59
PRE-FEASIBILITY STUDY GuimarasIloilo Ferry Terminals System Project AUGUST 2008

Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

  • Upload
    carl

  • View
    1.060

  • Download
    3

Embed Size (px)

Citation preview

Page 1: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-FEASIBILITY STUDYGuimaras‐Iloilo Ferry Terminals System Project

AUGUST 2008

Page 2: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

Table of Contents

Introduction

Background 4

Objectives & Scope  5

The Existing Situation 6

Technical Description of the Project

The Development Approach 7

The Projects

The Parola Station Project  8

The Buenavista Station Project 19

The Jordan Station Project 22

Design & General Specifications 25

Market Analysis 26

Institutional Proposal 27

Financial Viability 29

Next Steps 32

Annexes 33

Page 3: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

CITIES DEVELOPMENT INITIATIVE FOR ASIA (CDIA)

SUPPORT MIG, PHILIPPINES

Project No. 07.2029.2‐001.00

Guimaras‐Iloilo Ferry Terminals System Project

Pre‐Feasibility Study

(DRAFT)

Prepared by:

CONSULTANTS FOR COMPREHENSIVE ENVIRONMENTAL PLANNING, INC.

August 2008

1856 Asuncion St., Santiago Village, Makati City

Tel :  895‐1812 ; Fax :  890‐2480

E‐mail  :   [email protected]

Page 4: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

4

Introduction

Background

This Pre‐Feasibility Study report focuses on the proposed improvement ofthe three wharfs comprising the Guimaras‐Iloilo Ferry Terminal System(GIFTS), one of the major components of the Cities Development Initiativefor Asia (CDIA) Support to Metro Iloilo‐Guimaras, Philippines (Project No.07.2029.2‐001.00) – or CDIA‐MIG for short. Based upon a request from theMetro Iloilo‐Guimaras Economic Development Council (MIGEDC), thesubject project is supported by the CDIA, which is a regional initiative of theAsian Development Bank (ADB), the German Development Cooperation(GTZ) system, and the Swedish International Development CooperationAgency (SIDA). The CDIA is designed to support cities in ADB’s developingmember countries in strengthening the links between their urban planningand infrastructure investment programs, and to facilitate that identifiedprojects will be subjected to pre‐feasibility studies, full‐blown feasibilitystudies, and will be financed and implemented accordingly. It is within thisframework that the pre‐feasibility study of the GIFTS project is beingundertaken.

This project was originally referred to as the Parola Eco Port Project, whichwas aimed at developing the former Rotary Park in Iloilo City at the mouthof the Iloilo River popularly called “Parola” into a modern ferry terminal.However, midway in the preparation of the pre‐feasibility study for thiscomponent, it was decided to expand its scope to include the Buenavistaand Jordan wharfs on Guimaras Island which are Parola’s “counterpart”wharfs on the Guimaras side. Thus, the pre‐feasibility study has expandedits coverage to cover the ferry terminals in all the three sites.

The pre‐feasibility study (PFS) aims to establish the prima facie case to takethe project to feasibility level under standard agreement with a financinginstitution. The PFS report tries to adhere to a standard acceptable tonational and international financing institutions, with particular referenceto requirements for possible ADB financing under the GoP/ADB PhilippinesBasic Urban Services Sector (PBUSS) project, including flagging potentialissues requiring in‐depth review in accordance with the various ADBsafeguards guidelines at the subsequent feasibility study stage.

Figure  1. Jordan port ticketing station

Figure  2. Jordan Port Ferry Terminal

Figure  3 Parola Eco Port Ferry Terminal.

Page 5: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

5

Introduction

Objectives & Scope

The project aims to improve and modernize the Parola, Buenavista, andJordan wharfs to cater to the needs of an expanding number of dailycommuters between Guimaras and Iloilo, and to enhance the tourismindustry which is a vital element of the Metro Iloilo‐Guimaras (MIG)region’s economy. In line with this basic objective, the Project’s scopecovers the physical improvements of the three wharfs, particularly itspassenger terminals, the boat docking facilities, and related servicefacilities. The Project necessarily also covers the financing of theseimprovements as well as its implementation strategy and managementsystem. The Project also looks at the modernization of the existing ferryboats which can be undertaken at a future phase.

The Project’s implementation, financing, and management strategyspecifically takes into account the fact that there are several majorstakeholders involved, including the association of ferry boat owners andoperators, possible private investors, and the local governments namelythe province of Guimaras, the municipalities of Buenavista and Jordan, andthe City of Iloilo. It recognizes the financial constraints of these LGUs andconsiders the role and possible contribution of the private business sectoras well as the ferry boat owners and operators.

An important concern of the Project is the presence of informal settlerhouseholds in and immediately adjacent to the Parola site, as well assidewalk vendors in the vicinity of all the three wharfs. While thesehouseholds and vendors presently contribute to the sanitation andenvironmental problems of the wharfs, they are also seen as potentialservice providers. The Project, therefore, considers appropriate measuresfor the relocation and resettlement of the informal settler families, and theaccommodation of the sidewalk vendors in viable commercial facilities thatare integral to the ferry terminals.

Figure  4. Hawkers at the Jordan Port.

Figure  5. Buenavista Port Ferry Terminal.

Figure  6 . Guimaras‐Iloilo Ferry Boat.

Page 6: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

6

The Existing SituationThe present ferry system essentially consists of local boatservice between ‘ports’ in Iloilo City and the ports in themunicipalities of Buenavista and Jordan in Guimaras Province.While Parola on the Iloilo City side is the receiving anddispatching counterpart of Buenavista commuters, Ortiz ‘Port’handles the Jordan traffic.

On the Guimaras side, the two facilities operate out of themunicipal ports and have been marginally developed to providea minimum level of comfort to the commuters with queuingsheds for ticketing and waiting areas. On the Iloilo City side, twoinformal “ports” evolved from need for landing points to unloadand load the commuting public. These are located at Ortiz, adistrict of the City located on the strait directly facing to Jordanand at Parola which is the lighthouse at the mouth of the IloiloRiver. These loading and unloading areas consist of nothingmore than the breakwater, where the passengers board and exitthe boats from the stern (Ortiz) or by crossing via the middleoutrigger plank (Parola). The boats are traditional long woodenboats with a low roof and outriggers.

