Upload
joshua-bradley
View
224
Download
6
Tags:
Embed Size (px)
Citation preview
Plans for the upgrade of the CERN Plans for the upgrade of the CERN complex of proton acceleratorscomplex of proton accelerators
R. Garoby
ContentContent
Introduction (European Strategy & CERN white paper) Scenarios for the upgrade of the accelerators Linac4 SPL & PS2 Roadmap Summary
R. G. 2IDS meeting - CERN – 29 March
2007
INTRODUCTIONINTRODUCTION
Introduction
R. G. 3IDS meeting - CERN – 29 March
2007
Statement of the European Strategy Group (1/2)
Consolidation and upgrade of
injectors
LHC upgrade and maximum performance
injectors
R. G. 4IDS meeting - CERN – 29 March
2007
Statement of the European Strategy Group (2/2)
R & D for LHC upgrade and facility
preparation for facility
R. G. 5IDS meeting - CERN – 29 March
2007
Section 3: Further activities to be funded by additional resourcesSection 3: Further activities to be funded by additional resources
Theme 1: consolidation and basic improvements: Basic consolidation of existing accelerators New power supply for the PS New multi-turn ejection Etc.
Theme 2: renovation of the old injector complex: R & D for a new PS and his injector (SPL) Construction of Linac4
Theme 3: R & D for LHC upgrade and CLIC: R & D on superconducting magnets, RF and cryogenics R & D for LHC detectors Increased support for CLIC
Theme 4: miscellaneous R & D: SC RF High power target ELENA, HIE ISOLDE, 3rd phase NA-48…
“White Paper” (1/2)Submitted for information and
discussionat the 139th meeting
of the CERN Council (19 October 2006)
Material Material (MCHF)(MCHF)
Personnel Personnel (man.years)(man.years)
103103 246246
5555 185185
5858 212212
4141 145145
Total request: 240 MCHF during 2008-2010
R. G. 6IDS meeting - CERN – 29 March
2007
Section 4: Prospects over the period 2011-2016Section 4: Prospects over the period 2011-2016
1)
2) CLIC …
3) Infrastructure consolidation
4)
“White Paper” (2/2)Submitted for information and
discussionat the 139th meeting
of the CERN Council (19 October 2006)
R. G. 7IDS meeting - CERN – 29 March
2007
SCENARIOS FOR THE SCENARIOS FOR THE UPGRADE OF THE UPGRADE OF THE ACCELERATORSACCELERATORS
R. G. 8IDS meeting - CERN – 29 March
2007
CERN accelerator complex
R. G. 9IDS meeting - CERN – 29 March
2007
PSB SPL’RCPSB
SPSSPS+
Linac4
SPL
PS
LHC / SLHC DLHC
Out
put
ener
gy
160 MeV
1.4 GeV~ 5 GeV
26 GeV40 – 60 GeV
450 GeV1 TeV
7 TeV~ 14 TeV
Linac250 MeV
SPL: Superconducting Proton Linac (~ 5 GeV)
SPL’: RCPSB injector(0.16 to 0.4-1 GeV)
RCPSB: Rapid Cycling PSB(0.4-1 to ~ 5 GeV)
PS2: High Energy PS(~ 5 to 50 GeV – 0.3 Hz)
PS2+: Superconducting PS(~ 5 to 50 GeV – 0.3 Hz)
SPS+: Superconducting SPS(50 to1000 GeV)
SLHC: “Superluminosity” LHC(up to 1035 cm-2s-1)
DLHC: “Double energy” LHC(1 to ~14 TeV)
Proton flux / Beam power
Upgrades of the accelerator complex
PS2 (PS2+)
As proposed by the PAF working group
R. G. 10IDS meeting - CERN – 29 March
2007
Benefits for physics
STAGESTAGE 11 33 44
DESCRIPTIONDESCRIPTION ((new acceleratornew accelerator))
Linac4Linac4
PSBPSB
PSPS
SPSSPS
Linac4Linac4
SPLSPL
PS2 or PS2+PS2 or PS2+
SPSSPS
Linac4Linac4
SPLSPL
PS2 or PS2+PS2 or PS2+
SPS+SPS+
Performance of LHC Performance of LHC injectorsinjectors (SLHC) (SLHC)
++
Ultimate beam from Ultimate beam from PSPS
++++
Maximum SPS Maximum SPS performanceperformance
++++++
Highest performance Highest performance LHC injectorLHC injector
Higher energy LHCHigher energy LHC -- -- ++++++
