WELCOME YOU TO
PIRPANJAL RAILWAY TUNNELSITE
THE LONGEST TRANSPORTATION
TUNNEL IN INDIA
8/12/2019 pirpanjal railway tunnel
2/84
2
Location Overview Salient Features of The Tunnel Construction Approach
Pre-construction Planning Usage Of NATM in T-80 Construction Activities
Quality Assurance Environment Issues Social Impact
PRESENTATION COVERS
8/12/2019 pirpanjal railway tunnel
3/84
LOCATION OVERVIEW
8/12/2019 pirpanjal railway tunnel
4/84
4
ALIGNMENT PLAN
JAMMU-UDHAMPUR-SRINAGAR-BARAMULLA RAIL
LINK
QAZIGUND
SADURA
ANANTNAG
BIJBEHARAPUNZGAM
AWANTIPORA
KAKPORAPAMPORE
SRINAGAR
BUDGAM
RAJWANSHER
PATTANHAMRE
SOPOREBARAMULLA
BANIHALARPINCHALA
BHATTALOALE
KOHLISANGALDAN
BARALABASANDA--DHAR
REASI
KATRACHAKARWAH
UDHAMPUR
SALAL
RAMNAGARROADMANWAL
SANGARBAJALTAJAMM
U
SURUKOT
PIR PANJAL RAIL TUNNELLength 11100 mts.
South portal photo
SOUTH PORTAL
8/12/2019 pirpanjal railway tunnel
5/84
5
8/12/2019 pirpanjal railway tunnel
6/84
8/12/2019 pirpanjal railway tunnel
7/84
7
SALIENT FEATURES OF T-80(Contd.)
3 m wide road in tunnel for maintenance,emergency rescue & relief.
High mid point & sloping in both directions fordrainage.
Provision of system for ventilation, fire fighting &safety monitoring.
Adit & shaft for parallel working, to be used forventilation, maintenance & emergency reliefduring service.
Extensive instrumentation for monitoring duringtunneling
Consultants : M/s Geoconsult-RITES JV
8/12/2019 pirpanjal railway tunnel
8/84
8
MANY FIRSTS The Longest Transport Tunnel In The Country
(11Km)
Highest Over - burden of 1100M
Deepest Drill holes for GeotechnicalInvestigations 640M
First Large Scale Use of New Austrian TunnelingMethod (NATM) in India
First Use of Road header for Tunnel Excavation in Railway Tunneling
8/12/2019 pirpanjal railway tunnel
9/84
CONSTRUCTION
APPROACH
8/12/2019 pirpanjal railway tunnel
10/84
10
APPROACH TO CONSTRUCTIONNO ADIT
8/12/2019 pirpanjal railway tunnel
11/84
11
Vertcal Shaft
55m deep,
12m dia
Cross Passage 55 m
Adit 788 m
APPROACH TO CONSTRUCTIONWITH SHAFT AND ADIT
8/12/2019 pirpanjal railway tunnel
12/84
12
Tunnel
CrossSection:
STRUCTURAL GAUGE
8/12/2019 pirpanjal railway tunnel
13/84
8/12/2019 pirpanjal railway tunnel
14/84
14
TYPICALRAILWAYTUNNEL
SECTIONUSED ONJAMMU-
UDHAMPURRAIL LINK
SHOTCRETE(25mm+WIRE MESH +50mm)OR 50mm SFRS
300 TH. C.C. LINING
ISHB 150 @ 500 C/C
50mm TH. R.C.C. LAGGING
Min. EXCAVATION LINE
75 @ 2000 C/C
MS PLATE 12mm THICKISHB150-2NOS.
