Pmp Chapter 7 2004

Embed Size (px)

Citation preview

  • 8/2/2019 Pmp Chapter 7 2004

    1/33

    5/2

    Akram Al-Najj ar, PMP

    Proj ect Management Consult ant

    PMP

    Prepara t i on T ra in ing

    Your k ey in Successfu l Pro j ec tManagemen t

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 2

    Chapt er 7

    Pr o j ec t Cost

    Managemen t

  • 8/2/2019 Pmp Chapter 7 2004

    2/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 3

    AGENDA

    What is Cost Management?

    Cost Management Processes

    Some terms to be familiar with!

    How does the PMBoK Guide describe

    Cost Management?

    Discussion

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 4

    Pro j ect Cos t Managem ent

    Cost Est im at i ngCos t Budge t in g

    Cost Cont ro l

    Processes involved in planning, estimating,

    budgeting, and controlling costs so that the project

    can be completed within the approved budget.

  • 8/2/2019 Pmp Chapter 7 2004

    3/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 5

    Gantt Chart

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 6

    Planned Value (PV)

  • 8/2/2019 Pmp Chapter 7 2004

    4/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 7

    Planned Value (PV)

    Previously (and still in many places) called

    Budgeted Costs for Work Scheduled (BCWS).

    A monetary representation of how much work

    was scheduled to be done at a point in time.

    Example: After 4 months, we are scheduled to

    complete Activity 1 and 75% of Activity 2

    which are budgeted for a total of $32,000. The

    total project budget is $100,000. The PlannedValue at 4 months is $32,000.

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 8

    Work Plan Status

  • 8/2/2019 Pmp Chapter 7 2004

    5/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 9

    PV and EV

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 10

    Earned Value (EV)

    Previously (and still in many places) calledBudgeted Costs for Work Performed (BCWP).

    A monetary representation of how much workhas been completed, using the baseline cost forthat work, at a point in time.

    Example: After 4 months, we have completedActivity 1 and 50% of activity 2 . The budgetedcost for this work completed was $24,000. Thetotal project budget is $100,000. The EarnedValue at 4 months is $24,000.

  • 8/2/2019 Pmp Chapter 7 2004

    6/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 11

    PV , EV and AC

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 12

    PV , EV and AC

  • 8/2/2019 Pmp Chapter 7 2004

    7/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 13

    Actual Costs (AC)

    Previously (and still in many places) calledActual Costs for Work Performed (ACWP).

    The monetary representation of the costsincurred at a point in time, regardless of howmuch work has been done.

    Example: After 4 months, we have completedActivity 1 and 50% of activity 2. The projectcosts at this point in time are $29,000. The total

    project budget is $100,000. The Actual Cost at 4months is $29,000.

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 14

    Schedule Variance (SV)

    New:

    SV = EV PV

    = $24,000 - $32,000

    = ($8,000)

    Old:

    SV = BCWP - BCWS

    The project has

    delivered $8,000

    less work at this

    point in time than

    was planned. This

    project is behind

    schedule. This is a

    great way to depictahead or behind on

    schedule, even

    though it is in

    monetary terms!!!

  • 8/2/2019 Pmp Chapter 7 2004

    8/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 15

    Cost Variance (CV)

    New:

    CV = EV AC

    = $24,000 - $29,000

    = ($5,000)

    Old:

    CV = BCWP - ACWP

    The project has

    cost $5,000 more

    to deliver the work

    done so far than

    was planned. This

    project is over

    budget.

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 16

    Schedule Performance Index (SPI)

    New:

    SPI = EV / PV

    = $24,000 / $32,000

    = 0.75

    Old:

    SPI = BCWP / BCWS

    The project is

    delivering work

    slower than

    planned. The work

    is being done at

    75% of the

    expected rate.

  • 8/2/2019 Pmp Chapter 7 2004

    9/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 17

    Cost Performance Index (CPI)

    New:

    CPI = EV / AC

    = $24,000 / $29,000

    = 0.83

    Old:

    CPI = BCWP / ACWP

    The project is

    spending money

    faster than

    planned. Only 83%

    of work is being

    delivered for the

    amount of money

    being spent.

