Upload
vuongthu
View
222
Download
4
Embed Size (px)
Citation preview
© ABB| Slide 1September 21, 2016
Power System PlanningTechnical Colloquium Indonesia PLN - ABB
Nihar S Raj, Business Head – Power Consulting (Asia) , Presentation, Intercontinental, 22nd Sep 2016
© ABB| Slide 2
Important notices
September 21, 2016
1. Please be aware of Safety requirements & Emergency Exit2. Kindly keep your mobile phones in “SILENT MODE”. 3. More discussions / interactions on the topic.
Power ConsultingGlobal network of industry recognized subject matter experts…
Sri P.Trans. Planning& Operations
John D.Subsynch. Phenomenon
Dave D. HVDC/FACTS
Rodolfo K. System Stability& Dynamics
Albert K. System Studies
Sal G. Digital Grid /Distr. Planning
Lan T. Gen./Renewabl es Planning
Jin Z.Power Economics
Carlos H. SubstationAutomation
Ricardo G. Power SystemAnalysis
Bandaru K Failure Analysis Power Products
Manoj K Arc Flash Mitigation
Julia S. Industrial Power Systems
Arefeh S. Insulation Coordination
Andreas U. Distribution Sys. Modeling
Fahd H.WAMS
Ramana B.AC/DCInteraction
Alireza M.HarmonicsAnalysis
Ines Romero Renewables /Supergrids
Joaquin M. Microgrids
Paula F. Protection Coordination
Nihar R. Renewables Integration
© ABBAugust 3, 2016
Ron Willoughby T&D Planning Optimization
Khoi V.Energy Storage
A team of 125 technical experts with deep know-how, located worldwide to support you on extensive matters related to electrical power systems
© ABB| Slide 4September 21, 2016
Power System PlanningAgenda
1. Basic & System General Overview2. Some Challenges faced by Grid Owner3. Load Forecasting4. Generation Expansion5. Transmission Planning6. Substation Planning7. Distribution Planning
© ABB| Slide 5September 21, 2016
Power System PlanningNight View of Earth
http://geology.com/articles/night-satellite/satellite-view-of-earth-at-night.jpg
Europe, Eastern US, Japan, China & India shows higher night time consumptionEurope, Eastern US, Japan, China & India shows higher night time consumption
© ABB| Slide 6September 21, 2016
Power System PlanningBright view at Night
http://www.skyscrapercity.com/showthread.php?t=1591424
Beautiful Night view of Indonesia, Greater Jakarta to Greater SurabayaBeautiful Night view of Indonesia, Greater Jakarta to Greater Surabaya
