Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
G3 Terminal Vancouver Port Metro Vancouver Project Permit Application
APPENDIX XFire Risk and Dust Explosion Assessments
AP
PEN
DIX
W
FIRE AND DUST ASSESSMENT
As part of the building code review, G3 has prepared the following documents:
Fire Protection Matrix as a summary of the requirements for the relevant structures and areas.
Fire Protection System Description
Dust Hazard Analysis
The documents provided are in their draft format, and will be revised with feedback from City of North
Vancouver emergency response crews, as well as feedback from the Port of Metro Vancouver.
Fire Protection Matrix
Rail Receiving Tunnel ● ●Rail Receiving Building ● ●Transfer Tower ●Scale Tower ● ● ● ●Storage Silo Annexes ● ●Cleaning Building ● ● ● ●Pelleting and Pelleted Product Loadout ● ● ●Ship Loading Towers ● ● ●Administration Building ● ● ● ●Maintenance Building ● ●PDC's & MCC's ● ●Control Room ● ●Server Room(s) ● ●
Dust Filters, Cleaning Building ● ● ● ●Dust Filters, Rail Receiving ● ●Pellet Cooler ● ●Pellet Cyclone ● ●Bucket Elevators ●Duct work, Pelleting ●Duct work, Dust Collection NA NA NA NA NA NA NA NA NA NA NA NA NA
Building Explosion Ven
ting
Chem
ical Explosion Isolation
Manual activated
water deluge
system
Manual Valves from Fire Pumps in
the Cleaning Building to M
anual
Deluge System
Manual Valves from Dry Pipe from
FDC's
Non‐Sprinkled
International Shore Connection
Wet Sprinker System
Dry Standpipe w/ FD
C
Dry, Pre‐Action Sprinkler System
Heat Detection and Alarm
Smoke Detection and Alarm
Passive, M
echanical Explosion
Isolation
Westgate Export Grain Terminal TEI Project No.20014657 FPSD‐1 F.P. System Desc./A/Issued for Review
Fire Protection System Description for G3 Terminal Vancouver
Vancouver, BC, G3 Limited Partnership
1. Project Summary
G3 Terminal Vancouver is undertaking a major project with T. E. Ibberson Company/Kiewit as the
design and construction firm to build a state of the art rail receiving and export terminal grain elevator
facility at the Vancouver port. The state of the art design is very similar to the facility constructed in
Longview, Washington in 2013 by Bunge and EGT. Since the 1980’s, the standards of the industry have
moved towards minimization of bucket elevators, implementation of inclined belt conveyors and
enclosed conveyors where appropriate and/or feasible. Fire systems, alarm systems, and hazard
monitoring systems on the site will comply with OSHA and NFPA grain handling standards. The
Longview design has been proven for more than 2 years with successful operation. The facility will
receive all grain products by rail and send them out by ship, but will ship out pelleted dust materials and
grain by‐products via trucks to local markets. There is a rail receiving pit as well as tunnels for trucks and
personnel vehicles, but the number of these items is minimized to the maximum extent possible. The
number of operations personnel required is minimized due to extended automation of the facility; only
10‐12 operators will be required for performing inspections, maintenance, adjustments, and operations.
This is an important factor in regards to personnel protection from fire and explosion hazards associated
with older manually operated grain receiving, storage, and shipping facilities. The design for safety
approach incorporates PLC operation which will have extensive hazard monitoring features and
operations (including bearing temperature monitoring, equipment alignment detection, plug switches,
etc.).
2. Legislation, Standards, and Guidance
2.1. Legislation and Standards
2.1.1. CSA ‐ Canadian Standards Association
2.1.2. CSA A23.3 – Design of Concrete Structures
2.1.3. CSA S16 – Design of Steel Structures
2.1.4. CSA 22.1 – Canadian Electrical Code 2012
2.1.5. CCOHS Canadian Centre for Occupational Health and Safety
2.1.6. NFC – 2010 National Fire Code of Canada
2.1.7. 2012 BC Fire Code
2.1.8. BC Electrical code
2.1.9. UPC – Uniform Plumbing Code
2.2. Guidance
2.2.1. National Fire Protection Association (NFPA) 10, “Standard for Portable Fire Extinguishers”
2.2.2. NFPA 13, “Standard for the Installation of Sprinkler Systems”
2.2.3. NFPA 14, “Standard for the Installation of Standpipe and Hose Systems”
2.2.4. NFPA 15, “Standard for Water Spray Fixed Systems for Fire Protection”
2.2.5. NFPA 20, “Standard for the Installation of Stationary Pumps for Fire Protection”
Westgate Export Grain Terminal TEI Project No.20014657 FPSD‐2 F.P. System Desc./A/Issued for Review
2.2.6. NFPA 24, “Standard for the Installation of Private Fire Service Mains and Their
Appurtenances”
2.2.7. NFPA 61, “Standard for the Prevention of Fire and Dust Explosions in Agricultural and
Food Processing Facilities”
2.2.8. NFPA 69, “Standard on Explosion Prevention Systems”
2.2.9. NFPA 72, “National Fire Alarm and Signaling Code”
2.2.10. NFPA 654, “Standard for the Prevention of Fire and Dust Explosions from the
Manufacturing, Processing, and Handling of Combustible Particulate Solids”
3. Fire Protection for Buildings
All Buildings are to be constructed of non‐combustible materials. Buildings shall be designed to
minimize horizontal surfaces where combustible dust could accumulate. Such horizontal surfaces
shall be accessible to the maximum extent possible to assure that regular cleaning and visual
inspection can be performed. All equipment on the project site shall be designed to minimize or
entirely eliminate fugitive dust emissions via dust collection equipment and enclosed conveyors.
Fire protection systems shall be provided in locations where typical for standard industry practices.
Building layouts shall be designed to provide adequate space for escape in the event of fire per
national, provincial, and local codes.
3.1. Rail Receiving Pit
The facility will be designed to receive grains and oilseeds via rail cars. Up to 135 cars will be
provided per trains, with up to 3 such trains per 24 hour period. There shall be no airborne dust as
the train locomotive passes through the building. A dust collection system shall be provided by the
rail receiving pit which shall collect dust emissions from the rail car unloading process. Fire/Heat
Detection shall be provided within the Rail Receiving Pit area. Access and egress will be via stairs
with a secondary emergency escape ladder per NFPA 101.
3.2. Transfer Tower
The transfer tower is mostly open to atmosphere, and as such, does not have stringent fire
protection requirements included within. The tower shall be constructed of non‐combustible
materials, primarily structural steel with concrete foundations. Horizontal surfaces shall be
minimized for locations of dust accumulation. Access and egress will be via stairs.
3.3. Take‐up Towers
The take‐up towers are open to atmosphere at grade to 7’ above grade with siding and roof
above 7’, and as such, do not have stringent fire protection requirements. The towers shall be
constructed of non‐combustible materials. Horizontal surfaces shall be minimized for locations of
dust accumulation. Access and egress will be in accordance with NFPA 101. Open top sound barriers
will be provided. These will be open on the side facing the water.
