, Stage 1

30-Mar-13, Ground Treatment (CH.4200-CH.5600)

Excavation of Unsuitable Material

Laying of Geotextile Separator

Laying of Outlet Drain

Backfilling with Compacted Soil / hardcore Material

18-Dec-12, Ground Treatment (CH.1400-CH.2800)

Excavation of Unsuitable Material

Laying of Geotextile Separator

Laying of Outlet Drain

Backfilling with Compacted Soil / hardcore Material

08-Feb-13, Ground Treatment (CH.2800-CH.4200)

Excavation of Unsuitable Material

Laying of Geotextile Separator

Laying of Outlet Drain

Backfilling with Compacted Soil / hardcore Material

27-Oct-12, Ground Treatment (CH.0-CH.1400)

Excavation of Unsuitable Material

Laying of Geotextile Separator

Laying of Outlet Drain

Backfilling with Compacted Soil / hardcore Material

28-Sep-13, Electrical Works for Street Lighting (EB)

Electrical Works for Street Lighting Start (EB)

Electrical Works for Street Lighting Finish (EB)

28-Sep-13, Overall Stage 1

Testing and Commissioning

03-Apr-13, CH.1400-CH.2800

High Mast

Street Lighting

19-Feb-13, CH.0-CH.1400

High Mast

Street Lighting

17-May-13, CH.2800-CH.4200

High Mast

Street Lighting

02-Jul-13, CH.4200-CH.5600

High Mast

Street Lighting

01-Jul-14, Phase 2 (West Bound)

01-Jul-14, Site Clearance and Fencing (WB)

Site Clearance and Fencing Start (WB)

Site Clearance and Fencing Finish (WB)

29-Mar-14, Site Clearing and Fencing (CH.4200-CH.2800)

Site Clearing & Demolition Works

Demolition Works

Relocation & Installation of Temporary Signage & Gantry

Fencing and Gate

Miscellaneous Dismantling, Demolition and Excavation

12-Feb-14, Site Clearing and Fencing (CH.5600-CH.4200)

Site Clearing & Demolition Works

Demolition Works

Relocation & Installation of Temporary Signage & Gantry

Fencing and Gate

Miscellaneous Dismantling, Demolition and Excavation

15-May-14, Site Clearing and Fencing (CH.2800-CH.1400)

Site Clearing & Demolition Works

Demolition Works

Relocation & Installation of Temporary Signage & Gantry

Fencing and Gate

Miscellaneous Dismantling, Demolition and Excavation

30-Jun-14, Site Clearing and Fencing (CH.1400-CH.0)

Site Clearing & Demolition Works

Demolition Works

Relocation & Installation of Temporary Signage & Gantry

Fencing and Gate

Miscellaneous Dismantling, Demolition and Excavation

26-Jun-14, Earthworks (WB)

Earthwork Start (WB)

Earthwork Finish (WB)

26-Jun-14, Stage 2

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 7 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1

Page 8: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

CH.4200-CH.2800CH.4200-CH.2800 42 26-Feb-14 15-Apr-14 05-Mar-14 24-Apr-14 8

BD7100 Removal of Existing Pavement 32 26-Feb-14 03-Apr-14 05-Mar-14 10-Apr-14 6

BD7110 Turf ing (Remaining Works) 32 10-Mar-14 15-Apr-14 19-Mar-14 24-Apr-14 8

BD7120 Treatment of Existing Subsoil Drain 32 04-Mar-14 09-Apr-14 19-Mar-14 24-Apr-14 13

CH.2800-CH.1400CH.2800-CH.1400 42 04-Apr-14 24-May-14 11-Apr-14 04-Jun-14 8

BD7200 Removal of Existing Pavement 32 04-Apr-14 12-May-14 11-Apr-14 20-May-14 6

BD7210 Turf ing (Remaining Works) 32 16-Apr-14 24-May-14 25-Apr-14 04-Jun-14 8

BD7220 Treatment of Existing Subsoil Drain 32 10-Apr-14 19-May-14 25-Apr-14 04-Jun-14 13

CH.5600-CH.4200CH.5600-CH.4200 42 16-Jan-14 08-Mar-14 16-Jan-14 18-Mar-14 8

BD7000 Removal of Existing Pavement 32 16-Jan-14 25-Feb-14 16-Jan-14 25-Feb-14 0

BD7010 Turf ing (Remaining Works) 32 28-Jan-14 08-Mar-14 08-Feb-14 18-Mar-14 8

BD7020 Treatment of Existing Subsoil Drain 32 22-Jan-14 03-Mar-14 03-Feb-14 12-Mar-14 8

CH.1400-CH.0CH.1400-CH.0 37 14-May-14 26-Jun-14 21-May-14 05-Jul-14 8

BD7300 Removal of Existing Pavement 27 14-May-14 14-Jun-14 21-May-14 21-Jun-14 6

BD7310 Turf ing (Remaining Works) 27 26-May-14 26-Jun-14 05-Jun-14 05-Jul-14 8

BD7320 Treatment of Existing Subsoil Drain 27 20-May-14 20-Jun-14 05-Jun-14 05-Jul-14 13

Stage 1Stage 1 233 02-May-13 17-Feb-14 02-May-13 05-Jul-14 116

CH.5600-CH.4200CH.5600-CH.4200 77 02-May-13 02-Aug-13 02-May-13 26-Dec-13 116

BD6000 Excavate to Toe of Slope (CH.5600-CH.4200) 52 02-May-13 03-Jul-13 02-May-13 03-Jul-13 0

BD6010 Fill to Formation Level (CH.5600-CH.4200) 52 22-May-13 23-Jul-13 29-May-13 30-Jul-13 5

BD6020 Turf ing 52 03-Jun-13 02-Aug-13 18-Jun-13 20-Aug-13 13

BD6030 Instrumentation and Monitoring 58 22-May-13 31-Jul-13 16-Oct-13 26-Dec-13 118

BD6040 Soil Investigation 52 02-May-13 03-Jul-13 23-Oct-13 26-Dec-13 141

CH.2800-CH.1400CH.2800-CH.1400 77 07-Sep-13 10-Dec-13 07-Sep-13 03-May-14 116

BD6200 Excavate to Toe of Slope (CH.2800-CH.1400) 52 07-Sep-13 11-Nov-13 07-Sep-13 11-Nov-13 0

BD6210 Fill to Formation Level (CH.2800-CH.1400) 52 28-Sep-13 30-Nov-13 14-Oct-13 17-Dec-13 13

BD6220 Turf ing 52 08-Oct-13 10-Dec-13 24-Oct-13 27-Dec-13 13

BD6230 Instrumentation and Monitoring 58 28-Sep-13 07-Dec-13 25-Feb-14 03-May-14 118

BD6240 Soil Investigation 52 07-Sep-13 11-Nov-13 04-Mar-14 03-May-14 141

CH.4200-CH.2800CH.4200-CH.2800 77 04-Jul-13 07-Oct-13 04-Jul-13 03-Mar-14 116

BD6100 Excavate to Toe of Slope (CH.4200-CH.2800) 52 04-Jul-13 06-Sep-13 04-Jul-13 06-Sep-13 0

BD6110 Fill to Formation Level (CH.4200-CH.2800) 52 24-Jul-13 27-Sep-13 12-Aug-13 12-Oct-13 13

BD6120 Turf ing 52 03-Aug-13 07-Oct-13 21-Aug-13 23-Oct-13 13

BD6130 Instrumentation and Monitoring 58 24-Jul-13 04-Oct-13 19-Dec-13 03-Mar-14 118

BD6140 Soil Investigation 52 04-Jul-13 06-Sep-13 27-Dec-13 03-Mar-14 141

CH.1400-CH.0CH.1400-CH.0 77 12-Nov-13 17-Feb-14 12-Nov-13 05-Jul-14 116

BD6300 Excavate to Toe of Slope (CH.1400-CH.0) 52 12-Nov-13 15-Jan-14 12-Nov-13 15-Jan-14 0

BD6310 Fill to Formation Level (CH.1400-CH.0) 52 02-Dec-13 06-Feb-14 18-Dec-13 22-Feb-14 13

BD6320 Turf ing 52 12-Dec-13 17-Feb-14 28-Dec-13 04-Mar-14 13

BD6330 Instrumentation and Monitoring 58 02-Dec-13 13-Feb-14 26-Apr-14 05-Jul-14 118

