Upload
solomon-bogdan-daniel
View
535
Download
53
Embed Size (px)
Citation preview
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 1/73
No other publication enjoys such a long tradition as a key
source of information as the "Injection Moulding Pocketbook".
We realise from the many requests we have for copies of the
booklet from right across the injection moulding industry that a
new edition is now needed. This latest publication represents
the completion of our reference work on the subject of injection
moulding.
Technological developments are not so much the focal point
here. It is the complete optimisation of the injection mouldingmachine, which includes the evaluation and selection of pro-cess parameters and the elimination of surface defects, that iscentral to this handbook.
We should like to thank Martin Bichler, Gunter Seibold,
Ansgar Jaeger, Fritz RoBner and Dr. Sabine Pahlke for their
active support.
Injection Moulding Pocketbook
Special publication fromMannesmann Demag Kunststofftechnik
1st edition 10/97, circulation 20.000Copyright6 1997 by Mannesmann Demag Kunststofftechnik
Id. no.: 183 790 65
1 Procesul de injectie....................... 4
Principii 5
2 Prima reglare a unei masini de injectie
2.1 Pregatiri....... 6
2.2 Pregatirea masinii....... 8
2.2.1 Reglarea unitatilor de inchidere cu articulatie 8
2.2.2 Reglarea unitatilor de inchidere hidraulice 10
2.3 Reglarea unitatii de injectie 11
2.4 Inceperea productiei 12
3 Desfasurarea ciclului de injectie la o masina ERGOtech
3.1 Inchiderea unitatii de inchidere 14
3.2 Faza de injectie si cea de presiune ulterioara 16
3.3 Dozare, snec si retragerea unitatii de injectie 18
3.4 Deschiderea unitatii de inchidere 20
4 Mic indrumar despre materiale
4.1 Indicatii la prelucrarea celor mai importanti polimeri 22
4.2 Caracteristici de recunoastere a maselor plastice 74
4.3 Temperaturi de prelucrare si pre-uscarea 78
5 Optimizarea procesului la masina de injectie
5.1 Caracteristici de calitate si parametrii de proces 81
5.2 Calcularea timpului de racire 91
6 Evaluarea corecta si alegerea parametrilor importanti
din punct de vedere al calitatii pentru asigurarea calitatii
pieselor injectate 97
7 Identificarea si eliminarea defectelor de suprafata
la piesele injectate 119
8 Exemplu de calcul al fortei de inchidere 125
9 Instructiuni de operare cu sistemul de control
ERGOtech NC4 137
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 2/73
Procesul de injectie matritata
In ultimele decenii procesul de injectie matritata si tot ceea ce este
in legatura cu acesta, s-a dezvoltat mai puternic decat aproape
toate celelalte procese de fabricatie cuprinzand o varietate din ce
in ce mai larga de produse. Avantajele sunt clare:
• material convenabil
• consum redus de energie la matritare datorat temperaturilor
scazute de procesare
• cale directa de la materia prima la produsul finit (operatiune
intr-un singur pas, fara finisari ulterioare)
Exista o multitudine de factori de influenta care se pot combina pentru
a obtine eficienta si inalta calitate si, daca sunt corect selctionati si
folositi, conduc la obtinerea, prin injectare matritata, a unor produse
de prima clasa.
Factorii de influenta in productia prin injectie sunt clasificati dupa
cum urmeaza:
1. Om
Motivare, calificare, flexibilitate, experienta ...
2. Masina pentru injectat
Ergonomicitate, eficienta, acuratete, fiabilitate, proiectare corecta,
optiuni de monitorizare ...
3. Matrita
Componenta orientata catre material si exact proiectata,proiectare termica, rigiditate, intretinere ...
4. Materia prima
Corect aleasa, curata, pre-uscata,
5. Periferice
Unitati control temperatura, control canale calde ...
6. Mediul ambiant
Siguranta, influentele mediului ...
Omul este unicul factor de influenta ce are abilitatea de a invata si de a
reactiona. Acest fapt il pune intr-o pozitie delicata si odata cu cresterea in
complexitate a procesului de injectie el are nevoie din ce in ce mai mult
de un suport pe masura.
Obiectivul acestei Carti de Buzunar este de a oferi ceva din acest suport.
Princii
Acuratetea si ordinea sunt strict necesare pentru aplicarea unei
metode sistematice de lucru. Aceasta poate incepe cu repunerea
capacului pe palnia de alimentare sau resigilarea sacilor deschisi
de materia si incheiat cu intocmirea documentatiei informative
folositoare pentru fiecare pas din optimizarea procesului.
Este deasemenea important sa acordati atentie influentelor
constante ale mediului si a se evita lasarea usilor deschise, ventila-
toare sau unitati de incalzire pornite in vecinatatea masinii.
Intr egul echipament din sectia de productie trebuie intretinut cu
regularitate. Inclusiv masina, matrita si toate unitatile periferice
Din motive de siguranta urmatoarele lucruri trebuie supravegheate
pe parcursul productiei:
• Sa se lucreze la matrita deschisa numai atunci cand pompa
este oprita.
• Sa se utilizeze manusi si incaltaminte de protectie si sa sefoloseasca o tija de cupru cand se lucreaza la canalele calde.
• Toate mecanismele de siguranta ale masinilor se verifica la
intervale regulate.
Avand toate aceste indatoriri, atunci cand se face reglarea masinii,
reglorul trebuie sa fie capabil sa acorde toata atentia masinii si proce-
sului. Similar, operatiunea de reglare nu trebuie sa fie doar o
operatie de citire a unor tabele si formule, ci fiecare valoare se
considera in mod logic si se analizeaza. Observand aceste reguli
de baza si urmatoarele indrumari in procesare si punandu-le in practica
ve-ti dispune de toate cele necesare procesului de prelucrare prin
injectie a maselor plastice.
Speram ca ve-ti parcurge cu placere acest indrumar si va uram
succes in reglarea masinii dumneavoastra de injectie.
4 5
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 3/73
Reglarea primara a unei
imasini de injectie mase plastice
2.1 Preliminar - lista de verificare
Articol injectat
Am mai produs acest reper in trecut ?
Pe ce tip de masina?
Datele de reglaj sunt deja disponibile pe un hard disk, floppy disk etc.?
Cate repere sunt necesare?
Pana cand?Este necesar echipament special pentru masurare?
Materialul, dimensiunile si greutatea reperului?
Matrita
Unde este matrita depozitata?
Aceasta matrita necesita reparatii sau reparatiile au fost deja facute?
Cum poate fi transportata si ridicata pe masina?
Ce dispozitiv de prindere este necesar pentru fixarea matritei pe
masina?
Parametrii urmatori au fost urmariti pentru a verifica compatibilitatea
matritei cu masina folosita?
• dimensiunile de fixare a matritei
• cercul de centrare
• capacitatea de injectie
• tija aruncatorului si cuplajul masinii (dimensiuni pentru conectare)
• nozzle radius and bore and corresponding sprue bush size
it additional equipment (core pullers etc.)
Are peripheral units required such as temperature control units,cooling units, hot runner controllers, conveyor belt?
Are the fittings on the cooling water connections on the
machine and the mould compatible?
Has the mould been leak-tested in the cooling water region?
Machine
Is the proposed machine available for the productiontarget date?
Is the maximum clamping force sufficient?
Has the necessary maintenance work been carried out?
Has the machine been running problem-free lately?
Is the appropriate screw cylinder available
(cylinder head volume, injection pressure)?
Material
Is there sufficient material for the job?
Where is the material stored?
Does the material need to be pre-dried?
Is there a supply of masterbatch, if required?
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 4/73
2.2 Preparing the machine
2.2.1 Setting up the clamping unit for
ERGOtech toggle machines 125 to 1300
Attention!
All mould adjustments to be made in set-up mode only
(For pressure and speeds see screen page 10 on NC4 IBED)
1. Extend the toggle. The ACTUAL value for*mould stroke
must be "0".
2. Using the "Mould height" function keys,'set platen distance
slightly greater than the mould height.
3. Move the moving platen to maximum opening distance.
4. Attach the mould securely to the lifting gear.The mould must hang straight. Make sure that the mould
halves cannot slide apart.
5. Protect the machine tie bars from damage during mould
installation.
6. Position the mould on the fixed platen, centre and attach.
If the mould is to be fixed using clamping shoes ensure a
proper fit.
7. Extend the toggle. Mould stroke on the IBED must indicate"0". Take care that the ejector rod moves into the ejectorcoupling without being forced. Now by using mould heightadjustment move the moving mould half until platen contactis made. Clamping force is now "0" kN.
8. Tighten the mould half on the moving platen. Remove
safety strap from mould, if used. Connect the ejector rodwith the ejector coupling using the slide mechanism.
9. Open the mould far enough to allow the moulding to fallout safely in due course. An accurate setting of the openingstroke can be made later when optimising the injectionmoulding process.
10. Enter clamping force. When the Start key is pressed theclamp unit moves automatically to approx. 75% of the setvalue of the clamp force. In automatic mode, when clampforce control is fitted, clamp force is regulated in stages to100% of the pre-selected value. If necessary, clamp forcecan be increased or decreased using the "Mould height"function key.
11. Now move the clamp unit in set-up mode until platencontact is made and read off the ACTUAL value for mould
stroke.
The stroke point for "Mould protection end" must be setapprox. 0.5 mm higher than the ACTUAL value displayed,in order to be able to lock the mould.
12. The speeds and change-over points for the mould andthe ejector must be compatible with the specification ofthe mould (see comments in chapter on Cycle Sequence).
13. When clamp force is set, tighten the clamps up on the
mould. If necessary, heat the mould beforehand.
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 5/73
2.2.2 Setting up fully hydraulic machines
ERGOtech 25 to 110
Attention!
All mould adjustments to be made in set-up mode only
1. Move clamp unit to maximum opening distance.
2. Attach the mould securely to the lifting gear. The mouldmust hang straight. Make sure that the mould halves cannot
slide apart. ''3. Protect the machine tie bars from damage during mould
installation.
4. Position the mould on the fixed platen, centre and attach.If the mould is to be fixed using clamping shoes, ensure aproper fit.
5. Move the clamp unit until platen contact is made, takingcare that the ejector rod moves into the ejector couplingwithout being forced.
6. Set mould height using the program switch. ACTUAL mouldstroke is indicated as 2 mm.
7. Tighten the mould half on the moving platen. Removesafety strap from mould, if used. Connect the ejector rodwith the ejector coupling using the slide mechanism.
8. Enter required clamp force.
On Compact machines the required hydraulic pressure mustalso be set using a manually operated valve to correspondwith the value displayed under "Clamp force".
9. To achieve clamping pressure, stroke point"Mould protection end" must be approx. 0.5 mm higherthan the set mould height.
10. The speeds and change-over points for the mould and theejector must be compatible with the specification of themould (see comments in chapter on Cycle Sequence).
11. When clamp force is set, tighten the clamps up on the
mould. If necessary, heat the mould beforehand.
10
2.3 Setting the injection unit
Follow instructions in the operating manual to change thescrew cylinder.
1. Enter the material-related temperatures required for thecylinder heating zones and for flange temperature control.
2. Turn on water supply to the machine.
3. Switch on cylinder heating.
4. Set reference point for injection unit.All heating zones must be up to SET temperature and the
mould must be locked.
5. In set-up mode, move the nozzle to contact with the mould.Then set to zero using program switch "Reference point IU".
6. Check nozzle radius centring and dipping depth.
7. Enter nozzle contact pressure, strokes and speeds for the
injection unit.
8. Enter metering stroke according to the necessary shot
weight. Calculate, if need be, taking into account the neces-sary melt cushion.
9. Enter injection pressure, injection speed, follow-up pressure,follow-up pressure time, cooling time, back pressure andscrew speed. See Chapter 4.1 "Processing Guidelines".
10. Switch on program switch "Change over to follow-up pres-
sure dependent on volume" (pN volume).
11. Enter stroke point for "Follow-up pressure start". Follow-uppressure start should occur at around 80 to 90 % of the
shot volume. As a rule, we recommend that a mould fillingstudy be made on new moulds to determine the exactchange-over point. In this case, follow-up pressure shouldbe set to "0".
12. If necessary, set decompression to release pressure of melt
in the cylinder if an open nozzle is used.
11
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 6/73
2.4 Starting the injection process
When all settings have been checked the machine can beswitched to the "semi-automatic" program. To enable themachine cycle to commence once the Start key has beenpressed, the following start conditions must be fulfilled:
• Mould open stop reached
• Ejector back
• Dosing Stop reached (dose manually beforehand and, if
necessary, depending on the type of material, purge the
material a few times). If one or several of the start conditions
is not met, alarms will be raised on theiBED.
As a rule, no monitoring functions or tolerances should be setduring the start-up phase.
The machine can be switched to "fully automatic" after a fewcycles, once the mouldings are being ejected and falling clear.At this point process optimisation can begin (more detailedinformation can be found in Chapter 5 "Process Optimisation
on the injection moulding machine"). The following sequenceis recommended:
• optimise dosing
• optimise injection speed
• determine follow-up pressure and follow-up pressure time
• limit injection pressure
• determine cooling time
• ensure smooth operation of clamping unit
• optimise clamping force
• carry out checks on mouldings
When the mouldings have reached the required quality standard
and the cycle time is satisfactory, the important parameters can
be monitored by setting tolerance limits using process control.