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 18

    Case 1

    PV = $ 1,860

    EV = $ 1,860

    AC = $ 1,860

    This is the idealsituation, whereeverything goes

    according to plan.

  • 8/2/2019 Pmp Chapter 7 2004

    10/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 19

    Case 2

    PV = $ 1,900

    AC = $ 1,700

    In this Case, withoutEarned Value

    measurements, itappears were in goodshape. Expendituresare less than planned.

    Spending Variance =- $ 200

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 20

    Case 2

    PV = $ 1,900

    EV = $ 1,500

    AC = $ 1,700

    But with EV measurements,we see...$400 worth of workis behind schedule in beingcompleted; i.e., we are 21percent behind where we

    planned to be.

    SV = EV PV =- $ 400SV % = SV / PV x 100 =- 21 %

  • 8/2/2019 Pmp Chapter 7 2004

    11/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 21

    Case 2

    PV = $ 1,900

    EV = $ 1,500

    AC = $ 1,700

    In addition, we can see...Actuals exceed Value

    Earned (EV), i.e., $1,500worth of work wasaccomplished but it cost

    $1,700 to do so. We have a$200 cost overrun (i.e., 13%

    over budget) .

    CV = EV AC =- $ 200

    CV % = CV / EV x 100 =- 13 %

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 22

    Case 2

    PV = $ 1,900

    EV = $ 1,500

    AC = $ 1,700

    This means only 79 cents worthof work was done for each $1.00

    worth of work planned to bedone.

    And, only 88 cents worth ofwork was actually done for each

    $1.00 spent

    SPI = EV / PV = $ 0.79

    CPI = EV / AC = $ 0.88

  • 8/2/2019 Pmp Chapter 7 2004

    12/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 23

    Case 2

    PV = $ 1,900

    EV = $ 1,500

    AC = $ 1,700

    This is the worst kind of

    scenario, where allperformance indicatorsare negative.

    SV =- $ 400; SPI = 0.79

    CV =

    -

    $ 200; CPI = 0.88

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 24

    PV = $ 2,600

    EV = $ 2,400

    AC = $ 2,200

    In this case there isbad news and good

    news.

    Case 3

  • 8/2/2019 Pmp Chapter 7 2004

    13/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 25

    PV = $ 2,600

    EV = $ 2,400

    AC = $ 2,200

    The bad news is that ourwork efficiency is a bit

    low; were getting only 92cents of work done on the

    dollar. As a result, weare behind schedule.

    SPI = 0.92

    SV =- $ 200; SV % =- 8 %

    Case 3

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 26

    PV = $ 2,600

    EV = $ 2,400

    AC = $ 2,200

    The good news is thatwere under-running ourbudget. Were getting$1.09 worth of workdone for each $1.00

    were spending.

    CV = + $ 200; CV % = + 8 %CPI = 1.09

    Case 3

  • 8/2/2019 Pmp Chapter 7 2004

    14/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 27

    Budget At Completion (BAC)

    This is the baseline cost of the total project.

    How much we planned to spend by the time we

    finished.

    Example: After 4 months, we have completed

    Activity 1 and 50% of Activity 2 The project

    costs at this point in time are $29,000. The total

    project budget is $100,000. The Budget At

    Completion is $100,000.

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 28

    Estimate At Completion (EAC)

    Based on where we are now, how much will it

    cost when the project is done?

    The answer depends on whether your past

    performance is a good indicator of expected

    future performance more

  • 8/2/2019 Pmp Chapter 7 2004

    15/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 29

    Estimate At Completion (EAC)

    If we know that we can finish the rest of the

    work as it was originally planned

    Use actual to-date plus budgeted amount for the

    rest of the work

    EAC = AC + BAC EV

    = $29,000 + $100,000 - $24,000= $105,000

    (1st of 3 methods)

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 30

    Estimate At Completion (EAC)

    If the original estimates were flawed,we should build new estimates for allthe remaining work

    ETC is the Estimate to Complete theremaining work.

