    Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-2

    Human Resource Management

    Human Resource Management

    Organizational Planning

    Staff Acquisition

    Team Development

    Organizational Planning

    Staff Acquisition

    Team Development

    Processes required to make effective use

    of the people involved with the project

  • 8/14/2019 PMP Preparation Training

    3/30

    Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-3

    Managing People on the Project

    Managing People on the Project

    Select techniques that are appropriate for personal and

    organizational relationships that are temporary and new

    The nature and number of project stakeholders willoften change as the project moves from phase to phase.

    Choose techniques that are appropriate to the current

    needs of the project

    Team must be sufficiently aware of HR administrative

    requirements to ensure compliance

  • 8/14/2019 PMP Preparation Training

    4/30

    Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-4

    Human Resource Management

    Human Resource Management

    9.1Organizational

    Planning

    Planning

    9.3

    Team

    Development

    Executing

    9.2Staff

    Acquisition

  • 8/14/2019 PMP Preparation Training

    5/30

    Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-5

    Organizational Planning

    Individuals and groups may be part of the organization

    performing the project or

    may be external to it

    Internal groups are often associated with a specific functional

    department, such as engineering, marketing, or accounting

    Planning, identifying, documenting, and assigning project roles,

    responsibilities, and reporting relationships

  • 8/14/2019 PMP Preparation Training

    6/30

  • 8/14/2019 PMP Preparation Training

    7/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-7

    InputsInputs

    Project interfaces

    Organizational interfaces Formal and informal reporting

    relationships among different organizational units

    Technical interfaces Formal and informal reporting

    relationships among technical disciplines

    Interpersonal interfaces Formal and informal reporting

    relationships among different individuals working on the project

    Organizational Planning

  • 8/14/2019 PMP Preparation Training

    8/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-8

    Inputs (cont.)Inputs (cont.)

    Staffing requirements Definition of the kinds of competenciesrequired and in what time frame and from which kinds of individuals

    Constraints Factors that limit project teams options

    Organizational structure of the performing organization

    Strong matrix

    Weak matrix

    Collective bargaining agreements with unions or other employee groups

    Preferences of the project management team

    Skills and capabilities of the staff

    Organizational Planning

  • 8/14/2019 PMP Preparation Training

    9/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-9

    Tools & TechniquesTools & Techniques

    Templates Role and responsibility definitions or

    reporting relationships from a similar project

    HR practices Variety of policies, guidelines, andprocedures used as organizational-planning aid

    Organizational theory Body of literature describing

    how an organization can, and should, be structured

    Stakeholder analysis Ensures their needs are met

    Organizational Planning

  • 8/14/2019 PMP Preparation Training

    10/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-10

    OutputsOutputs

    Assignments Roles and responsibilities assigned

    to the appropriate stakeholder

    Organizational Planning

  • 8/14/2019 PMP Preparation Training

    11/30

  • 8/14/2019 PMP Preparation Training

    12/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-12

    Resource HistogramResource Histogram

    Organizational Planning

    Senior Designers

    0

    25

    50

    75

    100

    125

    150

    175

    200

    225

    250

    275

    300

    9 16 23 30 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22

    Resource Usage Staff Hours

    ResourceUsa

    ge

    Jan Feb Mar Apr May

  • 8/14/2019 PMP Preparation Training

    13/30

  • 8/14/2019 PMP Preparation Training

    14/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-14

    Staff Acquisition

    Getting the needed human resources

    assigned to and working on the projectGetting the needed human resourcesassigned to and working on the project

  • 8/14/2019 PMP Preparation Training

    15/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-15

    Inputs Staffing management

    plan Staffing-pool description Recruitment practices

    Inputs Staffing managementplan

    Staffing-pool description Recruitment practices

    Tools & Techniques Negotiations Pre-assignment

    Procurement

    Tools & Techniques Negotiations

    Pre-assignment Procurement

    Outputs Project staff assigned Project team directory

    Outputs Project staff assigned Project team directory

    Staff AcquisitionStaff Acquisition

  • 8/14/2019 PMP Preparation Training

    16/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-16

    InputsInputs

    Staffing management plan

    Staffing-pool description Characteristics of the potentiallyavailable staff Previous experience

