pirpanjal railway tunnel

Embed Size (px)

Citation preview

  • 8/12/2019 pirpanjal railway tunnel

    1/84

    WELCOME YOU TO

    PIRPANJAL RAILWAY TUNNELSITE

    THE LONGEST TRANSPORTATION

    TUNNEL IN INDIA

  • 8/12/2019 pirpanjal railway tunnel

    2/84

    2

    Location Overview Salient Features of The Tunnel Construction Approach

    Pre-construction Planning Usage Of NATM in T-80 Construction Activities

    Quality Assurance Environment Issues Social Impact

    PRESENTATION COVERS

  • 8/12/2019 pirpanjal railway tunnel

    3/84

    LOCATION OVERVIEW

  • 8/12/2019 pirpanjal railway tunnel

    4/84

    4

    ALIGNMENT PLAN

    JAMMU-UDHAMPUR-SRINAGAR-BARAMULLA RAIL

    LINK

    QAZIGUND

    SADURA

    ANANTNAG

    BIJBEHARAPUNZGAM

    AWANTIPORA

    KAKPORAPAMPORE

    SRINAGAR

    BUDGAM

    RAJWANSHER

    PATTANHAMRE

    SOPOREBARAMULLA

    BANIHALARPINCHALA

    BHATTALOALE

    KOHLISANGALDAN

    BARALABASANDA--DHAR

    REASI

    KATRACHAKARWAH

    UDHAMPUR

    SALAL

    RAMNAGARROADMANWAL

    SANGARBAJALTAJAMM

    U

    SURUKOT

    PIR PANJAL RAIL TUNNELLength 11100 mts.

    South portal photo

    SOUTH PORTAL

  • 8/12/2019 pirpanjal railway tunnel

    5/84

    5

  • 8/12/2019 pirpanjal railway tunnel

    6/84

  • 8/12/2019 pirpanjal railway tunnel

    7/84

    7

    SALIENT FEATURES OF T-80(Contd.)

    3 m wide road in tunnel for maintenance,emergency rescue & relief.

    High mid point & sloping in both directions fordrainage.

    Provision of system for ventilation, fire fighting &safety monitoring.

    Adit & shaft for parallel working, to be used forventilation, maintenance & emergency reliefduring service.

    Extensive instrumentation for monitoring duringtunneling

    Consultants : M/s Geoconsult-RITES JV

  • 8/12/2019 pirpanjal railway tunnel

    8/84

    8

    MANY FIRSTS The Longest Transport Tunnel In The Country

    (11Km)

    Highest Over - burden of 1100M

    Deepest Drill holes for GeotechnicalInvestigations 640M

    First Large Scale Use of New Austrian TunnelingMethod (NATM) in India

    First Use of Road header for Tunnel Excavation in Railway Tunneling

  • 8/12/2019 pirpanjal railway tunnel

    9/84

    CONSTRUCTION

    APPROACH

  • 8/12/2019 pirpanjal railway tunnel

    10/84

    10

    APPROACH TO CONSTRUCTIONNO ADIT

  • 8/12/2019 pirpanjal railway tunnel

    11/84

    11

    Vertcal Shaft

    55m deep,

    12m dia

    Cross Passage 55 m

    Adit 788 m

    APPROACH TO CONSTRUCTIONWITH SHAFT AND ADIT

  • 8/12/2019 pirpanjal railway tunnel

    12/84

    12

    Tunnel

    CrossSection:

    STRUCTURAL GAUGE

  • 8/12/2019 pirpanjal railway tunnel

    13/84

  • 8/12/2019 pirpanjal railway tunnel

    14/84

    14

    TYPICALRAILWAYTUNNEL

    SECTIONUSED ONJAMMU-

    UDHAMPURRAIL LINK

    SHOTCRETE(25mm+WIRE MESH +50mm)OR 50mm SFRS

    300 TH. C.C. LINING

    ISHB 150 @ 500 C/C

    50mm TH. R.C.C. LAGGING

    Min. EXCAVATION LINE

    75 @ 2000 C/C

    MS PLATE 12mm THICKISHB150-2NOS.

