Environmental Monitoring Report
Bi-Annual Environmental Monitoring Report (E-35, Hassanabdal – Havelian Expressway) (July – December 2016)
PAK: National Trade Corridor Highway Investment
Program (NTCHIP) – Tranche 3 (Package III)
Prepared by National Highways Authority for the Asian Development Bank.
NOTES
(i) The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its agencies ends on 30 June.
(ii) In this report, "$" refers to US dollars. This Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Bi-Anual Report I&II
Page 1 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Bi-Annual Environmental Monitoring Report
July- December 2016
CONSTRUCTION OF HASSANABDAL-HAVELIAN SECTION, E-35
Package III - ICB E-35: SARAI SALEH TO SIMLAILA
(Km 39+611 to Km 58+711)
Islamic Republic of Pakistan Financed by: Asian Development Bank and Government of the Pakistan
Project Number: 3197-PAK
Prepared by: Shazia Shahid, Environmental Specialist
(Dohwa Engineering Co, Ltd in association with M/s Engineering &
Management Services Pakistan & M/s Prime Engineering & Testing Consultant)
Reviewed by: National Highway Authority, Head Quarter Islamabad
For: Asian Development Bank
This report does not necessarily reflect the views of ADB or the Government concerned,
and ADB and the Government cannot be held liable for its contents.
Bi-Anual Report I&II
Page 2 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
List of Abbreviations
ADB Asian Development Bank BDL Below detectable limit CO Carbon monoxide CAP Corrective Action Plan DB Decibel EPA Environmental Protection Agency EIA Environmental Protection Agency EHS Environment, Health and Safety EMP Environmental Management Plan GOP Government of Pakistan GRC Grievance Redressal Committee IEE Initial Environmental Examination JV Joint Venture LPG Low Pressure Gas LDL Lowest detection Limit Mg/m3 Milligram per cubic meter NEQS National Environmental Quality Standards NOC No Objection Certificate NOX Nitrogen oxide NHA National Highway Authority
PPE Personnel Protective Equipment’s PM10 Particulate Matter ROW Right of Way SSEMP Site Specific Environmental Management Plan SSMC Social safeguards Management Consultants SC Supervision Consultant SO2 Sulphur dioxide TBT Tool Box Talks TMA Tehsil Municipal Administration TMP Traffic Management Plan Ug/m3 microgram per cubic meter ZKB Zahir Khan Brothers
Bi-Anual Report I&II
Page 3 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Table of Contents
Title Page
Abbreviations
1.Introduction……………………………………………………………………06
1.1 Project Background………………………………………………………………………………………………..……
1.2 Project Description and Scope of Work …………………………………………………………………..….
1.2.1 Package III
1.3 Construction Supervision……………………………………………………………………………………….……..
1.4 Progress of Environmental Safeguards ……………………………………....................................10
1.5 Summary of Environmental, Health and Safety plans …………………………………………..………
1.6 Project Supervision Consultants and Contractor………………………………………………………..…
1.7 Organizational Chart of the Consultant Staff……………………………………………………………….
1.7.1 Organization chart of the contractor MS- LIMAK- ZK…………………………………………………
1.8 Environmental Impact Assessment and NOC of EPA…………………………………………………....15
1.9 Project Data………………………………………………………………………………………………………………...17
2. PHYSICAL WORK PROGRESS OF CONSTRUCTION OF CONTRACTOR…………………………..18
3. STATUS OF ENVIRONMENTAL MANAGEMENT PLAN………………………………………………..21
3.1. Institutional Arrangement and Organization Chart for Environmental Safeguards
Implementation on project E 35 phase 1…………………………………………………………………………...21
3.2. Contractors Manpower……………………………………………………………………………………………...22
. . Co t acto s E uip e t’s …………………………………………………………………………………………..23
3.4. SSEMP………………………………………………………………………………………………………………………..24
3.5. ADB Monitoring Missions…………………………………………………………………………………………….24
3.6. Provision of Contractors Facilities………………………………………………………………………………..24
3.6.1. Contractors Construction Camp Site………………………………………………………………………………..24
Bi-Anual Report I&II
Page 4 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
3.6.2. Contractors Asphalt Plant………………………………………………………………………………………………….25
3.6.3 Concrete Batching Plants…………………………………………………………………………………………………...26
3.7. Daily Tool Box Talks ……………………………………………………………………………………………………………..26
3.8. Child Labour and Labour Laws……………………………………………………………………………………………….30
3.9. Occupational Workers Health and Safety……………………………………………………………………………...31
3.10. Traffic Management Plan…………………………………………………………………………………………………….32
3.10.1. General Traffic route of E35 for Vehicles movement of Limak and ZKB……………………………..32
3.11. Borrow Area use for Embankment Construction…………………………………………………………………..
3.12. Management of Disposal Areas…………………………………………………………………………………………….
3.13. Instrumental Monitoring………………………………………………………………………………………………………33
3.13.1 Ambient Air quality……………………………………………………………………………………………………………..
3.13.2 Surface Water quality……………………………………………………………………………………………………..
3.13.3 Drinking water quality…………………………………………………………………………………………………….
3.13.4 Noise level………………………………………………………………………………………………………………………
3.13.5 Soil Quality………………………………………………………………………………………………………………………
3.14. Grievance Redressal Mechanism…………………………………………………………………………………………..36
3.15. Monthly Environmental Reporting……………………………………………………………………………………..…
3.16. Penalty Against Non Co plia ce’s of EMP/SSEMP……………………………………………………………….36
4. Contractors Overall Performance against SSEMP/EMP………………………………………………………… 6
Attachments
Annexure 1: Pictorial views of the project …………………………………………………………………………… 8
Annexure 2: Site specific traffic management plan………………………………………………………………..