While most passengers have no difficulty boarding during hightide, at low tide, the top of the breakwater can have anelevation difference of over 2‐meters. There are no gangplanksto facilitate the boarding or discharge of passengers. Accordingto the Philippine Ports Authority and Coast Guard officials, themethod of loading and unloading is a function of thecharacteristics of the two sites. At Ortiz, where the breakwaterjuts out seaward, the tidal current is minimal and the boats candock perpendicular to the rock‐pile. The strong river current atParola pulls the boats side‐ways and forces them alongside therock‐pile. Both landing points have the minimum amenities forticketing. However, the walkways are congested with vendorsand informal settlers. In Ortiz, the settlement structures arebuilt‐up at the edge of the breakwater line on the land side.There is no room for expansion at Ortiz except by reclaimingland by way of extending the rock pile and breakwater.

During the north‐easterly season the operations are suspendedat Ortiz due to the large waves which batter the shoreline. Thesea becomes turbulent and large waves lash the breakwater.This makes the loading and unloading operations dangerous tothe commuters. There have been a number of accidentsinvolving passenger falling into the water while exiting the boatduring turbulent seas. As a precaution, when this season sets in,the Coast Guard and Marina allow the outriggers to continueoperations at Parola. During this period Parola handles allcommuter traffic to and from Guimaras and has traditionallydone so. Normally, Parola only handles the movement to andfrom Buenavista while Ortiz caters to the Jordan traffic. Theboat licences to operate specifies the route and the Buenavistaand Jordan routes are separate and distinct.

The daily commuters moving into Iloilo and out to Guimarasdaily is reported at 5,870 for Jordan and 4,800 for Buenavista.Commuters between the two points in Guimaras and Iloilo Citynumber over 4.2 million annually.

The growth of commuter traffic indicates a trend towardGuimaras as ‘bedroom’ of Iloilo City. A large number of thepopulation which moves between these points, actually resideon the Guimaras side and work in Iloilo city. This observation isborne out by the peak movement hours. The first three hours inthe morning are heavy outgoing from Jordan and Buenavista.Parola and Ortiz experience the peak outgoing traffic betweenthe hours of 4:00 in the afternoon to 7 in the evening. It isexpected that the growth trend will continue as more and moreresidential areas are opened on Guimaras.

Another evolving market is also expected to grow in theimmediate future, tourism. Local tourists or weekend visitors tothe beach resorts on Guimaras also account for an increasednumber of riders during weekends. It is also expected that theinternational visitor market will grow at a much higher rate inthe immediate term.

Page 7: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

7

Technical Description of the Project

The Projects

The Development Approach

The present ferry system essentially consists of local boatservice between ports in Iloilo City and the ports inBuenavista and Jordan in Guimaras Province (see Figure 7).The boats are traditional long wooden boats with a low roofand outriggers. On the Iloilo City side, while they have theminimum amenities for ticketing and boarding, the piersappear as a makeshift docking facility which is congestedwith vendors and informal settlers. On the Guimaras side, thetwo facilities provide a minimum level of comfort to thecommuters with queuing sheds for ticketing and waitingareas. The number of commuters between the points inGuimaras and Iloilo City now stands at almost 5‐million ayear.

Addressing the needs of the commuting public and in linewith MIGEDCs thrust to promote tourism, a suitable Pier andSea Transport facility that address the needs of the marketfor access to the emerging residential areas, beach and idyllicrural places in nearby Guimaras are proposed. More thanbeing just a utilitarian pier for loading and unloading, the piersites shall be converted into modern Ferry Stations completewith comfortable terminal lobby with ticketing and waitingspaces, shaded and safe loading arcades, public toilets, shopsand parking areas.

The Architecture and Engineering design idea for the projectsare presented in the Figure exhibits. The land use and thebuilding areas therein are deemed as a reasonable guide forthe activity flow within the respective sites and the basis ofthe budget for their construction. The perspective drawingsmeanwhile are images of how the development could looklike in the light of the global objectives of the project.

Specifically, the new Ferry Station projects are located in: 1)the Iloilo City’s Parola Port along Fort San Pedro Drive bythe mouth of the Iloilo River; and 2) in the activeBuenavista and Jordan Ports both in Guimaras Province justacross the Strait. The old ports shall be redeveloped to theextent that they meet the requirement of the growingmarket and the tourism objectives of MIGEDC. Theadvantageous technical features inherent within theexisting ports shall be adopted and developed while theundesirable facilities and operational practices shall bereconsidered and upgraded to the extent that they becomefirst class facilities providing optimal benefits for the portsites. The individual projects are further described in theforthcoming pages.

Figure  7. Location of Parola, Buenavista & Jordan Ports.

Page 8: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

8

Technical Description of the Project

The Projects (cont’d)

The Parola Station Project

Site Analysis

The Parola site is a 1.3 hectare property comprising of the oldRotary Park and the Coast Guard compound, located at themouth of the Iloilo River beside the port operated by thePhilippine Ports Authority. Aside from housing the CoastGuard offices, the site is also occupied by some 25 informalsettler families. Immediately outside the fence of the CoastGuard compound is the ticket booth and pier of the ferryboats servicing commuters between Iloilo City andBuenavista in Guimaras. The side of the site fronting the mainaccess road is lined with make‐shift stalls of vendors.

The Rotary Park has been turned over to the Iloilo CityGovernment, while the Coast Guard compound is, accordingto the Coast Guard, under their authority by virtue of aPresidential Proclamation. The Iloilo City Governmenthowever, maintains that the property is in the name of theGovernment of the Philippines and under the jurisdiction ofthe Department of Environmental and Natural Resources(DENR). Per the Office of the Mayor, the city government hasrequested the Office of the President to issue a PresidentialOrder giving Iloilo City jurisdiction over the entire property,and that this Order is expected to be released within theyear.

The site is situated behind the new PPA wharf. The side ofthe property facing this wharf is water‐logged even duringlow tide and will require substantial filling if it is to be builtupon. The site lacks proper drainage and utilities. Theexisting pier for the ferry boats is narrow. Entrance to thepier is congested with a mix of vendors, taxis, jeepneys andtricycles. The area is also lacking in proper solid wastemanagement.

The Iloilo City Urban Poor Affairs Office has identified the 25informal settler families occupying the site, and is preparinga relocation area for them. However, the site inspectionrevealed that outside but adjacent to the site, are informalsettlers who will also need to be relocated.

PAROLA ECO‐PORT SITE

Figure  8.  Parola Eco Port Site.

