Click here to load reader

PARTH REPORT

Embed Size (px)

Citation preview

L&T-MHI Turbine Generators

44

SUMMER INTERNSHIP REPORT(JUNE-JULY, 2013)ON

TIME STUDY AND EVALUATION ON PROCESS PARAMETERS FOR MACHINING OF HP PEDESTAL LOWER HALF

AT

L&T-MHI TURBINE GENERATORS PRIVATE LTD.HAZIRA, SURAT.

BY

PARTH GANDHITHIRD YEAR, MECHANICAL ENGINEERINGSARDAR VALLABHBHAI NATIONAL INSTITUTE TECHNOLOGYINTERNSHIP DURATION: JUNE 16, 2014-JULY 16, 2014

CONTENTSSr. No.TOPICPage No.

1Acknowledgement3

2About the company4-8

3Steam Turbines9-18

4Induction19-23

5PROJECT: Time Study And Evaluation Of Process Parameters

24-38

65S System39-42

7Kaizen43-45

ACKNOWLEDGEMENT

I am thankful to a lot of people for helping me in what has been an extraordinary venture, here at LMTG in the course of these four weeks. It has been a great leapfrog from the last of adolescence towards professionalism. Firstly, I would like to thank Mr. Aloke Sarkar, General Manager, Production Department at LMTG, for giving me an opportunity to be a part of this privileged company. He is an inspiration to one and all.I would like to extend my gratitude to my mentor Mr. Chetan Patil for their continued and uninterrupted guidance and valuable wisdom throughout my work period.I would fail in my duty if I dont thank Mr. Jigar Panchal, PPC Department, who has been extremely helpful and generously thoughtful throughout my journey at LMTG. His uncanny support made me feel a part of my new workplace since day one. I would also like to admit that I would not have been able to overcome the little problems faced by a newbie if it were not for him.Last but not the least a special thanks to all the operators, Nimesh Gangadiya and all, whose support and co-operation cannot be disregarded.

ABOUT THE COMPANY

Larsen & Toubro Limited is an Indian multinational conglomerate corporation headquartered in Mumbai, Maharashtra, India. The company has business interests in engineering, construction, manufacturing, information technology and financial services. L&T is Indias largest engineering and Construction Company, with a dominant presence in Indias infrastructure, power, hydrocarbon, machinery and railway related projects. It is one of the largest and most respected companies in Indias private sector. More than seven decades of a strong, customer focused approach and the continuous quest for world-class quality have enabled it to attain and sustain leadership in all its major lines of business. L&T has an international presence, with a global spread of offices.

L&T believes that progress must be achieved in harmony with the environment. A commitment to community welfare and environmental protection are an integral part of the corporate vision. In response to changing market dynamics, L&T has gone through a phased process of redefining its organization model that facilitates growth through greater levels of empowerment.

L&T-MHI Turbine Generators Private Limited, a JV between L&T Power & MHI of Japan, manufactures supercritical steam turbines of up to 1000 MW rating through a technology transfer agreement with Mitsubishi Electric Corporation, Japan. The company also manufactures generators to match the specified range. MHI products have the added advantages of ease in maintenance, reduction in vibration stresses and better performance in a corrosive environment. The JV also offers state-of-the-art facility for Generator Testing and High Speed Balancing.

MHI headquartered in Tokyo, Japan, is one the worlds leading heavy machinery manufacturers, with consolidated sales of 2590 billion yen in fiscal 2004. Its diverse line up of products and services encompasses shipbuilding, steel structures, power plants, chemical plants, steel plants, environment equipment, industrial & general machinery, aircraft, space rocketry and air conditioning systems.

This is a joint venture for setting up a manufacturing facility to supply supercritical turbines and generators which is further licensed in technology and technical assistance agreement for manufacture of supercritical generators between L&T MHI and MELCO (Mitsubishi Electric Corporation, Japan.

JV Agreement was signed on November 5, 2007 and it was locked in is for the term of 7 years. The technology license is in agreement for the next 20 years.

L&T VISION

L&T shall be a professionally managed Indian multinational, committed to total customer satisfaction and enhancing shareholder value. L&T-ites shall be innovative, entrepreneurial and empowered team, constantly creating value and attaining global benchmarks. L&T shall foster a culture of caring, trust and continuous learning while meeting expectations of employees, stakeholders and society.

