PI Tag Creation Deliverables The following services are performed: Pre-installation checklist review; confirmation that all prerequisites are met before proceeding Documented submittal of PI tags and PI digital sets to be created for customer approval Configuration and creation of required PI digital sets Configuration and creation of the PI tags on the PI server (Up to 20,000 tags) Creation of a stale and bad tag report (Electronic format) Provide coaching for the configuration and troubleshooting of specific interface PI tags to the system manager OSIsoft technical support overview Installation report Timeline The installation process, from ordering to completion, normally takes 2 to 3 weeks: Week 1 and 2 – Communication of prerequisites. Confirmation of on site date with OSIsoft. Provide to OSIsoft an electronic version of the raw tag information extracted from the data source. Week 3 – On site installation by OSIsoft (Up to two days) Requirements PI Server and PI Interface must be operational before OSIsoft's arrival Customer must provide an electronic version of required raw tag information extracted from the data source (Tagname, description, zero, span, engineering units, point type, state information and control system address). Required information will be validated during the pre-installation checklist review Customer's technical staff needs to be available to provide system support (Security, Network and Control Systems) Customer must provide a configuration station with the PI SMT tools and MS Excel software Customer must arrange for safety training, and any permits required Customer must provide all special safety equipment as required Suggested prerequisite package We recommend that the following service package or equivalent installation be done prior to ordering the above described service: Base PI System installation (part no: SVC-PACK-PIINST) Objectives The primary objective is to create tags for one or two standard PI Interfaces already installed at the customer site. The installation is performed on site by a qualified member of our OSIsoft PI system field service team. The scope of this package is limited to the configuration of 20,000 PI tags.

PITagCreation_2

Embed Size (px)

DESCRIPTION

Pre-installation checklist review; confirmation that all prerequisites are metbefore proceeding

Citation preview

  • PI Tag Creation Deliverables The following services are performed: Pre-installation checklist review; confirmation that all prerequisites are met

    before proceeding Documented submittal of PI tags and PI digital sets to be created for

    customer approval Configuration and creation of required PI digital sets Configuration and creation of the PI tags on the PI server (Up to 20,000

    tags) Creation of a stale and bad tag report (Electronic format) Provide coaching for the configuration and troubleshooting of specific

    interface PI tags to the system manager OSIsoft technical support overview Installation report Timeline The installation process, from ordering to completion, normally takes 2 to 3 weeks: Week 1 and 2 Communication of prerequisites. Confirmation of on site date with OSIsoft. Provide to OSIsoft an electronic version of the raw tag information extracted from the data source. Week 3 On site installation by OSIsoft (Up to two days) Requirements PI Server and PI Interface must be operational before OSIsoft's arrival Customer must provide an electronic version of required raw tag information

    extracted from the data source (Tagname, description, zero, span, engineering units, point type, state information and control system address). Required information will be validated during the pre-installation checklist review

    Customer's technical staff needs to be available to provide system support (Security, Network and Control Systems)

    Customer must provide a configuration station with the PI SMT tools and MS Excel software

    Customer must arrange for safety training, and any permits required Customer must provide all special safety equipment as required Suggested prerequisite package We recommend that the following service package or equivalent installation be done prior to ordering the above described service: Base PI System installation (part no: SVC-PACK-PIINST)

    Objectives The primary objective is to create tags for one or two standard PI Interfaces already installed at the customer site. The installation is performed on site by a qualified member of our OSIsoft PI system field service team. The scope of this package is limited to the configuration of 20,000 PI tags.

  • Package This package includes 2 days of OSIsoft field service excluding travel time. Travel and living expenses will be invoiced at cost.

    OSIsoft, Inc. 777 Davis Street Suite 250 San Leandro, CA 94577 (510) 297-5800

    www.osisoft.com

    Why SELECT OSIsoft PI system field services Our PI system field service staff works closely with OSIsoft development, training, and technical support teams to bring unique experience and knowledge of the OSIsoft product line to the customer site. Most of our PI system field service staff are Microsoft Certified Professionals. For further information, contact your Sales Representative. Version: June 2006 Part No: SVC-PACK-PITAG