    INVERT STRUT ISHB150 @ 500mm

    ISHB200 @ 750 C/C

    1676

    R 2 6 0

    0

    4 3 7 0

    1 3 1 2

    150150

    Max.150(max)

    50M20

    1 in 4 0

    RAIL LEVEL

    FINISH LINE

    PAY LINE 150 TH. FROM Min. EXCAVATION25 mm 3 to 5m ROCK BOLTS

    AS PER SITE REQUIREMENT

    ISHB 150 @ 750 c/c

    RESSURE RELIEF HOLES 5m DEEP @m c/c LONGITUDINALLY AS PER SITEEQUIREMENT

    150

    PAY LINEMIN. EXCAV. LINE

    BASE PLATE12mm THICK

    R 3 0 0 0

    I S H B 1 5 0 @

    5 0 0 c / c

    S H O T C R E T E 2 5 m m +

    W I R E M E S H + 5 0 m m O

    R 5 0 m m

    S F R S

    5 0 T H

    . R . C . C . L

    A G G I N G

    150

    P R E S S U R E R E L I E F H O L E S 5 m

    D E E P @

    3 m c / c

    L O N G I T U D I N A L L Y

    A R A S P E R S I T E R E Q U I R E M E N T

    B A C K F I L L I N G M - 1

    0

    50

    F I N I S H L I N E

    3 0 0 T H

    . C O N C

    . L I N I N

    G M - 2

    0

    150

    100

    9 0 0

    BLOWER

    8 @ 150 C/C50 675 150

    100

    65

    6 7 5

    2 5 m m

    3 m t o 5 m

    R O C K B O L T A S

    P E R S I T E

    R E Q U I R E M E N T

    S E C

    . A T A - A

    75

  • 8/12/2019 pirpanjal railway tunnel

    15/84

    15

    LOADING DIAGRAM FOR TUNNELTOP PRESSURE-15000KG/M

    AND SIDE PRESSURE-5000KG/M

  • 8/12/2019 pirpanjal railway tunnel

    16/84

    16

    BENDING MOMENTS DIAGRAM FORD-SHAPE TUNNEL

    TOP PRESSURE-15000KG/M AND SIDE PRESSURE-5000KG/M

    MAX BENDING MOMENT = 137KN-M

  • 8/12/2019 pirpanjal railway tunnel

    17/84

    17

    BENDING MOMENT DIAGRAM FOR ELLIPITCAL TUNNELTOP PRESSURE 15000KG/M AND SIDE PRESSURE 5000KG/M

    MAX. BENDING MOMENT = 35.80KN-M

  • 8/12/2019 pirpanjal railway tunnel

    18/84

    COMPARISION BETWEEN D-SHAPED AND ELLIPTICAL TUNNEL

    DESCRIPTION MAX.AXIAL

    FORCE

    MAX.BENDING

    MOMENT

    MAX.SHEAR

    FORCE

    MAX.DISPLACEMENT

    WITH TOP PRESSURE 15000 KG/M & SIDE PRESSURE5000 KG/M

    D-SHAPEDTUNNEL

    412.5KN 137KN-M 15129 KG 0.083 M

    ELLIPTICALTUNNEL

    567 KN 35.80KN-M 9025 KG 0.024 M

    WITH TOP PRESSURE 15000 KG/M

    D-SHAPEDTUNNEL

    412.5KN 48.10 KN-M 8565 KG 0.03 M

    ELLIPTICALTUNNEL

    639 KN 35.65 KN-M 9635 KG 0.028 M

  • 8/12/2019 pirpanjal railway tunnel

    19/84

    19

    CONSTRUCTION METHOD

    SELECTION DRILL AND BLAST

    ROAD HEADER

    TUNNEL BORING MACHINE (TBM)