    EAC = AC + ETC= $29,000 + $120,000= $1,49,000

    Assume this

    was the

    total ETC

    from a

    completely

    rebuilt

    estimate

    (2nd of 3 methods)

  • 8/2/2019 Pmp Chapter 7 2004

    16/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 31

    Estimate At Completion (EAC)

    If we assume that past performance is agood indicator of future performance

    Use actual to-date plus budgeted amount forthe rest of the work, modified by aperformance factor, such as CPI

    EAC = BAC/CPI

    = $100,000/0.83

    = $120,481 (rounded off)

    (3rd of 3 methods)

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 32

    EVM Performance Measures

  • 8/2/2019 Pmp Chapter 7 2004

    17/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 33

    EVM and Basic PM Questions

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 34

    Present Value

    Budgeting technique that debates the futurevalue of money based on inflation, etc.

    PV = FV

    (1 + r)t

    FV = amount of money t years from nowr = interest rate (also called discount rate)

    t = time period

  • 8/2/2019 Pmp Chapter 7 2004

    18/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 35

    Present Value

    Year FV PV

    0 $50,000 $50,000

    1 $35,000 $31,819

    2 $15,000 $12,397

    Assume a 10% interest (or discount) rate

    PV (Year 1) = FV / (1 + r)t

    =$35,000/(1 + 0.1)1= $31,819

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 36

    (NPV) Net Present value

    This Means the total benefits (income or revenue) less the cost. To

    calculate NPV you need to calculate the present value of each of

    the income and revenue figures then add up the present values.

    291353Total

    002253003

    00831002

    9110045501

    200200000

    Present Value at

    10% interest rateCosts

    Present Value at

    10% interest rate

    Income or

    revenue

    Time

    Period

    NPV =353-291=62

  • 8/2/2019 Pmp Chapter 7 2004

    19/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 37

    Payback Period

    The exact length of time needed to recover an initial

    investment as calculated from cash inflows.

    Month Costs Total Cost Benefits Total Benefits

    1 $5000 $5000 $0 $0

    2 $5000 $10000 $0 $0

    3 $8000 $18000 $0 $0

    4 $5000 $23000 $5000 $5000

    5 $2000 $25000 $10000 $15000

    6 $0 $25000 $10000 $25000

    7 $0 $25000 $10000 $35000

    PAYBACK PERIOD is 6 MONTHS

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 38

    Internal Rate Of Return (IRR)

    The interest (discount) rate where the present

    value of the benefits exactly equals the costs.

    The higher the rate, the better the project.

    An IRR of .15 means that you expect theproject to return an average of 15% on your

    investment over a given time period (usually a

    number of years).

  • 8/2/2019 Pmp Chapter 7 2004

    20/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 39

    Benefit Cost Ratio (BCR)

    Compares the cost to the benefits of different projects. A

    BCR of > 1 means the benefits are grater than the costs. A BCR

    of < 1 means the costs are grater than the benefits. A BCR =1

    means the costs and benefits are the same.

    If the BCR of project A is 2.3 and BCR of project B is 1.7

    which project would you select?

    The answer is A. the project with the higher BCR

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 40

    Exercise Accounting Standards

    Net p resen t V

    I RR

    Payback Per iod

    Benef i t Cost Rat io

    $95 . 00

    1 3 %

    1 6 M o n t h

    2 . 79

    Pr o j ect A Pr o j ect B

    $75 . 00

    17 %

    2 1 M o n t h

    1 .3

    Wh i ch you P ick?

    B

    A

    A

    A

  • 8/2/2019 Pmp Chapter 7 2004

    21/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 41

    Types Of Costs

    Di rect Cos t s - Cos t t ha t a re d i rect l y a t t r i bu t ab l e t o t he w o rk on p ro j ec t . Exam p les a re t eam t r ave l , t eam w ages,recogn i t i on and cost o f m a t e r i a l used on t he p r o j ec t

    I n d i r e ct c o s t s Ov e r h e ad i t e m s o r c os t s i n cu r r e d f o r t h e bene f i t o f m o re t han on e p ro j ec t . Exam p les inc l ude t axes ,f r i nge bene f i t s , and j an i t o r i a l se rv i ces .