Bi-Anual Report I&II
Page 5 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
List of Tables
1.1. Shows details on Plans of Environment, Health and Safety……………………......11 1.2. Shows details on status of EPA conditions of NOC regarding EIA-E35…………...15 1.3. Project data……………………………………………………………………………….17 2.1. Monthly Progress of the construction activities……………………………………….18
3.1. Details of Contractors Manpower……………………………………………………….22
3.2. Details of Contractors Equipment’s/machinery………………………………………..23 3.3. Tool box talks for month of July 2016……………………………………………………26 3.4. Tool box Talks for month of August 2016……………………………………………….27 3.5. Tool box talks for month of September 2016……………………………………………28 3.6. Tool box Talks for month of October 2016………………………………………………28 3.7. Tool box Talks for month of November 2016…………………………………………...29 3.8. Tool box Talks for month of December 2016……………………………………………30 3.9. Details of first aid cases on Monthly basis……………………………………………...31 3.10. Details of PPES………………………………………………………………………...….31 3.11. Management of Borrow Areas……………………………………..…………………….33 3.12 Ambient Air Quality CO values at asphalt Plant……………………………….……….33 3.13 Ambient Air Quality values at Asphalt Plant…………………………………………….34 3.14 PM10 values at active construction site………………………………………………...34 3.15 Surface water values of Dor River……………………………………………………….34 3.16 Drinking water values……………………………………...……………………………..35 3.17 Noise Level Values……………………………………………………………………….36 3.18 Oil and Grease Values…………………………………………………….…………….36 3.19 Grievance Redressal Committee local members……………………………………..36
Bi-Anual Report I&II
Page 6 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
1. INTRODUCTION
This Bi-Annual Environmental Monitoring Report of Project “Construction of Hassanabdal (Burhan)-Havelian (Samlaila) Motorway is the section of E-35, Package
III (Km 39+611 to 58 + 711). This Bi-Annual EMR covers the status of
Contractor’s compliance with SSEMP/EMP, ADB and GOP Environmental Safeguard Policies/guideliness from July-December, 2016.
Package III of the project was supervised and monitored by the Engineer’s Representative including Environmental Specialist. Environmental Specialist of Consultant, contractor and NHA were mostly available on site. NHA Environment Team including Director, Assistant Directors Environment (Head Quarter) and ADB have regularly visited project site every month. Contractor overall status of EMP implementation is improved due to these regular monitoring visits and guidance provided by ADB, NHA and SC, s Environmental Specialist.
Several meetings were held during reporting period. On 30th August, 2016 ADB & NHA highest level of Mission visited E35 project. On 25th October 2016, ADB Senior Environment Safeguards Specialist miss Zehra visited package III for monitoring EMP/SSEMP implementation status. She raised issue of modifying the batching plant by elevated ramp with water channel connected to water settling chambers. ADB mission also visited Package III section on 8th December 2016. The main focus of the mission was to review “Country’s Safeguard Policy’’ on the Project.
During in the reporting period, environmental conditions of the project area remained satisfactory because LIMAK –JV-ZKB has tried to minimize the impacts of construction activities on the environment. The dust suppression is being done by sprinkling of water on service road, active working sites for embankment construction, Sub base, base construction and other construction activities. Solid waste is being disposed in dustbins placed at camp site and asphalt plant than TMA Haripur collected and disposed in Municipal Solid waste disposal site. The waste water is being collected and treated by using septic tanks/soakage pits at the base camp. Drainage system for rain water accumulated in the base camp has been solved by placing drainage pipes and ultimately flows into city main sewers. Utensils area is properly constructed and wastewater flows through pipes to sewers. LPG is used at camp site and asphalt plant for cooking purposes. Mess hygienic conditions are improved by regular cleaning.
New fire extinguishers are placed at camp sites and asphalt plant. Old empty fire extinguishers are refilled and labelled showing date of filling and expiry.
Additionally services of a domestic firm experienced in social and community
development is also being procured as a Social Safeguards Management Consultant
(SSMC). The main objective of engaging the SSMC is to support NHA and its field
offices in capacity development, preparation and implementation of safeguards
documents including internal monitoring and reporting. The Consultant will also verify
and update baseline information, maintain an MIS system and develop relevant tools,
Bi-Anual Report I&II
Page 7 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
protocols and systems which may be easily transferable for use by NHA in
safeguards management.
NHA expects both consultants SSMC and the design review and Supervisory
Consultant to coordinate between each other for efficient project management of E-
35-P-III.
1.1 Project Background
The existing Hassanabdal – Mansehra Road is an important part of the entire communication network of Khyber Pukhtunkhwa and Northern Areas which links with
Azad Jammu & Kashmir, Kaghan Valley and China via “Karakoram Highway (KKH)”. Existing Hassanabdal - Mansehra Road is a three-lane single carriageway road with
a width of 10.5 meters. Heavy traffic load has been observed on this road since last
ten years. To support sustained growth and increase competitiveness, Government
of Pakistan (GOP) has taken a strategic approach to the transportation and has
launched a major initiative to improve the trade and transport logistics chain in KPK
and Punjab. National Highway Authority (NHA) planned to construct Hassanabdal -
Mansehra Expressway (E-35) as a part of “National Trade Corridor (NTC)” Project. The proposed project is financed by the “Asian Development Bank (ADB)” and Government of Pakistan.
Package III: 17.01 Km (Sarai Saleh- Havelian)
This Express Highway project is entitled as “Hassanabdal – Havelian section of E-35 is a new highway alignment which starts from Burhan Interchange of Islamabad-
Peshawar Motorway (M-1) and finally alignment is ended at Havelian near Hazara
University of Hazara Campus. This Project will connect and facilitate three districts
namely Attock, Haripur and Abbottabad. It curves away to North West of existing N-
35 passing near Shin Gali and Jabbar and then curves back passing near Kuldarra,
Chhaprian & Kalu Pind and finally crosses existing N-35 at Jarikas. From here, it
again curves away to North-East of existing N-35 crossing Hattar and Khanpur Roads
at Kot Najeebullah and Chichian respectively. Finally, the alignment ends at Havelian
near Hazara University, Havelian Campus. Total length of the E-35 Phase-1
alignment (Hassanabdal - Havelian Section) is 56.06 Km with total Right of Way
(ROW) of 80m for first 2 Packages and 60m ROW for Package III.
Currently all packages have been commenced for construction. Express Highway (E-
35) the construction of Express Highway E35 Burhan to Havelian is a Project under
the “Pakistan National Trade Corridor Highway Investment Program–Tranche 2 (Hassanabdal–Havelian Section)” of the Government of Pakistan sponsored/ funded by the Asian Development Bank (ADB). The National Highway Authority is the Client
of the Project and the key responsible Government Department.
Bi-Anual Report I&II
Page 8 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
1.2 Project Description and Scope of Work and Conversion from 4 lanes to 6 lanes
Initially this Express Highway project was entitled as “Hassanabdal – Havelian section of E-35” was a new highway alignment which starts from Burhan Interchange of Islamabad-Peshawar Motorway (M-1) and finally alignment is ended at Havelian near
Hazara University Campus. On 29th April 2016, ADB has issued approval of 6 lanes
motorway. Right of way of project will be identical and 6 lanes will be constructed.
1.2.1 Package III:
Package-III comprises the construction of 6 lane carriage way from Sarai Saleh to Simlaila. The carriage way will be facilitated with inner shoulders with 1.00 M and outer sides 2.5 M width.
There are two interchanges included scope of work of package III to be constructed by contractor in total length of 17.01 Km from Sarai Saleh to Simlaila. These are Shah Maqsood Interchange at Km 4+618 and Simlaila Interchange at Km 16+600.