Westgate Export Grain Terminal TEI Project No.20014657 FPSD‐3 F.P. System Desc./A/Issued for Review
3.4. Scale Building
Manual dry standpipe shall be provided with connection for fire department. Fire/Heat
Detection equipment is provided. Explosion venting per codes and regulations for the building shall
be provided. Access and egress will be in accordance with NFPA 101 and personnel hoist.
3.5. Silo Complex
Manual dry standpipes, with fire department connections, may be provided at each grain
storage silo complex (annex). Manual dry stand pipes at these locations are not required per the
NFPA or the local authority having jurisdiction, but may be installed as a courtesy. If installed, these
manual dry standpipes shall be configured in such a way so as to provide coverage at each annex
roof to meet or exceed local authority having jurisdiction standards. Access and egress shall be in
accordance with NFPA 101.
3.6. Cleaning Building
Manual dry standpipe shall be provided with connections for the fire department. In addition to
the dry standpipe, there shall be fire/heat detection and pre‐action sprinkler system. In the event of
heat detection, automatic equipment shutdowns will occur. The Cleaning Building Fire Pump Room
will also incorporate manual valves for deluge systems in the dust filters, pellet cooler, and bucket
elevators by the cleaning building. Access shall be provided to all equipment that includes manual
deluge equipment to facilitate periodic cleaning of the components located within said equipment.
Access and egress to the various building areas will be in accordance with NFPA 101 and personnel
hoist.
3.7. Ship Loading
Ship loading fire protection scope includes 4 hose connections per local fire department
requirements, one (1) international shore connection, and dry standpipes. A dedicated booster
pump may be required in order to provide adequate pressure across the wet fire protection lines;
this will be confirmed as design progresses. Access and egress will be via stairs where possible,
however, some ladders will be required due to the nature of the ship loading design.
3.8. Admin Building
The Administration Building fire protection systems shall be provided by the building
subcontractor. With the exception of rooms that contain plant computer control equipment and
other electronic and/or electrical equipment, the Admin Building shall be provided with all fire
protection features required to meet or exceed all codes regarding occupied buildings of this nature.
The Control and Server Room(s) will not have sprinklers, but will include heat detection.
Westgate Export Grain Terminal TEI Project No.20014657 FPSD‐4 F.P. System Desc./A/Issued for Review
3.9. Maintenance Building
The Maintenance Building fire protection systems shall be provided by the building subcontractor.
The Maintenance Building shall be provided with all fire protection features required to meet or
exceed all codes regarding occupied buildings of this nature.
4. Equipment
4.1. Bucket Elevators
All bucket elevators are located outside for passive isolation purposes and shall include full
hazard monitoring systems and manual deluge fire protection systems with dry standpipe. Pressure
relief venting shall be provided on all bucket elevators, and they shall also be located on the exterior
of buildings.
4.2. Conveyors
All belt conveyors involved in the main transfer of materials throughout the facility shall utilize
rubber belting and which shall be oil‐resistant, fire retardant, and non‐conductive. Fire protection
shall be in accordance with NFPA requirements.
4.3. Dust Filters and Cyclones
Dust filters and cyclones shall be located outside of buildings. Dust filters shall be provided
with deflagration venting. All dust filters shall include manual deluge systems and heat sensors.
Electrical Interlocking shall be provided in between the material handling process machinery and
dust filters to prevent the equipment from starting unless the associated dust filter is operating.
Passive mechanical explosion isolation equipment shall be provided on dust filters located at the
Cleaning Building.
5. Miscellaneous Fire Protection Items
5.1. Fire Protection Water Supply
Automatic Sprinkler systems shall be designed to current (less than 12 months old) local water
supply flow test results.
5.2. Fire Water Supply Main
A looped fire water main (minimum 10 inch diameter) with isolation or sectional control valves
and post indicators shall be provided. Post indicators shall not have tamper switches. 20 psi
residual pressure will be maintained in the system at all times for pumper fire trucks. Pumps will be
provided as necessary for the sprinklers.
Westgate Export Grain Terminal TEI Project No.20014657 FPSD‐5 F.P. System Desc./A/Issued for Review
5.3. Fire Hydrants
Hydrants shall be fed by minimum 6 inch connections coming from the fire main loop. Isolation
and/or sectional control valves shall be provided for each individual fire hydrant. Hydrants shall be
spaced within 100ft of Fire Department Connections, and spaced within 300ft maximum between
other structures (or as required per the Authority Having Jurisdiction).
5.4. Fire Pumps
Fire booster pumps shall be provided at any and all locations requiring pressure higher than
that available in the fire water loop. The pumps shall have a power supply reliable per NFPA
standards if electric, otherwise the pumps provided shall be diesel‐powered per NFPA standards. A
Booster pump is already confirmed as required and shall be provided at the Cleaning Building.
Additional booster pumps will be considered throughout the final design of the project, but are not
confirmed at this time.
5.5. Sprinkler System Protection
Automatic sprinkler system protection shall be provided for all enclosed buildings and
structures of or containing appreciable values or vital to continuation of terminal operations. The
Cleaning Building shall have this installed. An ordinary Hazard Group 2 sprinkler system protection
of .2gpm/ft2 over 1,500ft2 (over 1,950ft2 for dry or pre‐action systems) shall be provided as required
per NFPA and industry standards.
5.6. Fire Detection Alarm Systems
Smoke detectors shall be installed inside main electrical/MCC rooms. Heat detection devices
shall be installed inside the Cleaning Building and Scale Tower. Other sensors and switches shall be
provided on equipment which will detect issues before heat detection devices, therefore negating
the need to install heat detecting devices at these locations. All fire detection systems shall be
monitored at the Pre‐action monitoring panel and/or the main fire detection system monitoring
panel located in the control room, which shall be a constantly attended location. Additionally,
monitoring of manual valves for the Bucket Elevators, cyclones, pellet cooler, and dust filters shall
be handled by the main monitoring system.
5.7. Portable Fire Extinguishers
One minimum “2A” rated multi‐purpose “ABC” type extinguisher should be provided per
1,500ft2 building area or within maximum 75 ft. travel distances, whichever is more stringent.
Carbon Dioxide or other clean agent type extinguishers shall be provided in electrical and control
rooms. The control room is located within the administration building.
Westgate Export Grain Terminal TEI Project No.20014657 FPSD‐6 F.P. System Desc./A/Issued for Review
5.8. Fire Hose Standpipes
The local fire department shall be contacted for standpipe connection size, type, and location
requirements. Standpipe systems shall be sized based upon local fire department pumper truck
pump ratings and dry pipe requirements. All standpipes exposed to freezing shall be dry type or
appropriately heat traced.
5.9. Electrical/MCC Rooms
Electrical rooms shall be maintained under positive pressure. Local smoke detectors shall be
installed inside of all main electrical/MCC rooms and PDCs.
5.10. Electrical System and Equipment
Class II, Group G, Division I rated areas only apply to areas on the interior certain pieces of
equipment/hoppers/silos/etc. Class II, Group G, Division II rated fixtures and equipment shall be
provided in all areas exposed to combustible dusts.