  • 8/12/2019 pirpanjal railway tunnel

    20/84

    20

    DRILL AND BLAST CONVENTIONAL, ART

    WHICH COMES WITHEXPERIENCE

    GOOD IN HARD ROCKYSTRATA

    WITH EXPERIENCE, CANDELIVER GOOD PROGRESS

    NON CONTINUOUS- CYCLEINVOLVES VARIOUS

    ACTIVITIES IN SEQUENCE MAY SPRING SUDDEN

    SURPRISES

  • 8/12/2019 pirpanjal railway tunnel

    21/84

    21

    ROAD HEADER CONTINUOUS ADVANCE-

    LESS SURPRISES MORE CONTROLLED

    EXCAVATION- LESSOVERBREAK/CAVITY

    FORMATION SUITABLE FOR MEDIUM

    HARD ROCK CAN BE WITHDRAWN

    MID WAY TO GIVE WAYFOR OTHER METHODS

  • 8/12/2019 pirpanjal railway tunnel

    22/84

    22

    TUNNEL BORING MACHINE

    CONTINUOUS ADVANCE CIRCULAR SECTION NOT SUITABLE UNDER

    SQUEEZINGCONDITIONS

    CANNOT BEWITHDRAWN MIDWAYTO GIVE WAY TOOTHER METHODS

  • 8/12/2019 pirpanjal railway tunnel

    23/84

    23

    WHY NO TBM

    Likelihood of Mixed Geology Heavily Faulted Areas and/or Wide

    Fault Zones High Squeezing Anticipated in middle

    with High Overburden (1100 mts.) Heavy Water Flow in Lime Stone Zone

    with High overburden TBM may be Trapped by Ground

    Movement Behind the Face

  • 8/12/2019 pirpanjal railway tunnel

    24/84

    PRE-CONSTRUCTIONPLANNING

  • 8/12/2019 pirpanjal railway tunnel

    25/84

    25

    PRE-CONSTRUCTIONPLANNING

    Engagement of Consultant QCB System Of tendering

    Survey and Investigation

    Head start by Taking up ADIT and shaftworks in advance

    Tender Planning Key dates Multi Method Approach

    Road Header/ D&B

  • 8/12/2019 pirpanjal railway tunnel

    26/84

  • 8/12/2019 pirpanjal railway tunnel

    27/84

    27

    USAGE OF NATM IN T-80 Suitable for poor and Varying Geology of

    Himalayan Region X-Section designed to develop Maximum Self

    Supporting Capacity

    Face Mapping , Probe Hole & Instrumentationdata input for Initial Support Design RESS Primary Support System

    Resilient enough to Accept the deformations and readjustment ofstresses and Strong enough to take the loads

    Deformation Monitoring to assess the stressredistribution, and stabilization before finallining

  • 8/12/2019 pirpanjal railway tunnel

    28/84

    28

    INSTRUMENTATIONTo provide early information about tunnel behaviour in order to optimize

    excavation & support activities during construction and to recognize the requisiteremedial measures.

    Instrumentation data is basic input of the NATM, the observational approach.

    Instrumentation in Pir Panjal Tunnel:

    Optical 3 D monitoring : With bi-reflex targets to monitor deformation intunnel on daily basis

    Extensometers: To measure stresses in surrounding rock mass

    Radial Pressure Cells : To measure pressure of rockmass on shotcretelining

    Shotcrete Strain meter: To monitor stresses in shotcrete lining

    Piezometer: To monitor hydrostatic pressure during tunneling

  • 8/12/2019 pirpanjal railway tunnel

    29/84

    29

    CONSTRUCTION ACTIVITES

    Open excavation & portal development Tunnel mining & primary lining Water-proof membrane installation +

    drainage system. Secondary lining. Ventilation, system and safety

    installations Track laying

  • 8/12/2019 pirpanjal railway tunnel

    30/84

    30

    QUALITY ASSURANCE

    Laid down responsibilities,procedures and checklists forvarious activities through: CPM, CQM, SH&EM PPM, PSM Organogram

    QAP ITP

  • 8/12/2019 pirpanjal railway tunnel

    31/84

    31

    QUALITY ASSURANCE (contd)

    Availability of relevant documentation and definingthe manner of execution of various activities

    Maintaining compliance through appropriatemonitoring

    Ensuring adequate support facilities for successful& scheduled execution of work.

    Availability of competent/trained personnel to carryout various activities

    Compliance of statutory/regulatory requirementsrelated to safety, environment etc.