Page 9: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

9

Technical Description of the Project

The Parola Station Project (cont’d)

Rotary Park Area:  9,913 sqmPhil. Coast Guard Area:  3,627 sqm

Total Area of Titled Lots:  13,540 sqm

Figure  9. Delineation of lot parcels in Parola.

a) The berthing of larger boats at the river mouthpresents a hazard to the channel. The regulatoryagencies tolerate the presence of the outrigger boatsfor lack of other viable alternatives , and

b) Limitation to its development area boundaries due tothe existing PPA industrial wharves established andoperating around it.

c) Fort San Pedro Drive to Parola is a cu‐de‐sac of sorts.Public transport is not allowed through the PPA riverport area while private transport is only allowedthrough until the gates are closed at around 7:00 in theevening. Some arrangements will have to be agreedupon with PPA relative to this situation.

Currently, the facility services only the Buenavistacommuters under normal conditions. However, betweenJuly to September, and at the height of the typhoon season,the operations of Ortiz from Jordan are moved to Parola.From the average 4,800 daily commuters, the facility has tohandle the additional volume of 6,900 passengers fromJordan as well. So traditionally, Parola has the capacity tohandle all commuter movement from the two points inGuimaras.

Technical Considerations

Among other things, the technical problems facing thedevelopment of the Parola port are

Site Capacity

This lone station that is expected to service all commutersbetween Iloilo City and Guimaras will obviously contain themost number of ferry traffic. Short of perhaps anotherstation in another location in the future, the Parola Stationwill be counted on to accommodate all commuter boatscoming from, and heading to, both the Buenavista andJordan ports. While the Parola Port compound is collectivelymore than a hectare in size, its pier for docking is not thatconvenient and ideal according to the Coast Guard and PPA,and which situation needs to be rationalized.

Page 10: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

10

Technical Description of the Project

The Parola Station Project (cont’d)

Because of its original land uses, the Parola land complexearmarked for development under this project is also notfree vacant land that can be readily developed. Some 30informal settlers on the site and along the sidewalk need tobe relocated or dismantled prior to development. Theinterests of the hawkers who crowd the walkway to theloading and unloading as well as some settler families whoactually reside on the breakwater need to be addressed.

To effectively implement the terminal plan, the existing CoastGuard headquarters would need to be relocated to anotherarea within the site. In line with the City’s objectives, restorethe Rotary Park amenities and relocate the informal settlersthat have erected shanties there. Additionally, theDepartment of Environment and Natural Resources has alsorequested that they be allocated a parcel for the location oftheir regional office. Any development proposal must takeinto account these factors.

The Iloilo River has historically been the main port. On eitherside of the river, the Port of Iloilo is operated by thePhilippine Ports Authority. The Parola site is the only stretchwhich does not fall under the supervision of the agency.Parola is a property of the Philippine Government titledunder the Department of Environment and NaturalResources. The plot is covered by three (3) titles with a totalarea of 14,600 square meters. The Coast Guard was allowedthe use of over 3,000 square meters under an officialissuance.

The need for more port space has forced the PPA to developthe land strip along the strait and as recently extended thewharf up to the edge of the river entrance. However, thestructure was set‐off roughly 30 meters from the land side,respecting the sea frontage of Parola. This wharf handlesboth passenger and cargo from large international and inter‐island vessels. Meanwhile the river facilities continue tooperate including the fast craft ferries to other points ofVisayas.

Risk Factors

A description of the tidal pattern of the river and the straitwas given by a representative of the Coast Guard with theconcurrence of the Philippine Ports Authority. The deepchannel of the river is mainly at the center and is very tight.The channel has to be continuously dredged to maintain thedepth as siltation is a major problem.

The tides and current have a distinct effect on the rivertraffic. The larger cargo boats and the fast crafts need to go athigher speed at the junction of the river and the strait. It isdocumented that the river flow is at 18 knots depending onthe season while the strait current is at lower rate. Where thetwo currents meet, there is constant turbulence.

Page 11: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

11

Technical Description of the Project

Risk Factors (cont’d)

When the flow is toward high or low tide, ships entering orleaving the harbor must do so a high speeds or risk runningaground on the shallower sides of the river mouth. This highspeed maneuver in turn makes large waves which lash themoored boats at Parola. The turbulence also results in damageto the outriggers and complaints from the boat owners. Therehave been recorded instances where commuter have fall offthe outrigger planks as a result of the turbulence.

There have also been reports of the commuter outrigger boatsnot respecting the rules of sea traffic and actually moving intothe lane of the fast crafts forcing the larger boat to slow downand risk running aground. As a result of these violations, theoutriggers are no longer allowed to moor on the other bank ofthe river mouth while waiting for passengers.

TheDevelopment Options

In consideration of the existing situation, a range ofdevelopment options were deemed suitable options in the lightof the project requirement and the deemed optimal approachto the development. These development options for the ParolaStation Project are described and illustrated in the followingpages.

Option 1

This will pose the least disturbance on the non‐port handlingactivities in the site. This Option will consider the basicprovision of the Station requirement independent of thebigger site area that will be called the “Ecopark” of the site.If only to minimize the investment further, the Option willalso assume that the Coast facilities will be retained for themost part. Technically, only the commuter transaction,waiting lounge, dining areas and necessary shops could beprioritized for construction. The cost of breakwaterrehabilitation (facing the new PPA wharf), the filling of thedepressed area by the breakwater, and the Ecopark arealandscaping could be an optional investment, or a futureactivity, in so far as Option 1 is concerned. For purposes ofthis study though, the development estimate will includethe development of the whole site but excluding the largerpart of the Coast Guard area with its retained agencyoperations. See Figures 10 to 14 for details.

Page 12: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

12

Technical Description of the Project

Option 3

This option is is essentially a variation of Option 2. Option 3however seeks to frontally address the requirement of theprospective tourist trade by providing a convenient man‐made ‘docking bay’ primarily for them. This feature requirescutting away a substantial portion of the Parola grounds ifonly to create the special dock for the large boats of thefuture. This plan tends to ‘bring’ the terminal with itsrestaurant facilities and transaction center closer to theEcopark area. As a result, the whole development becomesmore integrative and synergistic overall while availing ofmore impressive area esthetics and vista. A downside is thatthe land site will be substantially smaller due to the creationof the dock. This new dock shall be designed to mainlyaccommodate the proposed large safer boats suitable fortourists and some of the commuters. See Figures 20 to 23 fordetails.

The Development Options (cont’d)

Option 2

The land use of the site maximizes the land use of the siteand will require the immediate relocation of the Coast Guardheadquarters and the illegal settlers and vendors. Since thedocking system under Option 2 essentially retains the oldway however, further technical studies will be necessary todetermine the viability of introducing larger boats in thefuture for the comfort of tourists. Regarding the depressedwater‐logged area inside the old Rotary Park, this will beconverted into a recreational pond within the park proper.This is deemed more suitable to do for this naturally low areainstead of filling it to acquire more land area which is notneeded at the moment. A given in this option is theagreement for the project to relocate the Coast Guardbuilding and to provide a site/lot for the use of DENR as well.See Figures 15 to 19 for details.