Safeguard the set machine data by storing the programme on
floppy disk. Also produce a hard copy.
12 13
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 7/73
The cycle sequence on
an ERGOtech machine
3.1 Closing the clamping unit
Fig. 1
Start conditions:
• Mould open stopif Hydraulic ejector back stop
• Guard door closed
• Cylinder up to temperature
• Start key depressed
14
Operating sequence
Assuming that the machine is an ERGOtech compact or system
model to standard design, the cycle will proceed as follows:
(see Fig. 1)
• All Start conditions must be met to enable the clamp unit to
be started (in semi- or fully automatic operation). (See Fig. 1)
• The clamp unit moves from Pos. [1] - "Mould open Stop" to
Pos. [2] on high pressure and at speed "Mould close V1".
if At Pos. [2] "Mould close" there is a change of speed to"Mould close V2".
• At Pos. [3] "Mould close" there is a change of speed to
"Mould close V3".
• Pos. [3] should be set so that speed V3 comes into effect at
the very latest by the start of reduced mould clamping pres-
sure at Pos. [4],
i If Pos. [3] is set after Pos. [4] there will be an automatic
change over to V3 at Pos. [4],
• Pos. [4] - "Mould protection start" - reduced mould clamp-ing pressure begins. This switch over point should occur30-60 mm before platen contact or, in the case of a slidingsplits mould, before the angled dowel moves into the splits.
it Reduced mould clamping pressure should be set just high
enough for the mould to close.
is On platen contact - Pos. [5] - the high pressure must beswitched on again at the control panel at "Mould protectionend" to achieve the set clamping force.
• At the same time as the mould closing movement "Mould
protection time" (determined empirically") starts at Pos. [4]and should not have finished by Pos, [5]. Otherwise, thecycle would be interrupted. (Exception: activation of "Mouldprotection repeat" program).
= = s . = ii i SB is!
15
Presiune
Viteza
Pozitie
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 8/73
3.2 Injection and follow-up pressure phase
Fig. 2
Injection stages - max. 10
Follow-up pressure stages - max. 10
Start conditions:
a Clamp force reached
• Guard door closed
• Injection unit guard door closed
• Cylinder up to temperature
• Dosing Stop and "Screw back" reached
Operating sequence
• When start conditions have been met (see Fig. 2) the injec-tion unit moves forward to Pos. [8] on speed "IU forward V".
• At Pos. [8] there is a change over to speed "IU forward V2".
The injection unit now moves forward on speed V2 until the
cylinder nozzle makes contact with the sprue bush on the
mould Pos. [9],
• Nozzle contact pressure now starts to build. When the given
nozzle contact pressure is reached, this initiates the com-mand for injection.
• The set values for "Injection pressure" and "Injection speed"
are also required.
• "Follow-up pressure start" at Pos. [10] initiates stroke
dependent change-over from injection pressure to follow-up
pressure. Alternatively, the change-over to follow-up pressure
can occur depending on time or pressure.
• If it is necessary to inject at varying speeds, the process can
operate on up to 10 different speeds. The speeds andstroke-dependent change-over points required can be set
on the "Injection profile" page.
• The follow-up pressure phase is operative from Pos. [10]
to Pos. [11]. If follow-up pressure needs to be stepped, this
can be set on the "Follow-up pressure profile" page.
in A reading for the actual melt cushion can be taken from the
Process Optimisation page.
• The actual value for the melt cushion should not be much
above or below the tolerance limits. The tolerances are set
on the "Process control" page.
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 9/73
3.3 Dosing, screw and injection unit back after dosing
Fig. 3
Dosing - max. 6 stages
Back pressure - max. 6 stages
Start conditions:
All activated follow-up pressure times have elapsed
Delayed feed has finished
"Screw back before dosing" has been completed, if sef
"IU back after dosing" program
19
Opera t i ng sequence
When the "Follow-up pressure times" have finished, "Cooling
time" begins. Dosing (melt processing) begins at Pos. [12]
when "Delayed feed" (Time) is over. Fig. 3.
Dosing begins at "Screw speed" Stage 1 and "Back
pressure" Stage 1 and ends at "Dosing Stop" Pos. [13].
It is possible, however, to operate on up to 6 different screw
speeds and 6 different screw back pressures per cycle. The
relevant change-over points can be set on the "Dosing pro-files" page,
Next, if set, comes screw decompression with "Screw back
after dosing" up to Pos. [14].
If the program "III back after dosing" is switched on, the
injection unit can be moved back on 2 speeds.
When time "IU back delayed" has elapsed, the injection unit
moves back on speed "IU back V1". At Pos. [15] there is a
change over to the second speed "IU back V2". The injection
unit now moves back on speed V2 as far as Pos. [16]
IU back stop".
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 10/73
3.4 Opening the clamping unit
Fig. 4
Operating sequence
• When start conditions have been met (Fig. 4) the clampingunit opens from Pos. [17] to Pos. [18] on speed "MouldopenVI".
• The slow speed facilitates the gentle demoulding of partsfrom the fixed mould half.
a With a sliding splits mould the change-over point"Mould open V1-V2" up to Pos. [18] is only activated after
the angled dowel is clear of the splits.• The clamping unit then moves to Pos. [19] on speed
"Mould open V2".
$ At Pos. [19] there is another change-over from speed
"Mould open V2" to "Mould open V3" to ensure smooth
running of the machine.
• The machine runs on this speed to Pos. [20]"Mould open stop".
• The entire opening stroke occurs at high pressure.
• The speeds for mould opening and mould closing and their
dedicated start points are shown on the "Speed profiles"
page.
Start conditions:
a Dosing stop
a "Screw back after dosing" is completed
• Injection unit back stop
a Cooling time is finished
20 21
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 11/73
Small material science
4.1 Processing guidelines for the most important plastics
This chapter sets out basic, relevant data for the treatment and
processing of the most important plastics.
Material Page
PP .' 23
PE : 26
PS 29
ABS 32
SAN 35
PA 38
POM 42
PC 46
PMMA 49
PPO 52
ABS/PC 55
PBTP 58
PETP 61
CA 64
PVC-U 67
PVC-P 70
22
Polypropylene, PP
Structure:
Partially crystalline
Density:
0.91-0.93 g/cm3
Thermal, optical, mechanical properties:Material is harder and more heat resistant than PE, but is less
resistant to low temperature (special low-temperature resistant
grade available). Particularly suitable for hinges. Hard, non-fragile,
excellent dielectric properties, non-toxic, not odour-proof.
Chemical properties:
resistant to
acids, alkaline solutions, salt solutions, alcohol, petrol,
fruit juices, oil, milk
not resistant to
chlorinated hydrocarbons, avoid contact with copper,
slight tendency towards stress cracking
Material identification:
PP is highly flammable, drips and continues to burn; burns brightly
with blue core, strong smell of paraffin (tar-like).
Cylinder temperature:
Flange 30- 50 °C / *50 °C
MH 1 160-250 °C/*200°C
MH 2 200-300 °C / *220 °C
MH 3 220-300 °C / *240 °C
MH 4 220-300 °C / *240 °C
DH 220-300 °C / *240 °C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 % and
for parts with a flow length/wall thickness ratio of between 50:1 and 100 :1.
Si ~ S B IB
23
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 12/73
Melt temperature:
220-280 °C
Reduced cylinder temperature:
220 °C
Injection pressure:
There is no build up of very high injection pressure
(800-1400 bar), since flow characteristics are generally good.Exceptions are thin-walled packaging parts. An injection pres-sure of up to 1800 bar can result on these parts.
Follow-up pressure and follow-up pressure time:
Very long follow-up pressure times are necessary to avoid sinkmarks (approx. 30 % of the cycle time).
Follow-up pressure approx. 30-60 % of the required injectionpressure.
Back pressure:
50-200 bar
Injection speed:
Fast injection speeds are needed (accumulator) for thin-walledpackaging parts. Under other circumstances average injectionspeeds suffice.
Screw speed:
Peripheral velocity of 1.3 m/sec is the maximum screw speedon the machine. However, this should only be set as fast as isnecessary for the plasticising process to finish before coolingtime expires.
Recommended min. and max. dosing stroke:
0.5-4.0 D dosing stroke can be utilised.
Residual melt cushion:
2-6 mm, depending on dosing stroke and screw diameter.
24
Pre-drying:
Not necessary; under poor storage conditions perhaps 1 hour
at80°C.
Re-processing:
Up to 100 % regrind can be processed.
Shrinkage:
1.2-2.5 %. Final shrinkage can only be assessed after
24 hours.
Gating:
Pin gate or multi-point pin gate, hot runner, insulated runner,ante-chamber; gate at the strongest point of the moulding.
Machine shut-down:
No other material is required to follow up. PP is very resistant to
high temperatures.
Cylinder equipment:
Standard screw; for packaging parts special geometry L:D 25:1
with shear and mixing section. Open nozzle, non-return valve.
25
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 13/73
Polyethylene, PE (HDPE)
Structure:
Partially crystalline
Density:
0.92-0.96 g/cm3
Thermal, optical, mechanical properties;
Material is flexible to soft, resistant to terjiperatures up to-40 °C depending on density, impact resistant, indestructible.
Good dielectric properties, low water absorption, non-toxic,not odour-proof.
Chemical properties:
resistant to
acids, alkaline solutions, solvents, alcohol, petrol, fruit juices,
oil, milk
not resistant to
aromatic solvents, chlorinated hydrocarbons, risk of stresscracking
Material identification:
PE is highly flammable, continues to burn when removed from
source of heat, drips. Luminous flame with blue core, smells like
paraffin (snuffed candles).
Cylinder temperature:
Flange 30- 50 °C / *50 °C
MH1 160-250 °C/ *2 00 °C
MH 2 200-300 °C/ *210 °C
MH 3 220-300 °C/ *230 °C
MH4 220-300 °C/* 240 °C
DH 220-300 °C /*240 °C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100:1.
2i iji.
26
Melt temperature:
220-280 °C
Reduced cylinder temperature:
220 °C
Injection pressure:
There is no build-up of very high injection pressure
(800-1400 bar), since flowability is good. Exceptions arethin-walled packaging parts. An injection pressure of up to
1800 bar can result on these parts.
Follow-up pressure and follow-up pressure time:
Long follow-up pressure times on dimensionaiiy accurate parts
due to relatively extensive shrinkage. Pressure approx. 30-60 %
of injection pressure.
Back pressure:
50-200 bar. Too little back pressure results in uneven mouldingweight or poor pigment dispersion during colouring.
Injection speed:
Fast injection speed (accumulator) required for thin-walled
packaging parts. Otherwise, average injection speed better.
Screw speed:
Peripheral velocity of 1.3 m/sec is max. setting for screw speed
on the machine. However, this should only be set as fast as is
necessary for the piasticising process to finish before cooling
time expires. Required screw torque is low.
Recommended min. and max. dosing stroke:
0.5-4.0 D dosing stroke can be utilised.
Residual melt cushion:
2-8 mm depending on dosing stroke and screw diameter.
27
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 14/73
Pre-drying:
Not necessary. Under poor storage conditions, perhaps 1 hour
at 80 °C.
Re-processing:
Up to 100 % regrind can be processed.
Shrinkage:
1.5-2.5 %, substantial shrinkage, substantial warpage. Finalshrinkage can only be assessed after 24 hours. (After-shrink-
Gating:
Pin gate, hot runner, insulated runner, ante-chamber pin gate.
Relatively small cross sections suffice.
Machine shut-down:
No other material is required to follow up. PE is very resistant to
high temperatures.
Cylinder equipment:
Standard geometry for packaging parts; special geometry L:D
25:1 with shear and mixing section; open nozzle, non-return
valve.
Polystyrene, PS
Structure:
Amorphous
Density:
1.05 g/cm3
Thermal, optical, mechanical properties:
Hard, stiff, fragile, very good dielectric properties, low water
absorption, good dimensional stability, crystal clear, brilliant,
good pigmentability, no smell or taste.
Chemical properties:
resistant to
acids, alkaline solutions, alcohol, grease, oil, salt solutions
not resistant to
petrol, benzene, large number of solvents, risk of stress
cracking
Material identification:
PS is highly flammable, burns bright yellow, produces a lot of
black smoke, and typically smells slightly sweet (styrene).
Cylinder temperature:
Flange 30 - 50 °C / *50 °C
MH 1 160-220 °C/ *2 00 °C
MH 2 180-240 °C/ *2 10 °C
MH 3 210-280 °C/ *2 30 °C
MH 4 220-280 °C/ *230 °C
DH 220 -280 °C /*230 °C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 1 00:1.
28 29
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 15/73
Melt temperature:
220-280 °C
Reduced cylinder temperature:
220 °C
Injection pressure:
There is no build-up of very high injection pressure
(800-1400 bar), because flowability is good.
Follow-up pressure and follow-up pressure time:
Relatively short follow-up pressure time. Pressure level30-60 % of injection pressure.
Back pressure:
50-100 bar. If back pressure is set too low, this can result inair burns in the melt (displayed as grey or black streaks in themoulding).
Injection speed:
Generally fast. Stepped depending on shape of moulding.For thin-walled packaging parts, as fast as possible; partly with
accumulator.
Screw speed:
Fast screw speeds can be set up to a max. 1.3 m/sec peri-pheral velocity. However, plasticising is best carried out slowly
to suit cooling time.