There are total 6 lanes of main carriage way with internal and outer shoulders width of 3 lanes is 10.5 M on each side.
There are about 08 bridges, 42 box culverts. 27 pipe culverts and 02 flyovers (Km 000+031), (Km16+258) and 10 underpasses with two walkways.
Formation of embankment, clearing and grubbing of 17.01 Km, removal of surplus material and filling of depression, removal of un-suitable materials ROW and disposal into proper approved site(Km 08+100(500)L/S).
Retaining walls, stone pitching, slope protection measures and guards railing are included in scope of work of package III. Earth work, removal of unsuitable materials from 60M ROW and borrowing of suitable materials.
Contractor will put the following sub grades, Sub Grade course, Aggregate base course, asphaltic base course and finally asphaltic wearing course. Road furniture including marking, installation of traffic board’s etc.
1.3 Construction Supervision
The Supervision Consultant while supervising construction works will make all necessary arrangements for quality control and implementation of the works. The task of the Consultant will include but not be limited to:
Give Notice to contractor to commence works. Assure submission and advise NHA on the adequacy of the Contractors’
insurance policies, performance bonds, and advance payment guarantees.
Review and approve the Contractor’s work programs and progress schedules ensuring that the Contractors have incorporated/followed the most effective and expeditious methodology of carrying out the works.
Provide advance advice to NHA concerning the Schedule of handing over of sites, and possible delays due to lack of possession with a view to assure that the Contractors are given Possession of Site in accordance
Bi-Anual Report I&II
Page 9 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
with the agreed work programs.
Assess construction equipment, plant and machinery requirements, and Contractors’ equipment.
Assure the receipt of and maintain as permanent records of all warranties. Check and approve the contractors' Working Drawings, Method
Statements and Temporary Works proposals.
Carry out any subsequent design changes, and expeditiously issue supplementary drawings, site instructions, variation orders and day work orders.
Review and approve the traffic management and safety plan.
Check the Contractors setting out including staking the right-of-way limits, centreline, and grade and confirm permanent monuments in the construction area.
Inspect quarries and borrow pits, and crushing plants, and order tests of materials and approve the sources of materials.
Monitor the Contractors' laboratory testing; evaluate the Portland cement concrete and bituminous mixture designs.
Assure quality of the works during construction, continuously inspect the soils and materials; construction operations and the works with regard to workmanship and approve or disapprove and certify the works.
Give notice to the Contractors of any defects and deficiencies, and issue instructions for the removal and substitution of the improper works.
Attend and make measurement and computation of quantities of the completed works.
Undertake project performance monitoring and evaluation.
Monitor and appraise progress of the works.
Issue monthly-consolidated progress reports on a format.
Check the Contractor’s periodic statement of the estimated value of work.
Issue the interim certificates to NHA for payment to the Contractors.
Assist with interpretation of the Contract Documents, explain and or reconcile any ambiguities and or discrepancies in the Contract Documents.
Advice NHA on need for effective liaison with local authorities, police, landowners, utility owners, the public and other organizations.
Carry out the duties related to environmental mitigation.
HIV/AIDs and Human Trafficking. Monitor that the contractors comply and carry out required actions as provided in the respective
Bi-Anual Report I&II
Page 10 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
contract documents.
Jointly inspect with NHA the completed civil works, and assist in formal taking over and review and approve or prepare "as built" drawings.
Inspect the completed works periodically during the defect liability period.
Establish a comprehensive system of maintaining site records. 1.4 Summary on Progress of Environmental Safeguards
Overall the progress against SSEMP/EMP is partially satisfactory in terms of providing
facilities (camp & asphalt Plant), traffic management, Health and Safety measures etc.
Further improvement is needed to maintain these facilities by keeping good
housekeeping on regular basis, providing adequate and job specific PPEs and ensuring
its regular usage by all staff and workers, delivering regular training to the staff/workers
and carrying out instrumental monitoring of environmental parameters on regular basis.
Limak-JV-ZKB ensures regular water sprinkling at active construction sites, access roads, sensitive receptors/residential areas and on areas where water sprinkling are required to avoid and minimize dust emissions.
Environmental Trainings have been delivered on site by Contractor and the Supervision Consultant Environmental Staff. Good EHS practices are followed by project implementers. Tool Box Talks, Fire Control practices, First aid facilities, use of good quality of PPE’s are in practice. Use of wood is strictly not allowed and controlled by placing LPG cylinders at camp site and asphalt plants for cooking purposes.
Analytical/Instrumental monitoring was carried out on 28thDecember, 2016 for measurement of environmental parameters i.e. air, water, noise and soil quality. The report is not yet submitted to date.
From July- December 2016, the main focus was to regular maintain the facilities and good housekeeping at sites, usage of PPEs on regular basis, control of wastewater from toilets, oil spillage at camp site, regular submission of contractor’s reports.
Regular water sprinkling were done to minimize dust emissions.
Regular HSE tool box talks (TBT) are in practice.
Personnel Protective equipment’s are provided to workers but still needs improvement by providing sufficient and specific PPEs to all workers and ensure its regular usage.
Dispensary is established at base camp and experienced paramedic staff is employed to provide treatment to patients/injuries at site for 24 hours.
Toilets Wastewater is disposed through septic tank/soakage pit and drainage water through pipes to city sewers at camp site. Septic tank and soakage pit is also provided at asphalt plant.
Solid waste is collected in dustbins; TMA vehicle collect the stored waste and disposed at TMA designated point (camp site).
Bi-Anual Report I&II
Page 11 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Bore water is used for drinking purposes and is fit for drinking as samples are tested and found no contamination (both at camp and asphalt plant).
Sufficient and Good quality of food is provided to all staff and workers.
Two kitchens and two messes are provided one each for senior and junior staff.(camp site)
Kitchen with mess is under construction at Asphalt Plant.
Mosque is provided at camp site.
Total 300 staff/workers are residing at camp site while 72 workers are residing at Batching and asphalt plant RD. 8+974.
Total one major accident with one fatality and 4 minor accidents occurred.
3970 first aid cases are registered at dispensary from July-December 2016.
Site specific Traffic Management Plans are prepared, prepared and implemented at sites. Appropriate signage boards are installed at various sites to control smooth flow of traffic and to avoid occurrence of accidental incidents.
1.5. Environmental, Health and Safety Plans
Contractor has prepared the following environmental, health and safety plans mentioned below in
table 1.1.
