PARAMETRICCOST
ESTIMATINGSPEAKER: OTTORINO MAGGIORE VAN BEEST - PMP®
SAN DONATO MIL.SE - APRIL 9, 2010
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 1
TABLE OF CONTENTS
PARA... WHAT? PARA... WHEN? PARA... WHY? PARA... START!
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 2
PARA... WHAT?
PMI PMBOK
CHAPTER 7 - PROJECT COST MANAGEMENT
PARA 7.1 - ESTIMATE COSTS
SUB-PARA 7.1.2 - ESTIMATE COSTS: TOOLS AND TECHNIQUES
POINT 7.1.2.3 - PARAMETRIC ESTIMATING (PAGE 172)
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 3
PARAMETRIC ESTIMATING USES A STATISTICAL RELATIONSHIP BETWEEN HISTORICAL DATA AND OTHER VARIABLES (E.G. SQUARE FOOTAGE IN CONSTRUCTION) TO CALCULATE AN ESTIMATE FOR ACTIVITY PARAMETERS, SUCH AS COST, BUDGET AND DURATION. THIS TECHNIQUE CAN PRODUCE HIGHER LEVELS OF ACCURACY DEPENDING UPON THE SOPHISTICATION AND UNDERLYING DATA BUILT INTO THE MODEL. PARAMETRIC COST ESTIMATES CAN BE APPLIED TO A TOTAL PROJECT OR TO SEGMENTS OF A PROJECT, IN CONJUNCTION WITH OTHER ESTIMATING METHODS.
PARA... WHAT?
PARAMETRIC COST ESTIMATING (PCE) = STATISTICAL OR STOCHASTIC COST ESTIMATE
PARAMETER = THE COST DRIVER(S)
COST ESTIMATING RELATIONSHIP (CER):
COST-TO-COST: ANCILLARIES F(MAIN ITEM)...
COST-TO-NO-COST: COST F(WEIGHT, MATERIAL, POWER, FLOW RATE, VOLUME, SURFACE, LENGHT, DWS. N°, LINES OF CODE, ...)
GENERAL FORM OF CER: Y = F (X)
F: FUNCTIONAL RELATIONSHIPX: INDEPENDENT VARIABLE OR PARAMETER
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING
4
PARA... WHAT?
TYPICAL CURVES USED FOR CERS:
LINEAR
SEGMENTED LINEAR
POLYNOMIAL
POWER LAW
LOGARITHMIC
EXPONENTIAL
RATIONAL
POWER SERIES
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 5
PARA... WHEN?
TIME & PROJECT DETAILS
ANALOGUS ESTIMATING
AACEI - RP N° 17R-97
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING
FOR ENGINEERING & CONSTRUCTION PROJECTS
6
PARA... WHY?
CAN BE ACCURATE AS DEFINITIVE COST ESTIMATES
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 7
PARA... WHY?
IF YOUR BOSS TELLS YOU: “WE NEED THE PROJECT COST ESTIMATE BY TOMORROW”
YOU...
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 8
PARA... WHY?
PARAMETRIC COST ESTIMATING - TOP BENEFITS:
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 9
CONSIDERABLY REDUCING COST & TIME CYCLE FOR PROPOSAL PREPARATION, EVALUATION AND NEGOTIATION
ABOVE BENEFITS CAN BE ACHIEVED WHILE MAINTAINING OR IMPROVING THE QUALITY OF THE ESTIMATES PRODUCED
COST AND CICLE TIME SAVINGS UP TO 80%
PARA... WHY?
PARAMETRIC COST ESTIMATING - MAIN ROADBLOCKS:
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 10
CULTURAL RESISTANCE
SIGNIFICANT INITIAL INVESTMENT
LIMITED GUIDANCE HOW TO MANAGE PROPOSALS BASED ON PCE
PARA... WHY?
PARAMETRIC COST ESTIMATING - OBJECTIVES:
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 11
PRODUCTION OF MORE RELIABLE ESTIMATES
SHORTER TIME REQUIRED
BETTER DATA UNDERSTANDING
EASIER TO COMPUTE CONCEPTUAL DESIGNS
NO OTHER MEANS TO ESTIMATE EARLY COSTING
BILL OF MATERIAL IS NOT REQUIRED
MUCH EASIER TO HANDLE SCOPE, TECHNICAL AND PERFORMANCE CHANGES
BETTER RISK MODELLING AND UNDERSTANDING
PARA... WHY?