beambeam -- ++ (++ (~100)~100) ++ (++ (~200)~200)
FactoryFactory -- +++ (~5 GeV prod. +++ (~5 GeV prod. beam)beam)
+++ (~5 GeV prod. +++ (~5 GeV prod. beam)beam)
k, k, --~400 kW beam at~400 kW beam at
50 GeV50 GeV
~400 kW beam at~400 kW beam at
50 GeV50 GeV
EURISOLEURISOL -- ++++++ ++++++
R. G. 11IDS meeting - CERN – 29 March
2007
Layout of the new LHC injectors
SPS
PS2
SPL
Linac4PS
R. G. 12IDS meeting - CERN – 29 March
2007
Proton driver for a Factory & EURISOL
Connection PS2 -> TT70
Accumulator & Compressor
SPL
R. G. 13IDS meeting - CERN – 29 March
2007
Possible layout of a Factory
storage
ring
Target
accelerator
Based on CERN scheme in 2001
SPL
R. G. 14IDS meeting - CERN – 29 March
2007
LINAC4LINAC4
Technical Design Report (December 2006) Technical Design Report (December 2006)
CERN-AB-2006-084, http://cdsweb.cern.ch/record/1004186
L. Arnaudon, P. Baudrenghien, M. Baylac, G. Bellodi, Y. Body, J. Borburgh, P. Bourquin, J. Broere, O.Brunner, L. Bruno, C. Carli, F. Caspers, S.; Cousineau, Y. Cuvet, C. De Almeida Martins, T. Dobers, T. Fowler, R. Garoby, F. Gerigk, B. Goddard, K. Hanke, M. Hori, M. Jones, K. Kahle, W. Kalbreier, T. Kroyer, D. Küchler, A.M Lombardi, L.A López-Hernandez, M. Magistris, M. Martini, S. Maury, E.Page, M. Paoluzzi, M. Pasini, U. Raich, C. Rossi, J.P Royer, E. Sargsyan, J. Serrano, R. Scrivens, M. Silari, M. Timmins, W.Venturini-Delsolaro, M. Vretenar, R. Wegner, W. Weterings, T. Zickler
R. G. 15IDS meeting - CERN – 29 March
2007
Linac4 parameters
2 operating modes: low duty for PS Booster (PSB) injection in the first phase, high duty for the SPL in a second phase.
Structures and klystrons dimensioned for 50 Hz Power supplies and electronics dimensioned for 2 Hz.
Will re-use 352 MHz LEP RF components: klystrons, waveguides, circulators.
Ion species H−Output Energy 160 MeVBunch Frequency 352.2 MHzMax. Rep. Rate 2 HzBeam Pulse Length 400 sMax. Beam Duty Cycle 0.08 %Chopper Beam-on Factor 62 %Chopping scheme:
222 transmitted /133 empty bucketsSource current 80 mARFQ output current 70 mALinac current 40 mAN. particles per pulse 1.0 × 1014
Transverse emittance 0.4 mm mrad
Max. rep. rate for accelerating structures 50 Hz
R. G. 16IDS meeting - CERN – 29 March
2007
Linac4 topology
DTL CCDTL SCL
3MeV
40MeV 90MeV 160MeV
Drift TubeLinac
352 MHz13.4 m3 tanks5 klystrons4 MW82 PMQuad
Side Coupled Linac
704 MHz28 m20 tanks4 klystrons12 MW20 EMQuads
Cell-Coupled Drift TubeLinac352 MHz25.3 m24 tanks8 klystrons6.5 MW24 EMQuads
Duty cycle:0.1% phase 1 (Linac4)3-4% phase 2 (SPL)(design: 15%)
4 different structures, (RFQ, DTL, CCDTL, SCL) 2 frequenciesTotal Linac4:
80 m, 18 klystrons
current: 40 mA (avg. in pulse), 65 mA (bunch)
CHOPPERRFQ
Chopper
352 MHz3.6 m11 EMquad3 rf cavity
Radio FrequencyQuadrupole(IPHI)352 MHz6 m1 Klystron1 MW
H-
3MeV95keV
RF volumesource(DESY)35 kVExtrac.60kV Postacc.
R. G. 17IDS meeting - CERN – 29 March
2007
The 3 MeV Test Stand
In construction, first beam foreseen in 2008.
- H- source (DESY type, - LEBT (2 solenoid)- IPHI RFQ- Chopper line (from CERN)- Diagnostics line (IPHI and CERN components)- Infrastructure (1 LEP Klystron, pulsed power supply, etc.)
Beam quality is generated in the front-end.
=> Its early understanding and optimisation is fundamental for a modern linac project.
R. G. 18IDS meeting - CERN – 29 March
2007
The IPHI RFQ
The 3 MeV Test Stand, Linac4 and finally SPL will use an RFQ built with IPHI technology (brazing at CERN).
