Project update Hamilton Section PART OF THE WAIKATO EXPRESSWAY November 2015 The NZ Transport Agency, Waikato District Council and Hamilton City Council invites the community to an information day where staff will be available to provide more detail on the finalised road network design for the Resolution Drive Interchange and connecting roads. When: Tuesday 8th December 2015 Where: Horsham Down Community Hall Time: Anytime between 2pm and 7pm Save the Date - Horsham Downs Open Day 8 December Explore the Cambridge section of the Waikato Expressway by foot, bus or bike. Tuesday 15 December 2015 between 3pm and 8pm. Free parking beside the Victoria Road Interchange, access off Laurent Road. Displays, activities, food stalls and a free bus running in a circuit from the Victoria Road interchange along the Expressway with stops at the Northern and Southern Interchanges and at the Karapiro Gully Viaduct. For more details go to www.nzta.govt.nz/cambridge Save the Date - Cambridge Community Day Contract Awarded The NZ Transport Agency is pleased to announce that the consortia of Fletcher Construction, BECA, Higgins and Coffey (FBHC) has been awarded the contract to build the Hamilton section of the Waikato Expressway. The 21.8km Hamilton section will be built by an Alliance between the NZ Transport Agency and FBHC. Over the next 12 months the Alliance will complete the detailed design of the section and some enabling work to get ready for the start of construction in spring 2016. What does an alliance mean? The alliance model allows for more flexibility during the detailed design phase and means any cost savings or over runs that result from amendments to the project are shared by the contractor and the Transport Agency. While the detailed design for the project may differ from the specimen design prepared by the Transport Agency, the changes must still comply with the designation and resource consent conditions and meet the high safety and environmental standards the Transport Agency requires, otherwise variations will need to be obtained. This contract model was used on the Waikato Expressway for the construction of the Te Rapa section and differs from the ‘design and construct’ model used for the construction of the Ngaruawahia and Cambridge sections. What happens now? The Hamilton section is the largest and most complex section of the Expressway. The Alliance will start work on the detailed design and management plans required to enable work to start, and some enabling work will take place, including the relocation of Transpower lines. A Notice of Requirement and resource consent applications will also be prepared for the Resolution Drive connection to the Expressway and the Horsham Downs link.

PART OF THE WAIKATO EXPRESSWAY Project update · Project update. Hamilton Section. PART OF THE WAIKATO EXPRESSWAY. November 2015 The NZ Transport Agency, Waikato District Council

  • Upload
    vanlien

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

Project updateHamilton SectionPART OF THE WAIKATO EXPRESSWAY

November 2015

The NZ Transport Agency, Waikato District Council and Hamilton City Council invites the community to an information day where staff will be available to provide more detail on the finalised road network design for the Resolution Drive Interchange and connecting roads.

When: Tuesday 8th December 2015 Where: Horsham Down Community HallTime: Anytime between 2pm and 7pm

Save the Date - Horsham Downs Open Day

8December

Explore the Cambridge section of the Waikato Expressway by foot, bus or bike.

Tuesday 15 December 2015 between 3pm and 8pm.

Free parking beside the Victoria Road Interchange, access off Laurent Road.

Displays, activities, food stalls and a free bus running in a circuit from the Victoria Road interchange along the Expressway with stops at the Northern and Southern Interchanges and at the Karapiro Gully Viaduct.

For more details go to www.nzta.govt.nz/cambridge

Save the Date - Cambridge Community Day

Contract AwardedThe NZ Transport Agency is pleased to announce that the consortia of Fletcher Construction, BECA, Higgins and Coffey (FBHC) has been awarded the contract to build the Hamilton section of the Waikato Expressway.

The 21.8km Hamilton section will be built by an Alliance between the NZ Transport Agency and FBHC. Over the next 12 months the Alliance will complete the detailed design of the section and some enabling work to get ready for the start of construction in spring 2016.

What does an alliance mean?

The alliance model allows for more flexibility during the detailed design phase and means any cost savings or over runs that result from amendments to the project are shared by the contractor and the Transport Agency. While the detailed design for the project may differ from the specimen design prepared by the Transport Agency, the changes must still comply with the designation and resource consent conditions and meet the high safety and environmental standards

the Transport Agency requires, otherwise variations will need to be obtained. This contract model was used on the Waikato Expressway for the construction of the Te Rapa section and differs from the ‘design and construct’ model used for the construction of the Ngaruawahia and Cambridge sections.

What happens now?

The Hamilton section is the largest and most complex section of the Expressway. The Alliance will start work on the detailed design and management plans required to enable work to start, and some enabling work will take place, including the relocation of Transpower lines. A Notice of Requirement and resource consent applications will also be prepared for the Resolution Drive connection to the Expressway and the Horsham Downs link.

2 | Waikato Expressway Hamilton section | Project update | November 2015

Hamilton Section

Waikato Expressway | 3Hamilton section | Project update | November 2015

Horsham Downs /Resolution Drive Hamilton City Council and the Waikato District Council have now both passed resolutions supporting the planned connections to the Hamilton section at Horsham Downs.

The councils along with the Transport Agency have agreed the connections to the Expressway at Horsham Downs should include: • The extension of Resolution Drive

to meet the Expressway and a link across the Expressway to Horsham Downs Road

• A bridge over the Expressway, including a footpath, at Osborne Road

• Closing Kay Road west of Resolution Drive and extending Borman Road to meet Kay Road.

