Upload
dinhdiep
View
227
Download
2
Embed Size (px)
Citation preview
LCS International, Inc.
PMP Review
Chapter 11
Controlling Work Results
Presented by
David J. Lanners, MBA, PMP
These slides are intended to be used only in settings where each
viewer has an original copy of the Sybex PMP Study Guide book.
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 2
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Controlling Work Results
• Monitor and Control Risk
• Control Costs
• Control Schedule
• Perform Quality Control
• Verify Scope
• Control Scope
Monitor and Control Risks Monitor and Control Risks is the process of tracking identified risks, implementing risk response plans, monitoring residual risks, identifying new
(secondary) risks, and evaluating risk process effectiveness throughout the project. Project work should be continuously monitored for changing
and outdated risks. The process applies techniques such as variance and trend analysis to determine if project assumptions are still valid and/or
analysis shows that an assessed risk has changed or can be retired. The process should keep contingency reserves aligned with project risks.
11.6 Project
Risk
Management
To Perform Integrated Change Control
From Identify Risks, Work Performance Information
Tools & Techniques .1 Risk reassessment
.2 Risk audits
.3 Variance and trend analysis
.4 Technical performance measurement
.5 Reserve analysis
.6 Status meetings
Inputs .1 Risk register
.2 Project management plan
.3 Work performance information
.4 Performance reports
Outputs .1 Risk register updates
.2 Organization process assets updates
.3 Change requests
.4 Project management plan updates
.5 Project document updates
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 4
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Controlling Work Results
• Monitor and Control Risk
• Control Costs
• Control Schedule
• Perform Quality Control
• Verify Scope
• Control Scope
Control Costs Control Costs is the process of monitoring the status of the project to update the project budget and managing changes to the cost baseline.
Updating the budget involves recording actual costs incurred to date. Any increase to the authorized budget can be approved only through the
Perform Integrated Change Control process. Monitoring the expenditure of funds without regard to the value of work being accomplished has
little value to the project other than to allow the project team to stay within the authorized funding.
7.3 Project
Cost
Management
To Perform Integrated Change Control
From Determine Budget, Direct Project Execution
Tools & Techniques .1 Earned value management
.2 Forecasting
.3 To-complete performance index (TCPI)
.4 Performance reviews
.5 Variance analysis
.6 Project management software
Inputs .1 Project management plan
.2 Project funding requirements
.3 Work performance information
.4 Organizational process assets
Outputs .1 Work performance measurements
.2 Budget forecasts
.3 Organization process assets updates
.4 Change requests
.5 Project management plan updates
.6 Project document updates
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 6
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Earned Value Technique
• Planned Value (PV) = Budgeted Cost of
Work Scheduled (BCWS)
• Actual Cost (AC) = Actual Cost of
Work Performed (ACWP)
• Earned Value (EV) = Budgeted Cost of
Work Performed (BCWP)
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 7
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Earned Value Chart
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 8
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Earned Value Performance
• Cost Variance
(CV) = EV – AC
• Schedule Variance
(SV) = EV – PV
• Performance Indices
• Cost Performance Index (CPI ) = EV ÷ AC
• Schedule Performance Index (SPI) = EV ÷ PV
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 9
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Earned Value Forecasting
• Budget at Completion = [Sum of All Project Budgets]
• Estimate at Completion EAC = AC + ETC [Assumptions Changed]
EAC = (AC + BAC) – EV [Variances will STOP]
EAC = [AC + (BAC – EV) ÷ CPI] [Variances will Continue]
• Estimate to Complete (ETC) = EAC – AC [See 1st Formula Above]
(ETC) = (BAC - EV) / CPI [Variances will Continue]
• Variance at Completion * (VAC) = BAC – EAC * [Not in Guide to PMBOK]
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 10
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Hint: All abbreviations in rows and colums are in alphabetical order.