6. Emergency Vehicle Access
Emergency vehicle access to the site shall be provided per all regulations and industry
standards. The City of Vancouver Fire Department has been consulted regarding access and shall be
consulted further throughout the design life of the project.
Page 1 of 19 Dust Hazard Analysis
Preliminary Dust Hazard Analysis for G3 Terminal Vancouver
Vancouver, BC, G3 Limited Partnership
G3 Limited Partnership is undertaking a major project with the design and construction firm Kiewit to build
G3 Terminal Vancouver, a state of the art export terminal grain elevator facility to be located at the Port of
Metro Vancouver, BC. The facility shall be a rail receiving facility that will receive grain products primarily
by rail and export them by loading ships. Total storage capacity shall exceed 6 million bushels with handling
rates of up to 120,000 Bushels per hour. The facility shall have the ability to clean the grain received as
needed to meet all Canadian grain standards. The design of G3 Terminal Vancouver is very similar to the
facility constructed in Longview, Washington, which was commissioned in 2012 by Bunge and EGT. The
design for G3 Terminal Vancouver is thus proven for operation and construction due to successes shown
throughout the life of the Longview project.
As stated earlier, the facility will receive grain products by rail and send them out by ship. Only pelleted
dust and screened materials will be shipped by trucks to local markets. The facility shall minimize safety
hazards as much as possible; some examples of safety in design include the minimization of below‐grade
locations (the only such location being the rail receiving basement), bucket elevators shall be located
outside, and full accessibility shall be provided as much as possible for maintenance of the project. The
facility shall be fully automated, requiring only 10 ‐12 persons involved in order to perform inspections,
maintenance and adjustments to support operations. This alone will greatly reduce personnel exposure to
any hazards compared to older manually operated export facilities. The design of G3 Terminal Vancouver
will be at the forefront of safety within the grain handling industry upon commissioning as a result of the
precautions taken during its design. The facility will utilize state of art Programmable Logic Controller (PLC)
operation which will have extensive hazard monitoring features and operations (such as bearing
monitoring, equipment alignment detection, vibration monitors, product level detectors, motion sensors,
speed sensors, plug switches, amp meters, and many others). As stated before, the G3 Terminal Vancouver
design and its implementation have been proven at the Longview facility, which was also built by parties of
Kiewit and G3 Limited Partnership. As a frontrunner within the grain handling industry, G3 Terminal
Vancouver shall meet or exceed all applicable codes, standards, and regulations.
Page 2 of 19 Dust Hazard Analysis
Purpose
The purpose of a dust hazards analysis (DHA) is to identify potential hazards within a facility and its
operations and document how those hazards are to be managed. The hazards addressed by this analysis
are the fire and deflagration hazards due to the potential presence of combustible dusts. The analysis will
identify relevant strategies to provide a reasonable and appropriate degree of protection to life and
property. Typical potential ignition sources and fuel hazards that occur in the types of operations in grain
handing, product cleaning and processing will be considered and discussed in detail. Historical data on the
causes and prevention strategies of combustible dust fires, deflagrations and explosions will be relied upon
throughout this analysis.
Overview
A DHA is a detailed analysis and documentation of the facility housing the grain handling operations. Each
part of operations is considered for potential fire and deflagration hazards which could interfere with
worker and facility operations safety. Further, where the hazard is managed, the means by which it is being
managed is evaluated and documented. The design shall utilize the concepts of separation and segregation
of operations in separate structures to greatly reduce the likelihood of an event in one building propagating
to other locations. Structures and portions of grain handling shall be remote from one other with long
elevated conveyors to elevate the grain to the next structure. Therefore, this design requires a large site to
handle the grains and serves to protect the operations.
The risk for a dust deflagration is based upon the potential for all four necessary and sufficient conditions
for a deflagration to exist at the point of consideration concurrently. If the combustion is sufficiently
contained it could develop as a very fast deflagration allowing pressure development with a sufficient shock
wave followed by a traveling flame front. Should the flame front arrive after a dust cloud is placed into
suspension in the enclosed area, a secondary event can potentially follow. Most people refer to the
contained initial event as an explosion since equipment and structures can suffer failure and rupture due to
the resulting pressure and acoustical shockwave results. The conditions for a deflagration are as follows:
(1) A particulate of sufficiently small dimension to propagate a deflagration flame front
(2)A means of suspending or dispersing the particulate
(3) Sufficient quantity of particulate to achieve the minimum ignitable concentration
(4) An ignition source of adequate energy or temperature to ignite the dust cloud or a dust layer.
Dust Hazard properties of grains and products
Dust Hazard properties of the grain materials to be handled at the G3 Vancouver facility and their related
dusts properties are shown in Table 1 below with density and explosive properties (Kst, Pmax, MEC, MIE.).
A new version of the NFPA 61 standard for the “Prevention of Fires and Dust Explosions in Agricultural and
Food Processing Facilities” is in the second draft stage and is expected to be finalized in 2016. The 2016
draft contains a provision 4.1 which states “It shall be permitted for the owner/operator to consider dust
generated from Bulk Raw Grain and other organically derived materials as Agricultural Combustible Dust”
Further published test data on grain materials can be relied upon to determined needed protections. The
drafted 2016 edition of NFPA 61 will be the first such document to require a dust hazard analysis be
Figure 1 is an illustration showing the G3 export terminal facility proposed to be
built at the Vancouver, BC port.
Page 3 of 19 Dust Hazard Analysis
performed for new construction. Other NFPA dust specific standards are expected to include a DHA
requirement as well.
Table 1 shows the grain material characteristics of some of the grains which will be handled at the G3TV
site. The grains in this table shall be used for facility design purposes. Additional grains and grain
byproducts to be handled and their respective frequencies are located below Table 1. Corn may be handled
as well. None of the byproducts will have more severe fire or explosion properties than the dust from
whole grains. Designing for wheat dust properties shall be adequate for protections planned for the facility
and its operations, however, explosion vent designs and isolation techniques, etc. will be considered for
handling corn. Structural designs will be based on the densest material to be handled (Whole wheat).
Canola properties are expected to be very similar to other oil seed grains (Soybean, sunflower and
Safflower). Subsequent or final DHA can fine tune this preliminary analysis for handling and for preventive
measures including management protection strategies deemed necessary (i.e. hotwork procedures and
permits, and housekeeping documentation). Based on the review of this information the system designs
shall be based on handling wheat and corn regarding fire protection throughout the facility.