Table 1.1. shows details of the Plans regarding Environment, Health and Safety
Sr. No Names of Plans
Package III
1. Site Specific EMP Submitted and Approved.
2. Base Camp Layout Plan Submitted and approved.
3. Batching Plant Layout Plan
Locations for Concrete Batching Plants are approved at km 4+800 and km 8+974 respectively.
4. Asphalt Plant Layout plan (km 8+974)
Submitted and approved
5. Solid Waste Management Plan Covered in SSEMP
6. Wastewater Management Plan
Covered in SSEMP
7. Base Camp Drainage Layout Plan Covered in SSEMP
8. Borrow Area Management Plan Covered in SSEMP
9 Disposal Area Management Plan Not yet in use or proposed
10. General Traffic Management Plan Covered in SSEMP
11 Emergency Preparedness Plan Covered in SSEMP
Bi-Anual Report I&II
Page 12 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
1.6 Project Supervision Consultants and Contractor
The Lead Design Review & Construction Supervision Consultant is M/s DOHWA
Engineering Co. Ltd in association with M/s Engineering & Management Services (Pvt)
Ltd., Pakistan, and M/s Prime Engineering & Testing Consultants (Pvt) Ltd.
The Project’s Construction Contractor for Package III is LIMAK from Turkey in association with local (National) contractor M/s ZKB Construction. The Engineer had
issued commencement letter to contractor for construction work. Contractor for
Package-III is mobilized on 14th December 2015.
Bi-Anual Report I&II
Page 13 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
1.7 Organizational Chart of Consultant Staff
Bi-Anual Report I&II
Page 14 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
1.7.1 Organization chart of Contractor
Bi-Anual Report I&II
Page 15 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
1.8 Environmental Impact Assessment (EIA) and Environmental Approval from EPA
As per requirement of ADB Environmental Safeguard Policy Statement June 2009 and
Pakistan Environmental Protection Act (PEPA) 1997 and IEE and EIA Regulation 2000,
NHA has carried out Environmental Impact Assessment (EIA) and got approval from
ADB and Environmental Protection Agency (EPA). NHA has issued the Environmental
NOC/Approval, received from EPA for E-35 and Package III to the Engineer. The
Engineer’s Environmental Specialist has carefully reviewed this Environmental Approval and accordingly advising the Contractor for Compliance. There were twelve
conditions/terms/actions issued with approval for project proponent to implement and
follow-up during the construction and operational phase of the project. Details of terms
and conditions are as follows;
Table 1.2. shows status on EPA (KP) conditions of NOC regarding EIA of E35
Environmental Terms/Conditions of NOC of Project issued by EPA
Status of Compliance
The proponent will adopt all
precautionary and mitigation
measures identified in EIA
Report as well as any
unanticipated impacts during the
construction and operational
phase of project.
EIA approved for project is broadly followed on
project by project implementers. Site Specific
EMP is prepared, approved and under
implementation on package III. Main theme of
overall environmental safeguards is to protect
all workers from any hazardous and ensure
sustainable development.
The Proponent must submit bi-
annual monitoring compliance
report to EPA for review.
Since Project start, the Engineer has prepared
and submitted 03 Biannual Environmental
Monitoring reports to NHA and NHA onward
submitted to EPA KP.
Land acquisition and
resettlement plan must be
submitted to this Agency before
starting the physical work.
Land Acquisition and Resettlement Plan of
Package III is submitted to NHA and forwarded
to EPA for their information and record. LARP is
under implementation on this package.
Afforestation plan must be
provided to this Agency before
the physical work is started on
the site.
Afforestation plan will be finalized with NHA as
during construction period plantation or
preparing platform/area for plantation will be
affected due to work progress.
Bi-Anual Report I&II
Page 16 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Environmental Terms/Conditions of NOC of
Project issued by EPA
Status of Compliance
Proper retaining and breast wall
should be constructed where
needed.
This requirement is already included in scope
of work of project. Retaining and breast walls
will be constructed.
Camp site must be located at least 500 meters away from the residential area.
The Base Camp is not 500m away from the local residential area. It is around 200m to 300m away from the residential area. Mitigation measures are taken at site to avoid any inconvenience to locals and surrounding environment.
Regular sprinkling of water for the control of dust pollution during the construction phase must be maintained.
There are several water sprinklers on project for water sprinkling on project carriage way, access/approach roads, residential and sensitive receptors. Dust pollution issue is resolved to maximum level.
Proper culverts must be constructed for the rainy water.
Sufficient culverts (box & pipe) are included in scope of work and maximum culverts are completed and open for use.
Number of affected business, houses, trees, agricultural land/crops and their compensation plan must be provided to the Agency before starting the physical work.
The requirements of Environmental NOC issued by EPA. LARP has been sent to EPA.
(Task Completed)
Non-technical jobs must be provided to the local people in the area.
Already complied with requirements of Environmental approval (about 50% labors and some technical staff are from local project area.
Preference should be given to the local people in technical jobs
Contractor has appointed some technical staff from local community.
Bi-Anual Report I&II
Page 17 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
1.9. Project Data
Table 1.3. shows project data Details
Package III
Length in KMs 17.01
Flyovers 02
Bridges 08
Underpass 10 with two walk ways
Box Culverts 42 and pipe culverts 27.
General 6 Lane Fenced Expressway with 120 Km/hr speed design
Employer’s Representative
GM (E-35) NHA
Engineer/Team Leader
Seol, Jeong-Ho
Appointment of Engineer
1(9)/GM(E-35)/NHA/2015/05 dated 13th
February 2015
Consultant DOHWA ENGINEERING CO. LTD in
association with EMS & PRIME
ENGINEERING
Consultant’s Mobilization Date 4th February 2015 Design Review
Six (06) weeks from 4th February 2015 to
22nd March 2015
Construction Contracts Contractor Contract Price
Package III
M.s LIMAK-ZKB Associates JVs
Rs. 8,188,128,880
Construction Contract Commencement Date
March 5,2015
Construction Contract Completion Date
Defect Liability Period 365 days December 6,2017
Bi-Anual Report I&II
Page 18 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
2. PHYSICAL WORK PROGRESS OF CONSTRUCTION
Construction works were on going on culverts, bridges; asphalt base and earth work
is nearly to completion about 73% earth works completed during reporting period.
On Package III, planned work progress was 55.28% while achieved work progress is
58.55%. The contract is ahead of its planned target in terms of construction progress.
The following given below table 2.1 is showing details of Monthly Progress of the
Contractor during reporting period.