Recommended min. and max. dosing stroke:
0.5-4.0 D dosing stroke can be utilised.
Residual melt cushion:
2-8 mm depending on dosing stroke and screw diameter.
Pre-drying:
1 hour at 80 °C if material has not been properly stored.
30
Re-processing:
Up to 100 % regrind can be processed.
Shrinkage:
0.3-0.6 %
Gating:
Pin gate, hot runner, insulated runner, ante-chamber. Relatively
small cross sections suffice.
Machine shut-down:
No other material is required to follow up. PS is resistant to high
temperatures.
Cylinder equipment:
• Standard screw
• Open nozzle
• Non-return valve
31
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 16/73
Acrylonitrile-butadiene-styrene, ABS
Structure:
Amorphous
Density:
1.06-1.19 g/cm3
Thermal, optical, mechanical properties:
Hard, tough even at -40 °C, good resistance to changes intemperature, resistance to low temperatures or heat (+100 °C)
depending on type, limited weather resistance, low water
absorption, non-toxic, electroplatable. Special purpose materialalso crystal clear.
Chemical properties:
resistant to
acids, alkaline solutions, hydrocarbons, oils, fats, petrol
not resistant to
acetone, ether, ethyl benzene, ethyl chloride, ethylene chloride,aniline, aniseed oil, benzene
Material identification:
ABS is highly flammable, burns bright yellow, produces black
smoke and typically smells slightly sweet (styrene).
Cylinder temperature:
Flange 40- 60 °C / *50 °C
MH 1 160-180 °C/*180 °C
MH2 180-230 °C/ *210°C
MH 3 210-260 °C/*24 0 °C
MH 4 210-260 °C/ *240 °C
DH 210-260 °C/ *240°C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100:1.
Melt temperature:
220-250 °C
Reduced cylinder temperature:
200 °C
Injection pressure:
1000-1500 bar
Follow-up pressure and follow-up pressure time:
Relatively short follow-up pressure time. Pressure level
30-60 % of injection pressure.
Back pressure:
50-150 bar. If back pressure is set too low, this can result in
air burns in the melt (displayed as grey or black streaks in themoulding).
Injection speed:
Best stepped, slow injection to begin with, then fast (frontal
flow). Fast injection speed is good for achieving glossy, spar-kling surfaces, a good, strong weld line and only a slight weld
line mark. Venting channels are required on the weld line.
Screw speed:
Peripheral velocity of 0.6 m/sec is max. setting for screw speed.
However, it is better to set screw speed sufficiently slow so that
piasticising finishes shortly before cooling time expires.
Recommended min. and max. dosing stroke:
0.5-4.0 D dosing stroke can be utilised.
Residual melt cushion:
2-8 mm depending on dosing stroke and screw diameter.
a ii! ill 11! 11! il l -Si IS i ll !!! s z, 81 Si s m i!r 18 = = a = = m s
32 33
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 17/73
Machine shut-down:
No more material is required to follow up.
Pre-drying:
To some extent ABS can be processed direct from the original
bags without pre-drying. Otherwise, pre-dry for 3 hours at
80 °C. Damp material causes stripes, streaks or blisters on the
moulding.
Re-processing:
Providing the material has not already been charred, up to 30 %
regrind can be added to virgin material.
Shrinkage:
0.4-0.7 %
Gating:
Pin gate possible, likewise hot runner. Wall thickness should not
be less than 0.7 mm.
Machine shut-down:
No more material is required to follow up.
Cylinder equipment:
• Standard screw
iii Non-return valve
• Open nozzle
34
Styrene-acrylonitrile copolymer, SAN
Structure:
Amorphous
Density:
1.08 g/cm3
Thermal, optical, mechanical properties:
Excellent transparency and high gloss, good stiffness and
hardness. Good resistance to changes in temperature, good
chemical resistance, good heat resistance.
Chemical properties:
resistant to
acids, alkaline solutions, saturated hydrocarbons, mineral oils,
vegetable and animal fats
not resistant toconcentrated mineral acids, aromatic hydrocarbons and chlori-
nated hydrocarbons, ester, ether and ketone
Material identification:
SAN is highly flammable, burns bright yellow, is very smoky and
smells typically of styrene.
Cylinder temperature:
Flange 30- 50 °C / *50 °CMH 1 160-180 °C/*180°C
MH2 180-230 °C/ *2 10 °C
MH3 210-260 °C/ *2 40 °C
MH 4 220-260 °C /*240 °C
DH 220-260 °C /*240 °C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100:1.
35
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 18/73
Melt temperature:
220-250 °C
Reduced cylinder temperature:
200 °C
Injection pressure:
1000-1500 bar
Follow-up pressure and follow-up pressure time:
Relatively short follow-up pressure time. Pressure 30-60 % ofinjection pressure.
Back pressure:
50-100 bar. If back pressure is set too low, this can result inair burns in the melt (displayed as grey or black streaks in themoulding).
Injection speed:
Fast injection speed is good for achieving glossy, sparklingsurfaces, a good, strong weld line and only a slight weld linemark.
Screw speed:
Max. screw speed equivalent to 0.6 m/sec peripheral velocity.Screw speed should always be set, however, so that plasticisingfinishes just before cooling time expires. Average screw torque
required.
Recommended min. and max. dosing stroke:
0.5-4.0 D dosing stroke can be utilised.
Residual melt cushion:
2-8 mm depending on dosing stroke and screw diameter.
36
Pre-drying:
If SAN is not stored or transported under the right conditions,it will absorb moisture. This can cause streaks, stripes or smallblisters to appear on the surface of the moulding duringprocessing.
Re-processing:
Providing no charring has occurred during initial processing,
up to 30 % regrind can be added to the virgin material. For highquality parts, however, virgin material should always be used.
Shrinkage:
0.4-0.7 %
Gating:
In principle, all types of gating systems can be used, and
likewise for hot runners.
Machine shut-down:
No other material is required to follow up.
Cylinder equipment:
• Standard screw
• Non-return valve
• Open nozzle
w
37
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 19/73
Polyamide, PA
Structure:
Partially crystalline
Density:
1.14 g/cm3
Thermal, optical, mechanical properties:
In balanced humidity (2-3 %), very tough. In dry conditions,
brittle. Hard, stiff, abrasion resistant, good frictional characteris-
tics. Good pigmentability, non-toxic, adhesive properties.
Chemical properties:
resistant to
oils, petrol, benzene, alkaline solutions, solvents, chlorinated
hydrocarbons, esters, ketone
not resistant to
ozone, hydrochloric acid, sulphuric acid, hydrogen peroxide
Material identification:
PA is flammable. It continues to burn when removed from
source of heat, drips and blisters, becomes stringy. Blue flame
with yellow rim. Smells like burnt bone.
Cylinder temperature:
PA 6
Flange 60- 90 °C / *70 °C
MH 1 230-240 °C/*240°C
MH 2 230-240 °C/ *2 40°C
MH3 240-250 °C/* 250 °C
MH 4 240-250 °C/*250 °C
DH 230-240 °C/* 250 °C
38
PA 6.6
Flange 60- 90 °C / *80 °C
MH 1 260-290 °C/*280 °C
MH2 260-290 °C/ *2 80°C
MH 3 280-290 °C/ *2 90°C
MH4 280-290 °C/ *2 90°C
DH 280-290 °C /*290 °C
1 Feed performance is most strongly affected by the flange temperatures and
the temperatures in zone MH 1. By raising these temperatures, feed performance
becomes more uniform.
Melt temperature:
PA 6 240-250 °C
PA 6.6 270-290 °C
Reduced cylinder temperature:
PA 6 220 °CPA 6.6 250 °C
Injection pressure:
1000-1600 bar; on thin-walled articles with long flow paths
(cable clip) up to 1800 bar.
Follow-up pressure and follow-up pressure time:
Normally, approx. 50 % of the resulting injection pressure. Short
follow-up pressure times are sufficient, as the material solidifiesrelatively quickly. As follow-up pressure decays, so the stress in
the moulding reduces.
Back pressure:
Set very accurately. 20-80 bar, as excessive back pressure
leads to uneven plasticising.
Injection speed:
Inject relatively quickly. Ensure that the mould is properly
vented, otherwise charring occurs on the moulding.
39
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 20/73
Screw speed:
Fast screw speed possible up to 1 m/sec peripheral velocity.However, it is better to set the screw speed slow enough, sothat plasticising finishes shortly before cooling time expires.Low screw torque required.
Recommended min. and max. dosing stroke:
0.5-3.5 D dosing stroke.
Residual melt cushion:
Small melt cushion (2-6 mm), depending on dosing stroke and
screw diameter.
Pre-drying:
Polyamides are hygroscopic, so store in moisture-proof
containers. Close feed hopper!
A moisture content of more than 0.25 % creates processingdifficulties. Process directly from canister, otherwise pre-dry for
4 hours at 80 °C.
Re-processing:
10 % regrind can be added to virgin material.
Shrinkage:
PA 6
0.7-2.0%
PA 6.6
0.3-0.8%
PA 6-GF30
0.7-2.0%
PA 6.6-GF300.4-0.7%
Parts with operating temperatures above 60 °C must be an-
nealed. Annealing cuts down after-shrinkage i.e. the parts aredimensionaily more stable and have lower stress. Steam treat-ment works best. Polyamide mouldings can be checked forstress using soldering fluid.
Gating:
Possible gating systems include pin gate, tunnel gate, film gate,sprue gate. Blind holes are recommended for cold siugs.PA can also be processed using a hot runner. The temperaturein the hot runner must be accurately controlled, as the meltsolidifies within a limited temperature range.
Machine shut-down:
No other material is required to follow up. Melt dwell time in thecylinder is possible up to 20 mins, thereafter thermal degrada-tion of melt occurs.
Cylinder equipment:
• Standard screw
• Non-return valve
• Open nozzle
Wear resistant cylinder equipment is required for glass fibre
reinforced materials.
40 41
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 21/73
Polyacetal, POM
Structure:
Partially crystalline
Density:
1.41-1.42 g/cm3
Thermal, optical, mechanical properties:
Hard, stiff, tough, indestructible up to -40 °C, good heat resis-tance, good abrasion resistance, good frictional characteristics,low moisture absorption, non-toxic.
Chemical properties:resistant to
weak acids, weak alkaline solutions, petrol, benzene, oils,alcohol
not resistant tostrong acids
Material identification:
Highly flammable, bluish flame, drips and continues to burn,smells like formaldehyde.
Cylinder temperature:
Flange 40 - 50 °C / *50 °C
MH 1 160-180 °C/*180 °C
MH 2 180-205 °C/*190 °C
MH 3 185-205 °C/*200 °C
MH4 195-215 °C/*205 °C
DH 190-215 °C/*205 °C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100:1.
Most favourable processing temperature around 210 °C.
Melt temperature:
205-215 °C
Reduced cylinder temperature:
150 °C
Injection pressure:
1000-1500 bar.
For thick walled technical parts with a wall thickness of3-4 mm, injection pressure amounts to approx. 1000 bar;for thin-walled parts it can rise to approx. 1500 bar.
Follow-up pressure and follow-up pressure time:
Dependent on the wall thickness of the moulding and on mouldtemperature. The longer the follow-up pressure, the less theshrinkage on the mouldings. Follow-up pressure should amountto approx. 800-1000 bar to achieve a pressure of around600-700 bar in the mould. Where precision mouldings are con-cerned, it is useful if injection and follow-up pressure are thesame (no drops in pressure). Extend follow-up pressure time forthe same total cycle time. Weigh mouldings until weight stabi-lises and optimum follow-up pressure time is established. Moreoften than not follow-up pressure time amounts to approx. 30%of the total cycle time. A moulding reaching 95% ideal weightshrinks by 2.3%. A moulding reaching 100% ideal weightshrinks by 1.85%. Slight, even shrinkage signifies consistantpart size.
Back pressure:
50-100 bar
Injection speed:
Average injection speed. If injection is too slow, pores appear
on the surface of the mouldings. If mould or melt temperature
is too low, the same thing happens.
42
• • • • •
43
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 22/73
Screw speed:
Max. equivalent to peripheral velocity of only approx. 0.7 m/sec.
Advisable to set it so that plasticising finishes just before cooling
time expires. Average screw torque required.
Recommended min. and max. dosing stroke:
0.5-3.5 D dosing stroke.
Residual melt cushion:
2- 6 mm depending on dosing strode and screw diameter.
Pre-drying:
Not necessary. If material has become moist, dry for approx.4 hours at 100 °C.
Re-processing:
100 % for less important applications. Up to 20 % regrind
possible for precision parts.
Shrinkage:
Approx. 2 % (1.8-3.0)
Final shrinkage only determined after 24 hours.
Gating:
Pin gate can be used for small parts with uniform wall thickness.Select gate thickness to 50-60 % of the most concentrated wallthickness on the moulding. It is helpful to inject against some
form of resistance in the mould cavity (core, wall), because ofthe laminar flow. Processing with hot runner moulds is state ofthe art.
Machine shut-down:
Switch off heating and set back pressure to "0" 5-10 minutesbefore production ends. Purge cylinder. When overmouldingwith another material e.g. PA or PC, PE should be run throughin between, as it has a broad processing latitude.