Table 1 This is a compilation of the density and deflagration properties of multiple materials:
Material Unit Weight of
bulk grain
Kst
Bar‐
m/sec
Pmax
Bar
MEC
g/m3
MIE
MilliJoules
mj
COMMENT
*Wheat
Durum wheat
47 ‐ 50 Lb./ft3
753‐801 kg/m3
112 9.3 60 Source NFPA 61
*Corn 45‐47 Lb./ft3
721‐753 kg/m3
100 6.5 45 g/m 40
Source
Bur of mines
*Canola 40‐44 Lb./ft3
640‐705 kg/m3
? ? ?? ? No data‐currently
available
*Soybeans 44 – 46 Lb./ft3
705‐737 kg/m3
125
7.5
35 g/m3 50 Source NFPA 61
Sunflower 44 7.9 125 Source NFPA 61
*Peas 48 Lb./ft3
769 kg/m3
4.6
calculated
50 g/m3 Source
Bur of mines
Page 4 of 19 Dust Hazard Analysis
The G3 Terminal Vancouver Project will handle the following grains with the listed approximate
frequencies:
Primary Products (90‐95% of Annual Average Throughput):
1. Wheat (all classes) 2. Canola 3. Durum Wheat 4. Barley 5. Peas
Secondary Products (5‐10% of Annual Average Throughput):
1. Soybeans 2. Corn 3. Oats 4. Flax Seeds 5. Screening Byproducts
a. Grain screenings pellets b. Feed screenings c. Mixed Feed Oats
6. Mixed Grains 7. Canola Meal Pellets
Rarely Handled Products (<5% of Annual Average Throughput):
1. Sunflower Seeds 2. Alfalfa Pellets 3. Mustard Seeds (Brown, yellow, oriental) 4. Lentils 5. Canary Seed 6. Beans (All types)
IV
V
V
V
Page 5 of 1Dust Hazard
The entire f
will be trea
elements. V
protection
dust hazard
whether th
portions of
I. 1. R
con
II. 2.
III. 3.
equ
V. 4.
V. 5.
VI. 6.
II. 7.
Figure 1 s
9 d Analysis
facility design
ted as combu
Vendors or e
for personne
d analysis is n
ey are in a co
the facility (
Rail receiving
nveyors up to
The Scale tow
The upper sil
uipment inclu
The cleaning
The pelleting
The reclaim s
Ship loading
shows the gen
n will be analy
ustible and th
quipment sup
l and equipm
eeded to con
ontained envi
as indicated o
g‐Including th
o the scale tow
wer and relat
lo bin deck of
uding dust sys
tower includ
g operations a
system for th
operations in
neral arrange
7
yzed for pote
he values show
ppliers will ut
ment at the fac
nsider the pot
ronment allo
on Fig. 1.):
e receiving b
wer and the r
ted conveyor
f the annex in
stems.
ding all specif
and equipme
e silo annex a
ncluding conv
ment of the f
ntial dust haz
wn in this tab
tilize dust exp
cility. An ove
tential for air
owing pressur
uilding, the ra
related equip
rs and scales.
ncluding conv
ic operations
ent including t
and related g
veyors, ship lo
facility and al
3
6
zards. All dus
ble are consid
plosion values
erview of the
borne dust, d
re and flame p
ail receiving b
ment and op
veyors and sto
s and related
truck loadout
gates and con
oaders, and lo
l portions con
I
st generated
dered suitable
s in order to p
design indica
dust layers, ig
propagation f
basement, all
erations.
orage bins an
equipment.
t and dust con
veyors and d
oading spout
nsidered in th
4
5
and accumul
e for the desig
provide neces
ates that a de
gnition source
for the follow
receiving
nd related
ntrol.
ust systems
ts
his analysis.
2
ated
gn
ssary
etailed
es and
wing
Page 6 of 1Dust Hazard
I. Rail Rec
Fig 2.
This operat
be received
west side o
through the
outlines spe
hazards ass
a)
b)
c)
9 d Analysis
eiving Dust H
Rail receivin
tion is to rece
d in a 24 hour
of the propert
e rail receivin
ecific function
sociated with
The rece
each en
the Nat
G, Divis
Group G
wet loc
Automa
over the
gates ar
shall be
prevent
shall be
equipme
objects,
remove
grain str
The grai
dust and
underne
capture
Hazard Analys
ng building w
eive grains and
r period. The
ty without de
g building. T
ns of rail rece
each functio
eiving buildin
nd to allow th
tional Electric
sion 2. Electr
G, Division 1.
ations.
atic hopper ga
e rail receivin
re opened as
two cars in le
tramp metal
effective in k
ent damage a
and any othe
d from the gr
ream are rem
in receiving h
d prevent fug
eath the grati
. Each of the
Rail Bldg
Receiving c
Rail leve
sis
with equipme
d oilseeds via
trains will m
coupling the
The conveyor
eiving operati
n:
g will be a ste
he train to pas
cal code with
rical devices i
Additionally
ate openers w
g basement.
the cars start
ength with a g
l and foreign
keeping hazar
and interfere
er unwanted
rate surface o
moved by mag
opper shall h
gitive dust em
ing shall be p
ten hoppers
g.
onveyor
el
nt shown.
a rail cars up t
ove through t
cars. The car
rs will be able
ons and spec
eel frame bui
ss through. T
all electrical i
nside equipm
y, outside loca
will open the
These roboti
t to move acr
grate over th
objects from
rdous objects
with safe equ
debris which
on a daily bas
gnets at the d
have dust asp
missions and k
rovided to he
will have a d
to 135 cars in
the rail receiv
rs will move a
e to handle up
cific measures
ilding with me
The building’
in the buildin
ment, hoppers
ated electrica
rail car hopp
ic openers ar
ross the hopp
e hoppers wi
entering the
s out of the gr
uipment ope
h might get int
is. Smaller fe
discharge of th
iration below
keep the rece
elp reduce the
ust pick up p
Rail r
n size. Up to 3
ving structure
at 0.6 miles p
p to 120,000
s taken to avo
etal cladding
s electrical sy
ng to be rated
s, etc. shall be
al equipment
per gates as th
re to be contr
per inlets. The
ith 2‐1/2” X 7
grain stream
rain stream w
rations. Tram
to the grain s
errous objects
he rail receivi
w the grating t
iving building
e air needed
oint to preve
receiving Base
3 such trains
e located on t
er hour or les
BPH. The foll
oid potential
siding and op
ystem shall m
d as Class II, G
e rated for Cl
shall be rated
hey begin to p
rolled to ensu
e receiving bu
7‐3/4” openin
m. The openin
which could ca
mp metal, for
stream are to
s that do ente
ing conveyors
to capture air
g clean. Baffl
and ensure d
ent dust emiss
ement
may
the
ss
lowing
dust
pen on
meet
Group
ass II,
d for
pass
ure
uilding
ngs to
ng size
ause
eign
o be
er the
s.
rborne
es
dust
sions
Page 7 of 19 Dust Hazard Analysis
and fugitive dust. All hoppers will have automatic gates which can be adjusted to needed
flow rates.
d) A dust collection system will supply the needed aspiration for the hoppers and receiving
conveyors in the receiving basement and shall be located on the west side of the receiving
building. This dust collection system shall be protected with explosion venting and fire
protection that meets NFPA criteria. The relief vent panels shall be cabled to the dust unit
to prevent the vents from flying away in an explosion event. The rotary airlock shall
prevent any deflagration propagation downstream of dust discharge.
1) The dust unit shall be equipped with pressure detectors that will allow viewing of
the pressure drop across the tube sheet to indicate the proper performance of the
dust system to ensure the filter does not blind or perform inefficiently. The
pressure readings will be provided to the PLC to warn if the filter is not performing
correctly. A low pressure drop (less than 1” water gauge) could indicate that a bag
has a hole in it emitting dust and a high reading (over 6” water gauge) may indicate
the filter is becoming blinded and air flow in the system is reduced. Both of these
conditions will warrant maintenance.