© ABB| Slide 7September 21, 2016
Power System PlanningVoltage Levels in World
Challenges
Reactive Power Management
Availability of Switchgear
Corona Loss
Sustainability of grid during contingencies
© ABB| Slide 8September 21, 2016
Grid is ChangingGrid is Changing
Power System PlanningNext Level Grids
1200kV UHVAC SYSTEM
800kV HVDC
765kV EHVAC SYSTEM
400kV EHVAC SYSTEM
~220kV/132kV SYSTEM
Through Control of Power Flow on HVDC sections
Next Level Transmission Network i.e. 1200kV UHVAC Network
Main Transmission Level : 1200kV UHVAC/800kV HVDC Network
765kV EHVAC and 500kV HVDC System would be used as support Tr. Network
400kV AC System would be used as Sub-transmission Network
© ABB| Slide 11
1. Load and Generation at different / distant places.
2. Reduce losses in the system
3. Requirement of high availability in the system
4. Integration of new technology solution within system
5. Trained & Experienced resources
6. Optimized investments / Costs
7. Over voltage / Under voltage issues within the system
8. Integration of Renewables
9. Increased short circuit levels
10. Selection of nominal rated current
11. ROW issues for transmission lines
12. High Reliability requirements
September 21, 2016
Power System PlanningImportance of planning to meet future challanges by Grid Owner
© ABB| Slide 12
13. Reactive Power Compensation requirements
14. Environmental issues
15. Acts of Nature (Problem of flood, earth quake)
16. Increase SAFETY
17. Lesser environmental impact
18. High Security
19. Bulk Power Transfer
20. Higher Utilization of existing Assets
21. Monitoring and Analyzing the Grid Performance
22. Have Futuristic Grid
23. Many more ………
September 21, 2016
Power System PlanningImportance of planning to meet future challanges by Grid Owner
© ABB| Slide 13September 21, 2016
Power System PlanningTime Horizon Perspective
Power System Planning1 year – 10 years
1 week – 1 year Maintenance scheduling
Unit Commitment
Economic dispatch & OPF
Automatic Generation Control
Power System Dynamics
Power System Transients
Minutes –1 week
Milliseconds -seconds
Nanoseconds–micro seconds
Pow
er s
yste
m
Ope
ratio
n
© ABB| Slide 14September 21, 2016
Power System PlanningBird Eye View
• Generation, Transmission & Distribution planning criteria are different.
• Each sector has a different set of challenges and solutions
© ABB| Slide 15
• Power system planning is a process in which the aim is to decide on new as well as upgradingexisting system elements, to adequately satisfy the loads for a foreseen future.
• The power system must respond to changes in the level and location of demand. Decisions arerequired on what and where new generating, transmission and distribution capacity is needed to meetcustomer demands and maintain quality standards.
September 21, 2016
Power System PlanningBasic : Definition
Reference Fig : RUPTL 2013 – 2022 Eng.pdf
A High, “Reliability”; Design & Operation as “Economical” as possible..A High, “Reliability”; Design & Operation as “Economical” as possible..
© ABB| Slide 16September 21, 2016
Power System PlanningStages
• Load forecast• Generation Expansion Planning with
optimization of cost• Network expansion Planning
• Reliability Analysis• A C load flow analysis• Short circuit studies• Stability studies• Optimum cost estimation studies• Insulation coordination (EMTP/
Over voltages study)• Distribution system Planning
Power System StudiesForecast of Annual Energy & Power
Demand
Load Modeling
Generation Expansion (Choice of Optimum Mix)
New Substations (Location & Capacity)
New Power Plants (Subdivision in the Main Areas)
Network Expansion
Optimization of Equipment Characteristics
© ABB| Slide 17September 21, 2016
Power System PlanningLoad Forecast - Requirement
Reference Fig : RUPTL 2013 – 2022 Eng.pdf
• Generation and transmission capitalinvestment
• Financial forecasting• Spinning reserve planning• Capacity planning• Planning of fuel ordering• Implementation schedule.
• The term forecast refers to projectedload requirements, determined usinga systematic process of definingfuture loads in sufficient quantitativedetail to permit important systemexpansion decisions to be made.
Load Forecast Power Demand Requirement
© ABB| Slide 18September 21, 2016
Power System PlanningLoad Forecasting – Uncertainity
• Forecasting the future needs for electricity is difficult, it is not possible to do Isolated forecasting.
• Electricity production and distribution are highly capital intensive
• Projects are large and lead times are long
• Role of electrical energy in the society should be reflected
• Government policy and strategic decisions taken by utility are important factors
• Forecasting should view that the future is open to the effects of many human actions.
• Uncertainties arise from the impact of the changes in public perceptions, viewpoints and policies.
• Load management planning and conservations policy give additional requirements on load forecasting.
• Need to have more plans, only single plan can be RISKY.
• By incorporating the role of uncertainty into the analysis techniques, the emphasis of planning moves from making an accurate forecast to constructing a system that can adapt readily to changes.
© ABB| Slide 19September 21, 2016
Power System PlanningLoad Forecasting – Factors Affecting…
Load forecast
Geographical Geographical factors
Historical Data
Population growth
Load density
Alternative
sources
Alternative energy sources
CommunityCommunityDevelopment
Plans
Industrial Plans
City plans
Land use
© ABB| Slide 20September 21, 2016
Power System PlanningGeneration Planning
• Generation Expansion Planning (GEP) is the first crucial step in long-term planning issues, after the load is properly forecasted for a specified future period.
