26
Performance Based Practical Design March 30 th , 2016 ITS Georgia

Performance Based Practical Design · • We learned from those who taught us how and why we follow the standards… • There are valid reasons that tell us we now need to work differently:

  • Upload
    hanhan

  • View
    213

  • Download
    0

Embed Size (px)

Citation preview

Performance Based Practical Design

March 30th, 2016ITS Georgia

DOT’s face increasing challenges

• We learned from those who taught us how and why we follow the standards…

• There are valid reasons that tell us we now need to work differently:

• Funding• Staff Resources• Aging infrastructure• Environmental considerations• Availability of reliable data and information• Technology

Engineering Culture

PBPD is a decision making approach that helps agencies better manage

transportation investments and serve system-level needs

and performance priorities with limited resources.

What is PBPD?

• New Policy, Regulation, or Requirement• Opportunity to disregard long -term needs:

• For short term cost savings• Overlooking future development

• Compromising on safety, user needs (bike, ped, etc.), or accommodation of freight to save money

PBPD is not:

PBPD – Overlapping

Context Sensitive Solutions

Value EngineeringSystem Performance

Indiana’s Version of PBPD

Existing Typical 9’ Lanes 3’ Shoulders

Proposed Initial Typical 12’ Lanes4’ Paved Shoulder 4’ Aggregate Shoulder

11’ Lane 2’ Paved Shoulder1’ Aggregate Shoulder

Practical Design Example

Practical Design SavingsItem Original Cost Practical Cost Savings

Pavement DesignReduce driving lane from 12' to 11' $3,600,000 $3,300,000 $300,000

Minimize Underdrain Depth and locations $120,000 $60,000 $60,000

Shoulder DesignReducing shoulder Aggregate width 4' to 1' $160,000 $40,000 $120,000

Reduce to 3:1 Side Slopes and V-bottom ditches $775,000 $525,000 $250,000

UtilitiesRelocate 8" gas line to lower elevation $3,000,000 $500,000 $2,500,000

Move OH utilities inside Clear Zone:Reduce trees to be removed $232,000 $132,000 $100,000

Reduce area of mitigated wetlands $500,000 $400,000 $100,000

Reduce number of mitigated trees $50,000 $10,000 $40,000

StructuresModify instead of replace most large structures $700,000 $200,000 $500,000

Structure Removal $120,000 $20,000 $100,000 Minimizing Cover Depth at Crest Curves $40,000

Structure Backfill $60,000 $20,000 $40,000

TOTAL PROJECT SAVINGS: $4,150,000

Performance Based Practical Design Example

Performance Based Practical Design Example

Performance Based Practical Design Example

Interactive Discussion:Expanding Freeway Capacity

• Predictive safety comparing alternatives.• 125,000 AADT• Values are for a 6-mile segment only

considering a continuous freeway segment (no merge, diverge or weave)

Alternative

No. of General Purpose

LanesTotal K A B C PDO

254.4 0.9 2.6 18.6 54.2 178.1Full Build 4 12 12 12 12 12 12

201.310 293.9 1.3 3.1 22.9 65.3

63.4 210.1

Alt. 1 4 4 11 11 12 12

12 12 293.6 0.8 2.3 16.8

Estimated Crash StatisticsEstimated average crash freq. during Study

Period, crashes/yr:

Inside Shoulder Width Lane Width Outside Shoulder Width

NoBuild 3 12 12 12

K – at least one fatality occursA – at least one disabling injury occursB – at least one evident, non-disabling injury occursC – at least one possible injury occursPDO – no injury occurs but property damage in excess of the

state’s minimum reporting threshold occurs

Which One Would You Choose?

14

Total K A B C PDO

254.4 0.9 2.6 18.6 54.2 178.1

201.3293.9 1.3 3.1 22.9 65.3

63.4 210.1

293.6 0.8 2.3 16.8

Estimated Crash StatisticsEstimated average crash freq. during Study

Period, crashes/yr:

12’ 12’ 12’ 12’12’

11’ 11’ 12’ 12’ 10’4’

12’ 12’ 12’ 12’12’

12’ 12’ 12’ 12’12’ 12’

Can we make more out of our

alternatives?Can we have the best of both?

Before

Operational Benefits of Shoulder Running

15

After

Shoulder Use and Limitations of the HSM

16

When Do the Lowest Fatalities Occur on Urban Freeways?

17

AM Peak Period

PM Peak Period

Is this a Rutting Issue?A Cross-Slope Issue? Or Some Combination of Both?

Is this a Rutting Issue?A Cross-Slope Issue? Or Some Combination of Both?

Is this a Rutting Issue?A Cross-Slope Issue? Or Some Combination of Both?

Hydroplaning Predictive Analysis Results

43

44

45

46

47

48

49

50

51

0

100

200

300

400

500

600

700

800

900

1000

1100

1200

1300

1400

1500

Hyd

ropl

anin

g Sp

eed

(mph

)

Section Length (ft)

Rainfall Intensity: 6 in/hrRainfall Intensity: 6.972in/hrSpeed Limit

LiDAR with drainage path length modeled

Fixing This Is Expensive & ComplicatedEspecially When Bridges Are Involved…

Variable Speed Limits

• What if the following assumptions are “off”?• Traffic data• Crash predictions• User costs• Construction/materials costs

When you consider the risk of being “off” on your predicted performance calculations…

The chances the alternative will outperform the calculated B/C are about 10%.

The chances the alternative will UNDERPERFORM the calculated B/C is greater than 89%.

30 1 22.1

Calculated Benefit/Cost

ALL ENGINEERING CHOICES HAVE TRADE-OFFS

Cost

Valu

e (O

pera

tions

, Saf

ety,

Eff

icie

ncy

etc.

)

Min

imum

Sta

ndar

ds

Below Design Criteria

Meets or Exceeds Design Criteria

Same Cost, Better Value

Same Value, Lower Cost

Which One Would You Choose?

FHWA is prepared to support States as they develop projects with a

system performance mindset using data-driven methods

FHWA Will be a good partner