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 42

    DEPRECIATION

    ST RAI GHT LI NE DEPRECI ATI ON : t he same amoun t o f dep rec ia t i on i s t aken each yea r , A US $ 1 , 000 i t em w i t h a t en yea r use f u l l i f e and no sa l vage va l ue (how m uch i t emi s wo r t h a t t h e end o f i t s l if e ) w ou ld be dep reci a t ed a t US$100 pe r yea r .

    ACCELERATED DEPRECI ATION you on ly need t o k now : T here a re t w o f o rm s o f acce le ra t ed dep reci a t i on Doub le Dec l in i ng Ba lance and Sum o f t he Yea rs D ig i t s .T hey dep rec i a t e f as t e r t h an s t ra i gh t l i ne .Y ou d o n o t h a v e t o k n o w w h a t t h e s e t w o f o r m s m e a n s o r do any ca lcu la t io ns .

  • 8/2/2019 Pmp Chapter 7 2004

    22/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 43

    LI FE CYCLE COSTI NG : Means t ha t th e cost o f opera t ion and ma in t enance phase t o be cons i de r and manage w i t h t he p ro j ec t cost

    PROJECT OPERATIONS ANDMAINTENANCE PHASE

    costs costs

    LI FE CYCLE COSTI NG

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 44

    PMBOK Chapt er 7

    There are 3 major processes:

    1. Cost Estimating

    2. Cost Budgeting

    3. Cost Control

  • 8/2/2019 Pmp Chapter 7 2004

    23/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 45

    Cost Managem ent

    Planning

    7.3

    Cost

    Budgeting

    7.4

    Cost

    Control

    Controlling

    7.2

    Cost

    Estimating

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 46

  • 8/2/2019 Pmp Chapter 7 2004

    24/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 47

    Cost Est im at i ng

    Difference between cost estimating andpricing: Cost es t im a t ing : Assessing how much it will cost the

    organization to provide the product or service

    Pr ic ing: Assessing how much the organization willcharge for the product or service

    Process of developing an approximation (or estimate)

    for the cost of the resources necessary to complete

    the project activities

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 48

    Cost Est im at i ng

    Inputs Enterprise Environmental Factors

    Organizational Process Assets Project Scope Statement

    Work Breakdown Structure

    WBS Dictionary

    Project Management Plan

    Schedule management plan.

    Staffing management plan.

    Risk register.

    Tools & Techniques Analogous estimating

    Determine Resource Cost Rates

    Bottom-up estimating

    Parametric estimating

    Project Management Software

    Vendor Bid Analysis

    Reserve Analysis

    Cost of Quality

    Outputs Activity Cost estimates

    Supporting detail

    Requested Changes

    Cost management plan

  • 8/2/2019 Pmp Chapter 7 2004

    25/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 49

    I n p u t s

    Ente r p r i se Env i ron m enta l Facto rs , considers:

    Marke tp lace cond i t i ons.

    Com m erc ia l da tabases.

    Organizat iona l Process Assets

    Cost es t im a t ing po l i c ies .

    Cost est im a t ing tem p la tes .

    H is to r i ca l i n fo rmat ion .

    Pro jec t f i l es.

    Pro j e c t t e a m k n o w l e d g e.Lessons learned .

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 50

    I n p u t s ( co n t .)

    Pro jec t Scope Sta tem ent

    descr ibes t he bus iness need , j us t i f i ca t ion ,re q u i re me n ts , a n d cu r re n t b o u n d a r i e s f o r t h epro jec t .

    Wo rk B re a kd o wn St ru c tu r e

    WBS prov ides the re la t ionsh ip among a l l theco mp o n e n ts o f t h e p ro j e c t a n d t h e p ro j e c t

    de l i ve rab les WBS Dict ionar y

    prov ide an iden t i f i cat ion o f t he de l i ve rab lesand a descr ip t ion o f the w ork in each WBScompon en t requ i r ed to p roduce eachde l i ve rab le .

  • 8/2/2019 Pmp Chapter 7 2004

    26/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 51

    I n p u t s ( co n t .)