  • 8/12/2019 pirpanjal railway tunnel

    32/84

    32

    Quality Assurance (contd)

    Check Lists and Forms for Process Control DuringExecution of Works:

    Required Excavation and Support Sheet (RESS) ATSS/ Shift Report/Blasting clearance report/ R/Bolt

    Installation report Shotcrete testing by Penetrometer test, Core

    crushing test , thickness verification etc. Geological mapping (Geological face mapping sheet)

    Lining Air Permeability Test All Material Testing at Site Lab

  • 8/12/2019 pirpanjal railway tunnel

    33/84

    33

    ENVIRONMENT ISSUES Identified Muck Dumping areas

    Recycling of Excavated Rocks aggregate for concrete constn.

    Effluent Settling Tank

    Fit for agriculture discharge Ventilation during Construction Stage

    Gas Analyser for air quality monitoring

    Controlled Blasting below Inhabitedareas Lined Waterproof Tunnel

    No long term impact on water table/ Aquifers

  • 8/12/2019 pirpanjal railway tunnel

    34/84

    34

    SOCIAL IMPACT All weather link, Alternate to Jawahar

    Tunnel Even at Construction stage, given a

    boost to local construction-industry Employment Transportation business

    A boost to Local economy of Banihal

  • 8/12/2019 pirpanjal railway tunnel

    35/84

    35Time Line

  • 8/12/2019 pirpanjal railway tunnel

    36/84

    36

    PIR PANJAL TUNNEL-EXCAVATION PROGRESS

    Year Excavation(mts.)

    Remarks

    2006 722 Two Faces

    2007 1876 Start From 4 Faces2008 2475

    2009 2533

    2010 1739 Two Faces after Jan10

    2011 947 High overburden,Squeezing, Shale

    2012 63

  • 8/12/2019 pirpanjal railway tunnel

    37/84

  • 8/12/2019 pirpanjal railway tunnel

    38/84

  • 8/12/2019 pirpanjal railway tunnel

    39/84

  • 8/12/2019 pirpanjal railway tunnel

    40/84

    40

    Miles to go

    A thing should be madeas simple as possible,

    but not simpler.

    Einstein

  • 8/12/2019 pirpanjal railway tunnel

    41/84

    41

    THANKS !

  • 8/12/2019 pirpanjal railway tunnel

    42/84

    42

    ENGAGEMENT OF CONSULTANT Investigations for Tunneling Methodology

    Assessment Initial Design

    Usage of NATM

    Usage of Water proof Membrane for Semi DryTunnel Development of 4-Arc Tunnel X-Section Additional Access through ADIT and Shaft Portal Location Review

    Real Time Monitoring / Instrumentationand Design Support

  • 8/12/2019 pirpanjal railway tunnel

    43/84

    43

    INVESTIGATIONS & PLANNING2003 Geological L-Section Profile Submitted by M/s

    RITES based on GSI data.-Used to decide the Bore hole Location.

    2003-04 Bore holes by RITES/ MECL-To Confirm Geological Mapping inference

    2004 Consultants engaged in Feb. 2004Geological Surface Mapping along the entire alignment by -For Detailed Geological Section

    2004 Data input for Tendering and a Decision Support System forADIT and Shaft decision

    Adit & Shaft Work Awarded in June 2004

    2004 Detailed Topographical Survey for PortalLocation

    2005 Main Tunnel Construction Work Awarded in

    August 2005

  • 8/12/2019 pirpanjal railway tunnel

    44/84

    44

  • 8/12/2019 pirpanjal railway tunnel

    45/84

    45

  • 8/12/2019 pirpanjal railway tunnel

    46/84

    46

  • 8/12/2019 pirpanjal railway tunnel

    47/84

    BASIC PRINCIPLES OF NATM Rock Mass is the major load bearing

    member Primary Support shall

    maintain the integrity & strength of Rock Mass

    light, have good and area contact (shotcrete)strengthen Rock Mass (bolt, grouting)provide protection to workers (steel rib, mesh)

    installed quickly Provide always an effective ring closure, ifnecessary by an invert if rock is notsuitable

  • 8/12/2019 pirpanjal railway tunnel

    48/84

    BASIC PRINCIPLES OF NATM (Contd.)