44
Cylinder equipment:
• Standard screw
• Open nozzle
• Non-return valve
s i m a • • •
45
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 23/73
Polycarbonate, PC
Structure:
Amorphous
Density:
1.2g/cm3
Thermal, optical, mechanical properties:*
Hard, stiff, impact resistant up to -100 °C, good heat resistance,crystal clear, non-toxic, good pigmentability, low moistureabsorption, weather resistant.
Chemical properties:
resistant to
oil, petrol, dilute acids, alcohol
not resistant to
strong acids, alkaline solutions, benzene
Material identification:
Does not burn easily, sample extinguishes away from source ofheat, burns bright yellow, is smoky, chars, blisters, has notypical smell.
Cylinder temperature:
Flange 70- 90 °C / *80 °C
MH 1 230-270 °C/*250 °C
MH 2 260-310 °C/*270 °C
MH 3 280-310 °C/ *2 90°C
MH 4 290-320 °C /*290 °C
DH 300-320 °C/ *2 90°C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100 :1.
46
Melt temperature:
280-310°C
Reduced cylinder temperature:
200 °C
Injection pressure:
Very high injection pressures are needed, as material does not
flow well (1300-1800 bar).
Follow-up pressure and follow-up pressure time:
Approx. 40-60 % of the required injection pressure. The lower
the follow-up pressure, the lower the stress in the mouldings.
Back pressure:
100-150 bar
Injection speed:
Dependent on flow length and wall thickness. Fast injection forthin-walled parts. If good surface quality is required, usestepped (slow-fast) injection speed.
Screw speed:
Max. 0.6 m/sec peripheral velocity. Adjust plasticising time
to suit cooling time. High torque is required on the screw.
Recommended min. and max. dosing stroke:
0.5-3.5 D dosing stroke can be utilised.
Residual'melt cushion:
2-6 mm depending on dosing stroke and screw diameter.
Pre-drying:
3 hours at 120 °C. Optimum mechanical properties if water
content is less than 0.02 %.
m m a §; ~ s
47
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 24/73
Re-processing:
Up to 20 % regrind can be mixed with virgin material. Heatresistance is also maintained if regrind quota is increased,but the mechanical properties deteriorate.
Shrinkage:
0.6-0.8 %
0.2-0.4 % glass fibre reinforced
Gating:
The diameter of the gate should correspond to at least 60-70 %of the most concentrated wall thickness on the moulding, but1.2 mm is the smallest gate diameter (gate - angle of cone 3-5°,on a good surface 2°). Pin gate can be used for smaller compo-nents with uniform wall thicknesses.
Machine shut-down:
Where breaks in production occur during the night, emptythe cylinder and drop temperatures to approx. 200 °C. Whencleaning the cylinder it is useful to inject through with high-viscosity PE. Draw the screw out of the heated barrel andremove residual material from the screw using a wire brush.
Cylinder equipment:
a Standard screw
B Non-return valve
• Open nozzle
48
Polymethyl methacrylate, PMMA
Structure:
Amorphous
Density:
1.18 g/cm3
Thermal, optical, mechanical properties:
Hard, brittle, very strong, scratch-proof, crystal clear, goodoptical quality, high gloss, extremely weather resistant, goodpigmentability, non-toxic.
Chemical properties:
resistant to
weak acids, weak alkaline solutions, fats and oils
not resistant to
strong acids and alkaline solutions, chlorinated hydrocarbons,risk of stress cracking
Material identification:
Highly flammable, burns brightly even when removed from
source of heat, crackling flame, rather smoky, sweet fruity
smell.
Cylinder temperature:
Flange 60- 80 °C / *70 °CMH 1 150-200 °C/*190 °C
MH 2 180-220 °C/*210°C
MH3 200-250 °C/*230°C
MH 4 200-250 °C /*230 °C
DH 200-250 °C /*230 °C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100:1.
49
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 25/73
Melt temperature:
220-250 °C
Reduced cylinder temperature:
170°C
Injection pressure:
High pressures needed due to poor flow characteristics
(1000-1700 bar).
Follow-up pressure and follow-up pressure time:
Very long and high follow-up pressure needed (2-3 mins) forthick walled parts (lenses etc.). Follow-up pressure in generalamounts to 40-60 % of injection pressure.
Back pressure:
Relatively high back pressure required. 100-300 bar. Insufficient
back pressure causes gas bubbles in the moulding.
Injection speed:
Dependent on wall thickness and flow length. For thick walledarticles initial injection should be extremely slow to achieve per-fect frontal flow. Stepped injection speed (slow-fast) to obtaingood surface quality near the gate.
Screw speed:
Plasticise as slowly as possible according to cooling time.
Screw requires high torque, max. 0.6 m/sec peripheral velocity.
Recommended min. and max. dosing stroke:
0.5-3.5 D dosing stroke can be utilised.
Residual melt cushion:
2-6 mm depending on dosing stroke and screw diameter.
Pre-drying:
PMMA absorbs up to 1 % water. Pre-dry for 4 hours atapprox. 80 °C.
50
Re-processing:
Possible with properly pre-dried and pigmented material. Crystalclear regrind no longer produces parts with good optical quality.
Shrinkage:
0.3-0.7 %
Gating:
Large gates required, as material does not flow easily. For lenses,gate must be 0.5 mm smaller than wall thickness on the outeredge of the lenses. Smallest gate diameter - most concentratedwall thickness on moulding. To achieve good surface qualitynear the gate it is important to avoid sharp edges between thegate and the moulding. Short, round or square gate cross-sec-tion needed for good, long pressure transfer. Wide, thin gatesare not advisable.
Machine shut-down:
No other material is required to follow up.
Cylinder equipment:
• Standard screw; in some cases, special geometry
• Non-return valve
• Open nozzle
51
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 26/73
Polyphenylene oxide, PPO
Structure:
Amorphous
Density:
1.05-1.1 g/cm3
Thermal, optical, mechanical properties:
Hard, stiff, good frictional and abrasion characteristics, goodheat resistance, low water absorption, good scratch resistance,non-toxic.
Chemical properties:
resistant to
acids, alkaline solutions, alcohol, fats, oils
not resistant to
benzene, chlorinated hydrocarbons
Material identification:
Does not ignite easily, flame extinguishes away from source,
does not drip, smoky, luminous flame, pungent smell. PPO is
not transparent.
Cylinder temperature:
Flange 40- 60 °C / *50 °C
MH 1 240-280 °C/*250 °C
MH 2 280-300 °C /*280 °C
MH 3 280-300 °C /*280 °C
MH4 280-300 °C/ *2 80°C
DH 280-300 °C/*280 °C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100:1 .
52
Melt temperature:
270-290 °C
Reduced cylinder temperature:
200 °C
Injection pressure:
1000-1400 bar
Follow-up pressure and follow-up pressure time:
40-60 % of injection pressure
Back pressure:
30-100 bar
Injection speed:
Mouldings with long flow paths require fast injection speed;
in such instances, however, it is important to ensure adequatemould venting.
Screw speed:
Average screw speeds. Max. peripheral velocity 0.6 m/sec.
Recommended min. and max. dosing stroke:
0.5-3.5 D dosing stroke can be utilised.
Residual melt cushion:
3-6 mm depending on dosing stroke and screw diameter.
Pre-drying:
2 hours at 110 °C
Re-processing:
Can be reprocessed as regrind providing the material has not
been charred.
53
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 27/73
Shrinkage:
0.8-1.5 %
Gating:
Pin/tunnel gate for small mouldings, otherwise sprue gate,
diaphragm gate, hot runner.
Machine shut-down:
Switch off heating; where screw back pressure is low, doseseveral times and purge cylinder.
Cylinder equipment:
• Standard screw
• Non-return valve
• Open nozzle
Acrylonitrile-butadiene-styrene + polycarbonate, ABS + PC
Structure:
Amorphous
Density:
1.15 g/cm3
Thermal, optical, mechanical properties:
Impact resistant, high gloss, light resistant, electroplatable, heat
resistant, good fracture resistance.
Chemical properties:resistant to
limited hydrolysis resistance
not resistant to
ketone, ester, chlorinated hydrocarbon
Cylinder temperature:
Flange 50 - 70 °C / *70 °C
MH 1 230-250 °C / *250 °C
MH 2 250-260 °C / *260 °C
MH 3 250-270 °C / *265 °C
MH 4 250-270 °C / *265 °C
DH 250-270 °C / *270 °C* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100:1.
Melt temperature:
260-270 °C
Reduced cylinder temperature:
200 °C
Injection pressure:
800-1500 bar
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 28/73
Follow-up pressure and follow-up pressure time:
Approx. 40-50 % of the required injection pressure in order toavoid sink marks appearing. Follow-up pressure must be set aslow as possible to produce low-stress mouldings.
Back pressure:
Only around 50-100 bar in order to avoid frictional heat.
Injection speed:
Average injection speed (up to 60 mm/sec) to keep frictionalheat down. Partially stepped - slow-fast.
Screw speed:
Max. screw speed corresponding to approx. 0.4 m/sec
peripheral velocity.
Recommended min. and max. dosing stroke:
1.0-3.0 D dosing stroke because the melt is susceptible to
overheating or because of excessive melt dwell time in the plas-ticising cylinder. Dwell time for the melt in the cylinder shouldnot exceed 6 mins.
Residual melt cushion:
2-5 mm depending on screw diameter and dosing stroke.
Pre-drying:
4 hours at 80 °C.
Re-processing:
Up to 20 % regrind can be added, provided it has been properlypre-dried and is not charred. It is better to use regrind for partswhere strength requirements are not so stringent.
56
Shrinkage:
Shrinkage is almost identical in all axes and amounts to0.5-0.7 %; 0.2-0.4 % on glass reinforced types.
Gating:
Any recognised type of gate can be used. When injecting viahot runner, temperature in the hot runner must be accuratelycontrolled.
Machine shut-down:
Switch off heating. Purge cylinder.
Cylinder equipment:
• Standard screw up to 50 mm diameter. Where larger screwdiameters are concerned, use screw with lower compressionand shorter metering section.
• Non-return valve
• Open nozzle
57
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 29/73
Polybutylene terephthalate, PBTP
Structure:
Partially crystalline
Density:
1.30 g/cm3
Thermal, optical, mechanical properties:
Good heat resistance, good stiffness and hardness, low waterabsorption, good resistance to stress cracking, excellent fric-tional characteristics and abrasion resistance, good dimensionalstability, non-toxic.
Chemical properties:
resistant to
oils, fats, alcohol, ether, petrol, weak acids, weak alkalinesolutions
not resistant to
benzene, alkalis, strong acids, strong alkaline solutions, ketone
Material identification:
Material does not ignite easily, extinguishes when removed fromflame, luminous flame, yellowy orange, smoky, slightly sweetaromatic smell.
Cylinder temperature:
Flange 50 - 70 °C / *70 °C
MH 1 230-250 °C /*240 °C
MH 2 240-260 °C/*250 °C
MH 3 250-260 °C/*260 °C
MH 4 250-260 °C/*260 °C
DH 250-260 °C/*260°C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100:1.
Melt temperature:
250-260 °C, narrow processing range
below 240 °C danger of freezing
above 270 °C material becomes charred
Reduced cylinder temperature:
210 °C
Injection pressure:
Injection pressure of 1000-1400 bar can result. Follow-uppressure should amount to 50-60 % of the resulting injectionpressure.
Back pressure:
Only approx. 50-100 bar in order to avoid frictional heat.
Injection speed:
Fast injection speeds are required because of melt setting
speed and the rate of crystallisation. Cooling or setting of themelt during injection must be avoided. Ensure mould is wellvented, otherwise there will be signs of charring at the end ofthe flow path as a result of compressed air.
Screw speed:
Max. screw speed corresponding to approx. 0.7 m/secperipheral velocity.
Recommended min, and max. dosing stroke:
0.5-3.5D dosing stroke because melt is susceptible to over-heating or because of excessive melt dwell time in the plasticis-ing cylinder. Dwell time for the melt in the cylinder should notexceed 5 mins.
Residual melt cushion:
2-5 mm depending on dosing stroke and screw diameter.
Pre-drying:
4 hours at 120 °C.
58 59
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 30/73
Re-processing:
Up to 10 % regrind can be added for material types containing
flame retardants, providing the material has not been charred
and has been properly pre-dried. Up to 20 % for material types
without flame retardants.
Shrinkage:
Very dependent on mould temperature. The higher the mould
temperature, the greater the shrinkage - 1-.4-2.0 %.
0.4-0.6 % for 30 % GF.
Gating:
Do not use concentric sprue or pin gate with glass fibre rein-
forced materials. Injection point should be selected so that the
cavity is filled evenly. When gating via hot runner, temperature
must be accurateiy controlled in the hot runner.
Machine shut-down:
Switch off heating. Empty cylinder. During breaks in productionand before restarting the machine, squirt the melt out until it is
free from bubbles.
Cylinder equipment:
• Standard screw
s Non-return valve
• Open nozzle
Polyethylene terephthalate, PETP
Structure:
Partially crystalline
Density:
1.35 g/cm3
Thermal, optical, mechanical properties:
Good impact strength, extreme hardness and stiffness (slightlymore so than PBTP), good dimensional stability, low water
absorption, only slight internal stress, good flowability.
Chemical properties:
resistant to
oils, fats, alcohol, ether, petrol, weak acids, weak alkaline
solutions
not resistant to
benzene, alkalis, strong acids, strong alkaline solutions, ketone
Material identification:
The material is difficult to ignite, extinguishes away from flame,
luminous flame, yellowy orange, smoky, slightly sweet aromatic
smell.
