Upload
lee-willis
View
214
Download
0
Embed Size (px)
Citation preview
First Assessment 1
PACS IQR 13 Jan 2005
The PI’s Self-Assessment
A. Poglitsch
First Assessment 2
PACS IQR 13 Jan 2005
Achievements
• PACS integrated FPU mechanical/thermal/optical qualification/performance verified (with some understood exceptions)– Subunits function/perform as expected after integration– Remaining open issues are concrete, isolated problems
that can be solved
• Almost all S/C interfaces settled, budgets (mass, electrical power, thermal power) stable
• PACS system operability (FPU + WE/OBSW + OGSE + EGSE) demonstrated
• Test & calibration plan + use of IA/QLA shown viable
First Assessment 3
PACS IQR 13 Jan 2005
The Schedule and Its Consequences
• Several subunits on critical path (detectors, DECMEC, DPU?)
• Some modifications of FM subunits and OGSE mandatory
• No margin• 6 month of FM ILT minimum• Delivery on official need date (Nov 2005)
impossible Project will have to find ways to accommodate
FM delivery in March 2006 – no recovery in sight
First Assessment 4
PACS IQR 13 Jan 2005
PACS Areas of Concern
Warm Electronics + OBSW• Late qualification / late delivery of QM/FM units• System stability / frequent crashes (H/W? S/W?)• Potentially insufficient autonomy functions
– If system stabilty does not improve dramatically then better recovery scheme needed
– Improper commanding can damage FPU H/W• DPU: Burst mode not working with CDMU• SPU: Memory corruption; insufficient compression with
reasonable CPU load• BOLC: No immunity to uncontrolled power loss• DECMEC: FPGA overheating, link losses; performance
and operability still need to be demonstrated. Grounding scheme still open
First Assessment 5
PACS IQR 13 Jan 2005
PACS Areas of Concern
• Photoconductor/readout performance– Required sensitivity not demonstrated yet– “FS” CREs to be used with FM detectors show promising
performance, but measurements with detectors still missing
• Bolometer performance– QM bolometer performance insufficient– FM bolometer performance at subarray level probably ok– Performance at PhFPU level to be demonstrated, yet
• OGSE performance– Reproducibility of alignment– Scale/focus error
First Assessment 6
PACS IQR 13 Jan 2005
PACS Areas of Concern
• Late availability of ILT analysis in some areas– There may be yet unidentified problems that could
surface too late to be addressed in the final H/W implementation
• Lack of resources in some partner institutes to address known problems in time
• L0 interface as provided by industry for EQM tests and as foreseen for FM is incompatible with PACS requirements
• H field susceptibility – photometer performance could be seriously compromised
First Assessment 7
PACS IQR 13 Jan 2005
Future Strategy
• Optimise/prioritise implementation of changes to H/W
• Improve reviewing/monitoring of subunit progress by PACS System Engineering– H/W + S/W– Subunits must be delivered fully tested
• Optimise FM ILT planning– Early execution and timely analysis of tests needed for
performance verification
• Keep planning flexible to accomodate any adjustment in S/C schedule– Work towards open exchange on schedule between all
involved parties– Extension of ILTs should always be possible/welcome