ACWP BCWP BCWS
AC EV PV
cpi ÷ ÷ spi
CV - - SV
Hint: Start with EV and then follow the arrows to create each formula
Earned Value Memory Aid
This chart is copyrighted by David J. Lanners, MBA, PMP
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 11
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Controlling Work Results
• Monitor and Control Risk
• Control Costs
• Control Schedule
• Perform Quality Control
• Verify Scope
• Control Scope
Control Schedule Control Schedule is the process of monitoring the status of the project to update project progress and manage changes to the schedule baseline.
It is concerned with determining the current status of the project schedule, influencing the factors that create schedule changes, determining that
the project schedule has changed, and managing the actual changes as they occur. Progress reporting and current schedule status includes
information such as actual start and finish dates for schedule activities and the remaining durations for unfinished schedule activities.
6.6 Project
Time
Management
To Perform Integrated Change Control
From Develop Schedule, Direct Project Execution
Tools & Techniques .1 Performance reviews
.2 Variance analysis
.3 Project management software
.4 Resource leveling
.5 What-if scenario analysis
.6 Adjusting leads and lags
.7 Schedule compression
.8 Scheduling tool
Inputs .1 Project management plan
.2 Project schedule
.3 Work performance information
.4 Organizational process assets
Outputs .1 Work performance measurements
.2 Organization process assets updates
.3 Change requests
.4 Project management plan updates
.5 Project document updates
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 13
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Controlling Work Results
• Monitor and Control Risk
• Control Costs
• Control Schedule
• Perform Quality Control
• Verify Scope
• Control Scope
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 14
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Schedule Compression
• Crashing
• Adding resources (always adds cost)
• Fast tracking
• Overlapping tasks (always adds risk)
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 15
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Controlling Work Results
• Perform Quality Control
• Verifying Project Scope
• Controlling Scope Changes
• Formulating Project Closeout
• Close Project or Phase
• Close Procurements
• Releasing Project Team Members
Perform Quality Control
Tools & Techniques .1 Cause and effect diagrams
.2 Control charts
.3 Flowcharting
.4 Histogram
.5 Pareto chart
.6 Run chart
.7 Scatter diagram
.8 Statistical sampling
.9 Inspection
.10 Approved change requests review
Outputs .1 Quality control measurements
.2 Validated changes
.3 Validated deliverables
.4 Organization process assets updates
.5 Change requests
.6 Project management plan updates
.7 Project document updates
Perform Quality Control (QC) is the process of monitoring and recording results of executing the quality activities to assess performance and
recommend necessary changes. Quality control is performed throughout the project. Quality standards include project processes and product
goals. Project results include deliverables and project management results, such as cost and schedule performance. The project management
team should have a working knowledge of statistical quality control, especially sampling and probability, to evaluate quality control outputs.
Inputs .1 Project management plan
.2 Quality metrics
.3 Quality checklists
.4 Work performance measurements
.5 Approved change requests
.6 Deliverables
.7 Organizational process assets 8.3 Project
Quality
Management
To Perform Quality Assurance
From Plan Quality
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 17
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Control Chart
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 18
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Process Capability
Process capability is measured by comparing the customer’s specification
width to the process’s “normal” output (which is calculated by monitoring
the process output and calculating ± 3 std deviations from the mean).
Cp >1 is needed to meet specs without waste.
Acceptable Specification Width
Process Output Width Cp =
Upper Spec – Lower Spec
6 Standard Deviations Cp =
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 19
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Process Capability Example
Upper Spec – Lower Spec
6 Standard Deviations Cp =
Process requires metal rods to be 5.000 inches long +- 0.050 inches.
The production process has a standard deviation of 0.006 inches.
(+ 0.050) – (- 0.050)
6 x (0.006) =
( 0.100 )
(0.036) = = 2.77
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 20
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Frequency of Failures
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 21
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Pareto Diagram
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 22
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Scatter Diagram
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 23
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Normal distribution (Bell-shaped curve)
| 68% |
| 95% |
| 99% |
Mean
2
3
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 24
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Measures of Central Tendency
Mean = Average
n
x...xxx n21
n
1i
i
80 + 10 + 10 + 50 + 70 + 90 ________________________
6
= 310 ____
6
= 51.67
52 (Rounded)
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 25
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Measures of Central Tendency
• Median – (Middle) as in Highway Median
• Data: 80 10 10 50 70 90
• First put in order: 10 10 50 70 80 90
• If an even number of data points, calculate the
midpoint between the two “middle” numbers.