Table 2.1. Monthly Progress of The construction activities
Month Planned % Achieved %
December 2016 55.28
58.55
November 206 49.83
51.35
October 2016 44.37
44.53
September 2016 38.86
38.16
August 2016 33.36
34.58
July 2016 27.13
27.43
Bi-Anual Report I&II
Page 19 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
2.1. Project Location Map of Construction of Hassanabdal (Burhan)-Havelian (Samlaila) Expressway Section of E-35Figure 1 Project Location
Map
Bi-Anual Report I&II
Page 20 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Figure 2.2. Location of Project on Country Map
Bi-Anual Report I&II
Page 21 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
3. STATUS OF ENVIRONMENTAL MANAGEMENT
3.1. Institutional Arrangement and Organization Chart for Environmental
Safeguards Implementation on Project E35 Phase-I
Institutional arrangement for proper implementation of Environmental Safeguards is an
integral part of the project. National Highway Authority (NHA) and its Environment Unit
had carried out EIA, prepared EMP and got approval from ADB and EPA in October 2013.
EMP is incorporated in Contract of project E35 (package III), signed and accepted by
Contractor LIMAK and ZKB(JVs) for implementation including contractual provisions
(Clauses) such as 4.18-Protection of Environments, 4.8-Safety Procedures, 6.4- Labour
Law, 6.5- Working Hours, 6.6-Facilities for Staff and Labours, 6.7-Health and Safety, 6.6-
Facilities for Staff and Labours, 6.15-Measures against Insect and Pest Nuisance, & 6.21-
Child Labours and Specifications SP Item 706-Tamporary Traffic Control Management
LIMAK in association with local Contractor M/s ZKB were mobilized on 14th December
2015 with official letter for commencement of work at site.
As per requirement of approved EIA, EMP of project and Contract document; contractor has
appointed Environmental Specialist to implement, handle and manage environmental
compliance at site. The Engineer and his representatives (Environmental Specialist) are
supervising and monitoring the overall Physical and Environmental Performance of project
while Contractor is responsible for overall contract implementation at site as per agreed
contractual obligations with Client.
Page 22 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
3.2. Contractors Manpower
Contractor is having total 1909 following staff/workers on the entire package during
reporting period.
Table 3.1. shows details of Contractors Manpower
Sr.No Description No's
1 General Manager/ Project Manager 1
2 Contract Specialist 1
3 Deputy Project Manager 2
4 Planning Engineer 1
5 Site Engineers 10
6 Quantity Survey Staff 5
7 Technical Staff 22
8 Trainee Engineers 20
9 Admin Staff 8
10 Account Staff 8
11 Survey Staff 60
12 Environmental / Safety Staff 6
13 Office Staff 7
14 Laboratory Staff 25
15 Mechanical Staff 47
16 Machinery Operators & Helpers /HTV Driver & Helpers 504
17 LTV Driver 35
18 Store Staff 9
19 Munshi staff 8
20 Batching Plant Staff 17
21 Asphalt Plant Staff 6
22 Agg. / Asphalt Paving Staff 50
23 Steel Yard Staff 7
24 Mess Staff 30
25 General Staff 20
26 Skilled Labour 400
27
Unskilled Labour 600
Total 1909
Page 23 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
3.3. Contractors Equipment’s/Machinery
Contractor is having the following given equipment’s/machinery on the site during reporting period.
Table 3.2. shows details of Contractors Equipment’s/Machinery
Sr.No Machine Type Quantity
1 Grader 18
2 Cement Bulker 8
3 Trailer Low Bed 3
4 Rollers 26
5 Water Bowsers 13
6 Cranes 8
7 Concrete Batch Plant 4
8 Asphalt Plant 1
9 Crusher Plant 2
10 Paver Machine 6
11 Tandem Roller 6
12 PTR 4
13 Concrete Pump 6
14 Transit Mixer 18
15 Loaders 12
16 Excavators 34
17 LT. Vehicles 48
18 Tower Light 8
19 Generator 16
20 Peter Engine 12
21 Mobile Diesel Tanker 3
22 Tractors with Trolleys 55
23 Dumper 85
24 Dumper (1200 CFT) 24
25 Auger Machine 6
26 Dozer 8
27 Tyre Machine 2
28 Welding Plant 5
29 Percussion Machine 27
30 Girder Launching Machine set 3
Total 471
3.4. Site Specific EMP (SSEMP)
SSEMP is prepared by contractor and approved by NHA and ADB. Contractor is contractually bound to follow and implement EMP/SSEMP during construction phase of the package. Overall status of Contractors SSEMP/EMP is partially satisfactory. Environmental
Page 24 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Specialist Mr Shaukat Zaman is hired at site to ensure project compliance with SSEMP/EMP. 3.5. ADB Missions On 30th August, 2016 ADB & NHA highest level of Mission visited E35 project. ADB Mission
visited Package III on 25th October 2016 & 8th December 2016. On 25th October 2016,
Madam Zehra, Senior Environmental Specialist of ADB visited package III for monitoring of
Environmental Safeguards. Madam Zehra had raised issue of modifying the concrete
batching plants to avoid wastewater flow on the ground.
ADB last recent mission visit was on 8th December 2016 on package III. The main focus
was to review “Country’s Safeguard Policy” at Project (Environment and Social aspects).
3.6. Provision of Facilities 3.6.1. Contractor Construction Camp site
Contractor has established camp site at RD 3+500. Contractor has constructed offices,
main store, workers accommodations, workshop, two kitchens along two messes and
steel yard. First Aid facilities are also provided at Camp site. Contractor has established
a dispensary with paramedical staff; fulltime available at camp. Adequate and relevant
First aid medicines/bandages are provided at dispensary. Ground water is used as
drinking water. Water purifier has been installed to make the drinking water safer for
drinking. Good quality and adequate food is provided to all staff and workers.
All type of solid steel scraps from steel yard and work shop are collected in specifically
marked bins and is shifted to scrap yard. The scrap is stored and sold in market when
required. Kitchen solid waste and office solid wastes are collected in similar manner and
sent to solid waste collection point (Dustbins placed at various points) .Ultimately TMA on
weekly basis collect the solid waste for final disposal at Government designated places. As
far as the matter of collection of used oil is concerned it is being collected in fuel spill trays
from the motor workshop and shifted to liquid waste collection point on daily basis where
these are stored in drums properly covered with shed and ultimately sold out to oil dealer on
quarterly basis or whenever required.
Waste Water Generation and Treatment as per requirement of EIA and SSEMP is
carried out at Base Camp. Contractor has constructed Septic Tanks, Soakage pit and
retention small manholes system. Toilets/washrooms waste water is treated through
septic/soakage pit. The wastewater of kitchen (washing utensils) and rain water goes
through pipes laid by Contractor at camp site and ultimately final disposing into city
sewers.