L&T MISSION

We are in the business of design and manufacturing of hi-tech custom built, fabricated equipment/ vessels, system and related services.We serve process industries in Oil and Gas Refinery, Petrochemicals, Fertilizers and Chemicals, Power, Defense, Nuclear and Shipbuilding.We shall attain the Global leadership in these areas of business by pursuing opportunities in the international market. We shall achieve this through total employee involvement with emphasis on: Innovation, automation and continual improvement Cycle time and cost reduction Focused manufacturing Efficient working capital management Effective knowledge sharing and training Safety, health & environment friendly practicesWe shall ensure reliability and customer satisfaction with world-class quality products and services.

LMTG MISSION

To emerge as a market leader in the field of Design, Manufacture and Supply of Steam Turbines and Generators through continual improvement, employee involvement and respect for environment.

FACILITIES AT LMTG The plant, encompassing 70 acres of land at Hazira, is divided into a Production Shop, a Blade Shop, a Packaging facility and an Administrative Block among major establishments. Major Machine Tools Heavy Machines- 46 Medium Machines- 38 Major Equipment- 59 (CNC Cutting, 200T Press, Furnace ,Shot Blast etc.,) Generator Test Bed (1000 MW) High Speed Balancing ( 4500 rpm) Blade Manufacturing The Production Shop is divided into six sub-divisions along with a Main Store. The six sub-divisions are four Machine Shops and two Fabrication Shops, being listed from T1 to T4 and T5 to T6 respectively.

PRODUCTS AT LMTG

LMTG receives first contract in March 2010. The company manufactures tandem compounded steam turbines with the following arrangement: First company in India to produce super-critical turbines in-house. Produces 4000 MW barrier equipment in a year. Efficiency of a sub-critical turbine is around 38-40% whereas that of a super-critical turbine is around 42%. Ultra-super-critical turbines have the efficiency of 45%. Unit sizes ranging from 500 MW to 1000 MW. One 1000 MW turbine requires around 146,000 tons of coal per day which needs around 7 boogie-trains per day delivering it. Two 500 MW turbines more preferable over one 1000 MW turbine in case one shuts down, other still operates. The combined HP/IP turbine is applied to 500 MW, 600 MW and 800 MW while separated HP/IP is provided for 1000 MW ratings. 500 MW has one LP turbine while 600 MW has 1 or 2 depending on the temperature. 800 MW and 1000 MW have two sets of LP turbines.

Main steam pressure is 24.2 MPa and the temperature lies between 538C and 600C.

Steam parameters Main Steam Pressure 242 BarMain Steam Temp above 500 CReheat Temp around 593 C

STEAM TURBINE

A steam turbine is a mechanical device that converts the heat energy of steam to mechanical energy. This mechanical energy, in the form of rotary motion of the turbine is particularly suited to drive an electrical generator. The interior of a steam turbine comprises of several blades. One set of stationary blades are connected to the turbine casing and one set of rotating blades connected to the shaft. The sets of intermesh with minimum clearance, with the size and configuration of sets varying efficiently exploit the expansion of steam at each stage.In large power stations, the steam turbine is divided into three distinct power stages, the first being high pressure (HP), the second Intermediate pressure (IP) and the third low pressure(LP). Separate cylinders for IP and HP stage can be used or both the turbines can be housed in one casing and called HIP turbine. This combining is done mainly to reduce the axial thrust on the shaft. Other advantages include lesser rotor length and lesser components used. Steam turbines can be configured in many different ways. Several IP or LP turbines can be incorporated into one steam turbine. A single shaft or several shafts coupled together may be used.

CLASSIFICATION OF STEAM TURBINES

Application Industrial Utility Exhaust of Steam Condensing Back Pressure Number of cylinders Single Double Triple Arrangement of Cylinders Cross Compounded Tandem Compounded Design Principle Impulse Reaction Type of Governing Throttle Nozzle Speed Full Speed Half Speed

STEAM TURBINE & ITS WORKING PRINCIPLE

Steam Turbine is one of the principle equipment of a thermal power plant along with boiler, condenser and heaters which work together on closed liquid vapour cycle. Steam turbine is regarded as a prime mover which rotates the generator for producing electricity.

The driving force for rotation in turbine is generated by superheated steam supplied from boiler. The potential energy of superheated steam available in the form of pressure, temperature & heat is converted into kinetic energy in the row of fixed blades arranged circumferentially to form nozzles. The high velocity steam generated at the expense of pressure drop in nozzles passes through this row; the steam reverses its path which gives rise to change in momentum. This change develops driving force according to second law of Newton, which states that whenever there is change in momentum an impressed force is generated, which is proportional directly to rate of change of momentum. Since these blades are mounted on shaft, which is free to rotate, the developed force starts rotating the shaft.