    Pro j ec t Managemen t P lan

    Schedu l e managemen t p l an : The t ype and qu an t i t y o fresou rces and t he amou n t o f t i m e t hose resou rcesa re app l i ed t o comp l e t e t h e wo r k o f t he p ro j ec t i s am a j o r p a r t o f d e t e r m i n i n g t h e p r o j e c t c o st .

    St a f f i ng m anagemen t p l an .

    P ro j ec t s t a f f i ng a t t r i bu t es and pe rsonne l r a t es

    (Sect i on 9 . 1 .3 . 3 ) a re necessa ry com ponen t s f o r

    deve l op i ng t he schedu l e cos t es t i ma t es .

    Risk reg is te r .

    T he cos t es t i ma t o r cons ide rs i n f o rm a t i on on r i sk

    responses (Sect i on 1 1 . 2 .3 . 1 ) w hen p rodu c i ng costes t i ma t es .

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 52

    Too ls & Techn iq ues

    A n al og o u s es t im a t i n g ( Ex p e r t j u d g m e n t ) U se d t oes t i ma t e t o t a l p ro j ec t cost s i f t he re i s a l i m i t ed am oun to f de t a i l ed i n f o rm a t i on

    Determ ine Resour ce Cost Rates

    B o t t o m - u p e st i m a t i n g Es t i ma t i ng t he cos t o fi nd i v i dua l wo r k i t em s and t hen ro l l i ng up t he cos t s t oa r r i ve a t a p ro j ec t t o t a l

    Param e t r i c est i m a t i ng Us ing p ro j ec t cha ract e r i s t i cs( o r p a r a m e t e r s) i n a m a t h e m a t i ca l m o d e l t o p r e d i c tcos ts (e .g . , p r i ce per squar e foo t )

    P r oj e c t M an a g em e n t So f t w a r e - PM s of t w a r e an dspreadsheets

  • 8/2/2019 Pmp Chapter 7 2004

    27/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 53

    Too ls & Techn iq ues

    Vendor B id Ana lys is

    Reserve Ana ly s is : Cont ingency r eserves a re es t im atedcost s t o be u sed a t t he d i sc re t i on o f t h e p ro j ec tm anage r t o deal w i t h an t i c i pa t ed , bu t no t ce r t a i n ,e v en t s . Th e se e v en t s a r e k n o w n u n k n o w n s a n d a r epa r t o f t he p ro j ec t scope and cos t base l ines .

    Cost o f Qua l i t y :Cost o f qu a l i t y ( Sect ion 8 .1 .2 .4 ) can a lsobe used t o p repa re t h e schedu l e ac t i v i t y cos t es t i ma t e .

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 54

    O u t p u t s

    Act i v i t y Cost es t im a tes Qu a n t i t a t i veassessm ents o f th e cost o f r esources (e .g .,u n i t s o f cu r re n cy o r s t a f f h o u rs )

    Types o f es t im a tes

    Or d er o f m ag ni t ud e ( - 2 5% / + 7 5 % )

    Bu d get est im a t e ( - 1 0% / + 2 5 % )

    Def in it iv e est i m at e ( - 5 % / + 1 0 % )

    Suppor t ing de ta i l Desc r i p t i on o f es t i ma t ed scope o f w o rk

    Docum en t a t i on o f t he bas i s f o r t he es t i ma t e

    Docum en t a t i on o f any assum p t i ons made

    Range o f poss ib le resu l t s

  • 8/2/2019 Pmp Chapter 7 2004

    28/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 55

    Out pu t s ( con t .)

    Request ed Changes

    The Cost Est im a t ing p rocess may g enera terequested changes tha t m ay a f fec t the costm a n a ge me n t p l a n , ac t i v i t y r e so u rce re q u i rem e n tsa n d o th e r co mp o n e n ts o f t h e p ro j e c t ma n a g e me n tp lan. Requested chan ges are processed for r eviewa n d d i sp os it i o n t h ro u g h t h e I n te g ra te d Ch a n g e

    Cost m anagement p lan

    Descr ibes how cost v a r iances w i l l bemanaged

    Par t o f the overa l l p ro j ec t p lan

    Cost Estimating

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 56

    Cost Budge t in g

    Aggregating the estimated costs ofindividual activities or work packagesto establish a cost baseline.

