34
LCS International, Inc. PMP Review Chapter 11 Controlling Work Results Presented by David J. Lanners, MBA, PMP These slides are intended to be used only in settings where each viewer has an original copy of the Sybex PMP Study Guide book.

LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

Embed Size (px)

Citation preview

Page 1: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc.

PMP Review

Chapter 11

Controlling Work Results

Presented by

David J. Lanners, MBA, PMP

These slides are intended to be used only in settings where each

viewer has an original copy of the Sybex PMP Study Guide book.

Page 2: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 2

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Monitor and Control Risk

• Control Costs

• Control Schedule

• Perform Quality Control

• Verify Scope

• Control Scope

Page 3: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

Monitor and Control Risks Monitor and Control Risks is the process of tracking identified risks, implementing risk response plans, monitoring residual risks, identifying new

(secondary) risks, and evaluating risk process effectiveness throughout the project. Project work should be continuously monitored for changing

and outdated risks. The process applies techniques such as variance and trend analysis to determine if project assumptions are still valid and/or

analysis shows that an assessed risk has changed or can be retired. The process should keep contingency reserves aligned with project risks.

11.6 Project

Risk

Management

To Perform Integrated Change Control

From Identify Risks, Work Performance Information

Tools & Techniques .1 Risk reassessment

.2 Risk audits

.3 Variance and trend analysis

.4 Technical performance measurement

.5 Reserve analysis

.6 Status meetings

Inputs .1 Risk register

.2 Project management plan

.3 Work performance information

.4 Performance reports

Outputs .1 Risk register updates

.2 Organization process assets updates

.3 Change requests

.4 Project management plan updates

.5 Project document updates

Page 4: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 4

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Monitor and Control Risk

• Control Costs

• Control Schedule

• Perform Quality Control

• Verify Scope

• Control Scope

Page 5: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

Control Costs Control Costs is the process of monitoring the status of the project to update the project budget and managing changes to the cost baseline.

Updating the budget involves recording actual costs incurred to date. Any increase to the authorized budget can be approved only through the

Perform Integrated Change Control process. Monitoring the expenditure of funds without regard to the value of work being accomplished has

little value to the project other than to allow the project team to stay within the authorized funding.

7.3 Project

Cost

Management

To Perform Integrated Change Control

From Determine Budget, Direct Project Execution

Tools & Techniques .1 Earned value management

.2 Forecasting

.3 To-complete performance index (TCPI)

.4 Performance reviews

.5 Variance analysis

.6 Project management software

Inputs .1 Project management plan

.2 Project funding requirements

.3 Work performance information

.4 Organizational process assets

Outputs .1 Work performance measurements

.2 Budget forecasts

.3 Organization process assets updates

.4 Change requests

.5 Project management plan updates

.6 Project document updates

Page 6: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 6

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Earned Value Technique

• Planned Value (PV) = Budgeted Cost of

Work Scheduled (BCWS)

• Actual Cost (AC) = Actual Cost of

Work Performed (ACWP)

• Earned Value (EV) = Budgeted Cost of

Work Performed (BCWP)

Page 7: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 7

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Earned Value Chart

Page 8: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 8

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Earned Value Performance

• Cost Variance

(CV) = EV – AC

• Schedule Variance

(SV) = EV – PV

• Performance Indices

• Cost Performance Index (CPI ) = EV ÷ AC

• Schedule Performance Index (SPI) = EV ÷ PV

Page 9: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 9

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Earned Value Forecasting

• Budget at Completion = [Sum of All Project Budgets]

• Estimate at Completion EAC = AC + ETC [Assumptions Changed]

EAC = (AC + BAC) – EV [Variances will STOP]

EAC = [AC + (BAC – EV) ÷ CPI] [Variances will Continue]

• Estimate to Complete (ETC) = EAC – AC [See 1st Formula Above]

(ETC) = (BAC - EV) / CPI [Variances will Continue]

• Variance at Completion * (VAC) = BAC – EAC * [Not in Guide to PMBOK]

Page 10: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 10

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Hint: All abbreviations in rows and colums are in alphabetical order.