The RFQ is expected at CERN before the end of 2008.
R. G. 19IDS meeting - CERN – 29 March
2007
The 3 MeV chopper line
Compact design 3.7 m lengthDynamic range 20 – 60 mASmall growth 4% long., 8% trans.Tolerant to alignment errors
Chopper structure: double meander strip line, 400mm length, metallized ceramic plate. 2 ns rise/fall time for bunch selectivity (352 MHz beam structure), ±500V between deflecting plates.
Dumping of chopped beam and collimation of unchopped beam in a conical dump structure
3 RF bunchers
R. G. 20IDS meeting - CERN – 29 March
2007
Cell Coupled DTL
Used above 40 MeV:Used above 40 MeV:
focusing periods can be longer focusing periods can be longer structure with external quadrupoles, structure with external quadrupoles, placed between short DTL-like tanks placed between short DTL-like tanks
With respect to DTL: can use electro-With respect to DTL: can use electro-magnets, easy access and cooling, magnets, easy access and cooling, easier machining and alignment, easier machining and alignment, simpler and more economic simpler and more economic constructionconstruction
Modules of 3 tanks connected by Modules of 3 tanks connected by coupling cells, 2 drift tubes per tank coupling cells, 2 drift tubes per tank
High-power prototype tested at CERNHigh-power prototype tested at CERN
R. G. 21IDS meeting - CERN – 29 March
2007
Beam dynamics, aperture and beam size
Large apertures (>5 times rms beam size) to minimise losses.Scraping foreseen to reduce maximum beam size in presence of errors.
R. G. 22IDS meeting - CERN – 29 March
2007
SPL SPL
Conceptual Design Report (July 2006) Conceptual Design Report (July 2006)
CERN-2006-006, http://cdsweb.cern.ch/record/975366
Baylac, M; (LPSC Grenoble) Gerigk, F (ed.); Benedico-Mora, E; Caspers, F; Chel, S (CEA Saclay) ; Deconto, J M (LPSC Grenoble) ; Duperrier, R (CEA Saclay) ; Froidefond, E (LPSC Grenoble) ; Garoby, R; Hanke, K; Hill, C; Hori, M (CERN and Tokyo Univ.) ; Inigo-Golfin, J; Kahle, K; Kroyer, T; Küchler, D; Lallement, J B; Lindroos, M; Lombardi, A M; López Hernández, A; Magistris, M; Meinschad, T K; Millich, Antonio; Noah-Messomo, E; Pagani, C (INFN Milan) ; Palladino, V (INFN Naples) ; Paoluzzi, M; Pasini, M; Pierini, P (INFN Milan) ; Rossi, C; Royer, J P; Sanmartí, M; Sargsyan, E; Scrivens, R; Silari, M; Steiner, T; Tückmantel, Joachim; Uriot, D (CEA Saclay) ; Vretenar, M;
R. G. 23IDS meeting - CERN – 29 March
2007
SPL New Layout (CDR2, 2006)
LINAC4
New SPL Design (CDR2, CERN Yellow Report 2006-006):
Linac4 (extended to 180 MeV) + 2 superconducting sections based on 5-cell elliptical cavities at 704 MHz (INFN/CEA).
Long cryomodules (LHC/TESLA-like, 12-14m), 6-8 cav./module, cold quads in cryomodules
Overall length 430m (for 3.5 GeV, was 690m in previous version for 2.2 GeV)
Medium Medium
High High
Cavity Cavity 0.650.65 11
R/Q (Ohm)R/Q (Ohm) 235235 575575
Aperture Aperture (mm)(mm) 8585 9090
EEpp/E/Eaccacc 2.62.6 2.42.4
EEaccacc (MV/m) (MV/m) 1919 2525
R. G. 24IDS meeting - CERN – 29 March
2007
SPL Beam parameters
3 different designs:
CDR2 (2006) based on 700 MHz high-gradient cavities
“slim-SPL” for LHC (2007) with low beam power, for the needs of the LHC
“MW-SPL” at higher energy, for the needs of neutrino production
CDR2CDR2 ““slim-SPL” for slim-SPL” for SPS & LHCSPS & LHC
““MW-SPL”MW-SPL”
Energy (GeV) 3.5 4 - 5 5
Beam power (MW) 4 0.15 – 0.19 4 - 8
Rep. frequency (Hz) 50 2 50
Protons/pulse (x 1014) 1.4 1.2 1
Av. Pulse current 40 10 40
Pulse duration (ms) 0.57 1.9 0.4
Bunch frequency (MHz) 352.2 352.2 352.2
Physical length (m) 430 ~460 535
R. G. 25IDS meeting - CERN – 29 March
2007
SPL cavities: elliptical, 704 MHz
Elliptical cavities at =0.5 (CEA, INFN) are giving promising results. Stiffened for pulse operation.