Cylinder temperature:
Flange 50- 70 °C / *70 °C
MH 1 240-260 °C/*250 °C
MH 2 240-260 °C /*250 °C
MH3 250-290 °C/ *2 70 °C
MH 4 250-290 °C/*270 °C
DH 250-290 °C /*270 °C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100:1.
60 61
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 31/73
Melt temperature:
270-280 °C
Reduced cylinder temperature:
220 °C
Injection pressure:
For thin walled articles, injection pressure up to 1600 bar canresult.
Follow-up pressure and follow-up pressure time:
Approx. 50-70 % of the required injection pressure in order to
avoid sink marks. Set follow-up pressure time only for as long
as is necessary. With amorphous materials in particular, exces-
sive follow-up pressure times cause increased stress, which
reduces the impact strength of the mouldings.
Back pressure:
Only around 50-100 bar in order to avoid frictional heat.
Injection speed:
Fast injection speeds are required because of melt settingspeed and the rate of crystallisation. Cooling or setting of themelt during injection must be avoided. Ensure mould is wellvented, otherwise there will be signs of charring at the end ofthe flow path as a result of compressed air.
Screw speed:
Max. screw speed corresponding to approx. 0.7 m/secperipheral velocity.
Recommended min. and max. dosing stroke:
0.5-3.5 D dosing stroke because melt is susceptible to over-heating or because of excessive melt dwell time in the plasticis-ing cylinder. Dwell time for the melt in the cylinder should notexceed 5 mins.
62
Residual melt cushion:
2-5 mm depending on dosing stroke and screw diameter.
Pre-drying:
4 hours at 140 °C.
Re-processing:
Max. 20 % regrind can be added providing it has not beencharred and has been properly pre-dried. Not possible to
achieve the same tensile, flexural and impact strength as whenvirgin material is used.
Shrinkage:
Varies greatly depending on material type, wall thickness, mould
temperature, follow-up pressure and follow-up pressure time -
1.2-2.0 %, or 0.4-0.6 % with 30 % GF.
Gating:
Any weil-known type of gate can be used. When injecting viahot runner, temperature in the hot runner must be accuratelycontrolled.
Machine shut-down:
Switch off heating. Empty cylinder. When changing to another
thermoplastic material it is advisable to flush through with PE
or PP beforehand.
Cylinder equipment:
• Standard screw
a Non-return valve
63
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 32/73
Cellulose acetate, CA
Structure:
Amorphous
Density:
1.2-1.3 g/cm3
Thermal, optical, mechanical properties:
Tough, resistant to boiling water, difficult to break, good scratchresistance and self-polishing effect, low electrical charging,non-toxic, good surface gloss. The strength of this material
makes it suitable for embedding metal parts (screw driver).
Chemical properties:
resistant to
oils, fats, benzene, petrol
not resistant to
vinegar, acids, alkaline solutions
Material identification:
Does not ignite easily, extinguishes away from flame, smoky
with greenish yellow flame, smells of burnt paper and vinegar.
Cylinder temperature:
Flange 30- 40 °C / MO °C
MH 1 140-160 °C/*150 °CMH 2 160-185 °C/ *170 °C
MH 3 170-200 °C/ *180 °C
MH 4 170-200 °C/ *180 °C
DH 170-200 °C/ *180 °C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100 :1.
Melt temperature:
200-210 °C
Colour change in the melt indicates that melt temperature is too
high. If melt temperature is too low, surface gloss and transpar-
ency deteriorate.
Reduced cylinder temperature:
160°C
Injection pressure:
800-1200 bar
Follow-up pressure and follow-up pressure time:
40-70 % of the injection pressure. Not too high if internal stress
is to be avoided. Relatively long follow-up pressure for thick
walled parts.
Back pressure:
50-100 bar
Injection speed:
Fast injection speed for thin walled parts. Inject slowly for thick
walled parts.
Screw speed:
Average screw speed, corresponding to max. 0.6 m/secstarting speed.
Recommended min. and max. dosing stroke:
1.0-3.5 D dosing stroke can be utilised.
Residual melt cushion:
3-8 mm depending on dosing stroke and screw diameter.
Pre-drying:
3 hours at 70 °C.
64 65
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 33/73
Re-processing:
Up to 20 % regrind can be added, providing it has not beencharred and is properly pre-dried.
Shrinkage:
0.4-0.7 %
0.4 % in direction of flow
0.6- 0.7 % across the direction of flow
Gating:
Pin/tunnel gate. Avoid jetting by spring actuated auxiliary core,otherwise surface defects will occur near the gate.
Machine shut-down:
Switch off heating. Plasticise several times without backpressure and squirt melt out.
Cylinder equipment:
• Standard geometry, in some cases special geometry
a Non-return valve
• Open nozzle
Polyvinyl chloride unplasticised, PVC-U
Structure:
Amorphous
Density:
1.35 g/cm3
Thermal, optical, mechanical properties:
Stiff, hard, transparent to opaque, good bonding properties,certain formulations non-toxic.
Chemical properties:
resistant to
acids, alkaline solutions, oils, fats, petrol
not resistant to
benzene, ketone, ester, stain removers
Material identification:
Does not ignite easily, smoky, burns green, sputters, smells ofhydrochloric acid, self extinguishing.
Cylinder temperature:
Flange 30- 50 °C / *50 °C
MH 1 140-160 °C/*150 °C
MH 2 165-180 °C/*170 °CMH 3 180-210 °C/*190°C
MH 4 180-210 °C/*200°C
DH 180-210 °C/*200°C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100:1.
Melt temperature:
210-220 °C
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 34/73
Reduced cylinder temperature:
120 °C
Injection pressure:
800-1600 bar
Follow-up pressure and follow-up pressure time:
Do not set too high. 40-60 % of injection pressure to suit themoulding and the gate.
Back pressure:
It is very important with PVC to select the right setting, because
the material is heat sensitive. Heat from the friction of the screw,
when properly directed, is better than heat from the cylinder
heater bands. Back pressure up to 300 bar is possible.
Injection speed:
Do not set too high. Make sure that the material has not
sheared. For this reason, stepped injection is advisable.
Screw speed:
Set as low as possible, corresponding to max. speed 0.2 m/secperipheral velocity. With long cooling times and despite slowscrew speed, delayed plasticising can be used to ensure thatdosing finishes just before cooling time expires. High, eventorque is required.
Recommended min. and max. dosing stroke:
1.0-3.5 D dosing stroke can be utilised.
Residual melt cushion:
1-5 mm depending on dosing stroke and screw diameter. Keep
cushion small and make sure axial screw clearance is minimal.
Pre-drying:
1 hour at 70 °C (only necessary if material has not been storedproperly).
Re-processing:
Can be reused providing material has not been charred.
Shrinkage:
0.5-0.7 %
Gating:
Sprue, film and diaphragm gates advisable. The gate must beradiused towards the moulding. Pin gate possible for smallparts.
Machine shut-down:
Switch off heating. Plasticise without back pressure, let the meltstand for 2-3 minutes and then squirt it out slowly. Repeat the
process until cylinder temperature has fallen to 160 °C, thenempty the cylinder.
Cylinder equipment:
• Screw geometry for rigid PVC
B Flighted or unflighted screw tip
• Open nozzle
.
68 69
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 35/73
Polyvinyl chloride plasticised (PVC-P)
Structure:
Amorphous
Density:
1.1-1.4 g/cm3
Thermal, optical, mechanical properties:
The material is flexible, rubbery-elastic, non-toxic.
Chemical properties:
resistant to
acids, alkaline solutions, detergents ,oils, fats
not resistant to
petrol, ester, chlorinated hydrocarbons
Material identification:
Does not ignite easily, smoky, burns green, sputters, smells of
hydrochloric acid with plasticiser.
Cylinder temperature:
Flange 30- 50 °C / *50 °C
MH 1 140-160 °C/*150°C
MH 2 150-180 °C/*16 5 °C
MH 3 160-220 °C/*180 °C
MH 4 160-220 °C/*190 °C
DH 160-220 °C/*200 °C
* These temperature profiles are valid for stroke utilisation of between 35 and 65 %
and for parts with a flow length/wall thickness ratio of between 50:1 and 100 :1.
iS B
70
Melt temperature:
200-220 °C
Reduced cylinder temperature:
120 °C
Injection pressure:
800-1200 bar
Follow-up pressure and follow-up pressure time:
30-50 % of the necessary injection pressure.
Back pressure:
50-100 bar
Injection speed:
Do not inject too fast if good surface quality is required -
(stepped injection, perhaps).
Screw speed:
Set average screw speed; max. equal to 0.5 m/sec peripheral
velocity.
Recommended min. and max. dosing stroke:
1.0-3.5 D dosing stroke can be utilised.
Residual melt cushion:
2-6 mm depending on dosing stroke and screw diameter.
Pre-drying:
1 hour at 70 °C (only if material has not been properly stored).
Re-processing:
Can be reused providing material has not been charred.
Shrinkage:
1-2.5 %
71
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 36/73
Gating:
The gate must be radiused towards the moulding. Pin gatepossible for small parts.
Machine shut-down:
Switch off heating. Plasticise several times without backpressure and squirt melt out.
Cylinder equipment: *
• Standard screw
• Open nozzle
• Non-return valve
72 73
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 37/73
4.2 Distinguishing characteristics of plastics 1
" • . MaterialDistinguishing characteristics __^
Appearance
Fracture
Float test
Burn test
Flame
Smell during burn test
Finger nail scratch test
transparent/opaque
crystal clear
no fracture
stress-whitening/tough
brittle fracture
floats
sinks
highly flammable
slow to ignite
self-extinguishing
continues to burn
smoky
not smoky
drips
does not drip •
luminous yellowbright with blue core
bluish
greenish/yellow
waxy/paraffin
burnt bone
slightly sweet
tar-like
pungent/formaldehyde
like fishike paper and vinegar
like styrene
fruity
like hydrochloric acid
not typical
scratch-proof
not scratch-proof
PE
X
X
X
X
X
X
X
X
X
X
pp
X
X
X
X
X
X
X
X
X
X
X
PS
X
X
X
X
X
X
X
X
X
X
SAN
X
X
X
X
X
X
X
X
X
X
X
ABS
X
X
X
X
X
X
X
X
X
X
POM
X
X
X
X
X
X
X
X
X
X
X
PMMA
X
X
X
X
X
X
X
X
X
X
PA
X
X
X
X
X
X
X
X
X
X
74 75
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 38/73
—;Distinguishing characteristics
Appearance
Fracture
Float test
Burn test
Flame
Smell during burn test
Finger nail scratch test
Material
transparent/opaque
crystal ctear
no fracture
stress-whitening/tough
brittle fracture
floats
sinks
highly flammable
slow to ignite
self-extinguishing
continues to burn
smoky
not smoky
drips
does not drip
uminous yellowbright with blue core
bluish
greenish/yellow
waxy/paraffin
burnt bone
slightly sweet
tar-like
pungent/formaldehyde
ike fishlike paper and vinegar
like styrene
fruity
like hydrochloric acid
not typical
scratch-proof
not scratch-proof
PC
X
X
X
X
X
X
X
X
x
X
CA
X
X
X
X
X
X
X
X
X
PPO
X
X
X
X
X
X
X
X
X
PETP
X
X
X
X
X
X
X
X
X
X
PBTP
X
X
X
X
x
X
X
X
X
X
ABSPC
X
X
X
X
X
X
X
X
X
PVC-U
X
X
X
X
X
X
* X
X
X
X
X
PVC-P
X
X
X
X
X
X
X
X
X
X
Si iSS
76
s ill a ill if isi iii ::.
77
4.2 Distinguishing characteristics of plastics 2
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 39/73
Optimizarea procesului la o
masina de injectie mase plastice
Principii:
1. Cand se optimizeaza parametrii este foarte important sa nu
se modifice mai mult de un parametru odata, pana cand nu se
realizeaza efectul acelui parametru asupra calitatii produsului
Sunt multe schimbari ce pot fi facute asupra parametrilor iar
influenta acestora apare imediat.
2. Optimizarea trebuie sa inceapa intotdeauna cu calitatea
injectiei in minte. Legaturile fundamentale dintre caracteristicile
calitatii si setarea parametrilor , sunt suficient de bine cunoscute.
(vezi diagrama in pagina alaturata). Este important sa realizatio evaluare atenta a caracteristicilor calitatii si ale limitelor acesteia.
Apoi stabilitatea si calitatea procesului trebuie optimizata
pe baza parametrilor si a distributiei curgerii.Numai dupa ce
acestea au fost realizate se poate face optimizarea timpului de ciclu .
3. In sistemul de control NC4 exista o pagina pentru optimizarea
procesului, pagina unde sunt comasati toti parametrii importanti.Toti pasii esentiali pentru optimizare pot fi modificati in aceasta pagina.Afisate in aceasta pagina sunt si toate valorile ACTUALE relevante.
Un sistem integrat de achizitii de date este disponibil pentru a permite
operatorului sa optimizeze profilele de presiune hidraulica sipresiune in cavitate pentru fazele in care efectul asupra calitatii
este semnificativ si decisiv.