BD6340 Soil Investigation 52 12-Nov-13 15-Jan-14 05-May-14 05-Jul-14 141

Drainage Works (WB)Drainage Works (WB) 318 04-Jun-13 30-Jun-14 10-Jun-13 05-Jul-14 5

BE4040 Drainage Works Start (WB) 0 04-Jun-13 05-Jul-14 323

BE4050 Drainage Works Finish (WB) 0 30-Jun-14 05-Jul-14 5

Stage 1Stage 1 188 04-Jun-13 22-Jan-14 10-Jun-13 28-Jan-14 5

Drainage (CH.5600-CH.4200)Drainage (CH.5600-CH.4200) 47 04-Jun-13 29-Jul-13 10-Jun-13 03-Aug-13 5

BE2000 Excavation 33 04-Jun-13 11-Jul-13 10-Jun-13 17-Jul-13 5

BE2010 Laying of Drain 33 12-Jun-13 19-Jul-13 18-Jun-13 26-Jul-13 5

BE2020 Backfilling 33 20-Jun-13 29-Jul-13 26-Jun-13 03-Aug-13 5

Drainage (CH.4200-CH.2800)Drainage (CH.4200-CH.2800) 47 30-Jul-13 26-Sep-13 05-Aug-13 02-Oct-13 5

BE2100 Excavation 33 30-Jul-13 09-Sep-13 05-Aug-13 14-Sep-13 5

BE2110 Laying of Drain 33 07-Aug-13 18-Sep-13 15-Aug-13 24-Sep-13 5

BE2120 Backfilling 33 17-Aug-13 26-Sep-13 23-Aug-13 02-Oct-13 5

Drainage (CH.2800-CH.1400)Drainage (CH.2800-CH.1400) 47 27-Sep-13 23-Nov-13 03-Oct-13 29-Nov-13 5

BE2200 Excavation 33 27-Sep-13 07-Nov-13 03-Oct-13 13-Nov-13 5

BE2210 Laying of Drain 33 05-Oct-13 15-Nov-13 11-Oct-13 21-Nov-13 5

BE2220 Backfilling 33 14-Oct-13 23-Nov-13 21-Oct-13 29-Nov-13 5

Drainage (CH.1400-CH.0)Drainage (CH.1400-CH.0) 47 25-Nov-13 22-Jan-14 30-Nov-13 28-Jan-14 5

BE2300 Excavation 33 25-Nov-13 04-Jan-14 30-Nov-13 10-Jan-14 5

BE2310 Laying of Drain 33 03-Dec-13 13-Jan-14 09-Dec-13 20-Jan-14 5

BE2320 Backfilling 33 12-Dec-13 22-Jan-14 18-Dec-13 28-Jan-14 5

Stage 2Stage 2 130 23-Jan-14 30-Jun-14 29-Jan-14 05-Jul-14 5

Drains (Remaining Works) and KerbsDrains (Remaining Works) and Kerbs 130 23-Jan-14 30-Jun-14 29-Jan-14 05-Jul-14 5

BE4000 CH.5600-CH.4200 32 23-Jan-14 04-Mar-14 29-Jan-14 10-Mar-14 5

BE4010 CH.4200-CH.2800 32 05-Mar-14 10-Apr-14 11-Mar-14 16-Apr-14 5

BE4020 CH.2800-CH.1400 33 11-Apr-14 21-May-14 17-Apr-14 27-May-14 5

BE4030 CH.1400-CH.0 33 22-May-14 30-Jun-14 28-May-14 05-Jul-14 5

Sub-Base, Roadbase and Pavement (WB)Sub-Base, Roadbase and Pavement (WB) 143 06-Jan-14 28-Jun-14 27-Jan-14 05-Jul-14 6

BF3020 Sub-Base, Roadbase and Pavement Start (WB) 0 06-Jan-14 05-Jul-14 149

BF3030 Sub-Base, Roadbase and Pavement Finish (WB) 0 28-Jun-14 05-Jul-14 6

Stage 2Stage 2 143 06-Jan-14 28-Jun-14 27-Jan-14 05-Jul-14 6

BF3010 Sub-surface Drainage Improvement (West Bound) 130 06-Jan-14 13-Jun-14 29-Jan-14 05-Jul-14 19

Sub-Base upto Pavement (CH.5600-CH.4200)Sub-Base upto Pavement (CH.5600-CH.4200) 38 27-Jan-14 14-Mar-14 27-Jan-14 18-Apr-14 30

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

15-Apr-14, CH.4200-CH.2800

Removal of Existing Pavement

Turf ing (Remaining Works)

Treatment of Existing Subsoil Drain

24-May-14, CH.2800-CH.1400

Removal of Existing Pavement

Turf ing (Remaining Works)

Treatment of Existing Subsoil Drain

08-Mar-14, CH.5600-CH.4200

Removal of Existing Pavement

Turfing (Remaining Works)

Treatment of Existing Subsoil Drain

26-Jun-14, CH.1400-CH.0

Removal of Existing Pavement

Turf ing (Remaining Works)

Treatment of Existing Subsoil Drain

17-Feb-14, Stage 1

02-Aug-13, CH.5600-CH.4200

Excavate to Toe of Slope (CH.5600-CH.4200)

Fill to Formation Level (CH.5600-CH.4200)

Turf ing

Instrumentation and Monitoring

Soil Investigation

10-Dec-13, CH.2800-CH.1400

Excavate to Toe of Slope (CH.2800-CH.1400)

Fill to Formation Level (CH.2800-CH.1400)

Turfing

Instrumentation and Monitoring

Soil Investigation

07-Oct-13, CH.4200-CH.2800

Excavate to Toe of Slope (CH.4200-CH.2800)

Fill to Formation Level (CH.4200-CH.2800)

Turfing

Instrumentation and Monitoring

Soil Investigation

17-Feb-14, CH.1400-CH.0

Excavate to Toe of Slope (CH.1400-CH.0)

Fill to Formation Level (CH.1400-CH.0)

Turf ing

Instrumentation and Monitoring

Soil Investigation

30-Jun-14, Drainage Works (WB)

Drainage Works Start (WB)

Drainage Works Finish (WB)

22-Jan-14, Stage 1

29-Jul-13, Drainage (CH.5600-CH.4200)

Excavation

Laying of Drain

Backfilling

26-Sep-13, Drainage (CH.4200-CH.2800)

Excavation

Laying of Drain

Backfilling

23-Nov-13, Drainage (CH.2800-CH.1400)

Excavation

Laying of Drain

Backfilling

22-Jan-14, Drainage (CH.1400-CH.0)

Excavation

Laying of Drain

Backfilling

30-Jun-14, Stage 2

30-Jun-14, Drains (Remaining Works) and Kerbs

CH.5600-CH.4200

CH.4200-CH.2800

CH.2800-CH.1400

CH.1400-CH.0

28-Jun-14, Sub-Base, Roadbase and Pavement (WB)

Sub-Base, Roadbase and Pavement Start (WB)

Sub-Base, Roadbase and Pavement Finish (WB)

28-Jun-14, Stage 2

Sub-surface Drainage Improvement (West Bound)

14-Mar-14, Sub-Base upto Pavement (CH.5600-CH.4200)

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 8 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1

Page 9: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

BF2010 Sub-Grade and Prepare Formation 24 27-Jan-14 26-Feb-14 27-Jan-14 26-Feb-14 0

BF2020 Laying of Lower Sub-Base 24 29-Jan-14 28-Feb-14 29-Jan-14 28-Feb-14 0

BF2030 Laying of Lower Upper-Base 24 03-Feb-14 03-Mar-14 03-Feb-14 03-Mar-14 0

BF2040 Laying of CBM 22 05-Feb-14 03-Mar-14 05-Feb-14 03-Mar-14 0

BF2050 Laying of WMM 22 07-Feb-14 05-Mar-14 07-Feb-14 05-Mar-14 0

BF2060 Laying of DBM 22 10-Feb-14 07-Mar-14 10-Feb-14 07-Mar-14 0

BF2070 Laying of ACBC 22 12-Feb-14 10-Mar-14 12-Feb-14 10-Mar-14 0

BF2075 Regulating 22 13-Feb-14 11-Mar-14 13-Feb-14 11-Mar-14 0

BF2080 Laying of ACWC 22 14-Feb-14 12-Mar-14 14-Feb-14 12-Mar-14 0

BF2090 Laying of SMA 22 18-Feb-14 14-Mar-14 18-Feb-14 14-Mar-14 0

BF2100 Dismantle Guardrail, NJB Installation & Misc. Works 32 05-Feb-14 14-Mar-14 13-Mar-14 18-Apr-14 30