Camp is fenced and security check post is available at entrance. Currently about 300
Staff and workers are residing in this camp. The kitchen, dining halls and residential of
senior staff and labour staff are properly protected from flies and mosquitoes and by
Page 25 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
providing steel gaze on windows while majority of sub-contractors workers are residing
in Tents along DOR river. Basic facilities like toilets, kitchen, and washrooms are not
available at site. Water for drinking is used from nearby available sources.
Emergency contact numbers, 25 numbers of fire extinguishers and 06 sand buckets are
provided at camp offices, fuelling point, workshop main store etc. Mosque is also
constructed at the camp for staff and workers prayers. Workshop area for vehicle
maintenance is kept paved to avoid soil contamination. Oil storage area is also paved
and covered with shed. Generator is also provided at site.
Environmental Education and Awareness about safety measures and good
housekeeping at steel yard, store area, oil/chemical storage area, and kitchen site are
done. Overall the conditions of camp site are in compliance with SSEMP and are
satisfactory.
3.6.2. Contractors Asphalt Plant at RD 8+974
The detailed plan and location of asphalt plant is approved. Contractors asphalt plant is
located near DOR River at RD 8+974 along with ROW of E35, village Akhoon Bandi. It is
about 200 m from river and more than 300 from residential area but all houses are at back
of mountain. Total 40 Kanals of land is leased by contractor. Normally wind direction is
blowing from West to East at day time and East to West at night time.
Local access road of Akhoon Bandi is available for transportation of small LTV but a narrow bridge on River Dor is located therefore Contractor is using own constructed services/approach road for supply of material etc.
Page 26 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Total 72 staff/workers are residing at site. Ground water (bore) is provided at site for
availability of drinking water and other water use of construction purposes. Electricity is
provided by generator.
Residential rooms with attached toilets are constructed. Septic tank, soakage pit and
small main holes are constructed for toilets/washroom wastewater treatment. Additional
washrooms, kitchen along mess and mosque are under construction. Soakage pit is
constructed for wastewater treatment of kitchen.
Asphalt plant is installed and wet scrubbers are constructed to minimize dust emissions.
Oil/bitumen is stored in tanks. Total 14 Fire extinguishers of 6 KGs are placed at site
while demand for 20 kg fire extinguishers is in process. First aid kit is available at site.
The area is still not fenced and levelled. Proper labelling is to be done. Asphalt plant is
operational from mid of December 2016.
3.6.3 Concrete Batching Plant
Two concrete batching plants are installed at RD 4+850 and RD 8+974. Both plant
locations are approved. Both are operational during reporting period. The bitumen/oil is
stored in drums. The ramp is paved at both concrete batching plants. Total 6 fire
extinguishers are placed on each concrete batching plant.
3.7. Tool Box Talks and Training Sessions
Contractor and Consultant had jointly arranged different training sessions on site for
labours and staff. Tool Box Talks/Meetings have been carried out by Contractor
Environment staff and HSE Team.
Regular tool box talks are in practice by contractor’s Environmental Specialist, Safety officer and Assistant; they are involved in delivery of daily tool box talks for labours,
workers and staff. Record is maintained and reflected in report. TBT are mostly given on
housekeeping, use of PPEs, Storage and handling of oil/chemicals, use of fire
extinguishers, good practices at site, disposal area management, first aid, proper use of
equipment’s, awareness about health, safety and environmental issues, etc.
Table 3.3. shows details of Tool Box Talks for month of July 2016
Sr. No
Date
Topic
Location
KM
No of Attendants
1 1/7/2016 slip, trip and fall Active sites 15
2 4/7/2016 Driving, PPEs, speed limit controls Main camp 11
3 9/7/2016 Management Of Heavy Equipment Main store 6
4 12/7/2016 Safety measures Active sites 12
Page 27 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Sr. No
Date
Topic
Location
KM
No of Attendants
5 16/7/2016 Usage of Fire fighting techniques Main camp 10
6 18/7/2016 First aid Practices 3+500 12
7 23/7/2016 Usage of PPEs, safety measures Active sites 14
8 25/7/2016 Awareness about cleanliness’ and good housekeeping
4+850 6
Table 3.4. Shows TBT for month of August 2016
Sr. No
Date
Topic
Location
KM
No of Attendants
1 5/8/2016 Electrical hazard 3+850 8
2 7/8/2016 slip, trip and fall Active sites 15
3 9/08/2016 handling flammable liquid Main camp and sub camp
19
4 12/8/2016 Usage of Fire fighting techniques Main camp and sub camp
10
5 15/08/2016 Health and Safety Active sites 22
6 19/08/2016 First aid Practices Active sites 9
7 24/08/2016 Awareness about cleanliness’ and good housekeeping
Main camp (kitchen)
5
8 27/08/2016 Usage of PPEs, safety measures Active sites 18
Page 28 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Table 3.5. shows details of Tool Box Talks for month of September 2016
Sr. No
Date
Topic
Location
KM
No of Attendants
1 1/9/2016 flammable chemical fire prevention Main camp and sub camp 15
2 4/9/2016 Safe driving Active sites 12
3 9/9/2016 A flood of danger 5+00 10
4 12/9/2016 slip, trip and fall Active sites 9
5 16/9/2016 Driving, PPEs, speed limit controls Active sites 25
6 18/9/2016 Management Of Heavy Equipment Main store 7
7 23/9/2016 Safety measures 11+200 10
8 25/9/2016 Usage of Fire fighting techniques Main camp and sub camp 14
Table 3.6. show details of Tool Box Talks for month of October 2016
Sr. No
Date
Topic
Location
KM
No of Attendants
1 03/10/2016 Storage and Handling of oil/chemicals
3+050 06
2 04/10/2016 Solid Waste Management 3+050 04
3 07/10/2016 Good Practices in Kitchen 3+050 07
Page 29 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Sr. No
Date
Topic
Location
KM
No of Attendants
4 10/10/2016 Management of workshop area 3+050 08
5 13/10/2016 PPEs, Steel work, welding 3+050 10
6 17/10/2016 Handling and storage of Pol/bitumen
8+974 04
7 19/10/2016 Health and Safety 8+974 03
8 22/10/2016 Batching plant management 8+974 06
9 27/10/2016 Health and safety 11+260 07
10 31/10/2016 Emergency Response preparedness
3+050 08
Table 3.7. show details of Tool Box Talks for month of November 2016
Sr. No
Date
Topic
Location
KM
No of Attendants
1 01/11/2016 Driving, PPEs, speed limit controls 2+000 08
2 04/11/2016 Management Of Heavy Equipment 2+240 06
3 09/11/2016 Safety measures Active sites 12
4 12/11/2016 Usage of Fire fighting techniques 3+050 08
5 16/11/2016 Health and Safety Active sites 08
6 18/11/2016 First aid Practices 3+050 12
7 23/11/2016 Awareness about cleanliness’ and good housekeeping
3+050 14
8 25/11/2016 Usage of PPEs, safety measures 4+850 06
Page 30 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Table 3.8. show details of Tool Box talks for month of December 2016
Sr. No
Date
Topic
Location
KM
No of Attendants
1 3/12/2016 Electrical hazard 3+500 8
2 6/12/2016 cold stress Active sites 6
3 8/12/2016 ladder inspection and safety All bridges 12
4 11/12/2016 flammable chemical fire prevention(asphalt plant)
Asphalt (8+975) 8
5 15/12/2016 winter driving All camp 12
6 19/12/2016 A flood of danger 5+000 15
7 23/12/2016 slip, trip and fall Active sites 14
8 26/12/2016 handling flammable liquid 4+850 6
9 28/12/2016 Effect of co2,co etc on human health and environment
Asphalt (8+975) 14
3.8. Child Labour and Labour Law
Child Labour and Labour Law of Pakistani are incorporated in contract and under
implementation on project. It is strictly and strongly instructed to contractors that as per
contractual provision no labour with less than 18 years will be involved in construction
work or hazardous work site. No child as labour is noticed and involved on this project.
