Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
PIP-II Booster CollimatorsPhysics Requirement Document (PRD)
Document number: ED0010237
Document Approval
Signatures Required Date Approved
Originator: Dave Johnson, Booster L3 Manager -
Concurrence: Alex Martinez, Integration Coordinator -
Approver: Ioanis Kourbanis, Accelerator Upgrades L2 Manager Signed in Teamcenter
Approver: Eduard Pozdeyev, Project Scientist Signed in Teamcenter
Revision History
Revision Date of Release Description of Change- 10/7/2019 Initial Release
PIP-II Booster Collimators
Page left intentionally blank for revision history.
Fermi National Accelerator Laboratory 2
PIP-II Booster Collimators
Table of Contents1. Purpose................................................................................................................................4
2. Scope...................................................................................................................................4
3. Acronyms.............................................................................................................................4
4. Overview.............................................................................................................................. 4
5. Reference Documents..........................................................................................................8
Fermi National Accelerator Laboratory 3
PIP-II Booster Collimators
1. Purpose
Physics Requirement Documents (PRDs) contain the summary parameters and configuration definitions for systems, sub-systems, and devices that impact higher-level requirements established in the PIP-II Global Requirements Document (GRD) [1]. PRDs establish a traceable link to lower-level requirements (FRSs, TRSs) that affect the PIP-II beam or machine performance. In the aggregate, the PRDs for the PIP-II Project contain the essential parameters and configuration developed through the preliminary design phase to enable completion of the PIP-II accelerator and complex design.
2. Scope
This document describes the high-level parameters for the Booster Collimators.
3. Acronyms
FRS Functional Requirements Specification
GRD Global Requirements Document
L2 WBS Level 2 System
L3 WBS Level 3 System
MEBT Medium Energy Beam Transport
PIP-II Proton Improvement Plan II Project
PRD Physics Requirements Document
TRS Technical Requirements Specification
4. Overview
The new two stage collimator to be installed in Booster utilizes thick primary collimator blades (H&H) to produce large angle scattering with two secondary collimators to intercept the scattered particles, all contained within the same monolithic device. The secondary collimators are made up of a fixed H&V aperture and an adjustable H&V aperture. The complete unit is designed to easily fit within a single Long straight section. Figure 5-1 shows the proposed transverse cross section of the collimator assembly and Figure 5-2 shows a corresponding isometric view.
Fermi National Accelerator Laboratory 4
PIP-II Booster Collimators
Figure 5-1. Transverse cross section of the proposed two stage collimator
Figure 5-2. Isometric view of the proposed collimator layout
Fermi National Accelerator Laboratory 5
PIP-II Booster Collimators
Radiological limits
There are two areas of concern when discussing accelerator produced radiation and radio-nuclides. One involves minimizing ionization radiation to workers outside the enclosure from prompt radiation and radiation to workers inside the radiation enclosure from residual activation of equipment. The other concerns the production of radionuclides that could enter the environmental watershed, either through “drinking water” or “surface water” contamination. These limits are determined by applicable state and federal EPA/DOE/FNAL rules/orders. The main radionuclides of concern at Fermilab are 3H and 22Na.
Table 5-1. Radiological limits
Constraint ValueDrinking water Cf < 20 piC/ml-yr 3H Cf < 0.2 piC/ml-yr 22Na
Surface water Ci < 2000 piC/ml-yr 3H Ci < 10 piC/ml-yr 22Na
Residual activation on exterior surface < 100 mRem/hr
Prompt dose at exterior of berm < 0.05 mRem/hr “unlimited occupancy”
The collimator and its shielding must meet or exceed the Radiological Requirements for ground water protection, surface water (collected by the Booster sump pumps), and human protection through limiting residual activation of the external surface of the collimators and the prompt dose at the exterior surface of the berm where personnel may be present.
Beam Parameters
This new compact 2SC collimator system will be installed and tested under the current 400 MeV injection operating conditions and therefore must satisfy the radiological requirements for expected scraping rates (defined below) at 400 MeV prior to PIP-II coming on-line. It is generally the goal of all collimation systems to provide a well shielded absorber to which large amplitude particles may be effectively captured to minimize their loss elsewhere, thus minimizing the activation of accelerator components outside the collimation region. The addition, of this new 2SC is anticipated to alleviate the some of the load on the existing system thus reducing the residual activation in the region of the existing collimation.
The exiting Booster collimation system made up of three absorbers with two located in the Long 6 straight section and one in the Long 7 straight section. These are used as single stage collimators with movable rectangular jaws capable of scraping in both planes. Figure 5-3 shows the residual activation measurements at 1 foot at the beginning of an access period in May 2019. Shielding design and amounts vary for different locations around the ring and small losses at higher energy produce larger
Fermi National Accelerator Laboratory 6
PIP-II Booster Collimators
residual (c.f extraction losses). The standard Radiation Safety survey at the beginning of a shutdown cannot distinguish what lost particle energy was responsible for the measured residual. Typically, the collimation system only acts on beam at the injection energy and very early in the acceleration cycle. The insert table in the figure shows that the relative contribution to the total residual activation for the three major categories, injection, collimation, extraction, and the rest of the ring. We see that the beam loss in the region of the collimation system is responsible for about half of the activation around the ring. If we assume that all the activation in the extraction region comes from 8 GeV extraction and we remove this contribution, the distribution of the losses is shown in parenthesis (). This is still consistent with half of the residual activation is from the collimation region.