ACWP BCWP BCWS

AC EV PV

cpi ÷ ÷ spi

CV - - SV

Hint: Start with EV and then follow the arrows to create each formula

Earned Value Memory Aid

This chart is copyrighted by David J. Lanners, MBA, PMP

Page 11: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 11

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Monitor and Control Risk

• Control Costs

• Control Schedule

• Perform Quality Control

• Verify Scope

• Control Scope

Page 12: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

Control Schedule Control Schedule is the process of monitoring the status of the project to update project progress and manage changes to the schedule baseline.

It is concerned with determining the current status of the project schedule, influencing the factors that create schedule changes, determining that

the project schedule has changed, and managing the actual changes as they occur. Progress reporting and current schedule status includes

information such as actual start and finish dates for schedule activities and the remaining durations for unfinished schedule activities.

6.6 Project

Time

Management

To Perform Integrated Change Control

From Develop Schedule, Direct Project Execution

Tools & Techniques .1 Performance reviews

.2 Variance analysis

.3 Project management software

.4 Resource leveling

.5 What-if scenario analysis

.6 Adjusting leads and lags

.7 Schedule compression

.8 Scheduling tool

Inputs .1 Project management plan

.2 Project schedule

.3 Work performance information

.4 Organizational process assets

Outputs .1 Work performance measurements

.2 Organization process assets updates

.3 Change requests

.4 Project management plan updates

.5 Project document updates

Page 13: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 13

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Monitor and Control Risk

• Control Costs

• Control Schedule

• Perform Quality Control

• Verify Scope

• Control Scope

Page 14: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 14

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Schedule Compression

• Crashing

• Adding resources (always adds cost)

• Fast tracking

• Overlapping tasks (always adds risk)

Page 15: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 15

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Perform Quality Control

• Verifying Project Scope

• Controlling Scope Changes

• Formulating Project Closeout

• Close Project or Phase

• Close Procurements

• Releasing Project Team Members

Page 16: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

Perform Quality Control

Tools & Techniques .1 Cause and effect diagrams

.2 Control charts

.3 Flowcharting

.4 Histogram

.5 Pareto chart

.6 Run chart

.7 Scatter diagram

.8 Statistical sampling

.9 Inspection

.10 Approved change requests review

Outputs .1 Quality control measurements

.2 Validated changes

.3 Validated deliverables

.4 Organization process assets updates

.5 Change requests

.6 Project management plan updates

.7 Project document updates

Perform Quality Control (QC) is the process of monitoring and recording results of executing the quality activities to assess performance and

recommend necessary changes. Quality control is performed throughout the project. Quality standards include project processes and product

goals. Project results include deliverables and project management results, such as cost and schedule performance. The project management

team should have a working knowledge of statistical quality control, especially sampling and probability, to evaluate quality control outputs.

Inputs .1 Project management plan

.2 Quality metrics

.3 Quality checklists

.4 Work performance measurements

.5 Approved change requests

.6 Deliverables

.7 Organizational process assets 8.3 Project

Quality

Management

To Perform Quality Assurance

From Plan Quality

Page 17: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 17

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Control Chart

Page 18: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 18

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Process Capability

Process capability is measured by comparing the customer’s specification

width to the process’s “normal” output (which is calculated by monitoring

the process output and calculating ± 3 std deviations from the mean).

Cp >1 is needed to meet specs without waste.

Acceptable Specification Width

Process Output Width Cp =

Upper Spec – Lower Spec

6 Standard Deviations Cp =

Page 19: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 19

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Process Capability Example

Upper Spec – Lower Spec

6 Standard Deviations Cp =

Process requires metal rods to be 5.000 inches long +- 0.050 inches.

The production process has a standard deviation of 0.006 inches.

(+ 0.050) – (- 0.050)

6 x (0.006) =

( 0.100 )

(0.036) = = 2.77

Page 20: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 20

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Frequency of Failures

Page 21: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 21

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Pareto Diagram

Page 22: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 22

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Scatter Diagram

Page 23: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 23

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Normal distribution (Bell-shaped curve)

| 68% |

| 95% |

| 99% |

Mean

2

3

Page 24: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 24

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Measures of Central Tendency

Mean = Average

n

x...xxx n21

n

1i

i

80 + 10 + 10 + 50 + 70 + 90 ________________________

6

= 310 ____

6

= 51.67

52 (Rounded)

Page 25: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 25

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Measures of Central Tendency

• Median – (Middle) as in Highway Median

• Data: 80 10 10 50 70 90

• First put in order: 10 10 50 70 80 90

• If an even number of data points, calculate the

midpoint between the two “middle” numbers.

