29
Primavera Pertmaster

Pert Master

  • Upload
    jun-pal

  • View
    373

  • Download
    4

Embed Size (px)

Citation preview

Page 1: Pert Master

Primavera Pertmaster

Page 2: Pert Master

2

Agenda

IntroductionsRisk Management OverviewPertmaster Value PropositionRisk Methodology

"Primavera has mastered the art of determining trends in the project portfolio management (PPM) market, identifying the PPM needs of its target markets, and acquiring solutions that fit the vendor's evolving product mosaic. Building on Primavera's own project management solution set, which addresses all nine of the PMBOK areas, the company has built a comprehensive and seamless suite of products that fit a broad base of industry verticals.”

Louis Cardin, The Forrester WaveTM

December 18, 2007

Page 3: Pert Master

3

Why Conduct Risk Analysis?

Eliminate project failureProjects fail because plans are unrealisticExecution is not to plan

Achieve greater confidence with project plansTrack past performance to forecast futureReduce uncertainty of estimatesMore realistic schedules

Set appropriate expectations for cost and scheduleDetermine probabilistic start or finish Manage and allocate resources accordinglyAccurate forecasting, Earned Value validation

Page 4: Pert Master

4

Project Risk Types

Estimate UncertaintyModel

Risk Distributions e.g. 3pt estimatesMonte Carlo simulation

Reduction of risk exposureContingencyRisk responses (e.g. mitigation)

Risk EventsModel

Risk register/logPI Matrices

Estimate Uncertainty + Risk Events = Total Risk ExposureEstimate Uncertainty + Risk Events = Total Risk Exposure

Page 5: Pert Master

5

Primavera Pertmaster Overview

Risk TechniquesSchedule improvement: PPM maturityRisk assessment: risk registerRisk Analysis: Monte Carlo simulation

Risk-Based Predictive Modeling Confidence in schedule/budgetRealistic forecast expectationsContingency assessment Cost-benefit of mitigation scenarios

Pertmaster’s proven techniques provide risk based predictive modelingacross the entire project lifecycle

Full Lifecycle Risk ManagementPortfolio risk – strategic project selectionProject risk – tactical project controls/PMCost and schedule risk analytics

IntegrationPrimavera: P3, P3e, P5, P6, SuretrakMS Project, EPM, Deltek

Page 6: Pert Master

6

Why Pertmaster for Risk Management?

P6 Risk CapabilitiesRisk log – basic risk registerNo risk analytics capabilitiesInput into Pertmaster

Input > Analysis > OutputAll inputs to Pertmaster

Pertmaster Risk CapabilitiesFull cost/schedule risk managementMC risk analytics enginePublish “Risk Adjusted” schedule into P6

"It's impossible to hide a bad plan in Primavera." Chris Morris, Agere

Page 7: Pert Master

7

Portfolio Analysis Project Planning Project Execution

• Project selection?• Capacity planning?• Minimize risk exposure?

• Project completion dates?• Confidence levels?• Contractor: “do-able” plan?• Owner: Max cost/benefit?

• Execution to plan?• Avoid risk events?• Reduce risk hot spots?

• Top-down phases• Project alternatives• Revenue / expenditure risk

• Determine contingency• Determine mitigation • Cost > schedule integration

• Update risk plans• Forecast accuracy

Pertmaster Value Proposition

"To improve programme confidence, we've mandated the use of Primavera Pertmaster in all key projects." David Ashkroft, Thales

Page 8: Pert Master

8

Risk Methodology

Schedule ReviewRisk Ready StateReview for logic & errors

Risk Identification Estimate UncertaintyRisk Events: Risk Register

Develop Preliminary Risk ModelEnter Estimate UncertaintyMap Risks to Activities

Preliminary Analysis & ReviewImpacted Risk PlanMonte Carlo simulation

Final Model & ReportRisk Event planResponse planning

Page 9: Pert Master

9

Schedule Check Report

Content can be customised

Examples:Open-ended tasks – If a task has no successor, and it gets delayed, it will not delay the project. Does this reflect reality?Most Constraints will fix a task to its constraint date, therefore during the analysis, this task will not be delayed, even if it is carrying duration uncertainty!Schedule logic

If issues are not resolved, then the analysis results will be effected.