Page 13: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

13

Technical Description of the Project

The Parola Station Project (cont’d)

Figure  10a . Arial Perspective.

Figure 11.  Land Use Plan.

Parola Eco Port Option 1

Figure  10a . Terminal  and Eco Park.

Page 14: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

14

Technical Description of the Project

The Parola Station Project (cont’d)

Figure  12 .  Ferry Terminal  & Plaza.

Figure  13 .  Pier & Waiting Area. Figure  14 .  Commercial & Restaurant Building.

Parola Eco Port Option 1

Page 15: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

15

Technical Description of the Project

The Parola Station Project (cont’d)

Figure  16 .  Land Use Plan.

Figure  15a .  Aerial Perspective.

Parola Eco Port Option 2

Figure  15b .  Terminal and Eco Park.

Page 16: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

16

Technical Description of the Project

The Parola Station Project (cont’d)

Figure  17.  Ferry Terminal & Parking.

Figure  18.  Commercial Area Figure  19.  Restaurant Building & Pier.

Parola Eco Port Option 2

Page 17: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

17

Technical Description of the Project

The Parola Station Project (cont’d)

Figure  20.  Aerial Perspective.

Figure  22.  Land Use Plan.

Parola Eco Port Option 3

Figure  21.  Pier & Waiting Area.

Page 18: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

18

Technical Description of the Project

The Parola Station Project (cont’d)

Figure  23.  Ferry Terminal & Restaurant.

Parola Eco Port Option 3

Page 19: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

19

Technical Description of the Project

The Projects (cont’d)

The two commuter points on Guimaras operate from theirindividual municipal ports. Although originally built andoperated by the Philippine Ports Authority, the ownership,operations and management of the facilities have beenturned over to the respective LGU’s.

The Buenavista Station Project

Located along the provincial road off the coast of Buenavistatown in Guimaras (directly across the sea from the ParolaPort), the Buenavista site is an active commuter port muchlike the Parola Port. The site has an existing industrial T‐wharf that is partially roofed. This wharf protrudes out intothe ocean and services not only commuters to and from IloiloCity but also industrial and commercial cargo.

The town has implemented reclamation work for the portarea in the past which includes the site where the PNPoutpost is now located. Today, the plan for the Station underthis project takes stock of the existing situation and proposesthat the best approach is the redevelopment of the existingPNP reclaimed area and the T‐wharf. It is suggested that theland use of the reclaimed area which contains the small PNPoutpost be better rationalized by overbuilding on it. The newconstruction would be a two level building structure that canhouse the relocated PNP outpost; the Terminaladministrative facilities; the public toilets; and shops andrestaurants.

Regarding the existing T‐wharf, it is understood that theindustrial and commercial activities will be in the traversedock (the “T”) at the end of it, while the commuter activitieswill be alongside the long stretch leading to the said traversedock. Considering that the width of the wharf is nominaland trucks pass it to access the industrial zone, expansion ofthe wharf width to create a safe and spacious commuterpier with is envisioned. This new strip shall be roofed,equipped with the loading ramps and provided completewith dock furniture and necessary signages. Both sides ofthe wharf shall be expanded since tidal influences suggest toboat operators which side of the wharf is safer for loading

and unloading for that time.

Page 20: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

20

Technical Description of the Project

The Buenavista Station Project (cont’d)

Figure 24. Land Use Plan. Figure 25. Aerial Perspective.

Page 21: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

21

Technical Description of the Project

The Buenavista Station Project (cont’d)

Figure 26a. Pier & Waiting Area.

Figure  27. Ferry Terminal & Parking.

Figure 26b. Another view of the waiting area.

Page 22: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

22

Technical Description of the Project

The Projects (cont’d)

The Jordan Station Project

The existing Jordan port facility is a limited area found at theend of the road by the coast. This port faces a protruding partof the land just across the mouth of the Jordan River. Thetown had actually diverted the route of the meanderingJordan River by creating a diversion channel outlet of the rivermore directly to the sea at the other side. This Jordan Riverbypass will minimize the siltation on the original river path tothe open sea beside the dock. It is understood that the townhopes to convert this protruding land (that has now becomean ‘island’ of sorts due to the diversion channel outlet to thesea) across the port to become a tourism ecopark area.

Jordan is the seat of the Provincial Government. It also servesas the gateway to the adjacent municipalities and resort areasof the province. Jordan operates a municipal port. On eitherside of the port are a private facility with a port within aprotected lagoon and the Philippine Ports Authority Roll On –Roll Off (RORO) facility. The larger ships and the FF Cruz ferrywhich can carry vehicles and passengers use this RORO astheir port of call. There are a limited number of trips madedaily by the RORO ferry between Iloilo City and Jordan.Outrigger boats plying between Jordan and Iloilo City use themunicipal port.

Jordan commuter terminal also has a covered and fencedwalkway for the ticket line but has no roof cover at theloading and unloading area. Entry and egress is through thestern of the boats again mirroring the method at Ortiz onthe Iloilo City side. Without passenger handling rampscommuters have difficulty at low tide with the boat restinglower than the top of the breakwater.

The presence of existing private commercial establishmentsand roadways in the dock area allows for very limitedexpansion land for the port. It is for this reason that theJordan port officials adopted a reclamation project parallelto the road. Together, the lands of the existing port facilitiesand the proposed area for reclamation shall be the site forthe new Jordan Station. Considering the many technicalstudies and initiatives by the town already in making thereclamation area a reality, the pier and part of the Terminalis proposed to be built on this proposed reclaimed area.Meanwhile, the tightly grouped existing port facilities shallbe cleared and redeveloped as the location for therestaurant and parking facilities of the project. The newrestaurant and shop shall have a scenic view of the Straitand which service is expected to be complemented by theother private commercial stores already in the area.

The details of the project are shown in the succeedingfigures.

Page 23: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

23

Technical Description of the Project

The Jordan Station Project (cont’d)

Figure  28a. Aerial Perspective.

Figure  29. Land Use Plan.

Figure  28b. Another Aerial Perspective.

Page 24: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

24

Technical Description of the Project

The Jordan Station Project (cont’d)

Figure  30b. Another View of the Ferry Terminal & Restaurant.

Figure  31. Pier & Waiting Area.

Figure  30a. Ferry Terminal & Restaurant.

Page 25: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

25

Technical Description of the Project

Design & General Specifications

For the said new Ferry Stations in the various locations underthe proposed GIFTS system, the efficiency and quality ofdevelopment shall be the same.