0
100
200
300
400
500
600
700
800
L20_
BRF2
1_U
S
L20_
BRF2
2_DS
L21_
RF9_
DS
S21
L22_
RF12
_US
L23_
RF13
_US
L23_
RF14
_DS
L24_
RF15
_DS
S24
LVT
L1_2
(2)
L2_D
S
MPO
2 L4
HORZ
.PR.
IN
VER.
PR IN
SEC.
CO
L 6A L7 L8 S9 L1
1
L12_
IN_U
S
MAG
NET
12_
3
L13_
US
S13
L14_
RF2_
US
L15_
RF3_
US
L15_
RF4_
DS
L16_
RF5_
DS
S16
L17_
RF8_
US
L18_
RF19
_US
L18_
RF20
_DS
L19_
RF17
_DS
S19
Activ
ation
mre
m/h
r @ 1
ft.
Loaction in ring
Booster Residual Activation Measurements at 1 ft on May 11, 2019Average Booster throughput 2.35E17 protons/hr
Injection
Extraction
CollimationActivation Distribution
Collimation 48% (55%)Extraction 20% (0%)Injection 14% (23%
Rest of ring 18% (21%)
Figure 5-3. Residual Activation in the Booster tunnel in units of mrem/hr @ 1ft
Table 5-2 shows the beam parameters, operational assumptions, and collimator scraping and power handling capability for several operational scenarios. The three scenarios are shown in the three
Fermi National Accelerator Laboratory 7
PIP-II Booster Collimators
columns are: 1) current 400 MeV operational mode, 2) an “upgraded” operational mode at 400 MeV, and 3) the PIP-II 800 MeV injection mode. We focus our attention on the last two columns which include the new 2SC collimator. The first column is for reference. The 2SC collimator system must meet the radiological requirements under the last two operational scenarios. The top section shows the Booster injection energy, injected intensity, beam energy/cycle, repetition rate, and power injected into the Booster under three configurations.
Table 5-2. Beam Scraping rates for applicable operational scenariosParameter Current "Upgrade" PIP-II Units
Beam energy 400 400 800 MeVprotons per hour 2.45E+17 2.80E+17 4.80E+17 pphprotons per sec 6.81E+13 7.78E+13 1.33E+14 ppsprotons per cycle 4.54E+12 5.19E+12 6.67E+12 ppBcreo rate 15 15 20 Hzbeam energy/cycle 290.4 331.9 853.3 Joulesbeam power 4.4 5.0 17.1 kW
Assumed eff @ inj energy 95 96 98 %lost particles/cycle 2.27E+11 2.07E+11 1.33E+11 pLpBclost particles/sec 3.40E+12 3.11E+12 2.67E+12 pLpsJoules lost per cycle 14.5 13.3 17.1 JoulesPower Lost 217.8 199.1 341.3 Watts
Fraction 0.50 0.50 0.50loss/cycle into all collimators 1.13E+11 1.04E+11 6.67E+10 pLpBcloss/sec into all collimators 1.70E+12 1.56E+12 1.33E+12 pLpsEnergy into all collimators 7.3 6.6 8.5 JoulesWatts into all collimators 108.9 99.6 170.7 WattsWatt distibuted around ring 108.9 99.6 170.7 Watts
Nbr Collimators 3 4 4Scraping rate 3.78E+10 2.59E+10 1.67E+10 pLpBc/collScraping rate for MARS 5.67E+11 3.89E+11 3.33E+11 pLps/collIncident beam energy/collimator 2.4 1.7 2.1 JoulesIncident beam power /collimator 36.3 24.9 42.7 Watts
Fraction of power loss going into collimators (from residusial activation)
Injected Beam Parameters
Acceleration Efficiency --> Beam Loss
Parameters/collimator (assume even distribution)
=
The next section discusses the Acceleration Efficiency and hence beam loss parameters (total beam loss, lost energy, and lost beam power for the assumed efficiency) for the entire Booster ring in the period from injection to shortly after the start of acceleration. Note that as the number of protons/sec increase under the last two scenarios the acceleration efficiency is increased. This assumption is based
Fermi National Accelerator Laboratory 8
PIP-II Booster Collimators
upon improvements in Booster efficiency due to injection optimization, resonance correction and ultimately injection energy increase in PIP-II.
For purposes of modeling we look at the distribution of the residual activation around the ring, particularly the contribution in the collimation region, and use this to scale how much of the total loss ends up in the collimation system. It is understood that the measured residual activation levels around the ring do not necessarily directly reflect the particle loss rate at a specific location, due to differences in shielding, but we will use the 50% level of the acceleration in efficiency as a guide to scale the expected number of particles captured in the collimation regions.
The current collimation system has three single stage collimators and for this exercise it is assumed the current loss is divided equally among the three collimatord. From loss monitor data and the detailed residual activation measurements in the collimation region we know that currently the loss is not evenly distributed, but we will not address this detail at this time. With the addition of the new 2SC system, we assume this will make four collimation systems and the loss will be distributed evenly among all three. Again, this is for the purpose of sizing the shielding.
The last section gives the scraping rates and lost power for the collimator design to assure the shielding provides adequate shielding to satisfy the radiological requirements in Table 5-2.
5. Reference Documents
# Reference Document #
1 PIP-II Global Requirements Document (GRD) ED0001222
2 PIP-II Preliminary Design Report (PDR) PIP-II DocDB# 2261
3 V.V. Kapin et al, “Numerical Simulations of Collimation Efficiency for Beam Collimation System in the Fermilab Booster”, NAPAC-2016. -
Fermi National Accelerator Laboratory 9