3.9. Occupational Workers Health and Safety
Workers health and safety measures are mandatory part of the contract. Total 744
workers/staff are working on the entire package. Therefore ZKB hired Mr Aqeel as
health and safety officer who is responsible to ensure safe and healthy environment for
all staff and workers at site. Contractor has provided first aid facilities at camp by
providing dispensary with sufficient medicines/bandages and experienced paramedic
staff available for 24 hours. Total 20 numbers of First aid kits are provided and available
at site with the site in charges. Total 4326 first aid cases are registered during reporting
period at dispensary, camp site RD 3+500.
Page 31 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Table 3.9. shows details of first aid cases on monthly basis
Month First Aid Cases
July 2016 790
August 2016 750
September 2016 720
October 2016 580
November 2016 740
December 2016 746
Total 4326
Contractor has provided Personal Protective Equipment (PPEs) to maximum labour at steel yard, labours on site at active construction sites. Contractor purchased more PPEs to overcome shortage of PPEs. Workers safety harnesses are provided to few workers. Contractor is advised for provision of safety measures to all workers working at height. Contractor has to improve conditions by providing adequate and job specific PPEs to all staff/workers and strictly ensure its usage on regular basis. Fire fighting equipment’s like sand buckets and fire extinguishers are provided at camp site, asphalt plant and batching plant to avoid or minimize risk in case of any occurrence of fire hazards. Some new fire extinguishers are provided while old empty fire extinguishers are refilled.
Table 3.10. shows details of PPEs
Type of PPE Quantity
Yellow Helmet 500
White Helmet 200
Orange Jackets 500
Green jackets 300
Safety Shoes with socks 379
Ear plug 100
Welding screens 10
Gloves 1000
Safety Harness 30
Face mask 1000 packets
Chemical Mask 50
Dust Mask 300
Fire Extinguishers 51
Further Contractor is advised to ensure measures of controlling insects and pests and
associated diseases with such as malarial and dengue etc. under contract clause 6.15
provision.
In reporting period there was one major accident occurred at RD 9+777 dated 11th
November, 2016 in which one worker was died; as steel bars collapsed and worker was
trapped for two hours in these steel bars. The death body was taken to his village
Page 32 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Muzzafar Garh by Contractor for funeral arrangements. Total 4 minor injuries occurred
during reporting period (2 in July and 2 in September 2016).
3.10. Traffic Management (Item 706 & 712)
Traffic Management Plans are prepared, approved and implemented according to SSEMP
requirements in collaboration with Supervision Consultant. These plans are documented
for record purpose. Details of some of the SSTMP prepared and implemented is as
follows;
Generally about 16 critical crossings including 07 intersections have been identified on
Package III, from RD 000+000 to RD 10+200, out of which seven (07) crossings are
critical, as mentioned below:
1. Intersection of Rehana road and service road (RD 000+000-SSTMP-1). 2. Crossing at Bandi Sher khan road and service road (RD 2+162 SSTMP-2). 3. Intersection of road and service road (RD03+983, SSTMP-3). 4. Intersection of E-35 and N-35, Haripur-Abbottabad road (RD 03+650- railway
crossing, SSTMP-4). 5. Intersection of E-35 and N-35,Haripur –Abbottabad road (RD 03+750-GT road,
STMP-5) 6. Intersection of E-35 and N-35(Haripur –Abbottabad road (RD,06+904,SSTMP-6) 7. Intersection of Akhun Bandi and GT road, RD 08+050
(See details about Traffic Management Plans as Annexure II)
3.10.1. General Traffic route of E-35 for vehicle movement of LIMAK-JV-ZKB
For Traffic Management the contractor has installed different sign boards such as speed
limit, speed control and warning boards etc.
Generally more than 150 sign boards have been installed during the reporting period; others
are New Gersy barriers, warning tapes, red /yellow reflective tapes and red color steel drums
pasted with reflective tapes at various locations for night vision. Contractor has also placed
various sign boards for guidance /instructions of company drivers.
3.11. Borrow Areas use for Construction of Embankments
Contractor has completed most section of embankment construction and materials are
borrowed from borrow areas. Material quality tests of about 04 borrow areas have been
carried out by Material Engineers and other representatives including Consultants,
Contractor and NHA Officials. Suitable materials are utilized by contractor from these borrow
areas currently only 02 borrow areas are operative .The contractor will restore all borrow
areas as per SSEMP Plan after the completion of project. Agreements between borrow
areas owners and the contractor has already been signed.
Page 33 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Table 3.11. shows details of Borrow Areas
Sr. No.