In general, the Stations shall contain 

1) a pier area with loading ramps; 2) a terminal area for ticketing and ferry administration; 3) public toilets; 4) restaurants and shops; 5) a commercial area with stalls for the vendors as required;             6) a boat queue area out on the pier side. 

The sizes and amenities of the stations will however varydepending on the given land for development, the availablelength and configuration of the pier dock, and the passengercapacities to be sustained by the market.

The architecture of the structures shall be basic modern. Thisapproach will not only bring the image of the stations up tocurrent global design trends that is attractive to the public,but it should also tend to lower construction cost due to thetrends’ minimalist approach to the configuration of structures.The building material finishes shall be low maintenance (high‐quality) finishes. The sites’ open areas shall be either pavedas concrete roads and walks or landscaped with bothhardscaping (boardwalks, pavers, etc.) and softscaping(native plant variety) features as required.

The Stations shall be provided with all necessary modernequipment such as area airconditioning, electric generatorand water pumps as required especially in enclosed publiccongregation areas and transaction places. The loadingramps shall be light mechanical devices that drop downfrom their upright position pier side onto boat decks duringloading time. The mechanical ramps shall be standardequipment import unless locally fabricated alternatives thatare just as effective are sourced.

The project construction and development budgets aresummarized as follows:

Table 1. Summary of project construction and development budgets.

The details of the above budgets are detailed in Annexes 39to 43. The costs for A&E and allied services, preparatoryactivities such as relocation of existing features on the landand necessary demolition and clearing within the site arenot part of the estimate. The costing looked took intoconsideration industry standard unit costs for like worksbased on today’s prices of labor and materials, importedequipment and current building systems.

No.  Station  Total Amount  Remarks 1  Parola     1a  Option 1  P125,519,500  Excludes  the  development 

of  the  Coast  Guard  and DENR sites. 

1b  Option 2  153,668,000  Commercial and park areas are maximized. 

1c  Option 3  202,720,000  Includes land cut process to effect the new dock. 

2  Buenavista  83,000,000  Include  expansion  of existing pier. 

3  Jordan  56,989,000  Includes reclamation work. 

Page 26: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

26

Market AnalysisNotwithstanding tourist arrivals, efficient, safe and convenientterminal facilities for the commuting public, between Guimarasand Iloilo City has long been identified as a need which has notbeen realized. Over the years the volume of commuter traffichas grown steadily and now tops 4 million passengers eachyear. The ridership figures were submitted to the project teamby the boat operators association. They are based on actualdaily ticket sales for the two ports on Guimaras and the twopoints in Iloilo City. As more and more Iloilo City based workers,employees and population in general consider Guimaras aspossible place of residence while conducting their employmentor business on the Iloilo City side, the figure will further rise.For purposes of this study, a series of annual increases wereprojected averaging 2.5%. The resulting figure shows a a veryconservative 75% increase over current ridership in 20 years.

The recent floods which ravaged the residential neighborhoodsacross the river from the old central business district of IloiloCity bring home the distinct possibilities of Guimaras asalternative place of residence.

The major thrust of national government in the area of tourismis also expected to impact on the sub‐region. Guimaras offerspristine beaches and pastoral agricultural landscape with easyaccess, a friendly and hospitable people. Coupled with theheritage and cultural assets on the Iloilo side, it is easy to see acoming boom in tourism.

For purposes of this study, a low figure for tourist movementbetween Iloilo City and Guimaras was set at 50,000 visitors.This will normally happen during the Dinagyang Fesitival, themango festival and other major tourist related activities. It isprojected that the volume of visitor arrival will increasedramatically over the next five years to 130,000 arrivals, twoand a‐half times its present level. A tapering to a normal 2% ‐7% annual growth beyond is further projected.

The fly in the ointment for the growth in tourism is the modeof transportation. While the outriggers present a quaint andunique experience for the visitor, organized tours may not beable to take‐off over the issue of insurance. The small, woodenhull outriggers are not covered by the formal insuranceindustry. This poses a major threat to the development of thetourism sector especially for Guimaras. Unless alternatives areexplored, prospects of a tourism boom may not materialize.

To address this issue, an alternative development option ispresented which allows the use of larger, wood or steel hullcraft which conform to international maritime standards. It isalso expected that the boats now plying the strait will evolveover time. As costs to operate become more prohibitive, fuelprices soar, the need to find more cost effective vessels willdrive the market. Better boats would mean higher fares whichin turn will impact on the individual boat operator finances.

A wide disparity in commuter fares and tourist fares will spurthe improvement of the boat service. In the future, theimproved versions of the vessels will allow higher efficiency atthe loading and unloading points.

The experience is proven in Boracay . From the smalloutriggers with less than a dozen load in the early 1980’s tothe 30‐50 seaters in the early 2000’s they now have non‐outrigger, more luxurious vessels plying the route. As theregulatory framework there takes effect (no loading andunloading on the beach) the vessels will be forced to evolvefurther.

One method to influence this evolution process is to chargedocking and berthing fees on a per square meter areaoccupied. The smaller the space the lower will be the feescharged. The outriggers take up large space versus the limitedpassenger load.

Page 27: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

27

Institutional Proposal

The operation of the GIFT must be viewed as one seamlesssystem. Its sphere of influence transcends individualgovernment units, economic benefits impact on the sub‐region. It is the premise therefore, that the sustainability ofthe system must be established and assured.

Local government units are subject to change, as new leadersare elected. Priorities are modified. Commitments aresidelined. Personalities and personal differences may play ahand in the situation. Cooperation can be lost in the future.

Project borrowings and project revenues have to beequitably set among the co‐operators. What happens in theevent of default by one party? How will the revenues beshared? What happens in case the operation of one point isfinancially poor and requires subsidy? These must besquarely addressed.

An innovative approach is proposed for the implementationof GIFT. This will be done through the creation of a specialpurpose corporation to be jointly owned by the four localgovernment units directly impacted by the project. These areGuimaras Province, Iloilo City, Jordan and Buenavista. Pleasesee flowchart in Annex X.

Guimaras Province shall contribute cash for one‐half therelocation of the coast guard building at Parola and possiblydefray some facilities already committed for the twomunicipalities (ex. Expansion of Buenavista roofed area, roadwidening, street lighting etc.)

Iloilo City shall contribute the right to use its vested rightsover Parola, undertake the relocation of illegal settlerfamilies on the site and contribute the other one‐half of thecoast guard building. It shall provide the area with runningwater, improve the road and street lighting to the area andimplement a traffic plan for the public and privatetransportation to and from the area.