• 50 + 70 = 120 / 2 = 60 is the median
• Mode - the most common (a la mode)
• 10 is the number that appears most frequently
• 10 is the mode
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 26
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Population
• Mean
• Variance
• Standard Deviation
Terms and symbols
Sample
• Mean
• Variance
• Standard
Deviation
2
_x
2s
s
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 27
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Variance & Standard Deviation
Population
2N
1i
i
2
N
x
Variance
2 Standard
Deviation
Sample
1
)( 2
12
n
xx
s
n
i
i
Sample
Variance
2ss Standard
Deviation
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 28
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Calculate the standard deviation () of this data:
80 10 10 50 70 90
1. Compute the mean, 310/6 = 51.67 52
2. Subtract the mean from the data point and square the result:
80 - 52 = 28, 28 x 28 = 784
10 - 52 = -42, -42 x -42 = 1,764
10 - 52 = -42, -42 x -42 = 1,764
50 - 52 = -2, -2 x -2 = 4
70 - 52 = 18, 18 x 18 = 324
90 - 52 = 38, 38 x 38 = 1,444
total = 6,084
3. Calculate variance (2) = 6,084 / 6 = 1,014
4. Calculate standard deviation () = 1014 = 31.84
Example
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 29
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Controlling Work Results
• Using Perform Quality Control Techniques
• Verifying Project Scope
• Controlling Scope Changes
• Formulating Project Closeout
• Close Project or Phase
• Contract Closure
• Releasing Project Team Members
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 30
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Controlling Work Results
• Monitor and Control Risk
• Control Costs
• Control Schedule
• Perform Quality Control
• Verify Scope
• Control Scope
Verify Scope Verify Scope is the process of formalizing acceptance of the completed project deliverables. Verifying scope includes reviewing the deliverables
with the customer or sponsor to ensure that they are completed satisfactorily and obtaining formal acceptance of deliverables by the customer
or sponsor. Scope verification differs from quality control in that scope verification is primarily concerned with acceptance of the deliverables,
while quality control is primarily concerned with conformance to specifications and meeting quality requirements specified for the deliverables.
5.4 Project
Scope
Management
To Control Scope, Close Project or Phase
From Collect Requirements, Perform Quality Control
Tools & Techniques .1 Inspection
Inputs .1 Project management plan
.2 Requirements documentation
.3 Requirements traceability matrix
.4 Validated deliverables
Outputs .1 Accepted deliverables
.2 Change requests
.3 Project document updates
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 32
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Controlling Work Results
• Monitor and Control Risk
• Control Costs
• Control Schedule
• Perform Quality Control
• Verify Scope
• Control Scope
Control Scope Control Scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline. Controlling
project scope ensures that requested changes and recommended corrective or preventive actions are processed through the Perform Integrated
Change Control process. Project scope control is also used to manage actual changes when they occur and is integrated with the other control
processes. Uncontrolled changes often are referred to as scope creep. Because change is inevitable, some kind of change control is mandated.
5.5 Project
Scope
Management
To Perform Integrated Change Control
From Collect Requirements
Tools & Techniques .1 Variance analysis
Inputs .1 Project management plan
.2 Work performance information
.3 Requirements documentation
.4 Requirements traceability matrix
.5 Organizational process assets
Outputs .1 Work performance measurements
.2 Organizational process assets updates
.3 Change requests
.4 Project management plan updates
.5 Project document updates
LCS International, Inc. PMP Exam Review - (Rev F) Chapter 11 - Slide 34
Reproduced from PMP Project Management Professional Study Guide by permission of Sybex, Inc. ISBN 0-7821-3601-X. ©2005, Sybex, Inc. All rights reserved.
Formulating Project Closeout
• Addition - (evolve into operations)
• Starvation - (resources are cut off)
• Integration - (resources distributed)
• Extinction - (natural completion)