Location Side Area in Kanal
Open/Closed Distance From ROW
1 RD 0+800 R/S 100 Closed 700 meter 2 RD 2+900 L/S 70 Closed 300 meter 3 RD 5+000 L/S 50 Open 200 meter 4 RD 8+900 L/S 100 Open 500 meter
3.12. Management of Disposal Areas
Contractor has not utilized or proposed any disposal area during reporting period. 3.13. Instrumental Monitoring of Environmental Parameters As per EMP/SSEMP, Contractor has to carry analytical monitoring on quarterly basis for noise, drinking water and air emissions while surface water is on monthly basis. ZKB last monitoring of environmental parameters was carried out on 28 December 2016 for measuring concentration of air, water, noise quality and soil quality. 3.13.1. Ambient Air Monitoring
Ambient air monitoring for concentration of CO, NO2, SO2 and PM10, were measured at
asphalt plant to get an overview of the air quality while Pm10 measurement was carried along active construction site RD 8+120. Results shows that all measured values of environmental parameters are below and within permissible limits (NEQS). Table 3.12 shows values for ambient air emissions of CO at Asphalt Plant
S. N
Time CO
Hours mg/m3
13:00 1.5
14:00 1.8 15:00 2.0
16:00 1.9
17:00 1.8
18:00 1.7 19:00 1.6
20:00 1.8
Average Concentration 1.76
NEQS Limits 10
Page 34 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Table 3.13 shows values of ambient air emissions at Asphalt Plant Rd 8+974 Parameters Unit Duration LDL Average
concentration NEQS Limits
Nitrogen Dioxide (NO2)
3 µg/m
02 hours
0.01 < 0.01
80 µg/m3 for 24 hours
Sulphur Dioxide (SO2)
3 (μg/ m )
02 hours 0.01 < 0.01 120 µg/m3 for 24 hours
Carbon monoxide
(mg/m3)
02 hours 1.00 1.76 5
(mg/m3)for 8 hours
Particulate matter (PM10)
3 (µg/m )
02 hours 1.00 143.84 150 µg/m3 for 24 hours
Table 3.14 showing Particulate Matter values at active construction site RD 8+120 Parameter Location Unit Results NEQS Limit PM10 8+120 (Road
side
3 µg/m
148.4 150
3.13.2. Surface Water Quality A sample was taken from DOR river where vehicles crossing through river. The sample is collected from upstream and downstream side. Table 3.15 shows values for surface water sample at Dor River Parameter Unit Up Stream
Down stream
PH Mg/L
7.85
7.98
Total hardness Mg/L
200
200
Total dissolved Solids (TDS)
Mg/L
271
271
Nitrate Mg/L
12.61
13.00
Chloride Mg/L
17.36
15.43
Sodium(Na) Mg/L
6.0
6.32
3.13.3 Drinking Water Quality Three samples were taken for measuring drinking water quality. The samples were taken
Page 35 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
from asphalt plant (8+974), Camp (3+500) and Mosque (camp). Result shows that total coliform and Faecal streptococci Enterococci at camp drinking water is high than permissible limits. The water is unfit for drinking consumption as water having bacterial contamination. Contractor is advised to do treatment of water for drinking purposes to avoid diseases (water borne) Table 3.16 shows monitoring values of Drinking Water Parameters Unit Asphalt
Plant Camp Mosque Limits
PH 7.70 7.62 7.68 6.5-8.5 Turbidity NTU
Page 36 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Table 3.18 shows oil and grease values Parameter Unit LDL Test Result Grease and Oil Mg/kg 5.00 9.22
3.14. Grievance Reporting and Resolution
The Grievance Redressal Committees (GRCs) on package-III has continually
consulted the local residents all the month, and during their regular site inspections, to
know about their problems and issues arising from the construction activities. The
Committee is composed of the Environmental Specialist of Contractor, Admin manager
of Contractor, Environmental Specialist of Supervision Consultant, Highway or
Structure Engineers, Project Manager of Contractor and Environment Cell (AD
Environment) of NHA, Deputy Director of NHA and Local Community members. A
complaint register has been established for documenting the complaints at base camp
km 3+500; an Environmental Specialist is responsible for maintaining and updating the
register and forwards the issues to concerned staff for solving the issues. This register
is checked and updated for necessary mitigation actions by concerned staff of Contractor and
SC staff. Total 35 complaints are registered to date. 34 complaints are solved while one
complaint is pending due to non-provision of NOC by railway Department regarding RCC
pipeline under the culvert of railway track.
Table 3.19. shows details of Grievance Redressal Cell/Committee (GRC) local
members
Name
RD/Location Contact Number
Mr. Younas
48+700 0300-5608027
Mr. Malik Naveed Sarai Saleh (Donalia Stop)
0321-9961307
Mr. Zahid Rehman Donalia Stop 0300-5341494
3.15. Monthly Environmental Reporting Monthly Environmental Reports till November 2016 by Contractor is submitted to SC.
Sometimes the contractor is submitting reports late.
3.16. Penalty against SSEMP/EMP Non Compliances ZKB is penalize amount of Rs. 90,000 (Rs. 3000 per day) for month of November 2016 against repeatedly non-compliances of SSEMP regarding non usage of PPEs by workers, bad housekeeping at campsite and asphalt plant, not carrying Analytical monitoring of environmental parameters 4. Contractors Overall Performance against SSEMP/EMP
Page 37 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Contractors overall performance during reporting period regarding SSEMP/EMP compliances is partially satisfactory as contractor showed willingness towards SSEMP/EMP Implementation. The following EMP compliances on site are as follows:
Provided established camp with basic arrangements like rooms, washrooms/toilets, drinking water availability etc.
Provided wastewater system like septic tank, soakage pit, drainage/sewerage lines at camp site and asphalt plant.
Provided equipped dispensary with qualified and experienced paramedic staff available for 24 hours.
Providing good and adequate food to all staff and workers. Provided PPES to almost all workers/staff Regular delivering TBTS at site. Regular submissions of monthly reports on environment. Following the recommendations of SC and implement on ground. Carrying regular water sprinkling at site
Furthermore, contractor needs to improve the following EMP requirements:
Maintaining regular cleanliness/ housekeeping at facilities by collection of garbage in drums and disposal frequently at TMA site.
To avoid oil spillage. To ensure wearing of PPES on regular basis. To be vigilant on workers safety at work. To deliver trainings regarding good practices, housekeeping to all workers especially
subcontractors.
To conduct Instrumental Monitoring Regularly.
Page 38 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Annexure 1
Pictorial Views of the Project
Page 39 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Photo.1. Paved Oil Storage Area at Camp RD 3+500
Photo.2. Driver wearing PPES while driving Heavy Vehicles
Page 40 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Photo.3. PPES usage by drivers while driving at site
Photo.4. Workers Training at site
Page 41 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Photo.5. Water sprinkling at active construction site
Photo 6. Safety Bund wall of 10 feet is provided for safety of people living at downward side of the construction site
Page 42 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Photo. 7. Construction work is totally stopped in morning and afternoon at school RD
11+125 Nowshera (opening and closing time of the school under supervision of Contractors
safety staff
Page 43 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Photo. 8 Air emission testing at Asphalt Plant Photo.9. Noise level measuring at generator, Plant
Photo.11 Drinking water sample, camp
Photo.10. Noise level monitoring at asphalt Plant
Page 44 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Photo.11. Soil testing sample, camp
Annexure 2
Traffic Management Plans
Page 45 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Page 46 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)
Page 47 of 47 Bi- Annual Report July- December 2016
Package III (Sarai Saleh-Simlaila KM39.611-58+711)