Jordan and Buenavista shall in turn contribute the use ofportions of their ports together with the currentimprovements found there.

For simplicity, it is proposed that the sharing be on equalbasis for all four LGUs. However, an appraisal of the land andimprovements may have to be undertaken to establish thebasis for the debt to equity ratio which the financialinstitution may require. To achieve an equal sharing, thedifferences may be contributed in the form of cash to thecorporation. However, the individual LGU may be contentwith the uneven set‐up then the additional cashcontribution will be unnecessary.

The financial projections should not show net deficits for theoperations. Instead, the terminal fee should be sufficient tocover all operating expenses including debt service. It is notadvisable to start with a low terminal fee since the publicmust be made aware that there is a cost attendant to safety,convenience and reliability.

There have been several instances where inter‐localcooperation has been achieved, in Cotabato and Bicol.

Page 28: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

28

Institutional Proposal

There is no prohibition regarding inviting theprivate sector to participate in the ownershipof the corporation. In fact, it may be advisableto invite the boat owners and operatorsassociation and potential developer / locatorsto join the corporation. Management of thecompany may be through the private sectorgroup /s. Where private ownership is morethan 50% it ceases to be a public corporationand moves out of the regulatory requirementsfor such corporations. (Ex. Fort BonifacioDevelopment Corporation, Camp John HayDevelopment Corporation)

The stability of the system, its falling outsideof the purview of political change, thepossibility of a highly professionalmanagement led by private enterprise is agoal which can be achieved.

The possible corporate setup for implementingthe projects are shown in figure 32.

Revenue Flows less Operating Expenses

CORPORATIONCORPORATION

EQUITY (Land or Land Lease, Port Improvement, Buildings or Cash)

JORDAN, ILOILO CITY, GUIMARAS, BUENAVISTA

May include Boat Assn., Others

EQUITYPRIVATE INVESTOR

Asian Development BankSpecial purpose vehicle loan window can be explored as 

financing source

LOAN LENDING AGENCY

Revenue sources from land leases, building leases and terminal fees. Expenses for 

operations and maintenance, debt service. 

• Solely for passenger ferry terminals between Iloilo City and Guimaras• Raises equity, contracts a loan to undertake the project• Repays from revenue stream

COMMUTER FERRY TERMINALSPAROLA – JORDAN – BUENAVISTA

FERRY TERMINALS PROJECT METRO ILOILO‐GUIMARAS ECONOMIC DEVELOPMENT COUNCIL (MIGEDC)

Und

ertakes

Project

Repays Loan

Revenue Flows less Operating ExpensesRevenue Flows less Operating Expenses

CORPORATIONCORPORATION

EQUITY (Land or Land Lease, Port Improvement, Buildings or Cash)

EQUITY (Land or Land Lease, Port Improvement, Buildings or Cash)

JORDAN, ILOILO CITY, GUIMARAS, BUENAVISTA

May include Boat Assn., Others

May include Boat Assn., Others

EQUITYPRIVATE INVESTOR

EQUITYPRIVATE INVESTORPRIVATE INVESTOR

Asian Development BankSpecial purpose vehicle loan window can be explored as 

financing source

Asian Development BankSpecial purpose vehicle loan window can be explored as 

financing source

LOAN LENDING AGENCY

LOAN LENDING AGENCYLENDING AGENCY

Revenue sources from land leases, building leases and terminal fees. Expenses for 

operations and maintenance, debt service. 

Revenue sources from land leases, building leases and terminal fees. Expenses for 

operations and maintenance, debt service. 

• Solely for passenger ferry terminals between Iloilo City and Guimaras• Raises equity, contracts a loan to undertake the project• Repays from revenue stream

• Solely for passenger ferry terminals between Iloilo City and Guimaras• Raises equity, contracts a loan to undertake the project• Repays from revenue stream

COMMUTER FERRY TERMINALSPAROLA – JORDAN – BUENAVISTA

FERRY TERMINALS PROJECT METRO ILOILO‐GUIMARAS ECONOMIC DEVELOPMENT COUNCIL (MIGEDC)

Und

ertakes

Project

Repays Loan

Figure  32. Ferry Terminals Project Implementation Plan.

Page 29: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

29

Schedule of Terminal Fees 

Passenger  Option 1  Option 2  Option 3 

Commuter  P 7.50 P 9.00 P10.00

Tourist  P20.00 P20.00 P20.00

Financial Viability

1. Income Projections. Based on the alternativedevelopment schemes, three sets of income projectionswere prepared. Annexes 1 to 6 present the three incomescenarios. The following were the relevant assumptions tothe projections.

a) Starting base for ridership for the commuter passengersis 4.2 million projected to increase to 7.5 million by the 20th

year. See Annexes 17 to 22 on fees and ridership projections.

b) Assumes that the Parola facility shall be used for bothBuenavista and Jordan commuter points.

c) The tourist ridership is projected at a base of 50,000annually and does not differentiate between domestic andinternational visitors. With the improved facilities formovement and the development of higher quality beachresorts on Guimaras, the traffic volume is expected toincrease dramatically by 150% over the next 5‐years.Succeeding years will show a more modest 2% ‐ 5% annualgrowth.

d) Fares were expected to increase at the rate of 5%annually against the average P12.60 per person per trip ofyear 2008. Should a higher quality boat go into operation,P20.00 was assumed as starting base fare.

e) The improved services and facilities would require aterminal fee to be charged above the fare rate. The faresaccrue entirely to the boat operators while the terminal feewould be the revenue for the operations, maintenance anddebt service of the project.

Table 2. Schedule of Terminal Fees

2. Other Revenue Sources. Commercial spaces weredesigned into all the facilities. These will allow restaurants,retail space and convenience stores to operate in theterminal compounds. The spaces will be leased out incommercial rates to chosen locators. Lease rates will rangefrom P500 – P750 per square meter. These specialtystructures may be postponed for implementation at a laterdate or entirely privatized to effectively reduce loan levelsand in turn drop the terminal fee rates.

3. Loan. It is assumed that 9%, 20 year money will beavailable with grace period of 5‐years on principalrepayment. The table on Annexes 13 to 14 presents thethree options with the corresponding Amortization Tablefor each option. It is assumed that the loan shall cover thetotal project cost following each design. Costs are based onthe current estimated cost to construct equivalentstructure in Metro Manila as of July 2008.