Length ~ 0.9mDesigned for 12 MV/m.
10 to 15 m
cryomodule
diagnostics,steering
1m 1m
* Feed 4 to 6 cavities per klystron: use high power phase and amplitude modulators.
R. G. 26IDS meeting - CERN – 29 March
2007
SPL Beam Dynamics
Control of losses, minimization of the emittance growth and halo development.
1) zero current phase advance always below 90 degrees, for stability; 2) longitudinal to transverse phase advance ratio (with current)
between 0.5 and 0.8 in order to avoid resonances 3) smooth variation of the transverse and longitudinal phase advance
per meter.
0
50
100
150
200
250
0 10 20 30 40 50 60 70
position [m]
phas
e ad
vanc
e [d
eg/m
]
kx
ky
kz
Selection of the working point (phase advances) on the Hofmann’s chart
Smooth phase advance variation
R. G. 27IDS meeting - CERN – 29 March
2007
PS2 PS2
Working group started at end 2006 Working group started at end 2006
Benedikt, M; Fabich, A; Goddard, B; Hancock, S; Jowett, J; Laface, E
R. G. 28IDS meeting - CERN – 29 March
2007
Justifications of PS2
Assure high reliability and availability of injector chain for Assure high reliability and availability of injector chain for LHC operationLHC operation PS main magnet coils and laminations Rotating machine main power converter
Increase performance of injector chain for LHC operationIncrease performance of injector chain for LHC operation Higher beam brightness by more favourable energy range Shorter filling time by improved cycling schemes
Improve performance for other physics applications in Improve performance for other physics applications in energy range PS to SPS (10 to 450 GeV).energy range PS to SPS (10 to 450 GeV).
Prepare long-term (energy) upgrade of complete accelerator Prepare long-term (energy) upgrade of complete accelerator chainchain Higher PS2 ejection energy to reduce SPS+ energy swing
Replace the PS !
R. G. 29IDS meeting - CERN – 29 March
2007
PS2 design goals
Beam brightness for LHC:Beam brightness for LHC: Reach twice brightness of the ultimate 25 ns LHC beam (20% reserve for
losses): 4.01011 per LHC bunch (inst. 1.71011) “Ultimate“ bunches at 12.5 ns, twice ultimate at 25ns, etc.
Determines average line density in the machine at injection and therefore the injection energy via incoherent SC tune spread.
Significantly higher injection energy into SPS (~50 GeV).Significantly higher injection energy into SPS (~50 GeV). Injection into SPS well above transition energy Reduced space charge at SPS injection Smaller transverse emittances and reduced losses Potential for long-term SPS replacement with higher energy.
Ejection energy determines PS2 machine size
As versatile as existing PSAs versatile as existing PS Protons, ions, high intensity physics beams, slow extraction, etc.
R. G. 30IDS meeting - CERN – 29 March
2007
Considerations on PS2 size
Existing PS with 25 GeV top energy: Existing PS with 25 GeV top energy: Combined function magnets with classical lattice. Bending radius of 70 m (~440 m length) (B = 1.25 T at 25 GeV) 114 m (174 m) of (fully used) straight sections. Average radius 100 m and machine circumference 628 m.
PS2: extraction energy ~50 GeV (NC)PS2: extraction energy ~50 GeV (NC) Separated function (eventually complicated lattice for imag. t)
Assume quads will occupy 30 % of integrated dipole length NC: dipole at ~ 1.8 T (i.e. bending radius ~100 m, length ~ 630 m) Additional space for quadrupoles: ~200 m Larger space requirements for insertions: ~300m
PS2 will have ~twice PS radius i.e. 200 m and 1250 m length
R. G. 31IDS meeting - CERN – 29 March
2007
Considerations on PS2 injection energy
Incoherent space charge tune spread at injection:Incoherent space charge tune spread at injection: Existing PS with 1.4 GeV injection energy just capable of
producing the ultimate LHC beam (Qv ~-0.3)
Bb… bunching factor (average / peak density for single bunch) Bb will decrease by factor 2 when putting the same bunch in a
machine with twice larger circumference (Q increases with R)!