A set of fixed blades forming nozzles and rotating blades mounted on shaft is called a stage of turbine. Depending upon steam condition and output; a number of such stages are envisaged in turbine. Aim is to have gradual pressure drop so as to reduce losses and abrupt changes. The torque produced by each stage gets added up and total is available at the coupling end to turn generator and produce electric power.

PICTORIAL VIEW OF A STEAM TURBINE

SUPERCRITICAL TECHNOLOGY

Supercritical technology has evolved over the past 30 years. Advancements in metallurgy and design concepts have made supercritical technology units extremely reliable and highly efficient. Modern supercritical technology is largely available in Japan and Europe for Boilers & Turbines ranging upto 1000 MW.The term "supercritical" refers to main steam operating conditions, being above the critical pressure of water (221.5 bars). The significance of the critical point is the difference in density between steam and water. Above the critical pressure there is no distinction between steam and water, i.e. above 221.5 bar, water is a fluid.If the steam pressure is greater than 275 bars, then conditions are Ultra Supercritical.

Supercritical steam cycle with one reheat.

a b: Condensate cycle up to Deaeratorc : Boiler feed pump dischargec d : Feed water heatingd e : Main steam generatione f: Expansion in turbinef g : Reheat steam generationg h : Expansion in turbine

In supercritical cycle, equipment is designed to operate above the critical pressure of water. Supercritical boilers are once-through where in the feed water enters the economizer and flows through one path and main steam exits the circuit. Typically current supercritical units operate at 242 bar main steam pressure, 565C main steam temperature and 593C reheat steam temperature.Advantages Of Modern Supercritical Technology

HIGHER EFFICIENCY: Supercritical steam conditions improve the turbine cycle heat rate significantly over sub-critical steam conditions. The extent of improvement depends on the main steam and reheat-steam temperature for the given supercritical pressure. A typical supercritical cycle having turbine throttle pressure of 242 bar with temperatures for main steam and reheat steam as 565C and 593C respectively, will improve station heat rate by more than 5%. This results in fuel savings to the extent of 5%. Overall supercritical power plant efficiency of 42% is achievable with current supercritical parameters. If the unit size is increased, both fuel cost and additional investment per MW reduces.

EMISSIONS: Improved heat rate results in 5% reduction in fuel consumption and hence 5% reduction in CO2emissions per MWh energy output. Supercritical technology based thermal power project is a potential candidate to avail the benefits under Clean Development Mechanism (CDM) established by United Nations Framework Convention on Climate Change (UNFCCC).

OPERATIONAL FLEXIBILITY: Supercritical technology units also offer flexibility of plant operation such as:

Shorter start-up times Faster load change flexibility and better temperature control Better efficiency even at part load due to variable pressure operation High reliability and availability of power plantMAIN COMPONENTS OF A STEAM TURBINE

Blades Turbine Casing Rotor Gland Seals Couplings Bearings Bearing Pedestals Stop & Control Valves Governing System Lubrication System Drain System Control & Instrumentation Turning Gear

Turbine Blades: Blades are the key component of turbine as conversion of energy to develop driving force takes place therein. The blades which form nozzles and are fixed are called stationary or guide blades. The blades mounted on rotor are called moving blades.

Turbine Casing: The guide blades of various stages are held in the stationary body called casing. It also acts as a cover for steam passage with connections for steam admission, exhaust and other flows.

Rotor: It holds the moving blades of various stages in the grooves machined in it.

Gland Seals: Since turbine casing and rotor are respectively stationary and rotating parts, there is bound to be clearance between the two at the ends. The steam tries to escape through these clearances causing working atmosphere non conducive in power station for working personnel. To minimize this leakage, gland seals are provided at the two ends of turbine.

Couplings: They connect the rotor s together and transmit the torque finally to generator for turning.

Bearings: For supporting the rotors at the two ends to enable them rotate freely bearings are provided. These bearings are journal bearings supplied with forced lubrication. Ball bearings are not suitable as they are not capable to take high loads. Bearing Pedestal: They support the bearings and house the lube oil piping and drain oil pipe work. They also enclose various instrumentation which monitors healthiness of turbine during operation.

Stop & Control Valves: Turbine does not run at full load at all the times. Its output is regulated by the electric grid it is connected. For producing power, matching to varying load demand, the supply of steam quantity is regulated by control valves. For taking care of emergency situations stop valves are also provided which cut off the supply of steam turbine under such situation. They have only two positions either fully open or fully closed.