BF2110 Temporay Road Marking & Traffic Diversion/Contra Flow 32 05-Feb-14 14-Mar-14 13-Mar-14 18-Apr-14 30

Sub-Base upto Pavement (CH.4200-CH.2800)Sub-Base upto Pavement (CH.4200-CH.2800) 38 08-Mar-14 21-Apr-14 02-Apr-14 05-Jul-14 62

BF2210 Sub-Grade and Prepare Formation 24 08-Mar-14 04-Apr-14 02-Apr-14 29-Apr-14 21

BF2220 Laying of Lower Sub-Base 24 11-Mar-14 07-Apr-14 04-Apr-14 02-May-14 21

BF2230 Laying of Lower Upper-Base 24 13-Mar-14 09-Apr-14 07-Apr-14 05-May-14 21

BF2240 Laying of CBM 22 15-Mar-14 09-Apr-14 09-Apr-14 05-May-14 21

BF2250 Laying of WMM 22 18-Mar-14 11-Apr-14 11-Apr-14 07-May-14 21

BF2260 Laying of DBM 22 20-Mar-14 14-Apr-14 14-Apr-14 09-May-14 21

BF2270 Laying of ACBC 22 22-Mar-14 16-Apr-14 16-Apr-14 12-May-14 21

BF2275 Regulating 22 24-Mar-14 17-Apr-14 17-Apr-14 14-May-14 21

BF2280 Laying of ACWC 22 25-Mar-14 18-Apr-14 09-Jun-14 03-Jul-14 62

BF2290 Laying of SMA 22 27-Mar-14 21-Apr-14 11-Jun-14 05-Jul-14 62

BF2300 Dismantle Guardrail, NJB Installation & Misc. Works 32 15-Mar-14 21-Apr-14 19-Apr-14 28-May-14 30

BF2310 Temporay Road Marking & Traffic Diversion/Contra Flow 32 15-Mar-14 21-Apr-14 19-Apr-14 28-May-14 30

Sub-Base upto Pavement (CH.2800-CH.1400)Sub-Base upto Pavement (CH.2800-CH.1400) 38 15-Apr-14 30-May-14 28-Apr-14 05-Jul-14 30

BF2410 Sub-Grade and Prepare Formation 24 15-Apr-14 14-May-14 28-Apr-14 27-May-14 11

BF2420 Laying of Lower Sub-Base 24 17-Apr-14 16-May-14 30-Apr-14 29-May-14 11

BF2430 Laying of Lower Upper-Base 24 19-Apr-14 19-May-14 03-May-14 31-May-14 11

BF2440 Laying of CBM 22 22-Apr-14 19-May-14 06-May-14 31-May-14 11

BF2450 Laying of WMM 22 24-Apr-14 21-May-14 08-May-14 04-Jun-14 11

BF2460 Laying of DBM 22 26-Apr-14 23-May-14 10-May-14 06-Jun-14 11

BF2470 Laying of ACBC 22 29-Apr-14 26-May-14 14-May-14 09-Jun-14 11

BF2475 Regulating 22 30-Apr-14 27-May-14 15-May-14 10-Jun-14 11

BF2480 Laying of ACWC 22 02-May-14 28-May-14 09-Jun-14 03-Jul-14 30

BF2490 Laying of SMA 22 05-May-14 30-May-14 11-Jun-14 05-Jul-14 30

BF2500 Dismantle Guardrail, NJB Installation & Misc. Works 32 22-Apr-14 30-May-14 29-May-14 05-Jul-14 30

BF2510 Temporay Road Marking & Traffic Diversion/Contra Flow 32 22-Apr-14 30-May-14 29-May-14 05-Jul-14 30

Sub-Base upto Pavement (CH.1400-CH.0)Sub-Base upto Pavement (CH.1400-CH.0) 35 19-May-14 28-Jun-14 26-May-14 05-Jul-14 6

BF2610 Sub-Grade and Prepare Formation 24 19-May-14 16-Jun-14 26-May-14 23-Jun-14 6

BF2620 Laying of Lower Sub-Base 24 20-May-14 17-Jun-14 27-May-14 24-Jun-14 6

BF2630 Laying of Lower Upper-Base 24 21-May-14 18-Jun-14 28-May-14 25-Jun-14 6

BF2640 Laying of CBM 22 24-May-14 19-Jun-14 31-May-14 26-Jun-14 6

BF2650 Laying of WMM 22 26-May-14 20-Jun-14 03-Jun-14 27-Jun-14 6

BF2660 Laying of DBM 22 27-May-14 21-Jun-14 04-Jun-14 28-Jun-14 6

BF2670 Laying of ACBC 22 29-May-14 24-Jun-14 06-Jun-14 01-Jul-14 6

BF2675 Regulating 22 30-May-14 25-Jun-14 11-Jun-14 05-Jul-14 9

BF2680 Laying of ACWC 22 31-May-14 26-Jun-14 09-Jun-14 03-Jul-14 6

BF2690 Laying of SMA 22 04-Jun-14 28-Jun-14 11-Jun-14 05-Jul-14 6

BF2700 Dismantle Guardrail, NJB Installation & Misc. Works 30 24-May-14 28-Jun-14 31-May-14 05-Jul-14 6

BF2710 Temporay Road Marking & Traffic Diversion/Contra Flow 30 24-May-14 28-Jun-14 31-May-14 05-Jul-14 6

Road Furniture (WB)Road Furniture (WB) 75 01-Apr-14 30-Jun-14 01-Apr-14 05-Jul-14 5

BG3000 Road Furniture Start (WB) 0 01-Apr-14 05-Jul-14 80

BG3010 Road Furniture Finish (WB) 0 30-Jun-14 05-Jul-14 5

Stage 2Stage 2 75 01-Apr-14 30-Jun-14 01-Apr-14 05-Jul-14 5

CH.5600-CH.4200CH.5600-CH.4200 19 01-Apr-14 22-Apr-14 01-Apr-14 28-Apr-14 5

BG2000 Traffic Signs 19 01-Apr-14 22-Apr-14 01-Apr-14 22-Apr-14 0

BG2010 Road Markings 19 01-Apr-14 22-Apr-14 07-Apr-14 28-Apr-14 5

BG2020 Ancillary Finishings 19 01-Apr-14 22-Apr-14 07-Apr-14 28-Apr-14 5

CH.4200-CH.2800CH.4200-CH.2800 19 23-Apr-14 16-May-14 23-Apr-14 22-May-14 5

BG2100 Traffic Signs 19 23-Apr-14 16-May-14 23-Apr-14 16-May-14 0

BG2110 Road Markings 19 23-Apr-14 16-May-14 29-Apr-14 22-May-14 5

BG2120 Ancillary Finishings 19 23-Apr-14 16-May-14 29-Apr-14 22-May-14 5

CH.2800-CH.1400CH.2800-CH.1400 19 17-May-14 09-Jun-14 17-May-14 14-Jun-14 5

BG2200 Traffic Signs 19 17-May-14 09-Jun-14 17-May-14 09-Jun-14 0

BG2210 Road Markings 19 17-May-14 09-Jun-14 23-May-14 14-Jun-14 5

BG2220 Ancillary Finishings 19 17-May-14 09-Jun-14 23-May-14 14-Jun-14 5

CH.1400-CH.0CH.1400-CH.0 18 10-Jun-14 30-Jun-14 10-Jun-14 05-Jul-14 5

BG2300 Traffic Signs 18 10-Jun-14 30-Jun-14 10-Jun-14 30-Jun-14 0

BG2310 Road Markings 18 10-Jun-14 30-Jun-14 16-Jun-14 05-Jul-14 5

BG2320 Ancillary Finishings 18 10-Jun-14 30-Jun-14 16-Jun-14 05-Jul-14 5

Utilities and Services (WB)Utilities and Services (WB) 221 01-Oct-13 30-Jun-14 07-Oct-13 05-Jul-14 5