2. If the filter needs maintenance attention the maintenance personnel will be
notified to look at and correct the problem.
3. A plug switch or high level sensor set in the filter unit will trigger an alarm if dust is
not properly being emptied and the unit is plugging or bridging over.
4. The dust system will be interlocked with the rail receiving operations and the
receiving take away conveyors. This will be done via site communications and the
PLC.
5. The rotary discharge valve will be monitored and have an indicator to the operator
that the unit is operating
6. The dust system duct work will be designed to a minimum velocity of 3200 FPM
and a maximum velocity of 4200 FPM. The system will be equipped with blast
gates which are used to balance the air flow in the system and at each pick up
point. This helps to ensure that dust is properly flowing to the filter and the duct
work will not fill up with dust.
7. All dust systems that utilize dust filters with hopper bottoms are to be equipped with passive mechanical explosion isolation to prevent flame propagation back into the unit from upstream equipment. Dust collectors with multiple sources will have isolation systems to prevent flame propagation back into the process.
d) A fully enclosed belt conveyor shall be utilized in the rail receiving basement and be
automatically fed by gates to load the belt. The gates and the subsequent belt conveyors
are to be controlled by the PLC. The enclosed conveyors shall deliver the grain from the
basement to ground level where grain shall be transferred to the belt conveyors going up
Page 8 of 19 Dust Hazard Analysis
to the scale tower. Belts will be flame retardant and static resistant (less than 300
megaohm conductivity) per NFPA and OSHA requirements to minimize potential hazards.
Head and tail Bearings are to be monitored for operating temperature, shown on the PLC,
and sound an alarm if they are over heating or need maintenance. Furthermore, belt
alignment on the head and tail pulleys with rub block temp monitoring shall also be tied
into the PLC with alarms. Grain depth sensors are to be used to monitor the capacity
loading on the belt conveyors to avoid overload conditions.
e) Speed sensors will be installed on all belt conveyors. Screw conveyors are to be limited to a
speed of 150 rpm and length to not exceed that which would require internal hanger
bearings. Conveyor drive motors will be equipped with thermal protection for overheating
and have a vibration sensor to indicate if the motor is operating out of balance.
f) Welding and cutting will not be allowed if any operations are ongoing. A strict welding and
cutting policy will be enforced with a permit required for any welding needs with strict
cleanup, wet down, use of welding blankets and established fire watch.
g) A safety device bypass permit shall be issued prior to any device being taken out of service.
This permit shall ensure that the method is in place to monitor the hazard and ensure that
the device is repaired and put back into service.
h) Housekeeping via manual means will be minimized as the facility will include a dust system
on all handling equipment and the maximized use of totally enclosed equipment. All
operating areas will be inspected daily and housekeeping scheduled as needed to minimize
dust accumulations.
i) Preventive maintenance of all equipment is to be built into the PLC system to ensure it is
completed and recorded when needed and at proper intervals.
j) A key component to preventing unsafe operations throughout the facility is the extensive
use of a hazard monitoring system which will be tied to the plant PLC. This will give the
operators needed information that the system needs attention. Automatic shutdown
conditions will be set into the programming of the system. Safety devices are to be
inspected and tested as needed to ensure they remain operational. This includes, but is not
limited to: bearing monitors, alignment monitors, speed switches and level sensors.
k) An Evacuation Plan will be developed for the facility. The operations and maintenance
employees will have radio communication with the control room which can immediately
advise them of needed actions including evacuation. The employees will be trained and
required to report any hazardous conditions to the control room operations so needed
steps can be taken to notify emergency responders and others at the facility. In addition to
a facility wide alarm horn, a local alarm will be sounded in the rail receiving building areas
to advise the need for evacuation.
Page 9 of 19 Dust Hazard Analysis
Figure 4. Scale Tower
II. Scale Tower Dust Hazard Analysis
The scale tower will be a multi‐level structure approximately 140 feet tall with explosion vents installed in the walls of the building. Grain and grain products are to be conveyed to the 120 foot level of scale tower by inclined belt conveyors from the rail receiving belts and directed to the upper scale garner. Belts are to be enclosed for the tail sections and head sections inside the scale tower to minimize dusting. Conveyor belts outside of structures are not to be totally enclosed but will be covered for rain protection and to reduce wind interference. The drives for the conveyors are to be located in a take‐up tower which provides the needed power to drive the belts and maintain belt tension. All bearing and alignment sensors on the drive and take‐up are to be temperature monitored. There are to be motion sensors to detect 10 and 20 % slow down on all belt conveyors. All sensor outputs are to be sent to the plant PLC with appropriate alarm settings. The take‐up tower shall be open on the bottom to eliminate dust containment. Take up towers will be checked during housekeeping inspections. Grain shall be weighed automatically in batches using the PLC. The material is to be released to the lower garner and discharged to belt conveyors to go to the silo complex for storage. All operations are to be interlocked to prevent operational upsets. Dust collection shall be provided at the tail pulley of the outgoing belts. A separate scale system is also to be in the tower to weigh reclaimed grain from the silos to ship loading. This weighed grain is to be directed to the conveyors going to ship loading or to grain storage or cleaning operations. The two systems (receiving and shipping) are each planned to be capable of operating at 120,000 bushels per hour. Four point‐of‐use filters shall be located on an outside platform and serve to collect dust from the garner and scale with level and pressure sensors to indicate they are operating in normal range to the PLC with appropriate alarms. Collected material is then to be returned to the lower garner.
Grain in
Scales
Grain out
to silos
Page 10 of Dust Hazard
Pot
hou
Em
nee
tha
Pot
tied
tem
ma
also
ext
bea
ma
upp
min
enc
inte
Cla
loc
wh
MC
Dus
pre
sca
we
pro
occ
on
Figu
III. The
Grain is
grain is
belts fo
G
19 d Analysis
tential dust h
usekeeping in
ployees will b
eding more im
at exceed the
tential equipm
d to the PLC.
mperatures an
intenance. B
o shall be tied
ernal to the c
arings are to b
terial from th
per garner to
nimize ignitio
closures are t
erior of hopp
ss II, Group G
ations and m
ere they are
CC rooms sha
st control usi
event dust lea
le and garner
ighing functio
oduct. The PL
curs in the flo
a PLC screen
re 5. Grain st
e upper silo b
s to be convey
deemed read
or loading. Th
Grain into co
azards in the
nspection, and
be trained an
mmediate att
facility guide
ment failures
Head and ta
nd will be sho
Belt alignment
d into the PLC
conveyors an
be anti‐frictio
he receiving b
help remove
n hazards, all
o be Class II,
ers, chute wo
G, Division 2.