INVERT STRUT ISHB150 @ 500mm
ISHB200 @ 750 C/C
1676
R 2 6 0
0
4 3 7 0
1 3 1 2
150150
Max.150(max)
50M20
1 in 4 0
RAIL LEVEL
FINISH LINE
PAY LINE 150 TH. FROM Min. EXCAVATION25 mm 3 to 5m ROCK BOLTS
AS PER SITE REQUIREMENT
ISHB 150 @ 750 c/c
RESSURE RELIEF HOLES 5m DEEP @m c/c LONGITUDINALLY AS PER SITEEQUIREMENT
150
PAY LINEMIN. EXCAV. LINE
BASE PLATE12mm THICK
R 3 0 0 0
I S H B 1 5 0 @
5 0 0 c / c
S H O T C R E T E 2 5 m m +
W I R E M E S H + 5 0 m m O
R 5 0 m m
S F R S
5 0 T H
. R . C . C . L
A G G I N G
150
P R E S S U R E R E L I E F H O L E S 5 m
D E E P @
3 m c / c
L O N G I T U D I N A L L Y
A R A S P E R S I T E R E Q U I R E M E N T
B A C K F I L L I N G M - 1
0
50
F I N I S H L I N E
3 0 0 T H
. C O N C
. L I N I N
G M - 2
0
150
100
9 0 0
BLOWER
8 @ 150 C/C50 675 150
100
65
6 7 5
2 5 m m
3 m t o 5 m
R O C K B O L T A S
P E R S I T E
R E Q U I R E M E N T
S E C
. A T A - A
75
8/12/2019 pirpanjal railway tunnel
15/84
15
LOADING DIAGRAM FOR TUNNELTOP PRESSURE-15000KG/M
AND SIDE PRESSURE-5000KG/M
8/12/2019 pirpanjal railway tunnel
16/84
16
BENDING MOMENTS DIAGRAM FORD-SHAPE TUNNEL
TOP PRESSURE-15000KG/M AND SIDE PRESSURE-5000KG/M
MAX BENDING MOMENT = 137KN-M
8/12/2019 pirpanjal railway tunnel
17/84
17
BENDING MOMENT DIAGRAM FOR ELLIPITCAL TUNNELTOP PRESSURE 15000KG/M AND SIDE PRESSURE 5000KG/M
MAX. BENDING MOMENT = 35.80KN-M
8/12/2019 pirpanjal railway tunnel
18/84
COMPARISION BETWEEN D-SHAPED AND ELLIPTICAL TUNNEL
DESCRIPTION MAX.AXIAL
FORCE
MAX.BENDING
MOMENT
MAX.SHEAR
FORCE
MAX.DISPLACEMENT
WITH TOP PRESSURE 15000 KG/M & SIDE PRESSURE5000 KG/M
D-SHAPEDTUNNEL
412.5KN 137KN-M 15129 KG 0.083 M
ELLIPTICALTUNNEL
567 KN 35.80KN-M 9025 KG 0.024 M
WITH TOP PRESSURE 15000 KG/M
D-SHAPEDTUNNEL
412.5KN 48.10 KN-M 8565 KG 0.03 M
ELLIPTICALTUNNEL
639 KN 35.65 KN-M 9635 KG 0.028 M
8/12/2019 pirpanjal railway tunnel
19/84
19
CONSTRUCTION METHOD
SELECTION DRILL AND BLAST
ROAD HEADER
TUNNEL BORING MACHINE (TBM)
8/12/2019 pirpanjal railway tunnel
20/84
20
DRILL AND BLAST CONVENTIONAL, ART
WHICH COMES WITHEXPERIENCE
GOOD IN HARD ROCKYSTRATA
WITH EXPERIENCE, CANDELIVER GOOD PROGRESS
NON CONTINUOUS- CYCLEINVOLVES VARIOUS
ACTIVITIES IN SEQUENCE MAY SPRING SUDDEN
SURPRISES
8/12/2019 pirpanjal railway tunnel
21/84
21
ROAD HEADER CONTINUOUS ADVANCE-
LESS SURPRISES MORE CONTROLLED
EXCAVATION- LESSOVERBREAK/CAVITY
FORMATION SUITABLE FOR MEDIUM
HARD ROCK CAN BE WITHDRAWN
MID WAY TO GIVE WAYFOR OTHER METHODS
8/12/2019 pirpanjal railway tunnel
22/84
22
TUNNEL BORING MACHINE
CONTINUOUS ADVANCE CIRCULAR SECTION NOT SUITABLE UNDER
SQUEEZINGCONDITIONS
CANNOT BEWITHDRAWN MIDWAYTO GIVE WAY TOOTHER METHODS
8/12/2019 pirpanjal railway tunnel
23/84
23
WHY NO TBM
Likelihood of Mixed Geology Heavily Faulted Areas and/or Wide
Fault Zones High Squeezing Anticipated in middle
with High Overburden (1100 mts.) Heavy Water Flow in Lime Stone Zone
with High overburden TBM may be Trapped by Ground
Movement Behind the Face
8/12/2019 pirpanjal railway tunnel
24/84
PRE-CONSTRUCTIONPLANNING
8/12/2019 pirpanjal railway tunnel
25/84
25
PRE-CONSTRUCTIONPLANNING
Engagement of Consultant QCB System Of tendering
Survey and Investigation
Head start by Taking up ADIT and shaftworks in advance
Tender Planning Key dates Multi Method Approach
Road Header/ D&B
8/12/2019 pirpanjal railway tunnel
26/84
8/12/2019 pirpanjal railway tunnel
27/84
27
USAGE OF NATM IN T-80 Suitable for poor and Varying Geology of
Himalayan Region X-Section designed to develop Maximum Self
Supporting Capacity
Face Mapping , Probe Hole & Instrumentationdata input for Initial Support Design RESS Primary Support System
Resilient enough to Accept the deformations and readjustment ofstresses and Strong enough to take the loads
Deformation Monitoring to assess the stressredistribution, and stabilization before finallining
8/12/2019 pirpanjal railway tunnel
28/84
28
INSTRUMENTATIONTo provide early information about tunnel behaviour in order to optimize
excavation & support activities during construction and to recognize the requisiteremedial measures.