• What types of power plants do we have to install?
• Where do we have to install the power plants?
• What capacities do we have to install?
• As there may be an outage on a power plant (either existing or new), should we install extra generations to account for these situations? If yes, what, where and how?
• Optimization of cost
© ABB| Slide 21September 21, 2016
Power System PlanningGeneration Planning
Reference Fig : RUPTL 2013 – 2022 Eng.pdf
• Size, type and quality of various plants tobe known.
• Deep know how of the availableresources to ensure which type ofgeneration can give a committedexpansion
• Availability of historical data : Loadforecast, availability of generation, inputsof generation units etc.
• Max utilization of existing generationresources to take care of the base loadand utilization of gas based plants andstorage scheme for peak load.
Generation mix to meet demand with reliability Typical Generation Mix
© ABB| Slide 22September 21, 2016
Power System PlanningPlanning Hirarchy
Reference Fig : RUPTL 2013 – 2022 Eng.pdf
Generation – HL-1
Transmission – HL-2
Distribution – HL-3
Conceptual task at HL-1 Evaluation
© ABB| Slide 23September 21, 2016
Power System PlanningRenewables
Source : https://energyclub.stanford.edu & ABB Technical Reviw 02/2015
Sun does not glow for the entire day and Wind does not blow for 24 hours. Solar is best especially during day time when sun is at the peak.
With big tummy and long neck, requirements to ramp is still stringent
© ABB| Slide 24September 21, 2016
Power System PlanningRenewables..
Source : CBIP Conference on Solar 2015
Monthly Generation trends shows variation in month wise generation.
© ABB| Slide 25September 21, 2016
Power System Technology TrendsSome Challanges with Renewables...
1. Different load curves in different areas with different ramp rate.2. Reactive Power requirements and fault ride through requirements.3. Compliance to Grid Code 4. Frequency control. 5. Congestion in transmission networks. (Needs to be studied in detail)6. Increasing peak to off peak ratios, load changeovers, and increase penetration of renewables7. Market Structure8. Managing Variability & Uncertainty of the load itself is challenge and higher penetration of
renewable sources may further increase it9. Wind power not coincident with peak load10. Plants connected at remote / concentrated location with weak transmission network11. Renewable plant providing less grid support during plant disturbances
© ABB| Slide 27
1. Once Generation and load forecast is done it is easy to identify how many lines to be built and what length
2. System shall be evolved based on detail power system study
1. Power flow
2. Short circuit
3. Stability studies (Including transient stability, voltage stability and steady state oscillatory studies
4. EMTP studies to determine switching and temporary over voltages
• Note: Voltage stability, oscillatory stability and EMTP studies may not formpart of perspective planning studies. These are however required to be donebefore any scheme report is finalised.
September 21, 2016
Power System PlanningTransmission Planning – New Scheme
© ABB| Slide 28
• Addition of new Transmission lines to avoid overloading of existing system. (wheneverthree or more circuits of the same voltage class are envisaged between two substations, the next transmission voltage should also be considered.)
• Application of Series Capacitors in existing transmission line to increase power transfercapability.
• Upgradation of the existing AC transmission lines
• Re-conductoring of the existing AC transmission line with higher size conductors or withAAAC.
• Use of Narrow base towers
• Adoption of multi-voltage level and multi-circuit transmission lines.
• Use of HVDC Transmission (Both LCC and VSC Scheme)
• Use of AIS / GIS/ Hybrid technology as per requirements
September 21, 2016
Power System PlanningTransmission Planning – Strengthening Exisiting Scheme
© ABB| Slide 29
• In case of transmission system associated with Nuclear Power Stations there shallbe two independent sources of power supply for the purpose of providing start-uppower facilities. Further the angle between start-up power source and the NPPswitchyard should be, as far as possible, maintained within 10 degrees.