Parametrii importanti pentru optimizarea procesului pot fi considerati
urmatorii:
1. Temperatura cilindrului de plastifiere si a topiturii
2. Temperatura matritei
3. Viteza de injectie
4. Volumul de comutare5. Timpul de mentinere in presiune
6. Presiunea de mentinere
7. Timpul de racire
8. Viteza de dozare
9. Contra-presiunea
10. Decompresia (retragerea snecului)
11. Monitorizarea parametrilor
5.1 Corelatia dintre caracteristicile calitatii si parametrii de
proces prezentate ca profil al presiunii in cavitate
80 81
Suprafata
(rugozitate, stralucire, culoare)structura, orientare la suprafata,
cristalinitate
definire contur
formare structura,greutate,deviatiidimensionale
greutate, deviatii dimensionale
contractie , goluri in structurastriatii, orientare
interna
Viteza de injectie
Temperatura
Temperatura matritei
punctul decomutaretemperaturacilindrului
temperaturamatritei
presiunea de mentinere
timpul presiunii de mentinere
temperatura cilindrului
temperatura matritei
Timpul de injectie
Presiunea integrala de injectie
Temperatura topiturii
Temperatura matritei
presiunea max.hidr. sau a cavitati
presiunea integrala in cavitate
temperatura topiturii
temperatura matritei
Faza de Injectie Faza de Faza de Mentinere in presiunecompresie .
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 40/73
1. Temperatura cilindrului de plastifiere si a topiturii
Temperaturile pre-setate ale cilindrului, impreuna cu forta de frecare
indusa de viteza snecului, asigura caldura suficienta pentru a
topi materialul plastic (plastifiere).
Recomandarile de setare pot fi gasite in datele de setare individuale
ale materialelor (vezi Capitolul 4 al carticelei).
Valabil pentru toate materialele:
Temperatura topiturii prea mare:
• Degradare termica
• Diferente de culoare / schimbare de culoare
• Contractie marita / variatii dimensionale
• Prelungirea timpului de racire
• Proprietati mecanice inferioare
Temperatura topiturii prea mica:
• Topitura neomogena
• Tensionare ridicata in piesa injectata
• Presiunea de injectie necesara este ridicata• Liniile de curgere si cele de imbinare sunt clar vizibile
Uzual, temperaturile cilindrului sunt setate in profil crescator
(exceptie: PA). Primele doua zone de incalzire (MH1 si MH2)strebuiesc setate la limita inferioara deoarece acolo este cursa cu
utilizare minima si la limitele superioare pentru cursele intens utilizate.
82
2. Temperatura matritei
Temperaturile matritei asigura curgerea libera a materialului
pana ce cavitatea este complet umpluta.
Recomandari pentru setarea temperaturilor matritei poti fi
gasite in Capitolul 4.3 al acestei carticele.
In principiu:
O temperatura mare a matritei asigura:
• Contractie post-injectie redusa• Orientare redusa, tensionare interna mica
• Necesita presiune scazuta
• Cristalinitate crescuta
Temperatura prea mare a matritei:
• Timp de racire prelungit (2%/1 °C)
• Deviatii dimensionale
Temperatura prea mica a matritei:
• Suprafata mata• Efect de unda
• Linii de curgere / linii de imbinare vizibile clar
• Tensionare crescuta in piesa injectata
O unitate de control al temperaturii de inalta performanta se
poate folosi pentru a mentine temp. constanta in matrita . Temp.
matritei este unul din cei mai importanti parametrii si trebuie mentinut
in limite de toleranta foarte stranse. Pentru piese cu proprietati de
contractie (ex. piese tehnice), este recomandat sa se foloseasca
unitati de control temp. integrate, ale carei valori setate pot fimemorate si monitorizate de catre IBED (ErgoControl).
83
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 41/73
Re. 3 Viteza de injectie
Viteza de injectie influenteaza rata de dispersie a topiturii in
matrita. In principiu, trebuie setata cat de rapid posibil.
In cazul pieselor cu variatii in grosimea peretilor poate fi necesar
setarea unui profil in trepte. In faza start si, respectiv, sfarsit de
umplere poate fi nevoie de un profil ascendent si,respectiv, descendent.
Viteza de injectie prea mare:
• bavura
• defecte de suprafata langa duza
• arsuri la capatul caii de curgere
• necesar de forta de inchidere mare
Viteza de injectie prea mica:
• efect de unda
• piesa umpluta partial
• deformare
• linii de imbinare vizibile
Inainte de toate, monitorizarea presiunii trebuie setata la maximum pentru
a optimiza viteza de injectie. Cand presiunea de injectie limita este atinsa,aceasta este indicata in ecranul de achizitii de date, se datoreaza faptului
ca a fost schimbata viteza de injectie (valorile setate) iar timpul de injectie a
ramas neschimbat.
84
Re. 4 Comutare in functie de volum (punct de comutare)
Comutarea pe presiune de mentinere reprezinta tranzitia de la
reglajul dependent de viteza din timpul injectiei la reglajul dependent
de presiune din timpul fazei de mentinere in presiune .
In general, comutarea trebuie sa aiba loc atunci cand aprox. 95 %
din volumul cavitatii a fost umplut. La piesele cu pereti subtiri poate
fi necesar sa se umple chiar 98 % din volumul cavitatii.
Comutare prea devreme:
• urme specifice de comutare
• cavitate umpluta incomplet
• supturi
• subdimensionare
• urme pe liniile de imbinare
Comutare intarziata:
• bavura
• necesar de forta de inchidere mare
• supradimensionare• probleme la demulare
• tensionare ridicata in piesa injectata
La inceput trebuie selectat un punct de comutare devreme. Gradual
acesta se seteaza intarziat (studiu al umplerii mattritei) pana ce
umplerea volumului este aproape realizata. Aceasta procedura
furnizeaza informatii valoroase cu privire la profilul frontului de curgere
in matrita si descoperirea urmelor de curgere si de imbinare.
85
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 42/73
Re. 5 Timp de mentinere in presiune
Dupa umplerea volumetrica, contractia este stabilizata in timpul
mentinerii in presiune prin racirea cavitatii matritei.
Timpul de mentinere in presiune se seteaza ca durata necesara
topiturii sa se solidifice langa duza.
Timp de mentinere in presiune prea lung:
• timp rezidual insuficient ramas pentru plastifiere
• consum de energie crescut
Timp de mentinere in presiune prea scurt :
• supturi, goluri
• variatii in greutate a pieselor
• subdimensionare
• topitura curege inapoi in cilindru
• fluctuatii ale pernei de material
Pentru stabilirea timpului optim de mentinere in presiune cresteti
continuu valoarea setata pana ce piesele, fara culee, nu mai cresc in
greutate. Concluzie: Determinarea timpului optim de mentinere inpresiune se face prin controlul greutatii.
0 2 4 6 8 1 01 2 1 4 1 6 Timp de mentinere (s)
86
i
Re. 6 Presiunea de mentinere
Presiunea de mentinere este presiunea hidraulica activa pe
durata timpului de mentinere si are menirea de a combate
formarea urmelor de tip suptura.
De regula, presiunea de mentinereeste de 30-50 % din
presiunea necesara de injectie.
Presiunea de mentinere prea mare:
• bavura
• necesar de forta de inchidere mare
• tensionare ridicata in piesa injectata
• supradimensionare
• probleme la demulare
• urme de ejector
Presiunea de mentinere prea mica:
• supturi, goluri
• subdimensionare
• contractie mare de volum• fluctuatii mari in greutate
Re. 7 Timp de racire
Timpul de racire reprezinta perioada finala de racire a piesei
in cavitate pana ce se atinge stabilitatea dimensionala suficienta
pentru demulare. Caracteristicile urmarite aici sunt dimensiunile si
deformarea pieselor .
Timp de racire prea lung:• creste timpul de ciclu
Timp de racire prea scurt:
• deformare
• urme de aruncator
• creste contractia post-injectie
Verificati si Capitolul 5.2 - Calculul timpului de racire.
87
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 43/73
Re. 8 Viteza de rotatie a snecului
Viteza snecului este responsabila pentru plastifiere, adica pentru
pregatirea termica, mecanica si omogenizare a materiei prime.
Limita superioara setata a vitezei snecului este forta periferica
maxima admisa de snec pentru diferite tipuri de material. Timpul de
dozare rezultat, nu trebuie sa fie cu mult mai scurt decat timpul de
racire, asta pentru a se realiza o plastifiere cat mai delicat posibil.
.
Viteza de rotatie prea mica:
• fluctuatii ale timpului de ciclu (in cazul t doz> t r a c i r e )
Viteza de rotatie prea mare:
• degradare termica si mecanica a materialului
• diferente mari ale temperaturii topiturii dealungul lungimii snecului
• creste uzura snecului si a valvei non-retur
Re. 9 Contra-presiunea
Contra-presiunea reprezinta presiunea din fata toprilei, impotriva careiasnecul trebuie sa lucreze pe parcursul dozarii.
Contra-presiune prea mare:
• degaradarea materialului datorita frictiunii excesive
• capacitate redusa de plastifiere, timp lung de dozare
Contra-presiune prea mica:
• neomogenitate a topiturii
(fluctuatii mecanice si termice)
• granule de material netopit
• bule de aer
88
Re. 10 Decompresiea (retragerea snecului)
Decompresia serveste la reducerea presiunii topiturii in spatiul
din fata snecului, dupa dozare. Trebuie sa fie aprox. 4 % din
volumul de dozare dar, ca valoare, sa nu fie mai putin de 10 %
din diametrul snecului. Pentru mai multe detalii vezi Capitolul
4.1 "Indrumar de procesare pentru cele mai importante
materiale plastice".
Decompresie prea mare:
• bule de aer in jurul punctului de injectie
Decompresie prea mica:
• scurgeri de material pe la duza sau duze calde
Re. 11 Parametrii de monitorizare
Parametrii pentru monitorizare se regleaza numai dupa ce toti
parametii importanti au fost optimizati si nivelul de calitate este
constant mentinut in limitele de toleranta.
a) Monitorizarea injectiei (limitarea presiunii de injectie)
In timpul fazei de umplere exista o dependenta intre pres.hidr.
si viteza de injectie setata, dependenta co relata cu rezistenta
la curgere a topiturii. In situatii normale acest profil de presiune
este repetitiv. Aceasta presiune poate creste involuntar numai
daca o defectiune are loc in timpul procesului sau daca unul
dintre parametrii fluctueaza.
Din acest motiv, presiunea de injectie limita este setata aprox.
10-15 % peste presiunea maxima de umplere. Daca aceasta
este depasita, apare un mesaj de eroare si masina se opreste
fara sa afecteze in nici un fel matrita sau duzele calde.
b) Monitorizarea injectiei
Deasemeni, in timpul fazei de umplere apare si un timp actual
de injectie dependent de viteza de injectie setata. Devierile
evidente de la acest timp inseamna o eroare in proces. Limita
timpului de injectie trebuie setata cu aprox. 10-15 % peste
timpul actual de injectie.
89
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 44/73
Typical pressure profile during mould filling
Pressure (p)
Injection pressure monitoring
Change-over
Time (t)
90
5.2 Cooling time
Cooling time is calculated using the following formula:
cooling time
wall thickness
For an initial estimate of cooling time with the aid of a diagram,the cooling time equations can be grouped according to thedifferent plastics. These groups are determined by taking asa basis the average temperatures for melt, cavity wall and de-moulding. (Compare with Chapter 4.1 "Processing guidelinesfor plastics".)
Changes in melt temperature have no appreciable effect withwall thicknesses up to 4 mm (< 1 sec).
Changes in cavity wall temperature, on the other hand, must
be taken into consideration.
91
with
effective thermal diffusivity
melt temperature
mean demoulding temperature
average cavity wall temperature (average valuederived from minimum and maximum cavitywall temperature over the course of an injectionmoulding cycle)
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 45/73
s = wail thickness [mm]
tcoo! = cooling time [sees]
Notes on producing the cooling time diagram
Control equations:
PC: toool = 2 .17x s
PA6, PBTP, LDPE tcool = 2.64 x s
ABS, PS, SAN, PA 6.6:t0OOl = 2.82 x s2
HDPE, PMMA toool = 3.00 x s2
PP tcool = 3.67 x s2
POM toool = 4.18xs2
The curve points for the different groups of plastics are given in
the following table. These curve points are also entered on the
two subsequent diagrams, where s = 1 to 2.5 mm and s = 2.5
to 4 mm.
Wall thickness
Change in cavity walltemperature by [°C]
Change in cooling timeby [sees.]
s = 2 mm
+10
+5
+5
+2
-5
-1.2
-10
-2
s = 4 mm
+10
+20
+5
+7.5
-5
-5
-10
-9
Influence of cavity wall temperature on cooling time with
wall thicknesses of 2 and 4 mm
92
5.2 Cooling time as a function of wall thickness (1 to 2.5 mm)
93
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 46/73
5.2 Cooling time as a function of wall thickness (2.5 to 4 mm)
The correct evaluation and selection
of process parameters for quality
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 47/73
p p q y
assurance in injection moulding
Ever shorter innovation cycles, the growing complexity of pro-ducts and increasingly stiff competition all call for economicinjection moulding production. Quality assurance and the abilityto reduce scrap to a minimum are becoming increasinglyimportant.
Only those processors who can accurately predict the output of
perfect mouldings will have costs under control, be able to meet
delivery deadlines and be acknowledged as reliable partners.
When it comes to quality control, the control and analysis
features on modern injection moulding machines are highlyefficient. The operator can have complete control over theproduction process, carry out long-term statistical evaluationsor anticipate trends.
