Plan Aceleración_Avance Disciplinas

Embed Size (px)

DESCRIPTION

PLAN DE ACELERAMIENTO

Citation preview

Page 1: Plan Aceleración_Avance Disciplinas

7/17/2019 Plan Aceleración_Avance Disciplinas

http://slidepdf.com/reader/full/plan-aceleracionavance-disciplinas 1/1

15‐may‐15 22‐may‐15 29‐may‐15 05‐ jun‐15 12‐ jun‐15 19‐ jun‐15 26‐ jun‐15 03‐ jul‐15 10‐ jul‐15 17‐ jul‐15 24‐ jul‐15 31‐ jul‐15 07‐ago‐15 TOTAL

5% 6% 7% 8% 9% 10% 10% 10% 10% 10%

PROCESOS   64.57% 71.97% 79.18% 86.44% 92.51% 95.47% 98.06% 98.51% 100.00% 100.00% 100.00%

CIVIL   43.73% 53.33% 60.67% 70.64% 77.74% 83.75% 88.28% 91.23% 95.44% 98.23% 100.00%

TUBERÍA   41.84% 48.44% 52.40% 62.46% 76.19% 86.17% 91.66% 95.00% 97.78% 99.52% 100.00%

MECÁNICA   30.02% 39.44% 43.05% 47.89% 61.36% 79.67% 88.20% 92.61% 95.77% 98.86% 100.00%

ELÉCTRICA   54.11% 63.32% 71.19% 76.75% 84.14% 92.31% 96.27% 98.43% 98.84% 99.93% 100.00%

INSTRUMENTACIÓN   47.58% 55.87% 64.59% 73.59% 85.02% 90.02% 96.62% 97.88% 100.00% 100.00% 100.00%

PROCESOS   76.97% 85.18% 93.44% 100.51% 104.47% 108.06% 108.51% 110.00% 110.00% 110.00%

CIVIL   58.33% 66.67% 77.64% 85.74% 92.75% 98.28% 101.23% 105.44% 108.23% 110.00%

TUBERÍA   53.44% 58.40% 69.46% 84.19% 95.17% 101.66% 105.00% 107.78% 109.52% 110.00%

MECÁNICA   44.44% 49.05% 54.89% 69.36% 88.67% 98.20% 102.61% 105.77% 108.86% 110.00%

ELÉCTRICA   68.32% 77.19% 83.75% 92.14% 101.31% 106.27% 108.43% 108.84% 109.93% 110.00%

INSTRUMENTACIÓN   60.87% 70.59% 80.59% 93.02% 99.02% 106.62% 107.88% 110.00% 110.00% 110.00%

PORCENTAJE DE AVANCE PLANIFICADO (DE ACUERDO A LA CURVA)

PORCENTAJE DE AVANCE PLANIFICADO (ACELERADO)