Governing System: An elaborate governing system is provided for turbine to control the opening of control valves to supply amount of steam according to varying load demand. The system senses the load variation in the form of speed change, convert it to hydraulic signal, amplify it and operate the actuators/ servomotors coupled to control valves. Apart from load changes, the system also acts during emergency situations to safe guard the turbine. The system comprises of mix of electronic, electrical & hydraulic devices.

Lubrication System: The TG journal bearings are provided with forced lubrication so as to form hydraulic film between journal & bearing surface to support the rotor. During the course of running the lube oil gets heated up due to friction and need to be cooled, filtered, purified and pumped back to bearings. A closed lubrication system consisting of a reservoir, pumps, filter cooler and purifier forms the essential part of turbine. Drain System: During non steady state operating conditions, the mismatch between turbine component metal temperatures and steam causes condensation which gets collected in piping & casings. This condensate is withdrawn by drain system otherwise it would flash back during load changes and deform casing rotor and blading.

Control & Instrumentation: During operation a host of parameters e.g. steam pressure, temperatures, lube oil pressure temperature, metal temperatures, expansions, rotor speed & eccentricity etc. are continuously monitored, supervised through various instruments and supervisory devices. On the basis of these control & instruments, safe, reliable and uninterrupted operation of turbine within defined design limits is ensured.

Turning Gear: A turning gear is provided to rotate the turbine rotor slowly prior to start-up and after the turbine is shutdown to allow unified warm-up and cooling, maintain eccentricity and to prevent the thermal distortion of the rotor. It can be electric motor driven unit and in others oil driven driving unit/hydraulic motor.

INDUCTION At very first day of induction T1 SHOP was introduced where I learnt about different types of rotors like HP, HIP, IP, LP1, and LP2. The machining processes were being done on all CNC based lathe, milling, turning machines. Here the Rotor for turbine and generator is made with very accurately and with use of latest machines like SIDE ENTRY GROOVE machine, which is absolutely new for me. In T2 SHOP the casings for turbine and generators casing which are made either from casting or fabrication are machined and certain quality of them are being checked and improved. Here Indias largest machine GANTRY PLANOMILLER is used for machining heavy castings without moving them, but by moving gantry. Also here VTL (vertical turning lathe), HBM (horizontal boring machine), EDM (electro discharge machining). In T3 SHOP machining operations are done on machines which are mentioned above as per the requirement and quality consideration. Also here deburring and finishing operations are done for removing stress from component and make them super finished. The project work was allotted in this machine shop. In T4 SHOP fabrication is being carried out. The casings for LP1 & LP2 rotors which have large volume and density are being fabricated here. Here also gantry Plano miller is used for machining heavy fabricated casings.

T5 & T6 SHOP(FABRICATION SHOP)In this shop, Basic machining operations are done on small components of turbine and generator section. Here surface grinding, CNC plasma cutting machine, tool point grinder, pipe bending, regrinding machine, radial drilling machine , cutting tool edges maker, hydraulic press are different types of machines used for respective operations. Also Shot blasting Process (to remove rust), Painting(to protect against corrosion), and Gas fired Bogie Hearth Batch type Heat treatment furnace(to reduce stress) are used on components. Also internal threading , automatic tool changer, sine bar for levelling, surface attachments on milling machine, different types of JIGS & FIXTURES , GO & NOGO gauges, etc. very useful and informative parameters are known by me. Also heat treatment furnace for heating and removing stresses and strains from object and further cooling is done for v making it very hard and sustainable for high load capacity.Also, Different types of welding machines like TIG, MIG, SMAW, GMAW, etc. are used. The welding processes are done according to type of joint and accuracy customer want. Here also STATOR FRAME VERTICAL FABRICATION & SIMPLE STATIONARY BLADE MACHINE, welding for big blades MANIPULATOR POSITIONER WELDING MACHINE is used. TURBINE ASSEMBLY

HIP ASSEMBLY FLOWCHARTInterference check of inner components with respect to outer componentsGland Bore settingHIP Outer Casing LevelingHIP Casing Hydro Test

Top halves installationRotor TravelRotor TravelClearance AdjustmentInner components installation

LP ASSEMBLY FLOWCHARTOuter Casing Lower InstallationOuter Casing Upper InstallationRotor InstallationRotor TravelLP Bore Adjustment

Steam Deflector InstallationSteam Chamber InstallationInner casing L/H installation & centering