Of course, to make best use of these resources the setterneeds to know which machine and process parameters influ-ence the quality of a moulding - and, most importantly, to whatextent.
Practice shows, however, that the significance of these para-
meters varies from application to application and is determinedby the demands of the particular moulding.
The following report and data tables are the result of extensivelong-term testing and the evaluation of a large number of indi-vidual cases. They assist in the selection and evaluation of thecorrect parameters and in defining the required tolerances forquality control on the machine.
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 48/73
The table opposite (Fig. 6.1) shows the 5 most significant qualitycharacteristics and their relative importance for the productionof different product groups. For technical precision parts, dimen-sional stability is clearly of greatest importance, while for opticalparts, for example, surface quality and melt homogeneity arecrucial factors.
Of course, there are still a good many other quality characteris-tics -the "inherent properties", for example, like molecularweight, orientation on the skin and the core, dispersion of fillers
and reinforcing materials etc. These selected criteria, however,represent essential performance properties which can also besubjected to direct and mainly non-destructive testing.
At this point, of course, there is still no indication of whichparameters are required for controlling the quality of themouldings.
Fig. 6.1
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 49/73
Fig. 6.2 shows important process parameters and their relationto the various quality characteristics. The correlation between
machine or setting parameters and the characteristics of the
mouldings is sometimes very complex. In almost all instances,
there are several setting parameters relating to a single quality
characteristic, which is why more than one parameter needs tobe controlled.
Fig. 6.2
ft ill • • • • • • • Si 81 Si
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 50/73
Fig. 6.3 illustrates the connection between quality characteristicsand process parameters with the aid of the (integral) cavitypressure profile. It shows clearly how the majority of qualitycharacteristics are influenced during the follow-up pressurephase. Consequently, the cavity pressure profile must fall withinspecified tolerance limits during this phase. The diagram alsoshows those setting and monitoring parameters relevant toquality. The cavity pressure profile, mould temperature and melttemperature are the most significant and informative factorshere.
In 50 % of all cases cavity pressure monitoring proves very use-ful from a processing point of view, but it is only realistic in 3 %of these, since the cost in terms of machine, mould and per-sonnel is relatively high. Cavity pressure monitoring is appliedto around 20 % of mouldings, predominantly technical precisionand functional components, optical products and automotiveparts.
The use of cavity pressure enables the setting parameters forthe machine and peripheral equipment to be largely indirectly
monitored, because the smallest changes or disruptions - tomould or melt temperature, to the function of the non-returnvalve, to the change-over point to follow-up pressure or to thebatch of material - all have an effect on cavity pressure. Veryoften it is possible to monitor several settings via one singleparameter and also to document them in accordance withDIN ISO 9000.
The time profile for cavity pressure can be divided into threephases. These are the injection, compression and follow-up
pressure phases.
In the injection phase cavity pressure is determined mainlyby flow resistance, viscosity of the moulding compound andinjection speed. During the compression phase the melt iscompressed up to the so-called change-over point, which theninitiates the follow-up pressure phase. In this latter phase, thepressure rises in the mould initially, because the mould is nowcompletely filled. As the melt cools down, so the pressure fallsslowly. In conjunction with the cooling process, this phase isdecisive in terms of shrinkage and internal orientation, and alsofor crystallisation in partially crystalline materials.
Fig. 6.3
• • • • • • • • • •
01
Si Si Si Si it Hi i ii f ! Si • • •
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 51/73
Pressure transducers have been used in the mould for morethan 20 years and at the moment are probably the simplestform of total control, without directly including the characteris-tics of the moulded part. Care should be taken to ensure thatthe cavity pressure sensor is located at a quality-determiningpoint - as close to the sprue as possible - approx. 30-40 % ofthe way along the flow path. A pressure sensor can also beintegrated in the hydraulic circuit (in or on the hydraulic injectioncylinder).
Fig. 6.4 shows a characteristic profile of hydraulic and cavitypressure. If, for example, the hydraulic pressure (upper curve)rises during the injection phase as a result of a lower mouldtemperature (caused by increased flow resistance during injec-tion), then cavity pressure falls - (with hydraulic pressure remain-ing constant during the follow-up pressure phase) - due to thereduced pressure transfer performance of the low-viscositymelt. The result is a lower integral cavity pressure. If it were onlythe hydraulic pressure being monitored, no indication would begiven as to the quality of the mouldings. The rise in hydraulicpressure during the injection phase would indeed be noticeable,but the effects of this increase once change-over has occurredcould not be monitored, since hydraulic pressure during thisphase is regulated at a constant level. By selecting integralcavity pressure with suitable integral limits, however, the quality-related phases can be accurately monitored.
The most important factors for technical precision parts aredimensional stability, melt homogeneity and low warpage, whichmeans that the parameters for monitoring must be selectedfrom relevant phases in the process. Dimensional stability and
warpage are mainly influenced during the follow-up pressurephase, which is why integral cavity pressure is particularlysuitable.
Changes in melt homogeneity occur during the dosing phasedue to fluctuations in screw speed and/or back pressure, andthese can be diagnosed by monitoring the above-mentionedparameters. Where particularly sensitive materials are con-cerned, the dosing operation can also be monitored via thescrew load.
Fig. 6.4
104 105
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 52/73
Selection criteria
On the assumption that the machine has been optimally setprior to the start of the production cycle, the following selectioncriteria have emerged in the course of daily practice for the8 most significant process parameters which need to be keptconstant.
In general, cycle time says little about component quality,apart from when processing thermally sensitive materials insemi-automatic operation.
Consistent injection time is important for short injection timesand for parts with stringent surface requirements.
Ideally, a constant dosing time should be observed, particularlywhen processing (plasticising) material blends (LDPE-HDPE),blends for automotive parts and regrind. It is also importantwhere irregularities occur during plasticising as a result of thematerial (PA-PMMA), and when colouring using pigment pasteor masterbatch.
A decreasing melt cushion when processing with filled materials
indicates wear on the non-return valve. Fluctuations are often asign of inhomogenous melt. Where there is only very slight fluc-tuation in the melt cushion and the non-return valve is function-ing correctly, the dimensions of the moulded part will thenremain constant. For products with relatively dense wall thick-nesses requiring a correspondingly long, high and uniformfollow-up pressure profile, integral cavity pressure is the firstchoice.
Maximum cavity pressure is informative for products withsmall wall thicknesses and a short follow-up pressure time orhigh injection pressure.
Melt temperature is important for thermally sensitive materials.This is equally so for materials with a narrow processing rangeor for materials whose properties change at the slightest varia-tion in temperature.
Finally, accurate mould temperatures are required, particularlywhen processing any of the engineering materials (PC, PA,POM, PMMA ...), for example, for the production of opticallenses in PMMA or gear wheels in POM.
In order to be able to put these findings to practical use, it isnecessary first of all to evaluate the relative importance of the
individual process parameters for the different product groups
and to establish the tolerances.
Fig. 6.5 summarises the selection criteria and also evaluates theextent of the influence of the individual process parameters onthe quality of the various product groups. The quality character-istic here is the percentage weight fluctuation which can beachieved on the mouldings. The data shown is a recommen-dation as to the level of quality to which the mouldings in thedifferent product groups can be manufactured.
" 1 " denotes a parameter with the largest influence on quality,while "8" denotes minimum influence. These should not, how-ever, be seen as absolute values for comparison between thevarious product groups, but as being based on a specificcharacteristic value for each product group.
Fig. 6.6 goes one step further by showing the permissible per-centage deviations (+/- tolerances) for each of the parameters.The variation in values is as a result of varying processing con-
ditions for the respective products. For example, the mouldtemperature for technical functional parts is around 80 °C, whilefor high speed precision parts it is only 25 °C. Thus, when con-verted to absolute values, the permissible deviations are almostidentical.
The percentage values also utilise the evaluation capacity ofmodern injection moulding machines. Modern control systemssuch as NC4, enable deviations to be represented in percent-ages (see fig. 6.10). The recommended values can be directly
compared with the current Actual values. If the deviations fallwithin the tolerance limits, the component quality is acceptable.
106 107
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 53/73
Fig. 6.5 Fig. 6.6
108 109
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 54/73
Even if the quality depends essentially on the constancy of the8 previously mentioned parameters - and even if, in general,3-5 of these would suffice - it is still necessary for the lessimportant parameters to adhere to specific tolerances (fig. 6.7).
110
Fig. 6.7
111
± 1.0 % ± 2.0 % ±5.0 %
±1.0% ± 2.0 % ± 5.0 %
±1.0% ± 2.0 % ± 3.0 %±0. 1% ±0.2% ±0.3%
±1.0% ±1.5% ±2.0%
± 2.0 % ± 3.0 % ±4.0 %
± 0.1 % + 0.2 % ±0.3 %
+ 2.0 % ± 3.0 % ±4.0 %
±2.0 % ± 3.0 % ±4.0 %
±1.0% ±2.0% ±3.0%
±1.0% ±2.0% ±3.0%
± 1.0 % ±2.0 % ± 3.0 %
±3.0 % ±4.0 % ±5.0 %
±10.0% ±15.0% ±20.0%
± 2.0 % ± 4.0 % ± 6.0 %
± 2.0 % ± 3.0 % ± 4.0 %±5.0% ±8.0% ±10.0%
±1.0% ± 2.0 % ± 3.0 %
± 3.0 % ± 6.0 % ± 8.0 %
± 2.0 % ± 3.0 % ± 4.0 %
± 2.0 % ± 4.0 % 1 8.0 %
Piasticising time
Injection time
Cycle timeDosing stop
Change-over point for follow-up pressure
Residual melt cushion
Mould open - stop
Mould temperature
Flange temperature
Cylinder temperature
Melt temperature
Hot runner temperature
Hydraulic oil temperature
Room temperature
Injection pressure
Follow-up pressureBack pressure
Max. cavity pressure
Intecj-al cavity pressure
Clamping; force
M ou l d f i l l t ; i ii i 11 • • • ! 11 • i . i i i 11 ' . : : i n m ou l d
• • • • •
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 55/73
Quality control on the machine
When activating quality control it is important to establishwhether the process is normally distributed i.e. without influ-ences inherent in the system. Quality control is only possiblewith normal distribution. A mean value and independent upperand lower tolerance limits are then specified for the quality-determining process parameters.
Fig. 6.8 shows a screen page from the new NC4 control systemwhich was introduced with the ERGOtech machine range.
Using this page the machine setter can select from a total of25 available parameters those which are most important for aparticular moulding. The Process Statistics page can displayup to 20 parameters, and the selected parameters can then becontrolled either continuously (CPC) or statistically (SPC).
Fig. 6.8
112 113
38 38 fit 8 S • • • • • • •
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 56/73
Fig. 6.9 shows the maximum injection pressure in an unstableprocess and how dosing time fluctuations depend on and influ-ence the residual melt cushion. In a stable process the statisti-cal evaluation reveals only minor fluctuations for all relevantprocess parameters.
With the aid of just 2 statistics pages the machine setter caneasily monitor process constancy. "Process Statistics 1" indi-cates the ACTUAL values for the last 16 cycles. The penultimateline also shows the mean value, and theiast line the range ofmeasured values. The control system provides not only tabular
displays, but also a wide range of control features in graphform.
Fig. 6.9
At the touch of a key the system not only provides graphicevaluation, but also percentage deviation from the mean value,and the statistical distribution - (black bars to the right of thescreen) - over the last 100 cycles for each selected processparameter (injection time, dosing time, hydraulic pressure, meltcushion, cycle time ...). A thermal printer integrated in the opera-tor terminal is also available as optional equipment for printingout all screen pages. It enables the relevant quality data andproof of quality to be documented directly at the machine.
Fig. 6.10
114 115
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 57/73
Fig. 6.11 looks at tolerance settings for the selected processparameters, (parameters selected are indicated by a blacksquare in the column headed "permissible deviation"). In addi-tion to the upper and lower tolerances, the permissible numberof deviations per 1000 parts is also indicated. If a variableexceeds its set tolerances, by using selected parameters rejectindication can be given and this is then shown in the deviationcounter.
In such cases, providing tolerance deviation is switched on,mouldings can be automatically sorted by means of mechanical
quality flaps or a robot fitted with a reject signal. Only the mostadvanced machine control systems can offer such a compre-hensive range of possibilities for keeping processing parametersconstant over long periods of production. Such systems canindicate the effects of any emerging influences by deviationsin the process parameters and enable statistical evaluation.This represents the first step towards our aim of "Total QualityControl".
Fig. 6.11
116 117
Recognition and elimination of
surface defects in the injection
moulding process
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 58/73
g p
Injection moulding is an extremely complex process, in whichthe quality of the moulded parts is determined by a variety of
factors which differ from one application to the next.
Flaws in quality can be caused by machine or processing param-eters being wrongly set and by incorrect mould or moulded partdesign.
The causes of potential faults, unfortunately, are as diverse asthe injection moulding process itself. Starting with visual defectssuch as streaks, sink marks or gloss variation, through to inad-
equate mechanical properties - entrapped air, voids or unmeltedmaterial in the moulding, for example - and ending with all man-ner of dimensional deviations (see table on page 120).
This poses the question of what practical steps can be taken toeliminate the wide variety of faults.