Page 30: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

30

Financial Viability

4. Equity. Each station has an existing project site withimprovements. For simplification purposes, eachparticipating local government unit will be expected tocontribute P50 million in value of land and improvements;relocation expenses or cash. In the actual practice, the sameshall have to be identified and valued by average of anumber of appraisals for land and improvements. Should itbe decided that it be equal sharing, the difference should becontributed in cash. The cash would effectively lower theloan component when taken up against the developmentcost.

5. A simplified tabulation of Areas and Costs is presented asAnnexes 7 to 11.

6. Annex 23 shows the carrying capacity of the improvedterminals. Loading and unloading cycles for the three pointswere projected to occur during a 6‐hour peak period. Thesewould be 3‐hours in the early morning for originating fromGuimaras points, a corresponding 3‐hour peak arrivals atParola and a reverse 3‐ hour peak in late afternoon. Giventhe volume of commuters, the boats would have between11‐15 minutes to load or unload. When taken in the contextof a 12‐hour operating day, the cycle increases the allowableloading and unloading per boat.

7. Annex 24 is an attempt to relate ridership to potentialsales capture rate from the point of view of a retailer. Over4‐million commuters will pass through the terminals.Assuming a catchment potential of 15% of this volume, at anaverage purchase of P50, the resulting potential sales wouldbe P32 million annually. Given a 40% gross operating profiton sales (higher for fast‐food outlets), the locators wouldgenerate a potential P13 million. If 20% of the amount isused for amortizing a 10 year loan at an interest rate of 12%and Debt/Equity of 60%/40% then a P25 million project canbe set up by the private proponent.

8. Annexes 25 to 26 tries to show the revenue stream ofthe boat operators from the fares generated for thecommuting public. Assuming that a larger boat is operatedfor the tourist trade with a P20 fare and limited trips per day,how would the revenue picture look. This is does not evenconsider the possibility of charters. The idea is to try toshow to the boat owners/operators the logic of upgradingtheir vessels.

Page 31: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

31

SUMMARY OF FINANCIAL HIGHLIGHTS 

(in P1,000,000)  Option 1  Option 2  Option 3 

Total Project Loan  P    271.5 P    305.2 P    353.3

Total Project Equity  P    200.0 P    200.0 P    200.0

Total Project Cost  P    471.5 P    505.2 P    553.3

Gross Revenue 20 years  P 1,609.9 P 1,849.7 P 2,056.1

Value Added Tax  P    193.1 P    222.0 P    246.7

Net Revenue  P 1,416.7 P 1,627.7 P 1,809.4

Depreciation  P    198.2 P    219.2 P    254.3

Interest  P     290.3 P    333.3 P    406.2

Total Operating Expense  P     806.5 P    935.7 P 1,008.4

Net Profit before Tax  P     610.3 P    692.0 P     801.0

Amortization  P     412.0 P    473.2 P    576.6

 

Financial Viability

Note in Table 3 that the interest and depreciation expensesare more than sufficient to cover the loan amortization total.The same is true on an annual basis which means that thecash flow for the project shall be positive. Considering alsothat the terminal fees will be collected on a daily basis, theproject may be interesting to the private sector to take up asa completely private venture. A sweetener would be thecapture rate income discussed in the previous section.

Table 3.Summary of Financial Highlights

Page 32: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

32

Next Steps

The next steps will involve the conduct of a FeasibilityStudy of the project. This will necessarily entail a numberof specific actions to provide the basis for the decision toproceed with the project. These actions include:

• Validation of the physical design concepts for each of thethree ports in consultation with MIGEDC, the LGUs andnational agencies concerned as to whether suchconcepts are consistent with objectives andcircumstances which may arise after the submission ofthis PFS report;

• A more detailed market analysis to reconfirm if thedesign concepts, particularly in terms of the capacity andfeatures of the port facilities, will meet the expecteddemand;

• Based on the two actions above, finalization of thearchitectural and engineering designs as well as relatedconstruction documents, phasing, timeframe, andbudgets;

• Firm up the revenue projections, project costs, cashflows, and repayment terms;

• Firm up funding source(s) and/or investors;

• Firm up inter‐local arrangements among LGUs concernedand establish the project institutional structure andmanagement systems.

The interesting feature about the ferry terminal system isthat there is the distinct possibility that the financialreturns may be sufficient to pursue the venture. Given thatthe land on the Iloilo City side will be available, that thesettler families and the hawkers can be organized to putorder into the site, there are enough features which makethe project feasible.

1. There is a distinct need to upgrade the terminal facilitieson the Iloilo City side as well as the Guimaras ports.

2. There is a growing demand for the services.

3. Tourism will play a major development role in the sub‐region in the immediate future.

4. Guimaras can offer a viable alternative for thedevelopment of residential communities which are lessprone to flooding, easy access at a relatively lower cost.

Page 33: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

33

Annexes

Projected Income Statement1 2 3 4 5 6 7 8 9 10

Year 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018GROSS REVENUEBuilding Leases 2.5% 16,965,000 16,965,000 17,389,125 17,389,125 17,389,125 17,813,250 17,813,250 17,813,250 18,237,375 18,237,375Terminal Fees 33,604,270 34,872,807 36,155,605 37,447,620 38,761,155 49,582,191 50,677,658 51,727,550 52,799,529 53,894,071

Sub‐Total 50,569,270 51,837,807 53,544,730 54,836,745 56,150,280 67,395,441 68,490,908 69,540,800 71,036,904 72,131,446Value Added Taxes 12% 6,068,312 6,220,537 6,425,368 6,580,409 6,738,034 8,087,453 8,218,909 8,344,896 8,524,428 8,655,773

NET REVENUE 44,500,958 45,617,270 47,119,363 48,256,336 49,412,246 59,307,988 60,271,999 61,195,904 62,512,475 63,475,672

EXPENSESMOOE 2.5% 12,451,000      12,762,275    13,081,332    13,408,365    13,743,574    14,087,164         14,439,343    14,800,326    15,170,334    15,549,593   Depreciation 9,909,183        9,909,183      9,909,183      9,909,183      9,909,183      9,909,183            9,909,183      9,909,183      9,909,183      9,909,183     Interest Expense 19,926,765      19,926,765      19,926,765      19,926,765      19,926,765      19,926,765         19,248,082      18,508,317      17,701,973      16,823,058     

Sub‐Total Expenses 42,286,948      42,598,223      42,917,280      43,244,314      43,579,523      43,923,112         43,596,608      43,217,826      42,781,491      42,281,835     

GROSS OPERATING PROFIT 2,214,009        3,019,047      4,202,082      5,012,022      5,832,723      15,384,876         16,675,391    17,978,077    19,730,984    21,193,837   

11 12 13 14 15 16 17 18 19 20Year 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028