BH0120 Utilities and Services Start (WB) 0 01-Oct-13 05-Jul-14 226

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

Sub-Grade and Prepare Formation

Laying of Lower Sub-Base

Laying of Lower Upper-Base

Laying of CBM

Laying of WMM

Laying of DBM

Laying of ACBC

Regulating

Laying of ACWC

Laying of SMA

Dismantle Guardrail, NJB Installation & Misc. Works

Temporay Road Marking & Traffic Diversion/Contra Flow

21-Apr-14, Sub-Base upto Pavement (CH.4200-CH.2800)

Sub-Grade and Prepare Formation

Laying of Lower Sub-Base

Laying of Lower Upper-Base

Laying of CBM

Laying of WMM

Laying of DBM

Laying of ACBC

Regulating

Laying of ACWC

Laying of SMA

Dismantle Guardrail, NJB Installation & Misc. Works

Temporay Road Marking & Traffic Diversion/Contra Flow

30-May-14, Sub-Base upto Pavement (CH.2800-CH.1400)

Sub-Grade and Prepare Formation

Laying of Lower Sub-Base

Laying of Lower Upper-Base

Laying of CBM

Laying of WMM

Laying of DBM

Laying of ACBC

Regulating

Laying of ACWC

Laying of SMA

Dismantle Guardrail, NJB Installation & Misc. Works

Temporay Road Marking & Traffic Diversion/Contra Flow

28-Jun-14, Sub-Base upto Pavement (CH.1400-CH.0)

Sub-Grade and Prepare Formation

Laying of Lower Sub-Base

Laying of Lower Upper-Base

Laying of CBM

Laying of WMM

Laying of DBM

Laying of ACBC

Regulating

Laying of ACWC

Laying of SMA

Dismantle Guardrail, NJB Installation & Misc. Works

Temporay Road Marking & Traffic Diversion/Contra Flow

30-Jun-14, Road Furniture (WB)

Road Furniture Start (WB)

Road Furniture Finish (WB)

30-Jun-14, Stage 2

22-Apr-14, CH.5600-CH.4200

Traffic Signs

Road Markings

Ancillary Finishings

16-May-14, CH.4200-CH.2800

Traffic Signs

Road Markings

Ancillary Finishings

09-Jun-14, CH.2800-CH.1400

Traffic Signs

Road Markings

Ancillary Finishings

30-Jun-14, CH.1400-CH.0

Traffic Signs

Road Markings

Ancillary Finishings

30-Jun-14, Utilities and Services (WB)

Utilities and Services Start (WB)

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 9 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1

Page 10: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

BH0130 Utilities and Services Finish (WB) 0 30-Jun-14 05-Jul-14 5

Overall Stage 1Overall Stage 1 221 01-Oct-13 30-Jun-14 07-Oct-13 05-Jul-14 5

BH0010 Testing and Commissioning 63 15-Apr-14 30-Jun-14 21-Apr-14 05-Jul-14 5

CH.5600-CH.4200CH.5600-CH.4200 71 01-Oct-13 27-Dec-13 07-Oct-13 19-Apr-14 92

BH5030 Temporary Works for Exist ing Utilities 71 01-Oct-13 27-Dec-13 24-Jan-14 19-Apr-14 92

BH5040 Waterworks, Relocation of Water Mains (CH.5450) 70 01-Oct-13 26-Dec-13 07-Oct-13 02-Jan-14 5

Telecommunication SystemTelecommunication System 60 01-Oct-13 13-Dec-13 07-Oct-13 22-Jan-14 31

BH5000 Lay Duct 36 01-Oct-13 14-Nov-13 07-Oct-13 20-Nov-13 5

BH5010 Relocation of OFC 36 16-Oct-13 28-Nov-13 23-Nov-13 07-Jan-14 31

BH5020 ITS System 36 30-Oct-13 13-Dec-13 07-Dec-13 22-Jan-14 31

CH.4200-CH.2800CH.4200-CH.2800 71 15-Nov-13 12-Feb-14 21-Nov-13 19-Apr-14 56

BH6030 Temporary Works for Exist ing Utilities 71 15-Nov-13 12-Feb-14 24-Jan-14 19-Apr-14 56

Telecommunication SystemTelecommunication System 60 15-Nov-13 28-Jan-14 21-Nov-13 08-Mar-14 31

BH6000 Lay Duct 36 15-Nov-13 28-Dec-13 21-Nov-13 04-Jan-14 5

BH6010 Relocation of OFC 36 29-Nov-13 13-Jan-14 08-Jan-14 22-Feb-14 31

BH6020 ITS System 36 14-Dec-13 28-Jan-14 23-Jan-14 08-Mar-14 31

CH.2800-CH.1400CH.2800-CH.1400 71 30-Dec-13 27-Mar-14 06-Jan-14 19-Apr-14 20

BH7030 Temporary Works for Exist ing Utilities 71 30-Dec-13 27-Mar-14 24-Jan-14 19-Apr-14 20

Telecommunication SystemTelecommunication System 60 30-Dec-13 14-Mar-14 06-Jan-14 19-Apr-14 31

BH7000 Lay Duct 36 30-Dec-13 13-Feb-14 06-Jan-14 20-Feb-14 5

BH7010 Relocation of OFC 36 15-Jan-14 28-Feb-14 24-Feb-14 05-Apr-14 31

BH7020 ITS System 36 29-Jan-14 14-Mar-14 10-Mar-14 19-Apr-14 31

CH.1400-CH.0CH.1400-CH.0 65 14-Feb-14 02-May-14 21-Feb-14 05-Jul-14 53

BH8030 Temporary Works for Exist ing Utilities 65 14-Feb-14 02-May-14 18-Apr-14 05-Jul-14 53

Telecommunication SystemTelecommunication System 50 14-Feb-14 14-Apr-14 21-Feb-14 19-Apr-14 5

BH8000 Lay Duct 36 14-Feb-14 28-Mar-14 21-Feb-14 03-Apr-14 5

BH8010 Relocation of OFC 36 22-Feb-14 04-Apr-14 28-Feb-14 10-Apr-14 5

BH8020 ITS System 36 04-Mar-14 14-Apr-14 10-Mar-14 19-Apr-14 5

Bridge Widening (WB)Bridge Widening (WB) 271 01-Jul-13 31-May-14 05-Aug-13 05-Jul-14 29

BJ1020 Bridge Widening Start (WB) 0 29-Aug-13 05-Jul-14 252

BJ1030 Bridge Widening Finish (WB) 0 31-May-14 05-Jul-14 29

Bridge Extension Over Jalan Damansara (BR B.1)Bridge Extension Over Jalan Damansara (BR B.1) 223 29-Aug-13 31-May-14 14-Oct-13 05-Jul-14 29

Pier 2Pier 2 54 03-Oct-13 07-Dec-13 14-Nov-13 22-Jan-14 35

BJ2760 Pile Cap Construction 22 03-Oct-13 29-Oct-13 14-Nov-13 09-Dec-13 33

BJ2770 Column Construction 32 30-Oct-13 07-Dec-13 13-Dec-13 22-Jan-14 35

Pier 1Pier 1 48 05-Oct-13 03-Dec-13 16-Nov-13 22-Jan-14 39

BJ2780 Pile Cap Construction 22 05-Oct-13 31-Oct-13 16-Nov-13 12-Dec-13 33

BJ2790 Column Construction 26 01-Nov-13 03-Dec-13 20-Dec-13 22-Jan-14 39

Precast BeamsPrecast Beams 12 17-Dec-13 31-Dec-13 23-Jan-14 07-Feb-14 29

BJ2900 Launching of Pre-tensioned Concrete Beams 12 17-Dec-13 31-Dec-13 23-Jan-14 07-Feb-14 29

Bridge DeckBridge Deck 40 02-Jan-14 21-Feb-14 08-Feb-14 27-Mar-14 29

BJ2910 Bridge Deck Construction 40 02-Jan-14 21-Feb-14 08-Feb-14 27-Mar-14 29

PilingPiling 40 29-Aug-13 17-Oct-13 14-Oct-13 22-Nov-13 29

BJ2500 Temporary Sheet Piling 6 29-Aug-13 05-Sep-13 14-Oct-13 21-Oct-13 37

BJ2505 Bored Piling 26 17-Sep-13 17-Oct-13 22-Oct-13 22-Nov-13 29

MiscellaneousMiscellaneous 95 07-Feb-14 31-May-14 14-Mar-14 05-Jul-14 29

BJ2940 Bridge Parapet, Lining to Abutment and Service Ducts 26 07-Feb-14 10-Mar-14 14-Mar-14 12-Apr-14 29