otors shall be
installed. All
ll be pressuriz
ng bin vent fi
akage from th
rs are to be in
on. All gates
LC will monito
ow and produ
and the syste
torage annex
bin deck
yed from the
dy for immed
he silo annex
nveyors to sil
Silo
scale tower a
d clean‐up w
d required to
ention, airbo
elines or build
and ignition
il bearings of
own on the PL
t on the head
C with alarms
d have seals t
on roller bear
building will p
e any ferrous
l electrical de
Group G, Div
ork, etc. All o
Any outside
e (Totally enc
electrical ins
zed to keep d
lters shall be
he systems (lo
nter‐vented t
shall have po
or the operat
ct handling.
em will be sh
x with receivin
scale tower t
diate shipping
shall have 3 s
los
o reclaim opera
are to be add
ith records ke
o notify the co
rne dust clou
d‐up of dust o
sources will b
all belt conve
LC and sound
d and tail pull
shown. All h
to separate th
ing design in
pass over a ma
objects which
evices that are
vision 1 rated.
other electrica
located elect
losed fan‐coo
tallations are
dust out.
provided to t
ocated outsid
o avoid air im
ositive seals to
ions and noti
If a hazardou
ut down or b
ng on top and
to the silo an
g or already c
sets of silo un
ations to Scale
dressed by eff
ept on a PLC u
ontrol room o
uds, dust accu
on bearings, m
be detected b
eyors are to b
d an alarm if t
eys with rub
head and tail
hem from the
accordance w
agnet in the a
h may still be
e exposed to
. This include
al equipment
rical equipme
oled) TEFC an
e to meet the
the scale and
de the buildin
mbalances and
o prevent lea
fy the operat
us condition a
e adjusted as
d grain reclaim
nex for temp
leaned, it ma
nits, each com
Grain from
e Tower
fective dust c
unit of house
of housekeep
umulations, e
motors, etc.
by the hazard
be monitored
they are over
block temper
pulley bearin
e inside the e
with accepted
at the belt dis
e in the grain s
the grain stre
es electrical e
t within the to
ent is to be ra
nd/or rated fo
Canadian Ele
d upper and lo
g on an attac
d to protect t
kage of dust
tor if an abno
arises an alarm
s needed.
m/shipping sy
porary storage
ay be directed
mprised of 4 X
m scale tower
control, regula
ekeeping work
ping condition
equipment lea
d monitoring s
d for operatin
heating or ne
rature monito
ngs are to be
equipment. A
d standards.
scharge to th
stream. To
eam and insid
equipment on
ower is to be
ated for wet
or the environ
ectrical Code.
ower garners
ched platform
the integrity o
or grain and
ormal conditio
m will sound o
ystem below.
e. In the case
d to the shipp
X 4 silos or 16
ar
k.
ns
aks
system
ng
eed
oring
All
The
e
de
n the
rated
nment
. All
to
m). The
of the
on
or flash
.
e that
ping
6 each
Page 11 of 19 Dust Hazard Analysis
for a total of 48 silos. Grain is to be delivered to the top of the silos by belt conveyors from the scale
building. It is then to be transferred to a totally enclosed belt conveyor (Hi‐Roller) which shall feed the
two shuttle belt systems that will place the grain in assigned storage bins. Bins designated as clean
grain can be directly conveyed to the ship loading belts for loading. Grains that need to go to the
cleaning building before being shipped for export will be placed in separate, designated bins. Clean
grain can be returned to the silo storage unit or may be stored in the limited clean grain bins which will
be located within the cleaning building.
There are no enclosures to be located on top of the bin deck (such as a gallery). The shuttle conveyors
are to be supported in bridge structures above the bins so the grain stream can be directed into
designated storage bins. The entire process shall be fully controlled by the PLC. Emergency stop
switches to halt the operation shall be installed should they be needed. Maintenance will be required
to go to the MCC to lock the unit our while they work on it.
Workers on the roof of the annex will be notified via a central emergency evacuation alarm located on
either end of the roof if a hazardous condition arises and evacuation is required. Additionally, workers
will be equipped with radios and can be notified by the control room if any problems arise. There are
several ladders and means to exit the roof to meet egress needs planned for the annex, including a
bridge into the cleaning building. Exit signs and egress diagrams will be prominently displayed on the
bin roof. Fire extinguishers will be located within easy reach and near motor drives and platforms.
The annex top structure will not have any deflagration hazards since it will be outside and fully open.
However the silos and the conveyors will contain combustible dusts. To manage the risks of a
deflagration hazard the following design elements and practices are to be used:
1. The shuttle conveyors shall have a dust collection system within the discharge
chutes. These dust collection points will collect dust from the bin and grain stream
at the inlet of the bin during bin loading. Captured dust shall be returned to the bin
while it is being filled. Historically, deflagrations do not begin in grain bins under
normal conditions. Electric spark, mechanical, or tramp metal sparks could be
potential ignition sources in a bin; however, these risks are mitigated by
mechanical protection devices earlier in the process flow as the stream passes over
a receiving grate in the receiving building then past a magnet prior to being
conveyed to storage. The belt conveyors shall have extensive hazardous
monitoring features which greatly reduces potential for any mechanical sparks. All
electrical exposed to the bin is to be rated as a Class II, group G, Division 2
hazardous area. Explosion venting is impractical for most grain bins. In this design
the venting through the roof is not possible due to equipment located on the roof.
Providing explosion vents in the upper bin wall would increase the height of the
bins by 25 to 30 feet greatly increasing the empty space of the bin. A higher bin
and grain drop would cause increase in grain breakage and dust in the grain. This
increased space and grain drop could increase hazard as opposed to reduce it.
Venting of grain bins is further impractical as there is no guarantee that a dust
explosion would not spread to adjoining bins. Considering the large number of
safety devices and controls utilize in this design the benefits of the other control
measures being installed here outweigh the benefit if any gained from explosion
Page 12 of 19 Dust Hazard Analysis
vents. Current NFPA 61 standards do not mandate explosion venting of grain bins.
2. The conveyors on the bin roof are to be fully enclosed with the bearings located
outside the equipment.
3. All conveyor head, tail, and take‐up pulley bearings shall be temperature
monitored to detect failure with alarms set in the PLC hazard monitoring system.
The belt conveyors shall also be equipped with speed detectors to detect
overloading conditions. Additionally, level indicators will be provided to further
detect overloaded conditions.
4. All foreign materials and ferrous objects shall be removed from the process flow
during grain receiving at the rail by a restrictive grate opening and by magnets on
the incoming flow to the scale building. Grain that is cleaned further shall be
subject to additional grating and magnets before being placed in cleaning
machines.
5. Some drag conveyors will be used to return clean grain back to the silo bins. The
drag conveyors shall have bearing monitoring and chain breakage sensors to shut
them down in the case of an upset condition.
6. All repairs or installation of equipment requiring welding will necessitate that a
permit be obtained and all guidelines followed for proper preparation. A fire watch
with an extinguisher on hand and use of welding blankets to isolate the work area
from any combustibles will constitute expected practice for such work to take
place.
7. No carrying of smoking materials shall be allowed within the plant.
8. All grain spills and leaks shall be required to be cleaned up as soon as practical.
9. Bucket elevators are to be used in the cleaning tower operations and elevate grain
to drag or screw conveyors before it would be conveyed back to the annex. The
bucket elevators are to be located outside with explosion venting in the leg casing
and head sections. They shall also have a full array of hazard monitoring devices to
detect bearing temperatures, belt alignment, belt speed, pulley design, inspection
doors, etc.