Instrumentation data is basic input of the NATM, the observational approach.
Instrumentation in Pir Panjal Tunnel:
Optical 3 D monitoring : With bi-reflex targets to monitor deformation intunnel on daily basis
Extensometers: To measure stresses in surrounding rock mass
Radial Pressure Cells : To measure pressure of rockmass on shotcretelining
Shotcrete Strain meter: To monitor stresses in shotcrete lining
Piezometer: To monitor hydrostatic pressure during tunneling
8/12/2019 pirpanjal railway tunnel
29/84
29
CONSTRUCTION ACTIVITES
Open excavation & portal development Tunnel mining & primary lining Water-proof membrane installation +
drainage system. Secondary lining. Ventilation, system and safety
installations Track laying
8/12/2019 pirpanjal railway tunnel
30/84
30
QUALITY ASSURANCE
Laid down responsibilities,procedures and checklists forvarious activities through: CPM, CQM, SH&EM PPM, PSM Organogram
QAP ITP
8/12/2019 pirpanjal railway tunnel
31/84
31
QUALITY ASSURANCE (contd)
Availability of relevant documentation and definingthe manner of execution of various activities
Maintaining compliance through appropriatemonitoring
Ensuring adequate support facilities for successful& scheduled execution of work.
Availability of competent/trained personnel to carryout various activities
Compliance of statutory/regulatory requirementsrelated to safety, environment etc.
8/12/2019 pirpanjal railway tunnel
32/84
32
Quality Assurance (contd)
Check Lists and Forms for Process Control DuringExecution of Works:
Required Excavation and Support Sheet (RESS) ATSS/ Shift Report/Blasting clearance report/ R/Bolt
Installation report Shotcrete testing by Penetrometer test, Core
crushing test , thickness verification etc. Geological mapping (Geological face mapping sheet)
Lining Air Permeability Test All Material Testing at Site Lab
8/12/2019 pirpanjal railway tunnel
33/84
33
ENVIRONMENT ISSUES Identified Muck Dumping areas
Recycling of Excavated Rocks aggregate for concrete constn.
Effluent Settling Tank
Fit for agriculture discharge Ventilation during Construction Stage
Gas Analyser for air quality monitoring
Controlled Blasting below Inhabitedareas Lined Waterproof Tunnel
No long term impact on water table/ Aquifers
8/12/2019 pirpanjal railway tunnel
34/84
34
SOCIAL IMPACT All weather link, Alternate to Jawahar
Tunnel Even at Construction stage, given a
boost to local construction-industry Employment Transportation business
A boost to Local economy of Banihal
8/12/2019 pirpanjal railway tunnel
35/84
35Time Line
8/12/2019 pirpanjal railway tunnel
36/84
36
PIR PANJAL TUNNEL-EXCAVATION PROGRESS
Year Excavation(mts.)
Remarks
2006 722 Two Faces
2007 1876 Start From 4 Faces2008 2475
2009 2533
2010 1739 Two Faces after Jan10
2011 947 High overburden,Squeezing, Shale
2012 63
8/12/2019 pirpanjal railway tunnel
37/84
8/12/2019 pirpanjal railway tunnel
38/84
8/12/2019 pirpanjal railway tunnel
39/84
8/12/2019 pirpanjal railway tunnel
40/84
40
Miles to go
A thing should be madeas simple as possible,
but not simpler.
Einstein
8/12/2019 pirpanjal railway tunnel
41/84
41
THANKS !
8/12/2019 pirpanjal railway tunnel
42/84
42
ENGAGEMENT OF CONSULTANT Investigations for Tunneling Methodology
Assessment Initial Design
Usage of NATM
Usage of Water proof Membrane for Semi DryTunnel Development of 4-Arc Tunnel X-Section Additional Access through ADIT and Shaft Portal Location Review
Real Time Monitoring / Instrumentationand Design Support
8/12/2019 pirpanjal railway tunnel
43/84
43
INVESTIGATIONS & PLANNING2003 Geological L-Section Profile Submitted by M/s
RITES based on GSI data.-Used to decide the Bore hole Location.