PARAMETRIC COST ESTIMATING - USE OF OUTPUTS:
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 12
PROPOSAL PRICING
ROUGH ESTIMATES
ECONOMIC STUDIES
ACTIVE PROJECT MANAGEMENT - SUPPORTS EARNED VALUE
RISK ANALYSIS
PARA... OWNER-CONTRACTOR...?
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 13
OWNER CONTRACTOR
screening or feasibility
stochastic or judgement
concept study or feasibility
primarly stochastic
budget, authorization, or
control
mixed, but primarly
stochastic
control or / bid / tender
primarly deterministic
check estimate or bid / tender
deterministic
POSSIBLE COMMON
UNDERSTANDING&
INVESTMENTS
PARA... FORMULA?
EXAMPLES: COST CAPACITY FORMULA
INDUSTRIAL PLANTS
C2 = C1 (Q2/Q1)K
LOG C2 = LOG C1 - K LOG Q1 + K LOG Q2
Y = A + K X
0.2 ≤ KAVERAGE = 0.6
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 14
LOG C
LOG Q
COMMERCIAL JET AIRPLANES
LOG C = F (LOG MAX TAKE-OFF WEIGHT) K = 0.85
LOG C = F (LOG NUMBER OF SEATS) K = 1.10
LOG C = F (LOG LENGHT) K = 1.90
PARA... FORMULA?EXAMPLES: PLANT EQUIPMENT
SHELL & TUBE HEAT EXCHANGER BEU TYPE - CARBON STEEL
CHE = EXP [A + B LN (W)]
4400 <W< 77400 KG7 <P< 85 BARGA = -2.910474B = 1.016550
R2 = 0.98
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 15
OIL INJECTED SCREW COMPRESSORS
CSC = EXP [A + BW + CW0.3]7 <W< 315 KW7 <P< 85 BARA = 2.193159320B = -0.01059287C = 0.450875824
R2 = 0.98
COST IN MILLION RIALSSTUDY BY MOHAMMED REZA SHABANI, REZA BEHRADI YEKTA
PARA... FORMULA?
ENTIRE PLANT
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 16
CE1 CE2 CE3 CE4 CE5 CE.. CEN
CET1 CET2 CET3 CET4 CET5 CET... CETN
OTHER FORMULAS OR FACTORS TO ACCOUNT FOR ANCILLARIES AND SURROUNDING PARTS
BASE COST = ∑I CETI
TOTAL COST = BASE COST + ESCALATION + CONTINGENCY
PARA... FORMULA?
EXAMPLE: OFFSHORE PLATFORM DECOMMISSIONING
PLUG AND ABANDONMENT
C1 = K0 + K1 CT + K2 JOB + K3 NW + K4 RIG + K5 WB + K6 SEASON + K7 WOW
CT = CONTRACT TYPE (=0 X RATE CONTRACT; = 1 TURNKEY CONTRACT)JOB = JOB SPECIFICATION (=0 TEMPORARY PLUG & ABANDON; =1 PERMANENT P&A)NW = NUMBER OF WELLSRIG = RIG DEPLOYMENT (=0 RIGLESS OPERAT.; =1 RIG OPERATION)WB = WORKBOAT DEPLOYMENT(=0 WORKBOAT NOT EMPLOYED; =1 WORKBOAT EMPLOYED)SEASON = SEASON WHEN THE WORK BEGANWOW = WAITING ON WEATHER (=NO WEATHER INTERRUPTION; =1 WEATHER INTERRUPTION)
STRUCTURE REMOVAL
C2 = H0 + H1 ST + H2 WD + H3 CF + H4 MW + H5 TW + H6 REEF + H7 TOW
ST = STRUCTURE TYPE (=0 CAISSON; =1 OTHERWISE)WD = WATER DEPHTCF = COMPLEXITY FACTOR = NC (NUMBER OF CONDUCTORS) + NPL (PIPELINE ATTACHMENTS) + NP (PILES) + NSP (SKIRT PILES ASSOCIATED WITH THE STRUCTURE)MW = MAXIMUM COMPONENT WEIGHTTW = TOTAL STRUCTURE WEIGHT (DECK + JACKET + EQUIPMENT + PILING AND CONDUCTORS)REEF = STRUCTURE DISPOSITION (=0 ON-SHORE REMOVAL; =1 ARTIFICIAL REEF DONATION)TOW = REEF REMOVAL METHOD (=0 TOPPLED-IN-PLACE OR PARTIALLY REMOVED; =1 TOWED TO SITE)
SITE CLEARANCE AND VERIFICATION
C3 = W0 + W1 AGE + H2 WD + H3 ND + H4 N
AGE = AGE YEARS UPON REMOVALWD = WATER DEPHTND = NUMBER OF DAYSN = NUMBER OF ITEMS COLLECTED
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 17
STUDY BY MARK J. KAISER
PARA... POWER FORMULA?