BJ2950 Installation of Movement Joints in Bridge Deck and Approach Slab 12 19-May-14 31-May-14 23-Jun-14 05-Jul-14 29

Pier 5Pier 5 48 26-Sep-13 23-Nov-13 31-Oct-13 22-Jan-14 47

BJ2700 Pile Cap Construction 22 26-Sep-13 22-Oct-13 31-Oct-13 27-Nov-13 29

BJ2710 Column Construction 26 23-Oct-13 23-Nov-13 20-Dec-13 22-Jan-14 47

Pier 4Pier 4 62 28-Sep-13 13-Dec-13 02-Nov-13 22-Jan-14 31

BJ2720 Pile Cap Construction 22 28-Sep-13 24-Oct-13 02-Nov-13 29-Nov-13 29

BJ2730 Column Construction 40 25-Oct-13 13-Dec-13 03-Dec-13 22-Jan-14 31

Pier 3Pier 3 62 01-Oct-13 16-Dec-13 07-Nov-13 22-Jan-14 29

BJ2740 Pile Cap Construction 22 01-Oct-13 26-Oct-13 07-Nov-13 02-Dec-13 29

BJ2750 Column Construction 40 28-Oct-13 16-Dec-13 03-Dec-13 22-Jan-14 29

West AbutmentWest Abutment 52 08-Oct-13 10-Dec-13 19-Nov-13 22-Jan-14 33

BJ2640 Pile Cap Construction 18 08-Oct-13 29-Oct-13 19-Nov-13 09-Dec-13 33

BJ2650 Abutment Wall 16 30-Oct-13 19-Nov-13 10-Dec-13 30-Dec-13 33

BJ2660 Wing Wall & Curtail Wall 10 20-Nov-13 30-Nov-13 31-Dec-13 11-Jan-14 33

BJ2670 Approach Slab 8 02-Dec-13 10-Dec-13 13-Jan-14 22-Jan-14 33

East AbutmentEast Abutment 52 24-Sep-13 26-Nov-13 29-Oct-13 22-Jan-14 45

BJ2600 Pile Cap Construction 18 24-Sep-13 14-Oct-13 29-Oct-13 20-Nov-13 29

BJ2610 Abutment Wall 16 16-Oct-13 02-Nov-13 10-Dec-13 30-Dec-13 45

BJ2620 Wing Wall & Curtail Wall 10 06-Nov-13 16-Nov-13 31-Dec-13 11-Jan-14 45

BJ2630 Approach Slab 8 18-Nov-13 26-Nov-13 13-Jan-14 22-Jan-14 45

Bridge Extension Over Segambut Dalam (BR B.2)Bridge Extension Over Segambut Dalam (BR B.2) 232 30-Jul-13 14-May-14 12-Sep-13 05-Jul-14 44

PilingPiling 38 30-Jul-13 14-Sep-13 12-Sep-13 21-Oct-13 29

BJ3500 Temporary Sheet Piling 6 30-Jul-13 05-Aug-13 12-Sep-13 19-Sep-13 35

BJ3505 Bored Piling 26 15-Aug-13 14-Sep-13 20-Sep-13 21-Oct-13 29

East AbutmentEast Abutment 62 22-Aug-13 07-Nov-13 16-Oct-13 18-Jan-14 58

BJ3600 Pile Cap Construction 22 22-Aug-13 18-Sep-13 16-Oct-13 12-Nov-13 44

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

Utilities and Services Finish (WB)

30-Jun-14, Overall Stage 1

Testing and Commissioning

27-Dec-13, CH.5600-CH.4200

Temporary Works for Exist ing Utilities

Waterworks, Relocation of Water Mains (CH.5450)

13-Dec-13, Telecommunication System

Lay Duct

Relocation of OFC

ITS System

12-Feb-14, CH.4200-CH.2800

Temporary Works for Exist ing Utilities

28-Jan-14, Telecommunication System

Lay Duct

Relocation of OFC

ITS System

27-Mar-14, CH.2800-CH.1400

Temporary Works for Exist ing Utilities

14-Mar-14, Telecommunication System

Lay Duct

Relocation of OFC

ITS System

02-May-14, CH.1400-CH.0

Temporary Works for Existing Utilities

14-Apr-14, Telecommunication System

Lay Duct

Relocation of OFC

ITS System

31-May-14, Bridge Widening (WB)

Bridge Widening Start (WB)

Bridge Widening Finish (WB)

31-May-14, Bridge Extension Over Jalan Damansara (BR B.1)

07-Dec-13, Pier 2

Pile Cap Construction

Column Construction

03-Dec-13, Pier 1

Pile Cap Construction

Column Construction

31-Dec-13, Precast Beams

Launching of Pre-tensioned Concrete Beams

21-Feb-14, Bridge Deck

Bridge Deck Construction

17-Oct-13, Piling

Temporary Sheet Piling

Bored Piling

31-May-14, Miscellaneous

Bridge Parapet, Lining to Abutment and Service Ducts

Installation of Movement Joints in Bridge Deck and Approach Slab

23-Nov-13, Pier 5

Pile Cap Construction

Column Construction

13-Dec-13, Pier 4

Pile Cap Construction

Column Construction

16-Dec-13, Pier 3

Pile Cap Construction

Column Construction

10-Dec-13, West Abutment

Pile Cap Construction

Abutment Wall

Wing Wall & Curtail Wall

Approach Slab

26-Nov-13, East Abutment

Pile Cap Construction

Abutment Wall

Wing Wall & Curtail Wall

Approach Slab

14-May-14, Bridge Extension Over Segambut Dalam (BR B.2)

14-Sep-13, Piling

Temporary Sheet Piling

Bored Piling

07-Nov-13, East Abutment

Pile Cap Construction

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 10 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1

Page 11: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

BJ3610 Abutment Wall 18 19-Sep-13 09-Oct-13 29-Nov-13 20-Dec-13 58

BJ3620 Wing Wall & Curtail Wall 12 10-Oct-13 24-Oct-13 21-Dec-13 06-Jan-14 58

BJ3630 Approach Slab 10 25-Oct-13 07-Nov-13 07-Jan-14 18-Jan-14 58

Pier 4Pier 4 56 27-Aug-13 02-Nov-13 21-Oct-13 18-Jan-14 60

BJ3700 Pile Cap Construction 22 27-Aug-13 23-Sep-13 21-Oct-13 16-Nov-13 44

BJ3710 Column Construction 34 24-Sep-13 02-Nov-13 06-Dec-13 18-Jan-14 60

Pier 3Pier 3 62 29-Aug-13 14-Nov-13 23-Oct-13 18-Jan-14 52

BJ3720 Pile Cap Construction 22 29-Aug-13 25-Sep-13 23-Oct-13 19-Nov-13 44

BJ3730 Column Construction 40 26-Sep-13 14-Nov-13 29-Nov-13 18-Jan-14 52

Bridge DeckBridge Deck 40 09-Dec-13 28-Jan-14 05-Feb-14 24-Mar-14 44

BJ3920 Bridge Deck Construction 40 09-Dec-13 28-Jan-14 05-Feb-14 24-Mar-14 44

Pier 2Pier 2 62 02-Sep-13 16-Nov-13 25-Oct-13 18-Jan-14 50

BJ3740 Pile Cap Construction 22 02-Sep-13 27-Sep-13 25-Oct-13 21-Nov-13 44

BJ3750 Column Construction 40 28-Sep-13 16-Nov-13 29-Nov-13 18-Jan-14 50

West AbutmentWest Abutment 62 09-Sep-13 23-Nov-13 01-Nov-13 18-Jan-14 44

BJ3640 Pile Cap Construction 22 09-Sep-13 04-Oct-13 01-Nov-13 28-Nov-13 44

BJ3650 Abutment Wall 18 05-Oct-13 26-Oct-13 29-Nov-13 20-Dec-13 44

BJ3660 Wing Wall & Curtail Wall 12 28-Oct-13 12-Nov-13 21-Dec-13 06-Jan-14 44

BJ3670 Approach Slab 10 13-Nov-13 23-Nov-13 07-Jan-14 18-Jan-14 44

Pier 1Pier 1 48 04-Sep-13 31-Oct-13 28-Oct-13 18-Jan-14 62

BJ3760 Pile Cap Construction 22 04-Sep-13 30-Sep-13 28-Oct-13 23-Nov-13 44

BJ3770 Column Construction 26 01-Oct-13 31-Oct-13 17-Dec-13 18-Jan-14 62

MiscellaneousMiscellaneous 98 15-Jan-14 14-May-14 11-Mar-14 05-Jul-14 44

BJ3930 Bridge Parapet, Lining to Abutment and Service Ducts 26 15-Jan-14 17-Feb-14 11-Mar-14 09-Apr-14 44