• The evacuation system for sensitive power stations viz., Nuclear Power stations, shallgenerally be planned so as to terminate it at large load centers to facilitate islandingof the power station in case of contingency.
• Where only two circuits are planned for evacuation of power from a generating station,these should be ( as far as possible) two single circuit lines instead of a doublecircuit line.
• Reactive power flow through ICTs shall be minimal. Normally it shall not exceed l0% ofthe rating of the ICTs. Wherever voltage on HV side of ICT is less than 0.975 pu noreactive power shall flow through ICT.
September 21, 2016
Power System PlanningTransmission Planning – Strengthening Exisiting Scheme
© ABB| Slide 30
• Thermal/nuclear Generating units shall normally not run at leading power-factor.However, for the purpose of charging, generating unit may be allowed to operate atleading power factor as per the respective capability curve.
• Critical loads such as - railways, metro rail, airports, refineries, underground mines, steel plants, smelter plants, etc. shall plan their interconnection with the grid, with 100% redundancy and as far as possible from two different sources of supply, in coordination with the concerned Utility
September 21, 2016
Power System PlanningTransmission Planning
© ABB| Slide 31
• Permissible line loading limit depend on many factors such as voltage regulation,stability and current carrying capacity (thermal capacity) etc.
• Surge Impedance Loading (SIL) gives a general idea of the loading capability of the line,it is usual to load the short lines above SIL and long lines lower than SIL (because of thestability limitations).
• For SIL loading (in-terms of surge impedance loading of uncompensated line )as afunction of line length assuming a voltage regulation of 5% and phase angular differenceof 30 degree between the two ends of the line. In case of shunt compensated lines, theSIL will get reduced by a factor k, where
k = square root (1-degree of compensation)• For lines whose permissible line loading as determined from the curve higher than the
thermal loading limit, permissible loading limit shall be restricted to thermal loading limit.
September 21, 2016
Power System PlanningTransmission Planning – Transmission lines
© ABB| Slide 32September 21, 2016
Power System PlanningTransmission Planning – Transmission lines
Reference Fig : RUPTL 2013 – 2022 Eng.pdf
Line Loading as function of length Thermal Loading Limits
© ABB| Slide 34September 21, 2016
Power System PlanningTransmission Planning – FACTS & HVDC
• Green solutions are possible
• Technology will solve future problems
• Losses will reduce.
© ABB| Slide 35September 21, 2016
Power System PlanningTransmission Planning – Voltages
CEA Tranmssion Planning Criteria
Voltage Rating TOV due to Load Rejection & SOV Limit
© ABB| Slide 36
• Max fault at any new station will not exceed 80% of rated rupturing capacity of CB.Additional 20% margin is for the future increase in short circuit levels
• Capacity of the substation at different voltage levels
September 21, 2016
Power System PlanningTransmission Planning – Substation Planning
© ABB| Slide 37
• Incase of augmentation with low Short circuit, voltage stability issues needs to bechecked.
• Switching configuration at UHV and EHV levels will be one and half CB scheme.• Switching configuration will also depend on availability and maintainability
September 21, 2016
Power System PlanningTransmission Planning – Substation Planning
© ABB| Slide 39
Power & AutomationPower & Automation
September 21, 2016
Power System PlanningSummary
ABB Power Consulting
One of the most vital element in Power System Planning – “System Studies”One of the most vital element in Power System Planning – “System Studies”
• Planning is the fist step in Power System for ensuring high reliabity
• It helps in integrating new technologies, meeting increasing load requirements and finalizing the areas to have enhancement in Generation
• Load forecasting is critical and requires a lot of inputs and coordination between planner and user
• Generation mix can help in optimizing the overall cost and ensuring availability of power
• Reliability is at a cost; this is some times inevitable
• New voltage levels can push high power but reactive power requirements need to be studied
• Different computer tools & smart algorithms have made the studies simpler.
• Different aspects are to be considered while planning on Generation, Transmission & Distribution.
Proper planning helps to reduce the gap between Demand and Supply of Power.Proper planning helps to reduce the gap between Demand and Supply of Power.