• 50 + 70 = 120 / 2 = 60 is the median

• Mode - the most common (a la mode)

• 10 is the number that appears most frequently

• 10 is the mode

Page 26: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 26

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Population

• Mean

• Variance

• Standard Deviation

Terms and symbols

Sample

• Mean

• Variance

• Standard

Deviation

2

_x

2s

s

Page 27: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 27

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Variance & Standard Deviation

Population

2N

1i

i

2

N

x

Variance

2 Standard

Deviation

Sample

1

)( 2

12

n

xx

s

n

i

i

Sample

Variance

2ss Standard

Deviation

Page 28: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 28

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Calculate the standard deviation () of this data:

80 10 10 50 70 90

1. Compute the mean, 310/6 = 51.67 52

2. Subtract the mean from the data point and square the result:

80 - 52 = 28, 28 x 28 = 784

10 - 52 = -42, -42 x -42 = 1,764

10 - 52 = -42, -42 x -42 = 1,764

50 - 52 = -2, -2 x -2 = 4

70 - 52 = 18, 18 x 18 = 324

90 - 52 = 38, 38 x 38 = 1,444

total = 6,084

3. Calculate variance (2) = 6,084 / 6 = 1,014

4. Calculate standard deviation () = 1014 = 31.84

Example

Page 29: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 29

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Using Perform Quality Control Techniques

• Verifying Project Scope

• Controlling Scope Changes

• Formulating Project Closeout

• Close Project or Phase

• Contract Closure

• Releasing Project Team Members

Page 30: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 30

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Monitor and Control Risk

• Control Costs

• Control Schedule

• Perform Quality Control

• Verify Scope

• Control Scope

Page 31: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

Verify Scope Verify Scope is the process of formalizing acceptance of the completed project deliverables. Verifying scope includes reviewing the deliverables

with the customer or sponsor to ensure that they are completed satisfactorily and obtaining formal acceptance of deliverables by the customer

or sponsor. Scope verification differs from quality control in that scope verification is primarily concerned with acceptance of the deliverables,

while quality control is primarily concerned with conformance to specifications and meeting quality requirements specified for the deliverables.

5.4 Project

Scope

Management

To Control Scope, Close Project or Phase

From Collect Requirements, Perform Quality Control

Tools & Techniques .1 Inspection

Inputs .1 Project management plan

.2 Requirements documentation

.3 Requirements traceability matrix

.4 Validated deliverables

Outputs .1 Accepted deliverables

.2 Change requests

.3 Project document updates

Page 32: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 32

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Controlling Work Results

• Monitor and Control Risk

• Control Costs

• Control Schedule

• Perform Quality Control

• Verify Scope

• Control Scope

Page 33: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

Control Scope Control Scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline. Controlling

project scope ensures that requested changes and recommended corrective or preventive actions are processed through the Perform Integrated

Change Control process. Project scope control is also used to manage actual changes when they occur and is integrated with the other control

processes. Uncontrolled changes often are referred to as scope creep. Because change is inevitable, some kind of change control is mandated.

5.5 Project

Scope

Management

To Perform Integrated Change Control

From Collect Requirements

Tools & Techniques .1 Variance analysis

Inputs .1 Project management plan

.2 Work performance information

.3 Requirements documentation

.4 Requirements traceability matrix

.5 Organizational process assets

Outputs .1 Work performance measurements

.2 Organizational process assets updates

.3 Change requests

.4 Project management plan updates

.5 Project document updates

Page 34: LCS International, Inc. PMP Review - leaderhelper.com · LCS International, Inc. PMP Review Chapter 11 ... PMP Exam Review - (Rev F) Chapter 11 ... .1 Risk register .2 Project management

LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 34

Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.

Formulating Project Closeout

• Addition - (evolve into operations)

• Starvation - (resources are cut off)

• Integration - (resources distributed)

• Extinction - (natural completion)