Gland Ring InstallationSpecial Stationary Blade Installation

Installing upper components & measuring top clearanceBottom Clearance Adjustment

BLADE SHOPIn this shop, different types of blades like stationary blade and rotating blade with different dimensions are made on CNC based 5 axis and 4 axis machines also having quality department and tool length measurement device which is very essential and adequate. The coordinates of blade are tested accurately by using CMM (Coordinate measuring machine), Profile Projector and Weight balancing Machine. The tools are very highly finished for making very sensitive and adequate part of turbine, blades.The blade path consists of reaction blades in the high pressure turbine, intermediate pressure turbine and low pressure turbine. The reaction type blading is adopted in large turbines because of its high efficiency. In the reaction blade path, the steam velocity is relatively slow resulting in lower friction loss namely better aerodynamic efficiency.

Blades have 3 principal parts:i. Aerofoil/Profile sectionii. Rootiii. Shroud

Roots are classified into:i. Hook rootii. T-rootiii. Fir tree rootiv. Finger/Fork rootv. Axial Fir tree root

STATOR COIL SPRING SHOPIn this shop, copper strap as raw material which are finally converted into coil of copper which are the root of magnetic field. Roebelling operation is done on coil strap for joining proper number of coil straps and makes one unit. After that consolidation and framing is done. Brazing and tapping with specially insulated material tap is done on 6 axis machine for making coil hard. Afterwards vacuum pressure impregnation and polymerization is done on it in big vacuum chamber with semi insulated painting on it.After that curing at 135 c is done for at least 24 hours. Finally by using core model the copper coil is made in definite final shape and then it is sent to assembly area.

STATOR COIL MANUFACTURING FLOWCHART:

PROJECT SUBJECT: TIME STUDY AND EVALUATION OF PROCESS PARAMETERSMENTOR: MR. CHETAN PATIL (T3 MACHINE SHOP)My project is to study the basic processes which are being done on particular machine with consideration of PPS and drawing chart of particular object.For performing this project first of all I visit the T3 SHOP completely, note down the specifications of each and every machine. Then I was allotted the COMPONENT called HP PEDESTAL LOWER HALF on VERTICAL PRECISION MILLING MACHINE (PM202) OR ST13. The object is to study the PPS of HP PEDESTAL LOWER HALF and compare the SMH(Standard Man Hours) timings with actual timing of the workers and engineers of L&T taken to complete the job.X-AXIS (TABLE)9000 MM

Y-AXIS (VERTICAL HEAD)4900 MM

Z-AXIS (RAM)1000 MM

W-AXIS (CROSS RAIL)2200 MM

DISTANCE BETWEEN COLUMNS4300 MM

MAX HEIGHT OF JOB3050 MM

RAM SIZE(400400) MM

TABLE SIZE(80003500) MM

SPINDLE DIA AND TAPER130 MM/ISO 50

SPINDLE SPEED4000 RPM

SPINDLE POWER45 KW

The specifications of the PM202 (made by Mitsubishi, Japan) are as follows:BEARING AND BEARING PEDESTALS

The Bearing performs the following functions: - It retains the rotor in correct radial position with respect to the cylinder. It provides low friction support and withstand dynamic load of rotating shaft. It takes away the heat generated due to friction.

Each turbine rotor has two journal bearings for both ends, and one shaft system has one thrust bearing. They are all of forced lubricated type, i.e., the load is carried by hydrodynamically generated film of lube oil. The bearing surface is made of Babbitt metal which is an alloy having low coefficient of friction and an excellent conductor of heat.

For cooling & lubrication, oil is supplied at about 1 to 1.5 bar pressure through oil pump. Temperature of oil is maintained at 30-35C. All the bearings have thermocouples for detecting the metal and oil drain temperatures. The turbine is incorporated with grounding device to prevent the shaft voltage trouble.

Bearing Pedestal performs the following functions: - It supports the rotor via journal bearing & maintaining gland clearances & also inter-stage clearances. It houses the lubricating & jacking oil supply piping & bearing oil drain pipe work. Encloses various instrumentation connections. E.g. bearing temperature, speed measurement, differential expansion, electricity, vibration pick-up, etc. It covers the rotor coupling. Oil guard rings provided at the two ends of pedestals prevents the leakage of oil & vapors.

MethodologyFirst of all I studied the PPS of HP PEDESTAL LOWER HALF and note the basic standard timing for completion of object.Then the analysis of drawing, that exactly what it is and how the machining operations are done on it, in which order, with how much tolerances and which operation are difficult to process.Then I watched the whole process done by operators on HP PEDESTAL LOWER HALF step by step and calculate amount of actual time required by them to complete the component.Then we match the actual time with planned time and we find that actual time was more than planned time but not by larger quantity.