BJ3940 Installation of Movement Joints in Bridge Deck and Approach Slab 12 29-Apr-14 14-May-14 23-Jun-14 05-Jul-14 44

Precast BeamsPrecast Beams 12 25-Nov-13 07-Dec-13 20-Jan-14 04-Feb-14 44

BJ3910 Launching of Post-tensioned Concrete Beams 12 25-Nov-13 07-Dec-13 20-Jan-14 04-Feb-14 44

Extension of Viaduct at Edinburgh Estate (BR B.3)Extension of Viaduct at Edinburgh Estate (BR B.3) 260 01-Jul-13 19-May-14 05-Aug-13 05-Jul-14 40

PilingPiling 36 01-Jul-13 14-Aug-13 05-Aug-13 19-Sep-13 29

BJ4500 Temporary Sheet Piling 6 01-Jul-13 06-Jul-13 05-Aug-13 13-Aug-13 29

BJ4505 Bored Piling 30 08-Jul-13 14-Aug-13 14-Aug-13 19-Sep-13 29

East AbutmentEast Abutment 62 15-Jul-13 30-Sep-13 04-Sep-13 20-Dec-13 66

BJ4600 Pile Cap Construction 22 15-Jul-13 12-Aug-13 04-Sep-13 30-Sep-13 40

BJ4610 Abutment Wall 18 13-Aug-13 03-Sep-13 01-Nov-13 23-Nov-13 66

BJ4620 Wing Wall & Curtail Wall 12 04-Sep-13 18-Sep-13 25-Nov-13 07-Dec-13 66

BJ4630 Approach Slab 10 19-Sep-13 30-Sep-13 09-Dec-13 20-Dec-13 66

Pier 10Pier 10 48 19-Jul-13 18-Sep-13 09-Sep-13 20-Dec-13 76

BJ4700 Pile Cap Construction 22 19-Jul-13 16-Aug-13 09-Sep-13 04-Oct-13 40

BJ4710 Column Construction 26 17-Aug-13 18-Sep-13 20-Nov-13 20-Dec-13 76

Pier 9Pier 9 58 22-Jul-13 02-Oct-13 11-Sep-13 20-Dec-13 64

BJ4720 Pile Cap Construction 22 22-Jul-13 19-Aug-13 11-Sep-13 07-Oct-13 40

BJ4730 Column Construction 36 20-Aug-13 02-Oct-13 08-Nov-13 20-Dec-13 64

Pier 8Pier 8 72 24-Jul-13 22-Oct-13 13-Sep-13 20-Dec-13 48

BJ4740 Pile Cap Construction 22 24-Jul-13 21-Aug-13 13-Sep-13 09-Oct-13 40

BJ4750 Column Construction 50 22-Aug-13 22-Oct-13 21-Oct-13 20-Dec-13 48

Pier 7Pier 7 72 27-Jul-13 24-Oct-13 17-Sep-13 20-Dec-13 46

BJ4760 Pile Cap Construction 22 27-Jul-13 23-Aug-13 17-Sep-13 11-Oct-13 40

BJ4770 Column Construction 50 24-Aug-13 24-Oct-13 21-Oct-13 20-Dec-13 46

Pier 6Pier 6 68 30-Jul-13 22-Oct-13 19-Sep-13 20-Dec-13 48

BJ4780 Pile Cap Construction 22 30-Jul-13 26-Aug-13 19-Sep-13 14-Oct-13 40

BJ4790 Column Construction 46 27-Aug-13 22-Oct-13 25-Oct-13 20-Dec-13 48

Pier 5Pier 5 68 01-Aug-13 24-Oct-13 21-Sep-13 20-Dec-13 46

BJ4800 Pile Cap Construction 22 01-Aug-13 28-Aug-13 21-Sep-13 17-Oct-13 40

BJ4810 Column Construction 46 29-Aug-13 24-Oct-13 25-Oct-13 20-Dec-13 46

Pier 4Pier 4 68 03-Aug-13 26-Oct-13 24-Sep-13 20-Dec-13 44

BJ4820 Pile Cap Construction 22 03-Aug-13 30-Aug-13 24-Sep-13 19-Oct-13 40

BJ4830 Column Construction 46 02-Sep-13 26-Oct-13 25-Oct-13 20-Dec-13 44

Pier 3Pier 3 58 06-Aug-13 17-Oct-13 26-Sep-13 20-Dec-13 52

BJ4840 Pile Cap Construction 22 06-Aug-13 03-Sep-13 26-Sep-13 22-Oct-13 40

BJ4850 Column Construction 36 04-Sep-13 17-Oct-13 08-Nov-13 20-Dec-13 52

Pier 2Pier 2 48 10-Aug-13 07-Oct-13 28-Sep-13 20-Dec-13 60

BJ4860 Pile Cap Construction 22 10-Aug-13 05-Sep-13 28-Sep-13 24-Oct-13 40

BJ4870 Column Construction 26 06-Sep-13 07-Oct-13 20-Nov-13 20-Dec-13 60

Pier 1Pier 1 40 13-Aug-13 30-Sep-13 01-Oct-13 20-Dec-13 66

BJ4880 Pile Cap Construction 22 13-Aug-13 07-Sep-13 01-Oct-13 26-Oct-13 40

BJ4890 Column Construction 18 09-Sep-13 30-Sep-13 29-Nov-13 20-Dec-13 66

West AbutmentWest Abutment 62 17-Aug-13 31-Oct-13 05-Oct-13 20-Dec-13 40

BJ4640 Pile Cap Construction 22 17-Aug-13 12-Sep-13 05-Oct-13 31-Oct-13 40

BJ4650 Abutment Wall 18 13-Sep-13 04-Oct-13 01-Nov-13 23-Nov-13 40

BJ4660 Wing Wall & Curtail Wall 12 05-Oct-13 19-Oct-13 25-Nov-13 07-Dec-13 40

BJ4670 Approach Slab 10 21-Oct-13 31-Oct-13 09-Dec-13 20-Dec-13 40

Precast BeamsPrecast Beams 16 01-Nov-13 21-Nov-13 21-Dec-13 10-Jan-14 40

BJ4900 Launching of Post-tensioned Concrete Beams 16 01-Nov-13 21-Nov-13 21-Dec-13 10-Jan-14 40

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

Abutment Wall

Wing Wall & Curtail Wall

Approach Slab

02-Nov-13, Pier 4

Pile Cap Construction

Column Construction

14-Nov-13, Pier 3

Pile Cap Construction

Column Construction

28-Jan-14, Bridge Deck

Bridge Deck Construction

16-Nov-13, Pier 2

Pile Cap Construction

Column Construction

23-Nov-13, West Abutment

Pile Cap Construction

Abutment Wall

Wing Wall & Curtail Wall

Approach Slab

31-Oct-13, Pier 1

Pile Cap Construction

Column Construction

14-May-14, Miscellaneous

Bridge Parapet, Lining to Abutment and Service Ducts

Installation of Movement Joints in Bridge Deck and Approach Slab

07-Dec-13, Precast Beams

Launching of Post-tensioned Concrete Beams

19-May-14, Extension of Viaduct at Edinburgh Estate (BR B.3)