    Rounded shape of Cross-Section Continuous control of system behaviour

    by monitoring Inner lining shall be installed only after

    balance of stresses (zero deformation)

  • 8/12/2019 pirpanjal railway tunnel

    49/84

    49

  • 8/12/2019 pirpanjal railway tunnel

    50/84

    503D Monitoring Targets

  • 8/12/2019 pirpanjal railway tunnel

    51/84

    51

  • 8/12/2019 pirpanjal railway tunnel

    52/84

    52

    EXTENSOMETER

  • 8/12/2019 pirpanjal railway tunnel

    53/84

    53

    EXTENSOMETER

    FACE MAPPING

  • 8/12/2019 pirpanjal railway tunnel

    54/84

    54

    FACE MAPPING

    PROBING SHEET

  • 8/12/2019 pirpanjal railway tunnel

    55/84

    55

    PROBING SHEET

  • 8/12/2019 pirpanjal railway tunnel

    56/84

    56

  • 8/12/2019 pirpanjal railway tunnel

    57/84

    57

  • 8/12/2019 pirpanjal railway tunnel

    58/84

    58

  • 8/12/2019 pirpanjal railway tunnel

    59/84

    59

    DeformationMonitoring in Primary

    Lining Before start ofSecondary Lining

  • 8/12/2019 pirpanjal railway tunnel

    60/84

    60

  • 8/12/2019 pirpanjal railway tunnel

    61/84

    61

  • 8/12/2019 pirpanjal railway tunnel

    62/84

    62Charging of Face

  • 8/12/2019 pirpanjal railway tunnel

    63/84

    63Ventilation Duct

  • 8/12/2019 pirpanjal railway tunnel

    64/84

    64Mucking

  • 8/12/2019 pirpanjal railway tunnel

    65/84

    65Wire mesh & Lattice Girder Erection

  • 8/12/2019 pirpanjal railway tunnel

    66/84

    66

    Face sealingFace sealing by Shotcrete

  • 8/12/2019 pirpanjal railway tunnel

    67/84

    67Drilling for Forepoling

  • 8/12/2019 pirpanjal railway tunnel

    68/84

    68Rock Bolting TUNNEL MINING

  • 8/12/2019 pirpanjal railway tunnel

    69/84

    69

    TUNNEL MININGActivity Cycle Time (hr.) 2 mt.RC IV

    Cycle time (hr.) 1.25mt. RC V

    Drilling & Excavation 1.7 0.9

    Charging , Blasting& Defuming 2.7 1.5

    Mucking 1.1 0.8

    Wire Mesh & LatticeGirder 2.4 2.3

    Shotcrete 0.9 0.8

    Rock Bolting 1.8 1.0

    Preparation of newface 0.3 0.3

    Maintenance 1.6 1.1

    Forepoling 1.6 1.7

    Total 14.1 10.4

  • 8/12/2019 pirpanjal railway tunnel

    70/84

    70

  • 8/12/2019 pirpanjal railway tunnel

    71/84

    71

    Kicker Beam Casting

  • 8/12/2019 pirpanjal railway tunnel

    72/84

    72Geotextile Fixing

  • 8/12/2019 pirpanjal railway tunnel

    73/84

    73PVC Membrane Fixing

  • 8/12/2019 pirpanjal railway tunnel

    74/84

    74 Membrane Stitching

  • 8/12/2019 pirpanjal railway tunnel

    75/84

    75Reinforcement for Overt Lining

  • 8/12/2019 pirpanjal railway tunnel

    76/84

    76Reinforcement Cage for Inner Lining

  • 8/12/2019 pirpanjal railway tunnel

    77/84

    77Concrete Lining Gantry

  • 8/12/2019 pirpanjal railway tunnel

    78/84

    78

    View of Finished Lining Concrete

  • 8/12/2019 pirpanjal railway tunnel

    79/84

    79

    Profile Checking with Total Station

  • 8/12/2019 pirpanjal railway tunnel

    80/84

    80 Core Cutting

  • 8/12/2019 pirpanjal railway tunnel

    81/84

    81Testing of Joints (Membrane)

  • 8/12/2019 pirpanjal railway tunnel

    82/84

    82

    Sedimentation Tank

  • 8/12/2019 pirpanjal railway tunnel

    83/84

    83

    Effluent QualityTest Report

  • 8/12/2019 pirpanjal railway tunnel

    84/84