2003-04 Bore holes by RITES/ MECL-To Confirm Geological Mapping inference
2004 Consultants engaged in Feb. 2004Geological Surface Mapping along the entire alignment by -For Detailed Geological Section
2004 Data input for Tendering and a Decision Support System forADIT and Shaft decision
Adit & Shaft Work Awarded in June 2004
2004 Detailed Topographical Survey for PortalLocation
2005 Main Tunnel Construction Work Awarded in
August 2005
8/12/2019 pirpanjal railway tunnel
44/84
44
8/12/2019 pirpanjal railway tunnel
45/84
45
8/12/2019 pirpanjal railway tunnel
46/84
46
8/12/2019 pirpanjal railway tunnel
47/84
BASIC PRINCIPLES OF NATM Rock Mass is the major load bearing
member Primary Support shall
maintain the integrity & strength of Rock Mass
light, have good and area contact (shotcrete)strengthen Rock Mass (bolt, grouting)provide protection to workers (steel rib, mesh)
installed quickly Provide always an effective ring closure, ifnecessary by an invert if rock is notsuitable
8/12/2019 pirpanjal railway tunnel
48/84
BASIC PRINCIPLES OF NATM (Contd.)
Rounded shape of Cross-Section Continuous control of system behaviour
by monitoring Inner lining shall be installed only after
balance of stresses (zero deformation)
8/12/2019 pirpanjal railway tunnel
49/84
49
8/12/2019 pirpanjal railway tunnel
50/84
503D Monitoring Targets
8/12/2019 pirpanjal railway tunnel
51/84
51
8/12/2019 pirpanjal railway tunnel
52/84
52
EXTENSOMETER
8/12/2019 pirpanjal railway tunnel
53/84
53
EXTENSOMETER
FACE MAPPING
8/12/2019 pirpanjal railway tunnel
54/84
54
FACE MAPPING
PROBING SHEET
8/12/2019 pirpanjal railway tunnel
55/84
55
PROBING SHEET
8/12/2019 pirpanjal railway tunnel
56/84
56
8/12/2019 pirpanjal railway tunnel
57/84
57
8/12/2019 pirpanjal railway tunnel
58/84
58
8/12/2019 pirpanjal railway tunnel
59/84
59
DeformationMonitoring in Primary
Lining Before start ofSecondary Lining
8/12/2019 pirpanjal railway tunnel
60/84
60
8/12/2019 pirpanjal railway tunnel
61/84
61
8/12/2019 pirpanjal railway tunnel
62/84
62Charging of Face
8/12/2019 pirpanjal railway tunnel
63/84
63Ventilation Duct
8/12/2019 pirpanjal railway tunnel
64/84
64Mucking
8/12/2019 pirpanjal railway tunnel
65/84
65Wire mesh & Lattice Girder Erection
8/12/2019 pirpanjal railway tunnel
66/84
66
Face sealingFace sealing by Shotcrete
8/12/2019 pirpanjal railway tunnel
67/84
67Drilling for Forepoling
8/12/2019 pirpanjal railway tunnel
68/84
68Rock Bolting TUNNEL MINING
8/12/2019 pirpanjal railway tunnel
69/84
69
TUNNEL MININGActivity Cycle Time (hr.) 2 mt.RC IV
Cycle time (hr.) 1.25mt. RC V
Drilling & Excavation 1.7 0.9
Charging , Blasting& Defuming 2.7 1.5
Mucking 1.1 0.8
Wire Mesh & LatticeGirder 2.4 2.3
Shotcrete 0.9 0.8
Rock Bolting 1.8 1.0
Preparation of newface 0.3 0.3
Maintenance 1.6 1.1
Forepoling 1.6 1.7
Total 14.1 10.4
8/12/2019 pirpanjal railway tunnel
70/84
70
8/12/2019 pirpanjal railway tunnel
71/84
71
Kicker Beam Casting
8/12/2019 pirpanjal railway tunnel
72/84
72Geotextile Fixing
8/12/2019 pirpanjal railway tunnel
73/84
73PVC Membrane Fixing
8/12/2019 pirpanjal railway tunnel
74/84
74 Membrane Stitching
8/12/2019 pirpanjal railway tunnel
75/84
75Reinforcement for Overt Lining
8/12/2019 pirpanjal railway tunnel
76/84
76Reinforcement Cage for Inner Lining
8/12/2019 pirpanjal railway tunnel
77/84
77Concrete Lining Gantry
8/12/2019 pirpanjal railway tunnel
78/84
78
View of Finished Lining Concrete
8/12/2019 pirpanjal railway tunnel
79/84
79
Profile Checking with Total Station
8/12/2019 pirpanjal railway tunnel
80/84
80 Core Cutting
8/12/2019 pirpanjal railway tunnel
81/84
81Testing of Joints (Membrane)
8/12/2019 pirpanjal railway tunnel
82/84
82
Sedimentation Tank
8/12/2019 pirpanjal railway tunnel
83/84
83
Effluent QualityTest Report
8/12/2019 pirpanjal railway tunnel
84/84