  • 8/2/2019 Pmp Chapter 7 2004

    29/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 57

    Cost Budge t in g

    Inputs Project Scope Statement

    Work Breakdown Structure

    WBS Dictionary

    Cost estimates

    Supporting Detail

    Project schedule Resource Calendars

    Contract

    Cost management plan

    Tools & Techniques Cost Aggregation

    Reserve Analysis

    Parametric Estimating

    Funding Limit Reconciliation

    Outputs Cost baseline

    Project Funding Requirements

    Cost Management Plan (Updates)

    Requested Changes

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 58

    I n p u t s

    Pro jec t Scope Sta tem ent :

    W BS I d e n t i f i es t h e p ro j e c t e le me n ts t o w h i chth e costs w i l l be a l loca ted

    WBS Dict ionar y

    Cost Est im ates

    Cost Est im a te Suppor t in g De ta i l

    Pro jec t schedu le Used t o ass ign costs t op ro j e c t e le me n ts f o r t h e t i m e p er i o d w h e ncosts w i l l be incur red

    Resour ce Calendars

  • 8/2/2019 Pmp Chapter 7 2004

    30/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 59

    I n p u t s

    Contract

    (Se ct i o n 1 2 .4 .3 .2 ) i n f o rma t i o n r e l ate d t o w h a tp roduct s , serv i ces, o r resu l ts have b eenp u rch a se d a n d t h e i r co st s a re u se d i ndeve lop ing the budge t .

    Cost Management Plan

    Th e co s t m a n a ge me n t p l a n co mp o n e n t o f t h ep ro j e c t m a n a ge me n t p l a n a n d o th e r su b s i d ia r yp lans a re cons ide red dur ing cost bu dge t ing .

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 60

    Too ls & Techn iq ues

    Cost Aggrega t ion

    Reserv e Analysis :

    Management con t ingency reserves a re budge tsreserved fo r unp lanned , bu t po ten t ia l l yrequ i red , changes to p ro j ec t scope and cost .

    Param et r i c Est im a t ing

    Fund ing L imi t Reconc i li a t i on

  • 8/2/2019 Pmp Chapter 7 2004

    31/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 61

    O u t p u t s

    Cost base l ine Ti me p h a se d b u d g et t h a t w i l lbe used to m easure and m on i to r t he costp e r f o rma n ce o f t h e p ro j e ct

    0

    20

    40

    60

    80

    100

    120

    140

    Jan Feb Mar Apr May Jun

    Reporting Period

    BCWS($K)

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 62

    O u t p u t s

    Pro j ec t Fund i ng Requ i rem en t s

    Cost Managem ent P lan (Updates)

    Requested Changes

  • 8/2/2019 Pmp Chapter 7 2004

    32/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 63

    Cost Con t r o l

    Includes:

    Monitoring cost performance to detect variances from theplan

    Ensuring that all appropriate changes are recorded

    Preventing incorrect, inappropriate, or unauthorizedchanges

    Informing the appropriate stakeholders of authorizedchanges

    Analyzing positive and negative variances and how theyaffect the other control processes

    Influencing the factors that create changes

    to the cost baseline to ensure that changes are agreed upon

    Determining that the cost baseline has changed

    Managing the actual changes when and as they occur

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 64

    Cost Cont ro l

    Inputs Cost baseline

    Project Funding Requirements

    Performance reports

    Work Performance Information

    Approved change requests

    Project management plan

    Tools & Techniques Cost change control system

    Performance measurement Analysis

    Forecasting

    Project Performance Reviews

    Project Management Software

    Variance ManagementOutputs Cost Estimates (Update)

    Cost Baseline (Updates)

    Performance Measurements

    Forecasted Completion

    Requested Changes

    Recommended Corrective action

    Organizational Process Assets (Updates)

    Project Management Plan (Updates)

  • 8/2/2019 Pmp Chapter 7 2004

    33/33

    5/2

    Akram Al-Najjar, PMP.Project Management Consultant

    [email protected]+20105394312

    Source: pmbok guide 2004 Slide 65

    Cost Cont ro l