10. All elements of NFPA 61 standard for prevention of fires and explosions in
Agriculture and food manufacturing shall be implemented.
Page 13 of Dust Hazard
IV. Clean
The cmeetgrainpelletscalpand a
b)
CLEANE
GRAIN I
19 d Analysis
IN
ning Tower Du
cleaning towet Canadian Gr shall be furthted products ers and condare addressed
a) Each tyto 6 difTwo tysecondthe maof cleacleaned
1.
2.
3.
4.
Each of may havcollectegrain strhour bu
RS
N
ust hazard An
er shall be a crain Standardher processedthat are suitaitioning equipd below:
ype of grain offerent materypes of cleanind for canola, paterials. Due ning. Grains d as follows:
Grains will p
Grains shall
The grains w
The grains w
type.
these procesve to be recycd. Product stream being fecket elevator
OUT
F
nalysis
oncrete strucs before shipd to recover aable for animpment. All of
or product berials will be hang operationspeas or corn. to the size ofwill need to p
pass through
be passed th
will then pass
will then pass
ses will creatcled to furthetreams of cleaed to the clears. Each prod
Figure 6. Clea
cture with a lapping (figure 6all grain of va
mal feed. Graif these opera
ing handled wandled, this rs will be used Each systemf this operatiopass through
scalpers to re
hrough rotary
s through asp
s through inde
e separate prer process foran grain will vaning tower wduct will be ha
aning tower
arge amount 6.). The residalue before usin is to be cleaations can cre
will require itrequires a vard for wheat, bm will have to on, 4 systems4 pieces of e
emove unwa
y cleaners.
irators to rem
ent machines
roduct streamr desire seedsvary from 10 will be performandled in sep
of equipmendual material sing the residaned using aseate combust
s own cleaninriety of equipbarley, durumbe configures must be devequipment to
nted debris a
move dust an
s which segre
ms to be hands and characteto 40 tons pemed by two 3parate convey
nt to clean graremoved fromdue to create spirators, screible dust conc
ng system. Siment addres
m wheat and ad to clean eavoted to eachbe properly
and materials
d light mater
egate grains b
dled. Some oeristics to be er hour. The 36,000 busheyors and Buck
ain to m the
eeners, cerns
ince 5 s each. a ch of h type
ials
by seed
of them
dirty ls per ket
Page 14 of 19 Dust Hazard Analysis
elevators. All dust collectors shall be located on the roofs and aspirate all of the cleaning equipment. All specialty product streams are to be handled in enclosed belt conveyors with separate spot filters (point of use dust collectors) at the tail and head pulleys. All bucket elevators associated with cleaning operations are to be located outside and fully explosion vented in the leg and head sections per NFPA standards. Hazard monitoring shall be used on all bucket elevator bearings, belt alignments, etc. Crown lagging will be provided on pulleys and belts with conductivity and flame retarding characteristics are utilized.
c) Drag conveyors will be provided with dust control. Key bearings on drags and screw conveyors shall be monitored as well as equipment speeds. Spills and product leaks are the greatest dust hazard and shall be controlled by PLC sensors regarding equipment aspiration and product flows.
d) Regular housekeeping inspections and clean‐up are to be conducted to ensure safe operations. This shall include vacuuming and sweeping as necessary. Prevention of product spills and leaks and their control will be paramount to efficient and profitable operations.
e) All electrical equipment in the cleaning tower areas is considered to be Class II, Group G, Division 2. Electrical equipment located inside the product stream or inside storage bins are considered to be Class II, Group G, Division 1. Electrical and control rooms shall be sealed off and pressurized in accordance with the national Electric code and as such shall be non‐ hazardous areas.
f) The cleaning tower equipment floors shall have pre‐action sprinklers throughout. g) An additional alarm horn will be placed in the cleaning building as personnel may not be
able to hear the central plant alarm. Personnel will have two way portable radios to communicate with the central control room regarding operations and conditions warranting evacuation.
h) The cleaning building shall have extensive louvers in the tower walls that will allow for makeup air into the process and help to relieve pressure if any deflagration develops.
Page 15 of Dust Hazard
V. Pel
The
the
fro
top
qua
ach
flow
The
pel
a d
(ha
The
scre
mil
disc
ele
sto
fab
sen
sec
to t
hav
19 d Analysis
leting operat
e pelleting op
e pelleting pro
m the grain p
p of the pellet
ality of feedin
hieve a unifor
w through the
e hammer mi
let operation
eflagration o
mmer mill) in
e material fro
ew conveyor
l will then co
charged to a
vator. This sm
rage bins. A
bric filter (whi
nds a signal ba
condary filter
the bins shall
ve continuous
tions Dust Ha
perations are
ocess (see Fig
product stream
tizing portion
ng pellets nee
rm mix and pa
e hammer mi
ll discharge a
ns. This separ
ccurs associa
n the pelletin
om the hamm
that will plac
mpress the m
cooling bin b
mall elevator
cyclone will p
ch will have e
ack to the pla
shall then be
have local bi
s level monito
Pelle
Hamm
Pel
Pell
F
azard Analysi
to be located
gure7 ). Colle
ms in the clea
of the buildi
eded. The m
article size. A
ill screens and
nd receiving
rate area shal
ted with the
g operation a
mer mill hoppe
ce the materia
material and p
efore being d
will discharg
pull wet air of
explosion ven
ant PLC for co
e recycled bac
n vent filters
or and high le
eting Bldg.
mermilll
llet mill
let cooler
igure 7. Pelle
s
d as a separat
cted dust fro
aning tower s
ng. Here, the
aterials will t
A filter will be
d collect any
hopper are to
ll have an ope
hammer mill
and provide p
er will then be
al (along with
pass it throug
discharged to
ge to another
ff of the pelle
nting, high‐lev
ontrol. Mate
ck to the pelle
on their disc
evel monitors
eting Operati
te section of t
om handling, c
shall be trans
ey shall be ble
hen be passe
e located outs
airborne mat
o be located
en vented wa
. This design
pressure relief
e fed to an is
h added steam
gh a pelleting
a conveyor w
drag conveyo
et cooling bin
vel sensors, a
rials collected
et mill. The
charge to the
s tied to the P
ons.
the cleaning t
cleaning, and
ferred to two
ended togeth
ed through a h
side the build
terial below t
in a separate
all to serve as
will isolate t
f.
olated rotary
m) into the pe
die. Pellets w
which will fee
or, which will
and discharg
and a pressure
d by the cyclo
drag conveyo
pellet bins. T
PLC to preven
tower dedicat
d refuse mate
o bins located
her based upo
hammer mill
ing to provid
the hammer m
e portion of th
a pressure re
he greatest h
y lock, then to
ellet mill. The
will then be
ed a small buc
l feed 1 of 3 p
ge the air into
e transducer)
one and the
ors carrying p
The pellet bin
nt an overflow
ted to
rial
d at the
on the
to
e air
mill.
he
elief if
hazard
o a
e pellet
cket
pellet
o a
) that
pellets
ns will
w or
Page 16 of 19 Dust Hazard Analysis
upset condition. The conveyors involved in pellet handling will be totally enclosed drag conveyors
to prevent dusting hazards. All conveyors shall have bearing monitoring to prevent a heat source
arising within the grain stream.