The decision has been made after extensive consultation with the community and ensures the Expressway connects to the local road network in a way that supports planned growth and development while also keeping the community connected.A Notice of Requirement and resource consent applications for the proposed works will be lodged early in 2016. This will be a publicly notified process and anyone can make a submission.

The current programme for the development and implementation of the Hamilton section is as follows:• November 2015:

Recommendation issued on Notice of Requirement for the SH26/Ruakura Rd/Lissette Rd Roundabout

• Early 2016: Notice of Requirement submitted for Resolution Drive connection to the Expressway and Horsham Downs Link

• November 2015 - March 2016: Preparation of detailed design and various management plans required as part of the designation and consent conditions, and to enable works to commence.

• Full construction due to commence late 2016, with completion targeted for 2020.

HAMILTON SECTION - WHAT HAPPENS NEXT?

4 | Waikato Expressway Hamilton section | Project update | November 2015

Expressway OverviewThe Hamilton section is part of the larger Waikato Expressway programme of work. The Waikato Expressway is one of the New Zealand Government’s seven Roads of National Significance for New Zealand.

Thames

Pukekohe

Tuakau

Meremere

Te Kauwhata

Rangiriri

Huntly

Taupiri

Ngaruawahia Morrinsville

Hamilton

Cambridge

Ohaupo

Pirongia

Raglan

Te Awamutu

WAIKATO RIVER

POKENO11.6km

HUNTLY15.2km

NGARUAWAHIA12.3km

HAMILTON21.8km

CAMBRIDGE16km

MERCER11.0km

OHINEWAI7.0km

TE RAPA7.3km

LONGSWAMP5.9km

RANGIRIRI4.8km

1

2

2

27

26

23

39

3

1

25

22

25

Hamilton urban area

Completed sectionsTerritorial authority boundary Existing state highwayOther roads

1B

TAMAHERE INTERCHANGE2.4km

Opened December 2013

Construction 2015-2020

Construction 2016-2020

Ahead of programme Possible completion

December 2015

Opened December 2012

Mainline opens 2016Entire project completed 2017

Construction 2016-2018

14-009 timeline

A hearing for the SH26/Ruakura Rd/Lissette Rd roundabout was held in October 2015 before an appointed commissioner. The commissioner’s recommendation in relation to the Notice of Requirement is likely to be issued in late November 2015. Changing the intersection from a “stop” controlled layout to a roundabout is to address safety issues associated with this part of the state highway network. Subject to a favourable commissioner’s recommendation, it is anticipated that construction of the roundabout will be undertaken by the Alliance as part of the overall construction of the Hamilton section.

TRISTRAM ST

LAKE RD

OSB

ORN

E RD

KAY RD

HORSHAM DOWNS RD

GO

RDO

NTO

N RD

PUKETAHA RD

GREENHILL RD

RUAKURA RD

RUAKURA RD

GA

LLOW

AY STW

AIRERE D

R

BOUNDARY RD

TRAM

WAY RD

WA

IRERE DR

FIFTH AVE

HOLLAND RD

TELEPHONE RD

WAIRERE DR

RIVER RD

RESOLU

TION

DR

TE RAPA

RD

POWELLS RD

MATANGI RD

MILL ST

HUKANUI RD

N.I.M

.T.R

E.C.M.T.R

GOOR RNBROEDV TIODNG ERD

0km 2km 4km

NOTEOverbridges carry traffic over the ExpresswayUnderbridges carry traffic under the Expressway

HAMILTON NORTHERN INTERCHANGE

WAIKATO EXPRESSWAY

GREENHILLINTERCHANGE

HAMILTONSOUTHERN

INTERCHANGE

EXISTINGTAMAHERE

INTERCHANGE

HORSHAM DOWNS RD OVERBRIDGE

GORDONTON RD OVERBRIDGE

PUKETAHA RD UNDERBRIDGE

KAY RD OVERBRIDGE

MANGAONUASTREAM BRIDGE

MANGAONESTREAM BRIDGE

EAST WESTLINK

TE RAPA SECTION

MATANGI RDOVERBRIDGE

RUAKURA INTERCHANGE

SUBJECT TO OBTAINING RMA APPROVAL

EXISTING STATE HIGHWAYS

NEW ROADS (HAMILTON SECTION)

PROPOSED BRIDGE

RAILWAY

RING ROAD

EXISTING ROADS

ROAD TO BE CLOSED

POTENTIAL FUTURE DEVELOPMENT (RUAKURA STRUCTURE PLAN)

RESOLUTION DR INTERCHANGE

SH26 ROUNDABOUT

NGARUAWAHIA SECTION

BORMAN RD

Follow us on facebookwww.facebook.com/waikatoexpressway

www.nzta.govt.nz/Hamilton

STATE HIGHWAY 26 ROUNDABOUT

NICOLA MARTIN Communications and Stakeholder Liaison NZ Transport Agency Telephone: 07 958 7260 Mobile: 027 292 8076 Email: [email protected]

OUR CONTACT DETAILS

This document is printed on environmentally-responsible paper manufactured using FSC-certified, mixed-source pulp harvested from sustainable well-managed forests and bleached using an elemental chlorine-free process.

DANA MCDONALD Hamilton Section Relationship Manager NZ Transport Agency Telephone: 079587246 Mobile: 0274738769 Email: [email protected]