14-Aug-13, Piling

Temporary Sheet Piling

Bored Piling

30-Sep-13, East Abutment

Pile Cap Construction

Abutment Wall

Wing Wall & Curtail Wall

Approach Slab

18-Sep-13, Pier 10

Pile Cap Construction

Column Construction

02-Oct-13, Pier 9

Pile Cap Construction

Column Construction

22-Oct-13, Pier 8

Pile Cap Construction

Column Construction

24-Oct-13, Pier 7

Pile Cap Construction

Column Construction

22-Oct-13, Pier 6

Pile Cap Construction

Column Construction

24-Oct-13, Pier 5

Pile Cap Construction

Column Construction

26-Oct-13, Pier 4

Pile Cap Construction

Column Construction

17-Oct-13, Pier 3

Pile Cap Construction

Column Construction

07-Oct-13, Pier 2

Pile Cap Construction

Column Construction

30-Sep-13, Pier 1

Pile Cap Construction

Column Construction

31-Oct-13, West Abutment

Pile Cap Construction

Abutment Wall

Wing Wall & Curtail Wall

Approach Slab

21-Nov-13, Precast Beams

Launching of Post-tensioned Concrete Beams

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 11 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1

Page 12: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

Bridge DeckBridge Deck 46 22-Nov-13 18-Jan-14 11-Jan-14 10-Mar-14 40

BJ4910 Bridge Deck Construction 46 22-Nov-13 18-Jan-14 11-Jan-14 10-Mar-14 40

MiscellaneousMiscellaneous 110 04-Jan-14 19-May-14 25-Feb-14 05-Jul-14 40

BJ4920 Bridge Parapet, Lining to Abutment and Service Ducts 32 04-Jan-14 13-Feb-14 25-Feb-14 02-Apr-14 40

BJ4930 Installation of Movement Joints in Bridge Deck and Approach Slab 18 26-Apr-14 19-May-14 16-Jun-14 05-Jul-14 40

Slope Improvement Works (WB)Slope Improvement Works (WB) 268 03-Jun-13 28-Apr-14 10-Aug-13 05-Jul-14 56

BL0030 Slope Improvement Works Start (WB) 0 03-Jun-13 05-Jul-14 324

BL0040 Slope Improvement Works Finish (WB) 0 28-Apr-14 05-Jul-14 56

Overall Stage 1Overall Stage 1 268 03-Jun-13 28-Apr-14 10-Aug-13 05-Jul-14 56

Cut AreaCut Area 268 03-Jun-13 28-Apr-14 10-Aug-13 05-Jul-14 56

Slope Improvement - Retaining Wall (CH.2300-CH.2080)Slope Improvement - Retaining Wall (CH.2300-CH.2080) 76 14-Dec-13 19-Mar-14 05-Apr-14 05-Jul-14 90

BL3500 Excavation 58 14-Dec-13 26-Feb-14 05-Apr-14 14-Jun-14 90

BL3510 Construction of Wall Base 58 21-Dec-13 05-Mar-14 12-Apr-14 21-Jun-14 90

BL3520 Construction of Retaining Wall 58 30-Dec-13 12-Mar-14 19-Apr-14 28-Jun-14 90

BL3530 Backfill 58 07-Jan-14 19-Mar-14 26-Apr-14 05-Jul-14 90

Slope Improvement - Horizontal DrainSlope Improvement - Horizontal Drain 268 03-Jun-13 28-Apr-14 10-Aug-13 05-Jul-14 56

BL3000 Installation of Horizontal Drain (CH.5600-CH.4200) 67 03-Jun-13 22-Aug-13 10-Aug-13 30-Oct-13 56

BL3010 Installation of Horizontal Drain (CH.4200-CH.2800) 67 23-Aug-13 14-Nov-13 31-Oct-13 23-Jan-14 56

BL3020 Installation of Horizontal Drain (CH.2800-CH.1400) 67 15-Nov-13 07-Feb-14 24-Jan-14 15-Apr-14 56

BL3030 Installation of Horizontal Drain (CH.1400-CH.0) 67 08-Feb-14 28-Apr-14 16-Apr-14 05-Jul-14 56

Fill AreaFill Area 54 24-Jun-13 28-Aug-13 02-May-14 05-Jul-14 252

Slope Improvement - Retaining Wall (CH.5380-CH.5280)Slope Improvement - Retaining Wall (CH.5380-CH.5280) 54 24-Jun-13 28-Aug-13 02-May-14 05-Jul-14 252

BL4000 Excavation 30 24-Jun-13 29-Jul-13 02-May-14 07-Jun-14 252

BL4020 Construction of Wall Base 30 08-Jul-13 14-Aug-13 17-May-14 21-Jun-14 252

BL4030 Construction of Retaining Wall 30 15-Jul-13 21-Aug-13 24-May-14 28-Jun-14 252

BL4040 Backfill 30 22-Jul-13 28-Aug-13 31-May-14 05-Jul-14 252

Ground Treatment Works (WB)Ground Treatment Works (WB) 208 15-May-13 28-Jan-14 21-May-13 05-Jul-14 130

BM0030 Ground Treatment Works Start (WB) 0 15-May-13 05-Jul-14 338

BM0040 Ground Treatment Works Finish (WB) 0 28-Jan-14 05-Jul-14 130

Stage 1Stage 1 208 15-May-13 28-Jan-14 21-May-13 05-Jul-14 130

Ground Treatment (CH.5600-CH.4200)Ground Treatment (CH.5600-CH.4200) 52 15-May-13 16-Jul-13 21-May-13 22-Jul-13 5

BM2000 Excavation of Unsuitable Material 46 15-May-13 09-Jul-13 21-May-13 15-Jul-13 5

BM2010 Laying of Geotextile Separator 46 17-May-13 11-Jul-13 23-May-13 17-Jul-13 5

BM2020 Laying of Outlet Drain 46 20-May-13 13-Jul-13 27-May-13 19-Jul-13 5

BM2030 Backfilling with Compacted Soil / hardcore Material 46 22-May-13 16-Jul-13 29-May-13 22-Jul-13 5

Ground Treatment (CH.4200-CH.2800)Ground Treatment (CH.4200-CH.2800) 52 17-Jul-13 20-Sep-13 27-Dec-13 03-Mar-14 130

BM2100 Excavation of Unsuitable Material 46 17-Jul-13 12-Sep-13 27-Dec-13 24-Feb-14 130

BM2110 Laying of Geotextile Separator 46 19-Jul-13 14-Sep-13 30-Dec-13 26-Feb-14 130

BM2120 Laying of Outlet Drain 46 22-Jul-13 18-Sep-13 02-Jan-14 28-Feb-14 130

BM2130 Backfilling with Compacted Soil / hardcore Material 46 24-Jul-13 20-Sep-13 04-Jan-14 03-Mar-14 130

Ground Treatment (CH.2800-CH.1400)Ground Treatment (CH.2800-CH.1400) 52 21-Sep-13 23-Nov-13 04-Mar-14 03-May-14 130

BM2200 Excavation of Unsuitable Material 46 21-Sep-13 16-Nov-13 04-Mar-14 25-Apr-14 130

BM2210 Laying of Geotextile Separator 46 24-Sep-13 19-Nov-13 06-Mar-14 28-Apr-14 130

BM2220 Laying of Outlet Drain 46 26-Sep-13 21-Nov-13 08-Mar-14 30-Apr-14 130

BM2230 Backfilling with Compacted Soil / hardcore Material 46 28-Sep-13 23-Nov-13 11-Mar-14 03-May-14 130

Ground Treatment (CH.1400-CH.0)Ground Treatment (CH.1400-CH.0) 52 25-Nov-13 28-Jan-14 05-May-14 05-Jul-14 130

BM2300 Excavation of Unsuitable Material 46 25-Nov-13 21-Jan-14 05-May-14 28-Jun-14 130

BM2310 Laying of Geotextile Separator 46 27-Nov-13 23-Jan-14 07-May-14 01-Jul-14 130

BM2320 Laying of Outlet Drain 46 29-Nov-13 25-Jan-14 09-May-14 03-Jul-14 130

BM2330 Backfilling with Compacted Soil / hardcore Material 46 02-Dec-13 28-Jan-14 12-May-14 05-Jul-14 130

Electrical Works for Street Lighting (WB)Electrical Works for Street Lighting (WB) 219 03-Oct-13 30-Jun-14 09-Oct-13 05-Jul-14 5