COMPARISON FOR LAST 3 PROJECTS

CASE STUDY ROUGHING OF BOTTOM FACE: Planned time (By SMH) 4 hours 18 minutes Theoretical program time 5 hours 4 minutes Actual time 11 hours 46 minutesProblemCauses Corrective ActionExtra Time Taken

2 extra passes had to be takenDepth of cut chosen was 2mm less than the planned value. An extra 2 hours 32 minutes of machining had to be done to compensate. 2 hours 32 minutes

2 extra passes had to be takenExtra material of 5mm was presentAn extra 2 hours 32 minutes of machining had to be done to compensate. 2 hours 32 minutes

Insert wear outInserts have to be replaced after every 1-2 passes. This replacement takes time.Include an estimate of the time taken for this in the planning or select working ranges in which this would not happen.

Insert changeFor a tool with 16 inserts, up to 20 minutes per pass was used in replacing worn out inserts.This time should be considered while calculating the approximate machining time. 1 hour 20 minutes

Offset had to be taken againFor every tool and insert change, the offset had to be taken again.Extra time was taken to take the offset again.40 minutes

Development of chips and coolant accumulationAnytime material removal is done, metal chips are developed and have to be cleared. Cleaning both takes approx. 5 minutes per pass.No corrective action possible. Necessary action done to ensure correct finish.40 minutes

Use of extension headExtension head installed could not operate at the desired cutting depth. -

Different cutting speeds, feeds and depth of cutValues prescribed in the PPS are difficult to match due to a variety of reasons.Timings in the PPS are ideal. They should be made in cohesion with production so as to have a better estimate of possible parameters.

Machining of oil groove: Planned time (by SMH) 2 hours 6 minutes Theoretical program time 2 hours 34 minutes Actual time 4 hoursProblemsCauses Corrective ActionTime Taken

Drilling done to generate slotDrilling had to be done to set the starting point for further machining.Extra time taken to drill the hole should be added to the PPS as it is a part of machining time.1 hour

Time taken for setupSetting of the drilling tool and taking offset for the same took up extra time. Can be added to the PPS as setup time for this operation.10 minutes

Development of chips and coolant accumulationAnytime material removal is done, metal chips are developed and have to be cleared. Cleaning both takes approx. 5 minutes per pass.No corrective action possible. Necessary action done to ensure correct finish.40 minutes

Different cutting speeds, feeds and depth of cutValues prescribed in the PPS are difficult to match due to a variety of reasons.Timings in the PPS are ideal. They should be made in cohesion with production so as to have a better estimate of possible parameters.

WHAT I LEARNT FROM IT? I got to know about different type of tools and inserts used for different processes. I also study the nomenclature and geometry of tools as well as inserts which are used for machining. By studying this I understood the insert geometry and nomenclature with respect to different processes also tool geometry which is mentioned below:

Tool Nomenclatures For external turningMInsert Clamping System

CInsert Shape

KTool holder Style

NInsert clearance angle

RHand of Tool

C, S, FAdditional information

25 25Shank Dimension

MTool length

12Insert size cutting edge length

For internal Turning

AConstruction featuring boring bar

25Shank dimensions

RLength of boring bar

MInsert clamping system

CInsert shape

LBoring bar style

NInsert clearance angle

RHand of tool

12Insert size cutting edge length

INSERTS NOMENCLATURESCInsert Shape

NInsert clearance angle

MTolerance class

GInsert features

12Size

04Thickness

08Corner radius, Hand of insert, Cutting edge

FMChip breaker

I came to know the basic process from operator by understanding loading condition, speed overwrite, feed overwrite, spindle overwrite, rpm, reference machining, maximum rotation diameter, coolant condition, chip conveyor arrangement, jigs and fixtures, tooling parts, dial gauge for levelling and centering, measuring devices, inserts, jaws and blocks and clamps, etc. As per working on this project I came to know very basic fundamental but new things like different types of inserts, clamping arrangement, very innovative magnetic chuck which is very user friendly and no clamping is required for that. It is very time saving parameter also it has some drawbacks like chip removal and unloading of object etc. but overall it is very good experience. During this I also came to know how to calculate feed and depth of cut by calculating rpm from range of cutting speed which is based upon job material, insert material, clamping condition, coolant and tool condition, past experience. I studied about the test done after machining which is done by quality department like DPT (DYE PENETRATE TEST), remote visual inspection, radiographic testing and low coherence interference to find defects in the component. Here also I understood the industrial management terms like wise EHS (ENVIRONMENTAL HEALTH AND SAFETY), 5 S,TBT (TOOL BOX TALK), HJS (HORIZONTAL JOINT SURFACE), ROUTE CARD, NCR (NON CONFORMANCE REPORT), PPS (PROCESS PLANNING SHEET), TOOLING LIST, PREVENTIVE AND PREDICTIVE MAINTENANCE CHECK SHEET etc. I also got to know about different process terms like spot facing, back spot facing, weld edge and dry run. Also, I learnt the use of the Go-NoGo Gauge from my project mentor, who also taught me how to use the same while checking the threading performed internally in holes and bores on the machined surface.