PS2: twice ultimate brightness in a twice larger PS2: twice ultimate brightness in a twice larger machine machine 4 times larger incoherent tune spread at given energy. Compensation with ratio 2 at injection:
Minimum injection energy PS2: 3.5 to 4 GeV
b2
n
b.C.S B
11NQ
PS2
2PS2 4
R. G. 32IDS meeting - CERN – 29 March
2007
PS2 preliminary parameters
PS2PS2 PSPS
Injection energy kinetic (GeV)Injection energy kinetic (GeV) 3.5 – 4.03.5 – 4.0 1.41.4
Extraction energy kinetic (GeV)Extraction energy kinetic (GeV) ~ 50~ 50 13/2513/25
Circumference (m)Circumference (m) ~ 1346~ 1346 628628
Maximum intensity LHC (25ns) (p/b)Maximum intensity LHC (25ns) (p/b) 4.0 x 104.0 x 101111 1.7 x 101.7 x 101111
Maximum intensity for fixed target physics (p/p)Maximum intensity for fixed target physics (p/p) 1.2 x 101.2 x 101414 3.3 x 103.3 x 101414
Maximum energy per beam pulse (kJ)Maximum energy per beam pulse (kJ) 10001000 7070
Max ramp rate (T/s)Max ramp rate (T/s) 1.51.5 2.22.2
Repetition time at 50 GeV (s)Repetition time at 50 GeV (s) ~ 2.5~ 2.5 1.2/2.41.2/2.4
Max. effective beam power (kW)Max. effective beam power (kW)400400 6060
R. G. 33IDS meeting - CERN – 29 March
2007
ROADMAPROADMAP
R. G. 34IDS meeting - CERN – 29 March
2007
20072007 mid-2007
Optimization of the layout on the CERN site Negotiation of detailed work packages with external partners CERN Council decision on the « White paper »
July September 2007 Finalization of the design (updated design report) Conclusion on allocation of work packages / distribution of « remaining »
tasks inside CERN Market survey for Civil Engineering
September December 2007 Project review Project organization inside CERN
January 2008: official start of the Linac4 projectJanuary 2008: official start of the Linac4 project Start of Civil Engineering Start of construction of Linac4 equipment
Mid-2010Mid-2010 Progressive beam commissioning of Linac4
Mid-2011Mid-2011 PSB stop for modification PSB beam commissioning
Beginning 2012: PSB operational for physics with Linac4Beginning 2012: PSB operational for physics with Linac4
Linac4 project
R. G. 35IDS meeting - CERN – 29 March
2007
end 2010 for LHC and SPSend 2010 for LHC and SPS Selection of the most promissing scenarios for the LHC upgrade Experience with the LHC and its practical limitations… Detailed technical design of the LHC upgrade Detailed technical design of the SPS upgrade Prototyping of critical components Detailed estimates of the necessary resources Negotiation with external contributors
end 2010 for the injectors of SPSend 2010 for the injectors of SPS Optimization of the layout on the CERN site Optimization of compatibility with other users (EURISOL, ’s, pbars, heavy ions…) Detailed technical design Prototyping of critical components Detailed Civil Enginering drawings Detailed estimates of the necessary resources Negotiation with external contributors
publication of Technical Design Reports with resources estimatespublication of Technical Design Reports with resources estimates
Preparation for the SLHC
R. G. 36IDS meeting - CERN – 29 March
2007
2011 2011 2015 for LHC and SPS 2015 for LHC and SPS Construction of components for the LHC and SPS upgrade Progressive modification of the SPS (vacuum chamber treatment, impedance
reduction etc.)
2011 2011 2015 for the injectors of SPS 2015 for the injectors of SPS Construction of SPL and PS2 Progressive beam commissioning of SPL Beam commissioning of PS2
20162016 Connection of PS2 to SPS & final modifications of the SPS (injection system etc.) Beam commissioning of the SPS Beam commissioning of the LHC
Implementation of the LHC luminosity upgrade
R. G. 37IDS meeting - CERN – 29 March
2007
CDR 2
Planning of the new injectors
Linac4 approval
3 MeV test place ready
SPL & PS2 approval
R. G. 38IDS meeting - CERN – 29 March
2007
SUMMARYSUMMARY
R. G. 39IDS meeting - CERN – 29 March
2007
CERN is soon going to commission the largest and CERN is soon going to commission the largest and most sophisticated particle accelerator ever built. most sophisticated particle accelerator ever built. Such an installation must be fully exploited.Such an installation must be fully exploited. It is time to prepare for securing its operation, increasing the
reliability of all the infrastructure for protons and ions.
It is time to develop solutions for pushing performance to the limit.
It is a unique opportunity to plan new accelerators that can satisfy a new generation of physics experiments.
Mid-2007 is a first crucial milestone in an overall Mid-2007 is a first crucial milestone in an overall planning that should last for a decade.planning that should last for a decade.