BN0030 Electrical Works for Street Lighting Start (WB) 0 03-Oct-13 05-Jul-14 224

BN0040 Electrical Works for Street Lighting Finish (WB) 0 30-Jun-14 05-Jul-14 5

Overall Stage 1Overall Stage 1 219 03-Oct-13 30-Jun-14 09-Oct-13 05-Jul-14 5

BN0200 Testing and Commissioning 60 18-Apr-14 30-Jun-14 24-Apr-14 05-Jul-14 5

CH.5600-CH.4200CH.5600-CH.4200 48 03-Oct-13 30-Nov-13 09-Oct-13 06-Dec-13 5

BN2000 High Mast 48 03-Oct-13 30-Nov-13 09-Oct-13 06-Dec-13 5

BN2010 Street Lighting 48 03-Oct-13 30-Nov-13 09-Oct-13 06-Dec-13 5

CH.4200-CH.2800CH.4200-CH.2800 48 02-Dec-13 30-Jan-14 07-Dec-13 07-Feb-14 5

BN2100 High Mast 48 02-Dec-13 30-Jan-14 07-Dec-13 07-Feb-14 5

BN2110 Street Lighting 48 02-Dec-13 30-Jan-14 07-Dec-13 07-Feb-14 5

CH.2800-CH.1400CH.2800-CH.1400 48 03-Feb-14 31-Mar-14 08-Feb-14 05-Apr-14 5

BN2200 High Mast 48 03-Feb-14 31-Mar-14 08-Feb-14 05-Apr-14 5

BN2210 Street Lighting 48 03-Feb-14 31-Mar-14 08-Feb-14 05-Apr-14 5

CH.1400-CH.0CH.1400-CH.0 48 01-Apr-14 28-May-14 07-Apr-14 04-Jun-14 5

BN2300 High Mast 48 01-Apr-14 28-May-14 07-Apr-14 04-Jun-14 5

BN2310 Street Lighting 48 01-Apr-14 28-May-14 07-Apr-14 04-Jun-14 5

Prime Cost and Provisional SumsPrime Cost and Provisional Sums 544 03-Sep-12 02-Jul-14 06-Sep-12 05-Jul-14 3

BP1000 Provisional Sums Start 0 01-Oct-12 05-Jul-14 524

BP1010 Provisional Sums Finish 0 02-Jul-14 05-Jul-14 3

Prime CostPrime Cost 544 03-Sep-12 02-Jul-14 06-Sep-12 05-Jul-14 3

BP3100 Traffic Management 544 03-Sep-12 02-Jul-14 06-Sep-12 05-Jul-14 3

BP3300 Landscaping Works 70 01-Apr-14 24-Jun-14 12-Apr-14 05-Jul-14 10

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

18-Jan-14, Bridge Deck

Bridge Deck Construction

19-May-14, Miscellaneous

Bridge Parapet, Lining to Abutment and Service Ducts

Installation of Movement Joints in Bridge Deck and Approach Slab

28-Apr-14, Slope Improvement Works (WB)

Slope Improvement Works Start (WB)

Slope Improvement Works Finish (WB)

28-Apr-14, Overall Stage 1

28-Apr-14, Cut Area

19-Mar-14, Slope Improvement - Retaining Wall (CH.2300-CH.2080)

Excavation

Construction of Wall Base

Construction of Retaining Wall

Backfill

28-Apr-14, Slope Improvement - Horizontal Drain

Installation of Horizontal Drain (CH.5600-CH.4200)

Installation of Horizontal Drain (CH.4200-CH.2800)

Installation of Horizontal Drain (CH.2800-CH.1400)

Installation of Horizontal Drain (CH.1400-CH.0)

28-Aug-13, Fill Area

28-Aug-13, Slope Improvement - Retaining Wall (CH.5380-CH.5280)

Excavation

Construction of Wall Base

Construction of Retaining Wall

Backfill

28-Jan-14, Ground Treatment Works (WB)

Ground Treatment Works Start (WB)

Ground Treatment Works Finish (WB)

28-Jan-14, Stage 1

16-Jul-13, Ground Treatment (CH.5600-CH.4200)

Excavation of Unsuitable Material

Laying of Geotextile Separator

Laying of Outlet Drain

Backfilling with Compacted Soil / hardcore Material

20-Sep-13, Ground Treatment (CH.4200-CH.2800)

Excavation of Unsuitable Material

Laying of Geotextile Separator

Laying of Outlet Drain

Backfilling with Compacted Soil / hardcore Material

23-Nov-13, Ground Treatment (CH.2800-CH.1400)

Excavation of Unsuitable Material

Laying of Geotextile Separator

Laying of Outlet Drain

Backfilling with Compacted Soil / hardcore Material

28-Jan-14, Ground Treatment (CH.1400-CH.0)

Excavation of Unsuitable Material

Laying of Geotextile Separator

Laying of Outlet Drain

Backfilling with Compacted Soil / hardcore Material

30-Jun-14, Electrical Works for Street Lighting (WB)

Electrical Works for Street Lighting Start (WB)

Electrical Works for Street Lighting Finish (WB)

30-Jun-14, Overall Stage 1

Testing and Commissioning

30-Nov-13, CH.5600-CH.4200

High Mast

Street Lighting

30-Jan-14, CH.4200-CH.2800

High Mast

Street Lighting

31-Mar-14, CH.2800-CH.1400

High Mast

Street Lighting

28-May-14, CH.1400-CH.0

High Mast

Street Lighting

02-Jul-14, Prime Cost and Provisional Sums

Provisional Sums Start

Provisional Sums Finish

02-Jul-14, Prime Cost

Traffic Management

Landscaping Works

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 12 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1

Page 13: Package B - Fourth Lane Widening

Activity ID Activity Name OriginalDuration

Early Start Early Finish Late Start Late Finish TotalFloat

Provisional SumsProvisional Sums 514 01-Oct-12 24-Jun-14 17-Oct-12 05-Jul-14 10

BP1100 Protection to All Services and Utilities 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14

BP1250 Environmental Management 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14

BP1300 Authority Fee 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14

BP1450 Rock Fences 70 01-Apr-14 24-Jun-14 12-Apr-14 05-Jul-14 10

BP1550 Slope Protection 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14

BP1600 Piled Embankment 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14

BP1700 Telecommunication Services 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14

BP1800 ITS System 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14

BP1900 Utilities Relocation Works Under the Bridges 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14

BP2050 Relocation Works 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14

BP2100 Dayworks 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14

Project CompletionProject Completion 273 02-Aug-13 05-Jul-14 05-May-14 05-Jul-14 0

Section 1 - East BoundSection 1 - East Bound 52 02-Aug-13 05-Oct-13 05-May-14 05-Jul-14 221

BQ1000 Clearing Up of Site 52 02-Aug-13 05-Oct-13 05-May-14 05-Jul-14 221

BQ1010 Final Demobilisation 26 05-Sep-13 05-Oct-13 06-Jun-14 05-Jul-14 221

BQ1020 Completion of Work 0 05-Oct-13 05-Jul-14 221

Section 2 - West BoundSection 2 - West Bound 52 05-May-14 05-Jul-14 05-May-14 05-Jul-14 0

BQ2000 Clearing Up of Site 52 05-May-14 05-Jul-14 05-May-14 05-Jul-14 0

BQ2010 Final Demobilisation 26 06-Jun-14 05-Jul-14 06-Jun-14 05-Jul-14 0

BQ2020 Completion of Work 0 05-Jul-14 05-Jul-14 0

-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014

24-Jun-14, Provisional Sums

Protection to All Services and Utilities

Environmental Management

Authority Fee

Rock Fences

Slope Protection

Piled Embankment

Telecommunication Services

ITS System

Utilities Relocation Works Under the Bridges

Relocation Works

Dayworks

05-Jul-14, Project Completion

05-Oct-13, Section 1 - East Bound

Clearing Up of Site

Final Demobilisation

Completion of Work

05-Jul-14, Section 2 - West Bound

Clearing Up of Site

Final Demobilisation

Completion of Work

NORTH-SOUTH EXPRESSWAY (PLUS)

PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B

Remaining Work

Critical Remaining Work

Milestone

Summary 13 of 13

WORK PROGRAMME

Date Revision Checked Approved

30-Jul-12 Rev.0

11-Sep-12 Rev.1