OBSERVATION Clogging of chips around the tool and the component that is machined makes it difficult to do the process properly. Excess use of coolant. It should be used within permissible limits as sometimes coolants goes in part of component where it is not required. Many times tools of the machine are taken by other machine operators or by other shop which sometimes stops the machining of component which increases actual time of machining. Leakage of air is observed in many machine and may be leading to losses. Also there is misuse of compressed air in the purposes where it is not required. At many instances, the operators ran the various operations at speeds lesser than the prescribed values, resulting in the need for multiple passes and therefore, more time than what is listed in the Standard Man Hours for the operation. Usually operators stops working during the last hour of their shift and would spend the time idle. This time can be used up for other purposes or at the very least another pass can be completed in the idle time. There are not proper schedule for worker to operate the crane or EOT (Electrical Overhead Transport), resulting in increase in Standard Man Hours for the operation.

SUGGESTIONS For removing the chips during machining the workers used to remove it by a steel rod which is dangerous and may also affect the surface finish of the component. For that there should be CHIP BREAKERS fitted with tool point, which will break the chips in discontinuous fashion, resulting in less clogging of chips around the component and between the job and the cutting edge of the tool. A set no. of tools should be present at every machine for all basic purposes. The usage of coolant should be regulated in a way to extend the usable life of the coolant. In many cases, multiple tubes or faucets delivering the coolant were switched on, some of which werent even aimed at the surface being machined, thereby causing major wastage of the coolant, which cannot be circulated permanently and has to be replaced after set periods of time. This can be implemented by properly observing and supervising the usage of coolant at the time of operation and then instructing the operators as to the proper use.

APPRAISAL POINTS First of all, the KNOWLEDGE SESSION which is arranged at every Wednesday is very good idea to share the knowledge with other executives and relevant departments. By attending this type of sessions one can easily enhance its engineering knowledge and being aware about how much productivity the company is doing at current going time. Second point is the planning and arrangement of each and every useful part which are necessary for operation. 5 S principles and KAIZEN principles are very seriously implemented which will surely affect the efficiency of department. Proper guidance and instructions are given to workers at the start of each and every shift. The orientation of each machines and cleaning staff is very good also the safety feature is at its peak level which should be praised as per the accidental damages to keep in mind. Proper specifications boards are available at each machine so visitor can easily identify particular machine with their code also. Safety is major aspect they are concerned about.

CONCLUSION

Thus this Summer Training for almost 30 days was very interesting and respective colleagues and engineers keep us willing to know more and more.Also it will be very useful for me to get the practical industrial based knowledge, their criteria, latest machines and latest machining processes which are carried out nowadays.It will also be an industrial experience as my further carrier is in this field only. So it will be very fruitful if I connect it with my theoretical knowledge and get the best output.

5S SYSTEM

Definition: A systematic approach to workplace organization and methodical house keeping with a sense of purpose.

1. SEIRI (Sorting)Identify and sort to segregate usable from non-usable.STEPS Remove all garbage and unnecessary tools from shop floor Remove all unnecessary papers from files Discard old files and stationary not in use Clean walkways Saves floor space Helps get rid of obsolete items

2. SEITON (Systematic arrangement)A rational orderly and methodical arrangement of all items we use, rework or write off.STEPS Ensure rational layout of machines, equipments and cabinets Place frequently used items at the point of use Pre-fix a place for everything and put everything in place Use labels, colour codes to identify Use index for files, records and drawings Plan storage with easy retrievability Mixed up items in cabinets should be organized Make cabinets, shelves, racks self-explanatory through identification aids

BENEFITS Material easily available Material easily retrievable Lesser production downtime Machines breakdown handled fast Time taken for searching is minimized

3. SEISO (Pick and Plan)Cleaning is not done not just for beautification but also with a sense of purpose. Sweeping floors and surroundings Dusting to make the place dust free Wiping to make oil, grease, moisture free Identifying root causes and establishing corrective action