    Personal interests

    Personal characteristics

    Availability

    Competencies and proficiency

    Recruitment practices Policies, guidelines, andproceduresgoverning staff assignments

    Staff Acquisition

  • 8/14/2019 PMP Preparation Training

    17/30

  • 8/14/2019 PMP Preparation Training

    18/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-18

    OutputsOutputs

    Project staff assigned Appropriate people have

    been assigned to work on the project full-time,

    part-time, or variably

    Project team directory Lists of all project team

    members and other key stakeholders

    Staff Acquisition

  • 8/14/2019 PMP Preparation Training

    19/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-19

    Team Development

    Enhancing the ability of stakeholders to contribute

    as individuals as well as enhancing the ability of

    the team to function as a team

    Enhancing the ability of stakeholders to contribute

    as individuals as well as enhancing the ability of

    the team to function as a team

  • 8/14/2019 PMP Preparation Training

    20/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-20

    Inputs Project staff Project plan Staffing management plan Performance reports External feedback

    Inputs Project staff Project plan Staffing management plan Performance reports External feedback

    Tools & Techniques Team-building activities General management skills

    Reward and recognition systems Collocation Training

    Tools & Techniques Team-building activities General management skills

    Reward and recognition systems Collocation Training

    Outputs Performance improvements Inputs to performance appraisals

    Outputs Performance improvements Inputs to performance appraisals

    Team DevelopmentTeam Development

  • 8/14/2019 PMP Preparation Training

    21/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-21

    InputsInputs

    Project staff

    Project plan

    Staffing management plan

    Performance reports

    External feedback Team measure itself against the

    expectations of those outside the project

    Team Development

  • 8/14/2019 PMP Preparation Training

    22/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-22

    Tools & TechniquesTools & Techniques

    Team-building activities Include management and individual

    actions taken to improve team performance

    General management skills

    Reward and recognition systems Formal management actions

    that promote or reinforce desired behavior

    Collocation Placing all or most of the team members in the same

    physical location

    Training Includes all activities designed to enhance the skills,

    knowledge, and capabilities of the project team

    Team Development

  • 8/14/2019 PMP Preparation Training

    23/30Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-23

    OutputsOutputs

    Performance improvements

    Improvements in individual skills

    Improvements in team behaviors Improvements in either individual skills or team

    capabilities

    Inputs to performance appraisals

    Team Development

    T D l

  • 8/14/2019 PMP Preparation Training

    24/30

    Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-24

    Management StylesManagement Styles

    Autocratic

    StrengthMature, well defined projectsQuick decisions required

    WeaknessLimits staff buy-in leading to low moralePossible arbitrary decisions

    Team Development

    T D l t

  • 8/14/2019 PMP Preparation Training

    25/30

    Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-25

    Management StylesManagement Styles

    Laissez-Fair

    StrengthInnovative projectsHigh morale of self-motivated staff

    WeaknessConfusion about objectives of the projectInability to make decisions

    Team Development

  • 8/14/2019 PMP Preparation Training

    26/30

  • 8/14/2019 PMP Preparation Training

    27/30

    T D l t

  • 8/14/2019 PMP Preparation Training

    28/30

    Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-28

    Hertzbergs Motivation TheoryHertzbergs Motivation Theory

    HygienePay; working conditions; bosss attitudePoor hygiene factors negatively impact motivation

    Good hygiene factors increase motivation

    Motivators

    Positive motivation leads to achievement and self-actualization

    Workers have a sense of personal growth andresponsibility

    Team Development

    T D l t

  • 8/14/2019 PMP Preparation Training

    29/30

    Source: pmbok guide 2000 2002 Robbins-Gioia, Inc. 9-29

    Communications Skills TipsCommunications Skills Tips

    WrittenUse active voice

    KISS principle

    OralAnticipate reaction

    Say what you meanMake eye contactNEVERLIE

    Team Development

  • 8/14/2019 PMP Preparation Training

    30/30

    Summary

    Review Questions