OPTIMIZATION STUDIES
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 18
FROM CONCEPT
TO ALTERNATIVE PROJECTS
ALTERNATIVES EVALUATED THROUGH COST ESTIMATES OF DIFFERENT “PRODUCT SCOPE”
PARA... FROM?
PARAMETRIC COST ESTIMATING - BUILDING CERS:
CERS ARE BUILT UPON STATISTICAL DATA ANALYSIS
SIGNIFICANCE OF CERS IS QUANTIFIED BY SEVERAL PARAMETERS; MOST IMPORTANT:
COEFFICIENT OF DETERMINATION R2 : REPRESENTS THE PORTION OF VARIATION IN THE INDEPENDENT VARIABLE THAT HAS BEEN EXPLAINED BY THE REGRESSION LINE
0≤R2≤1
R2 ACCEPTABLE ≥ 0.70
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 19
PARA... WHY?
PARAMETRIC COST ESTIMATING - ARE YOU SURE COST DRIVERS YOUR ORGANIZATION IS USING ARE CORRECT?
AN EXAMPLE - STUDY ON SAUDI ARABIAN RESIDENTIAL “VILLA”
COST = F (PARAMETER)
COST DRIVER = PERIMETER TO FLOOR RATIO = WALL AREA (M2) / PLAN AREA (M2)
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 20
TYPICAL:- GROSS FLOOR AREA ≅ 600 M2
- EXTERIOR DIMENSION ≅ 15 X 20 M- N° 2 FLOORS- STORY HEIGHT ≅ 3 M
TYPICAL
STUDY BY A.D. IBRAHIM, A.A. SHASH, S.A. ASSAF, O.A. JANNADI
PARA... CURVES?
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 21
PARAMETRIC COST ESTIMATING - BUILDING CERS:
CURVES USUALLY PROVIDE MORE CREDIBLE AND ACCURATE RELATIONSHIPS
LINEAR RELATIONSHIPS ARE VERY RARE AND OF LIMITED VALIDITY
PARA... PROCESS!
PARAMETRIC MODEL BUILDING PROCESS
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 22
MODELREQUIREMENTS
DATA SUPPORT MODEL REQUIREMENTS?
DATABASE DEVELOPMENT
NO
YES
MODELDEVELOPMENT
CALIBRATION AND VALIDATION?
NOT OK
UPDATE REQUIRED?
YES
OKDOCUMENTRESULTS
PARA... START!
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 23
DATABASE DEVELOPMENT - DATA NORMALIZATION
NORMALIZATION = DATA CORRECTION FROM DISSIMILARITIES, SUCH AS:
SOURCED FROM DIFFERENT ORGANIZATIONS
CHANGES IN ORGANIZATION
LEARNING / FORGETTING EFFECT
CURRENCY FLUCTUATION
ESCALATION
UNUSUAL EVENTS
ETC.
MAIN LIMITATION: UNRECORDERED DATA / INFO UNAVAILABILITY
PARA... START!
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 24
PARA... START!
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 25
PARA... START!
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 26
SOME IDEAS TO WORK ON
OWNER - CONTRACTOR RELATIONSHIP: PCES BASED BIDS✓ CONTRACT STRUCTURE✓ CONTRACT SCOPE AND PRICE
OWNER & CONTRACTOR COMMON INVESTMENTS✓ SHARE INFO & DATA✓ ESTABLISH COMMON TEAM✓ DEVELOP REAL PARTNERSHIP
...
PARA... START!
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 27
CONCLUSIONS
REQUIRES MANAGEMENT SUPPORT
NEEDS COMPANY CHAMPIONS
REQUIRED CONSTANT SELLING
CONSIDERABLE START-UP COST
TEAM REQUIRES TRAINING
REQUIRED CULTURE CHANGE
IMPLEMENTATION IS A CHALLENGING EFFORT
DATABASE DEV. AND DATA NORM. ARE THE MOST CHALLENGING EFFORTS
EFFORT: 95% DATABASE DEV. & DATA NORM., 5% CALIBRATION
REQUIRED PROJECT FULL UNDERSTANDING
PARA... START!
WWW.KEYST1.CH COPYRIGHT KEYST1 S.A. - ALL RIGHTS RESERVED - PARAMETRIC COST ESTIMATING 28
CONTACT:
OTTORINO MAGGIORE VAN BEEST
E-MAIL: [email protected]