The pellet load out operations shall be performed at an open structure which will house a bulk
loading scale and a loading spout. The loading spout shall be a dust suppression hopper, which will
minimize fugitive emissions via a spot filter tied directly into the hopper above the spout. The
following additional items shall be incorporated into the design to mitigate dust hazards for the
pelleting and load out processes:
a) All electrical in the pelleting portions of the building shall be rated as Class II, Group G,
Division 2 areas. Electrical exposures to the production stream or inside of equipment or
bins are to be rated as Class II, Group G, Division 1 areas. Electrical rooms are sealed off
and pressurized in accordance with the National Electric Code are considered to be non‐
hazardous areas.
b) All conveyors used in the pelleting processing and in pellet handling shall be totally
enclosed and therefore dust‐free operations. The only exposures to atmosphere during the
pelleting and loadout processes are the dust suppression hopper spot filter and the bin
loading spot filter (only one for all three bins).
c) All conveyors shall have necessary bearing temperature monitors and plug sensors tied to
the PLC.
d) Regular housekeeping inspections and clean‐up are to be conducted to ensure safe
operations. Prevention of product spills and leaks and their control are paramount to
efficient and profitable operations.
VI. Silo reclaim Operations Dust Hazard Analysis
All silo storage bins are to be equipped with metered gates and empty bin sensors to reclaim grain
directly to enclosed belt conveyors. These enclosed belt conveyors shall take the grain back to the
scale tower before shipping. (See Figure 5). Once weighed, the grain will return to the silo annex.
Once this step has taken place, the grain will then be conveyed to the dock area via a series of
conveyors. Bin vent filters shall be used at the tail and head sections of these conveyors to capture
dust emitted at transfer points. Transfer points with sampling will utilize fabric filter style dust
collection systems. All dust control systems are to be monitored for proper operation with the
appropriate pressure differentials, high level sensors, plug switches, etc. Belts will be oil resistant
and resistant to electric curents per NFPA 61 standards. In addition to the aforementioned dust
prevention mitigation methods, the following shall also be implemented:
a) All potential dust hazards in the reclaim areas under the bin annex are to be addressed by
effective dust control, regular housekeeping inspection, and clean‐up with records kept on
a PLC unit of housekeeping work. Employees will notify the control room of housekeeping
conditions needing more immediate attention, airborne dust clouds, dust accumulations
exceeding facility standards, and equipment leaks that exceed facility guidelines.
Page 17 of 19 Dust Hazard Analysis
b) Electrical equipment used in the reclaim under the annex is rated as Class II, Group G,
Division 2 areas. Electrical exposures to the production stream or inside of equipment/bins
are rated for Class II, Group G, Division 1. Related electrical rooms shall be sealed off and
pressurized in accordance with the Electrical Code of Canada and are to be considered in
non‐ hazardous areas.
c) All conveyors shall be monitored for their mechanical conditions with the hazard
monitoring system that is a part of the PLC showing bearing temperatures, belt alignment,
motor vibration, and belt loading level sensors.
VII. Ship Loading Operations Dust Hazard Analysis.
Once the grain is reclaimed, conveyor belts will carry the grain to dock side for ship loading. These
belts are to be conventional covered belts to protect from the weather including rain, snow and
wind interference. Before the water line, the conventional belts shall become enclosed in order to
Page 18 of 19 Dust Hazard Analysis
prevent dust exposure to the water beneath. Two belts capable of carrying 120,000 bushels per
hour each can be used to load a ship with two loaders simultaneously (loading rate of 240,000 bph).
Three Agrico ship loaders will provide the capability to reach all ship holes for loading. Each of the
three loaders shall be equipped with multiple bin vent filters to capture any emissions that could
arise during the loading and to pull a negative thru the loading spout. In addition, the ship loading
spouts shall incorporate dust elimination technology by creating a vacuum above the grain stream.
The ends of the loading spouts may be kept under the grain surface during loading as necessary to
minimize transient condition emissions. The loaders will be able to translate in and out and swivel
up to 180 degrees to reach all parts of the ship. Again, all critical bearings on equipment
(conveyors and ship loaders) shall be monitored for unacceptable temperatures. The ship loading
shall be fully automated with workers monitoring operations. Loading workers will also ensure the
spout position and depth in the grain as required. A preventive maintenance system will be
incorporated in the PLC for this equipment as well to ensure all items are inspected, lubricated and
repaired as warranted. Additionally, no deflagration hazard should arise at this location as the
operations are outside and open to the environment. The only issue that could arise is inside
equipment, which has been covered in previous sections. That said, the hazard monitoring system
and effective operating parameters will make this risk extremely small.
VIII. Conclusions:
This facility design will incorporate state of the art of automation and use of computer controls to monitor operations. The facility will be operated from a central control room in the administration building and will have many safety features built in to the programming of the PLC. There is an extensive hazard monitoring system which will be extended to all of the handling equipment to bearings, alignment, over loading, excess vibration of motors, proper equipment speeds, temperature and pressure sensors, etc. Mechanical explosion isolation (back blast dampers) shall be utilized to prevent flame propagation down‐ or up‐stream from equipment if a hazardous situation does arise. Dust collectors with multiple sources will also incorporate an isolation system to prevent flame propagation back into the process. Virtually all of the concerns regarding deflagrations have been taken into consideration for these operations and will be incorporated into the facility design.
For design purposes, wheat shall be considered as wheat has the greatest fire and explosion risks. Corn, if handled will also be a concern since it has a history of being involved in past deflagration events at grain operations. For this analysis hazard values for grain dust characteristics were taken from published literature.
This design will rely upon enclosed equipment whenever grains are handled inside of structures. Extensive dust control will also be utilized at this facility. In addition to using traditional bag houses and cyclones, this design will use point of use (spot) filters to provide dust control at remote locations (such at belt conveyor transfer points or bin filling) without the need to install long runs of dust control ducting throughout the operations. This will eliminate concerns with duct wearing and leaking, dust accumulation on top of ductwork, and secondary explosion concerns if a pre‐event were to occur. The cleaning building will utilize dust filters on the roof to control a lot of equipment in a small area. Mechanical explosion isolation will be used on dust systems to prevent flame propagation (such as a back pressure damper) into the duct unit from upstream equipment. Dust collectors with multiple sources will have an isolation system to prevent flame propagation back into the process.
Page 19 of 19 Dust Hazard Analysis
All of the elements and causes for a dust explosion and resulting fire will be incorporated into this facility design per the methods described within this DHA. The design will incorporate safety into the facility by separating hazardous items from one another wherever possible and by providing state‐of‐the‐art prevention technologies at hazardous locations which cannot be mitigated by other means. Including these methods described above, G3 Terminal Vancouver will be the face of safety within the grain handling industry for the entirety of its design life.