In order to narrow down the causes, the fault must be locatedand accurately defined i.e. what it looks like, where, when andhow often it occurs. To do this you need to be familiar with themachines and process parameters listed in the tables on pages120-123 and be able to make a careful evaluation of their poten-tial influence.
This will enable you to see at what stage in the injection mould-ing process a fault can occur. The cause of surface defects,for instance, is to be found predominantly in the plasticisingand injection phase. Dimensional deviations and inadequatemechanical properties, on the other hand, occur mainly duringplasticising and injection and in the follow-up pressure phase.
The design of the mould and moulded part also has a consider-
able effect on all types of fault, with clamp force, mould opening
and demoulding playing a secondary role.
118 119
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 59/73
At what stage do surface defects or mechanical anddimensional defects occur on the injection moulded part?
Flaws in appearance
Charred streaks
Moisture streaks
Coloured streaksGlass fibre streaks
Sink marks
Gloss, variations in gloss
Unmelted material pellets in the moulding (non-homogeneity)
Weld line, flow lines
Jetting
Diesel effect, charring
Visible ejector imprints
Ripple effectDark spots
Matt spots near the gate
Delamination of surface layer
Cold slug, cold flow marks
Grey/black clouds
Dimensional deviations
Mouldings not completely filled
Moulding overpacked (flash formation)
Deformation on demouldingComponent warpage
Dimensional variations on the moulding
Inadequate mechanical properties
Stress cracking on the moulding, stress whitening
Entrapped air, blistering
Voids
Charred melt
Unmelted material pellets in the moulding (non-homogeneity)
Process phase
P i a s t i c i s i n g
X
XX
X
X
X
X
X
X
X
X
X
X
XX
X
X
X
X
X
I n j e c t i o n
X
XX
X
X
X
X
X
X
X
X
X
XX
X
X
X
F o l l o w - u p
p r e s s u r e
X
X
X
X
X
X
XX
X
X
X
C l a m p f o r c e
X
O p e n m o u l d
X
D e m o u i i n g
X
XX
M o u l d
X
X
X
X
X
X
X
X
X
X
X
120 121
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 60/73
122 123
Correct procedure for the elimination of moulding defects
Defect:
Moisture streaks
Charred streaks
Glass fibre streaks
Coloured streaks
Grey clouds
Sink marks
Voids
Blistering, entrapped air
Charring, diesei effect(surface)
Flow line, weld line
Ripple effect
Gloss, variation in gloss(polished surface)
Gloss, variation in gloss(textured surface)
Jetting
Unmelted material particles,poor pigment dispersion
Delamination
Dark spots on the moulding
Cold slug
Moulding not filled
Moulding overpacked
Moulding too small
Moulding too large
Moulding too brittle
Procedure:
Change only one parameter at atime in the suggested sequence
M e l t t e m p e r a t u r e
M o u l d t e m p e r a t u r e
G a t e c r o s s s e c t i o n
•
F o
l l o w - u p
p r e s s u r e
B a c k p r e s s u r e
I n
j e c t i o n s p e e d
S t e p p e d i n j e c t i o n s p e e d
S c r e w
s p e e d
F o l l o w - u p
p r e s s u r e t i m e
C h a n g e - o v e r p o i n t f o r
f o
l l o w - u p
p r e s s u r e
V e n t i n g
M
o i s t u r e i n m a t e r i a l
S
c r e w r
e t r a c t i o n
C
l a m p f o r c eIncrease parameter value
Decrease parameter value
Example of clamp force calculation
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 61/73
124 125
Example of clamp force calculation1. Establish the projected area of the moulded part
(projected moulding area x number of impressions)
2. Material: flow characteristics and melt flow index
3. Establish required cavity pressure
Wall thickness
Flow lengthFlow length/wall thickness ratio
4. The required clamp force is then calculated from:
required cavity pressure x proj. moulding area
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 62/73
Example of calculation for a flowerpot
Article description:
Material:
Melt flow index:
Proj. moulding area:
Flow length:
Average wall thickness:
Flow length/wall thickness:
Flowerpot
PP
MFI 35 230°C/5 [g/10 min]
162 cm2
150 mm
0.55 mm
275 : 1
126
Calculation process:
Flow length/wall thickness ratio:
Effective cavity pressure:
(see diagram on page 133)
Mould design:
150 : 0.55 = 275 : 1
600 bar
single impression
Proj. moulding area x effective cavity pressure =
162 cm2 x 600 = 972000 N = 972 kN
Result:
Clamp unit
Clamp force reserve
ERGOtech 110
approx. 13 %
127
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 63/73
Example of calculation for a 10 litre bucket Calculation process:Effective cavity pressure required:
(see diagram on page 133) 570 bar
Proj. moulding area x cavity pressure = clamp force
572 cm2 x 570 bar = 3260400 N
= 3260 kN
selected: ERGOtech 330
Clamp force reserve 1 %
Flow length: 380 mm
Average wall thickness: 1.10 mm
Flow length/wall thickness ratio: 340 : 1
Proj. moulding area: 572 cm2
Available cavity pressure
ref. ERGOtech 330: 577 bar
128 129
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 64/73
Effective pressure location dependent on position of gate andcomponent geometry
B eaker :
gate
effectivepressurelocation close to gate
Plate:
gate
effective pressure location at halfway point along flow path
The difference in viscosity in the individual materials and the
varying injection speeds cause a pressure gradient to develop
during injection. When calculating the parts, calculate the pre-
vailing pressure at the point where the effective pressure ap-
plies.
Wall thickness zones requiring use of accumulator injection andfollow-up pressure
2.72.6
2.52.42.32.22.12.01.91.81.71.61.51.4
1.31.21.11.00.90.80.70.60.50.40.30.2
0.1
Follow-up pressure higher than injection pressure
Injection and follow-up pressure the same
Check need foraccumulator
Injection pressurehigher thanfollow-up pressure
130 131
Accumulatorrequired
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 65/73
Product group
1 Packaging parts
2 Tech. precision partsmulti-point connectors
3 Tech. functional parts
4 Optical parts
5 High speed precision parts
6 Medical parts
7 Automotive parts
8 Tech. packaging parts
9 Office supplies
10 Gen. purpose functional parts
11 Rigid PVC parts
12 Toys
Article
Yoghurt cartonsContainersAerosol capsBuckets
Plugs, sockets,PBTP
Gear wheels,program control cylinders
LensesRear light fittings
Disposable razorsSlide framesCable ties
Disposable syringesPipettes
Radiator grillsInstrument panelsBumpers
Music cassettes
Video cassettesCD packaging
RulersSet squares
HousingsCoversVacuum cleaner housingsStorage cases
Fittings
Articles with limitedrequirements for surface
quality and dimensions
Material
PSPEPPPP
PA, PC
POM, PAPBTP
PMMA
PSPSPA
PEPP
PPABSblends
PS
ABSPS
PS, SANCAB
PPABSPPPS
PVC
PEPP
PS
Cavity pressure (bar)
600- 800500- 700400- 600500- 700
500- 700600- 800
700- 800700- 800
600- 800500- 700
400- 500400- 500800-1200
400- 500500- 600
400- 500400- 500400- 500
350- 450
300- 400400- 500
400- 500
400- 500300- 400400- 500300- 400
400- 500
250- 350
132 133
Cavity pressures required for articles from different product groups
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 66/73
Effective cavity pressure for component group dependent oncomponent wall thickness and flow length/wall thickness ratio
134 135
Operating instructions for
ERGOtech NC4 control system
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 67/73
Operating instructions for ERGOtech NC4 control systemThe performance of the ERGOtech NC4 control system is basedessentially on the use of microprocessor controls. To ensurereliability of operation all disruptive influences must be kept wellaway from the controls. By screening electrical equipment andlaying screened cable, the manufacturer has suppressed anydisturbances which might possibly be generated by the machineitself.
Attention!
Do not use suppressor adapters with LEDs (24 V test lamps) onany proportional valves between the solenoid plugs and plug-inboards. The diodes in the adapters cause the valves to mal-function. The machine operator must take appropriate steps toavoid any potential external disturbance e.g. by screening peri-pheral units (attenuators). Please refer to instructions in theoperating manual.
136 137
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 68/73
T h e I B E D co n t r o l p a n e l 1 LCD display2 Function group keys
3 Numeric keypad
4 Manual function keys
5 Mode selection switches (IMM)
6 Q key
7 EMERGENCY STOP
8 Integral printer
9 Floppy drive, floppy disk box10 Pump, cylinder heating, mould heating ON - OFF
11 Start button
12 Keys for robot
13 Special function keys
14 Cursor keys
15 Function group keys
16 Softkeys for menu selection
138 139
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 69/73
Page selection
The screen unit comprises 3 sections:
• The LCD display
• Softkeys to call up pages within a function group
• Function group keys
When a function group key is pressed, the pages relating to the
function group are listed for selection.
The individual pages within the function group can then be
called up using the softkeys.
Example:
When the function group for "Mould" is selected, the page formould parameters is called up. By pressing the relevant soft-
keys, other mould-related pages can now be selected.
LCD-display
Functiongroup keys
Functiongroupkeys
140
Overview of page selection using function group keys:
141
Softkeysfor menuselection
- 00 Main menu - Machine
- Mould - Cores- Hydr. ejector - Cores IN- Pneu. valves - Cores OUT- Speed profile
- Process optimisation - Dosing profiles- Inject ion profi le - Follow-up pressure profile- Injection unit - Data acquisition- Intrusion
- Cylinder temperature - Hot runner- Temp, control unit - Mould heating
- Program pre-select - Switch-on program- Start-up program - Purge program- Switch-off matrix - Mould catalogue- Prog, inputs - Prog, outputs
- Process statistics 1 - Process statistics 2- Process control - Statistics configuration- Product counter- SPC configuration - SPC control chart
- Quality monitoring - CAP job- CAP - next job ' - CAP shift- CAP reject - CAP statistics- Fast mould clamping system
- Handling - Robot program- Robot diagnosis
- Page layout - Set-up IBED- Gen. data 1 - Gen. data 2- Print - Password
- Service - Amendment report- Function check - Putting into operation- Control parameters - Bit control
- Alarms
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 70/73
Cursor keys and numeric keypad
Input keys
Cursor keys,nextline/columnto...
left
down
Input variablelarger
Input variable• smaller
Enter/ acceptancekey
Clear key
Home position
Having selected a page, the cursor can be used to select any ofthe parameters, and set values can be entered via the numerickeypad.
The specified value is then stored in the IBED memory by pres-sing the E (Enter) key. When a set value is being entered, thetop section of the screen shows the permitted minimum andmaximum for that particular field. It also shows the value pre-viously stored for that field.
To speed the setting process, the arrow keys on the numerickeypad can be used to increase or decrease the selected value.
The cursor keys have the normal repeat function i.e. cursormovement on screen is accelerated when the cursor key is helddown.
The arrow key in the centre of the cursor pad moves the cursorback to home position.
142
Mode selection switches
Operating modes can be set via the Mode Selection switches,
as follows:1 Set up
2 Manual
3 Semi-automatic
4 Automatic
5 Quality keyThe Quality key triggers a quality log after a pre-selected
number of shots.The number of shots can be specified on page
"60 Quality monitoring".
Operating mode for robot:
6 Step: stepping mode for each axis
7 Reference: all axes move to base position
8 Set stop: the robot remains in the waiting position after
the next completed command
9 I/O: robot ON/OFF
143
Up
right
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 71/73
Manual function keys
1 Open - close mould
2 Hydr. ejector forward - back
3 Move cores in - out
4 Open - close automatic safety guard
5 Mould height larger - smaller
6 Nozzle forward-back
7 Injection, hydr. screw retraction
8 Dosing
The manual function (symbol) keys are used for set-up and
manual operation of individual machine functions.
Manual function keys
9 Printer - hardcopy
10 Reference
11 Switch to upper/lower case with text input forHelp functions
12 Switch to alphabetic text input
13 Pneumatic valves 1-4
14 F1-F16 for special functions
The 'F' keys are reserved for special functions. The 'ABC...' keyswitches the manual and 'F' keys over to ASCII characters. The'Shift' key switches between upper and lower case.
These functions are only active on pages used for text input
(e.g. Gen. data, Mould catalogue ...)
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 72/73
Emergency Stop, mould heating, cylinder heating and pump ON/OFF
1 EMERGENCY STOP
2 Cylinder heating ON-OFF
3 Mould heating
4 Pump ON-OFF
5 Start button
6 Integral printer
7 Floppy drive, floppy disk box
146
When the Emergency Stop button is pressed the machine shuts
down immediately. This includes
• pump motor- Off .
• cylinder heating - Off
• mould heating - Off
Each of the following functions is switched on by pressing the
green keys:
i pump
• cylinder heating
i mould heating
When the corresponding red buttons are pressed these
functions are switched off.
Start button:
When the Start button is pressed in "semi-automatic" and
"automatic" modes, this initiates the automatic machine cycle.
In "semi-automatic" mode the machine runs for only one cycle.
The Start button must be pressed to initiate each cycle.
In "automatic" mode the machine runs continuously.
Attention!
Start-up can only occur when the following conditions have
been met:
• mould fully open
• hydr. ejector back
• cores moved out
• dosing stop reached
147
MANNESMANNDEMAG
7/23/2019 PocketBook Demag ENG
http://slidepdf.com/reader/full/pocketbook-demag-eng 73/73
Injection Moulding
Pocketbook