Page 10: Pert Master

10

Risk Analysis

Distribution Graph:What is the likelihood of completing this project by 25th December?ONLY 32% of finishing on or before 25th December 07The earliest this project finished in the simulation was 19th October 2007, the latest was 04th April 2008

>Confidence Scale>“How confident are you?”

Page 11: Pert Master

11

Risk Analysis

Tornado Chart – Duration SensitivityDetermine the Risk Hotspots in the scheduleWhich tasks are the most sensitive? Which should we mitigate?

Page 12: Pert Master

12

Cost-load schedule

Initial Cost Estimate

Apply estimate uncertainty to cost items

Resources can be time-dependent or independent

Page 13: Pert Master

13

Cost-load schedule

Cost Distribution Graph

Chance of completing this project to budget? 28%

Page 14: Pert Master

14

Cost-load schedule

Tornado Chart – Cost SensitivityBiggest cost drivers may not be the same as the biggest project finish drivers!

Page 15: Pert Master

15

Cost-load schedule

Cost contingency is P80 cost – Deterministic Cost

Page 16: Pert Master

16

Cost-load schedule

Duration contingency is P80 Finish Date – Deterministic Finish Date

Page 17: Pert Master

17

Cost-load schedule

50% of the iterations when the project was delivered on time50% of the iterations when the project was delivered to budget

% number of iterations when the project was delivered on time and to budget is only in this bottom left-hand quadrant = 29%

The Scatter Plot

Page 18: Pert Master

18

7. Cost-load schedule

The dividers (highlighters) can be dragged. This is most effective when the quadrant is locked (50% in this case).

Reducing the budget pushes out the project finish date and vice-versa

Page 19: Pert Master

19

Risk Register

Uncertainty on time and cost has been estimated, but no risk events have been taken into account.

Discrete risks that, if occur, will have a significant impact on time and/or cost.

Risks can be directly inputted into the Risk Register or imported from external systems

Page 20: Pert Master

20

Risk Register

There is a workflow to using the Risk Register. It usually starts with the Risk Scoring scheme

Set up qualitative RiskScoring (PID) matrix (Edit > Risk Scoring)

Risk Scoring matrix can be configured from 2x2 to 9x9

All fields can edited to conform to the organizations scheme

Scoring templates can be saved, stored and distributed for future projects

Page 21: Pert Master

21

Risk Register

The qualitative risk assessments are inputted here.The values in the drop-down menu are taken from the risk scoring matrixFocusing on one risk, the risk assessment derives a risk score, e.g. 56 for ‘Key Resource Unavailable’

Page 22: Pert Master

22

Risk Tornado Chart

“Key Resource Unavailable”was highest scored risk. But is not the biggest driver!

Page 23: Pert Master

23

Risk Mitigation

We have analysed a project with just estimate uncertainty on time and cost, and then looked at a pre-mitigated plan – Shows the worst case scenario

Pre-mitigated result shows there is no chance of delivering this project on time or to budget

Let’s build in a mitigation strategy and see if it has reduces the risk exposure on this project.

Page 24: Pert Master

24

Risk Mitigation

Where we are now Where we want to beWhat we could do

Cost of each mitigation strategyFor e.g. it will cost £32m to reduce ‘Key Res. Unav.’ probability of occurrence down from H > VL, and Safety Impact from VH > N, overall score down from 56 to 1.

Page 25: Pert Master

25

Distribution Analyzer

Compare original vs. pre-mitigated – Impact of risks is 272.4 days (80% confident)

Page 26: Pert Master

26

Distribution Analyzer

Comparing pre and post at 80% confidence, shows that mitigating these risks will bring the project back by 208 days.

Page 27: Pert Master

27

Distribution Analyzer

Cost S-curves. Will mitigating these risks save money?

Page 28: Pert Master

28

Probabilistic Cash Flow

There is a cash demand in these periods

Amount of cash that was not used in each these periods

Page 29: Pert Master

29

Q&A