STEPS Develop standards of cleaning Clean-up workplace after use Clean-up machines and tools after use Clean-up supply lines (no leakage, blockage, clogging with oil & dirt) Assign clear responsibilities and schedules for cleaning Clean waste bins at end of shift/day Clean light bulbs, fans, shades, reflectors Pay special attention to scrap yard, gardens and godowns Scrap and chips from machines could fall directly into collecting bins

ADVANTAGES Clean machines and floor Fast corrective action Tools well laid out Smoother material flow Inventory levels can be found visually Lesser production downtime

4. SEIKETSU (Standardization, Serene atmosphere)Following of earlier 3 Ss, standardized work procedures, maintaining safe and hygienic conditions in work place contribute to a serene working atmosphere.STEPS Wear neat and clean uniform Wear protective clothing Provide adequate lighting, ventilation, exhaust Check electrical wiring, cable, switches Maintain sanitary conditions in washrooms, locker rooms, canteen and kitchen Look for heavy noise, vibration and heat in machines, analyze for root cause and take action

5. SHITSUKE (Self-Discipline)Training, sincerity constancy of purpose in following the rules and standards developed in the earlier 4 Ss.STEPS Create awareness of 4S Make them easily understandable Display correct work procedure on the floor Correct the deviations on the spot Maintain punctuality

BENEFITS OF 5S Nice to work in a clean, beautiful and organized work place. Reduction in M/C down time. Lesser time to retrieve things when required. Improved communication among employees. Improved morale of employees. Sense of ownership of workplace. Positive impact on the customer. More usable space. Higher productivity. Lesser accidents. Reduction in errors/defects due to standardization. Consistent improved quality.KAIZENKaizen, Japanese for "improvement", or "change for the better" refers to philosophy or practices that focus upon continuous improvement of processes in manufacturing, engineering, and business management. It has been applied in healthcare, psychotherapy, life-coaching, government, banking, and other industries. When used in the business sense and applied to the workplace, kaizen refers to activities that continually improve all functions, and involves all employees from the CEO to the assembly line workers. It also applies to processes, such as purchasing and logistics, that cross organizational boundaries into the supply chain. By improving standardized activities and processes, kaizen aims to eliminate waste (see lean manufacturing). Kaizen was first implemented in several Japanese businesses after the Second World War, influenced in part by American business and quality management teachers who visited the country. It has since spread throughout the world and is now being implemented in many other venues besides just business and productivity.The Japanese-Kanji- word "kaizen" simply means "good change", with no inherent meaning of either "continuous" or "philosophy" in Japanese dictionaries or in everyday use. The word refers to any improvement, one-time or continuous, large or small, in the same sense as the English word "improvement".[5] However, given the common practice in Japan of labeling industrial or business improvement techniques with the word "kaizen" (for lack of a specific Japanese word meaning "continuous improvement" or "philosophy of improvement"), especially in the case of oft-emulated practices spearheaded by Toyota, the word Kaizen in English is typically applied to measures for implementing continuous improvement, or even taken to mean a "Japanese philosophy" thereof. The discussion below focuses on such interpretations of the word, as frequently used in the context of modern management discussions.Kaizen is a daily process, the purpose of which goes beyond simple productivity improvement. It is also a process that, when done correctly, humanizes the workplace, eliminates overly hard work ("muri"), and teaches people how to perform experiments on their work using the scientific method and how to learn to spot and eliminate waste in business processes. In all, the process suggests a humanized approach to workers and to increasing productivity: "The idea is to nurture the company's human resources as much as it is to praise and encourage participation in kaizen activities."[6] Successful implementation requires "the participation of workers in the improvement."[7] People at all levels of an organization participate in kaizen, from the CEO down to janitorial staff, as well as external stakeholders when applicable. The format for kaizen can be individual, suggestion system, small group, or large group. At Toyota, it is usually a local improvement within a workstation or local area and involves a small group in improving their own work environment and productivity. This group is often guided through the kaizen process by a line supervisor; sometimes this is the line supervisor's key role. Kaizen on a broad, cross-departmental scale in companies, generates total quality management, and frees human efforts through improving productivity using machines and computing power.The cycle of kaizen activity can be defined as: Standardize an operation and activities. Measure the operation (find cycle time and amount of in-process inventory) Gauge measurements against requirements Innovate to meet requirements and increase productivity Standardize the new, improved operations Continue cycle ad infinitum

Parth Gandhi