GROSS REVENUEBuilding Leases 2.5% 18,237,375 18,661,500 18,661,500 18,661,500 19,085,625 19,085,625 19,085,625 19,509,750 19,509,750 19,509,750Terminal Fees 60,236,572 61,565,891 67,417,239 74,383,533 82,080,142 96,829,666 98,988,708 101,046,339 103,147,459 105,293,006

Sub‐Total 78,473,947 80,227,391 86,078,739 93,045,033 101,165,767 115,915,291 118,074,333 120,556,089 122,657,209 124,802,756Value Added Taxes 12% 9,416,874 9,627,287 10,329,449 11,165,404 12,139,892 13,909,835 14,168,920 14,466,731 14,718,865 14,976,331

NET REVENUE 69,057,073 70,600,104 75,749,291 81,879,629 89,025,875 102,005,456 103,905,413 106,089,358 107,938,343 109,826,425

EXPENSESMOOE 2.5% 15,938,333      16,336,791    16,745,211    17,163,841    17,592,937    18,032,760         18,483,579    18,945,669    19,419,311    19,904,793   Depreciation 9,909,183        9,909,183      9,909,183      9,909,183      9,909,183      9,909,183            9,909,183      9,909,183      9,909,183      9,909,183     Interest Expense 15,865,042      14,820,803    13,682,583    12,441,923    11,089,604    9,615,577            8,008,886      6,257,594      4,348,685      2,267,974     

Sub‐Total Expenses 41,712,558      41,066,777      40,336,977      39,514,948      38,591,725      37,557,520         36,401,649      35,112,446      33,677,179      32,081,951     

GROSS OPERATING PROFIT 27,344,515      29,533,327    35,412,313    42,364,682    50,434,151    64,447,936         67,503,764    70,976,912    74,261,164    77,744,474   

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry TerminalsMIGEDC ‐ Special Purpose Vehicle (SPV)

Income for Parola Option 1

Annex 1. Income Option 1

Page 34: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

34

Annexes

Terminal Operations Parola Jordan Buenavista TOTAL YearlyLight & Power 19,000        19,000        19,000        57,000        684,000              Manpower 9,295,000           Water 10,000              5,000                5,000                20,000              240,000              Cleaning Supplies 10,000              10,000            10,000            30,000            360,000             Garbage Collection Charges 10,000              10,000            10,000            30,000            360,000             Repairs and Maintenance 42,000              42,000            42,000            126,000          1,512,000          

Total  91,000              86,000            86,000            263,000          12,451,000       

Schedule of Light & Power Parola Jordan Buenavista TOTAL RATE TOTALPower Cost 15,000 15,000 15,000 45,000 540,000Bulb Replacements 2,000 2,000 2,000 6,000 72,000Fixtures Replacement 2,000 2,000 2,000 6,000 72,000

Total  19,000 19,000 19,000 57,000 684,000

Manpower Schedule Parola Jordan Buenavista TOTAL RATE TOTALTicketing 3 2 2 7 20,000 1,820,000Building Security 4 3 3 10 15,000 1,950,000Grounds Security 5 5 5 15 15,000 2,925,000Administrative Cost 4 3 3 10 20,000 2,600,000

Total Manpower 42 9,295,000

Other Expenses Parola Jordan Buenavista TOTAL RATE TOTALWater Consumption 10,000 5,000 5,000 20,000 240,000Cleaning Supplies 10,000 10,000 10,000 30,000 360,000Garbage Collection Schedule 10,000 10,000 10,000 30,000 360,000

Repairs and Maintenance Parola Jordan Buenavista TOTAL RATE TOTALToilets 2,000 2,000 2,000 6,000 72,000Airconditioning 0 0Loading Ramps 20,000 20,000 20,000 60,000 720,000Building 20,000 20,000 20,000 60,000 720,000

Total  42,000 42,000 42,000 126,000 1,512,000

Depreciation Schedule Parola Op‐1 Jordan Buenavista TOTAL PERIOD ANNUALBuildings 68,635,000 10,200,000 26,500,000 105,335,000 25 4,213,400          Infrastructure 54,784,500 45,889,000 60,600,000 161,273,500 30 5,375,783          Equipment 2,100,000 1,500,000 1,200,000 4,800,000 15 320,000             Total Annual Depreciation 9,909,183         

MIGEDC ‐ Special Purpose Vehicle (SPV)Schedule of Operating Expenses

MIG Commuter Ferry TerminalsMETRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCIL

Income for Parola Option 1 (cont’d)

Annex 2.Income Option 1

Page 35: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

35

Annexes

Projected Income Statement1 2 3 4 5 6 7 8 9 10

Year 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018GROSS REVENUE

Building Leases 2.5% 16,965,000 16,965,000 17,389,125 17,389,125 17,389,125 17,813,250 17,813,250 17,813,250 18,237,375 18,237,375Terminal Fees 40,095,124 41,571,368 43,041,726 44,505,894 45,995,886 58,806,473 60,086,426 61,324,492 62,588,411 63,878,730

Sub‐Total 57,060,124 58,536,368 60,430,851 61,895,019 63,385,011 76,619,723 77,899,676 79,137,742 80,825,786 82,116,105Value Added Taxes 12% 6,847,215 7,024,364 7,251,702 7,427,402 7,606,201 9,194,367 9,347,961 9,496,529 9,699,094 9,853,933

NET REVENUE 50,212,909 51,512,004 53,179,149 54,467,617 55,778,809 67,425,356 68,551,715 69,641,213 71,126,691 72,262,172

EXPENSESMOOE 2.5% 15,001,000      15,376,025      15,760,426      16,154,436      16,558,297      16,972,255         17,396,561      17,831,475      18,277,262      18,734,193     Depreciation 10,961,007      10,961,007      10,961,007      10,961,007      10,961,007      10,961,007         10,961,007      10,961,007      10,961,007      10,961,007     Interest Expense 22,883,130      22,883,130      22,883,130      22,883,130      22,883,130      22,883,130         22,103,756      21,254,239      20,328,265      19,318,953     

Sub‐Total Expenses 48,845,137      49,220,162      49,604,562      49,998,573      50,402,434      50,816,391         50,461,324      50,046,720      49,566,533      49,014,153     

GROSS OPERATING PROFIT 1,367,772        2,291,842      3,574,587      4,469,044      5,376,375      16,608,965        18,090,391    19,594,493    21,560,158    23,248,019   

11 12 13 14 15 16 17 18 19 20Year 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028

GROSS REVENUEBuilding Leases 2.5% 18,237,375 18,661,500 18,661,500 18,661,500 19,085,625 19,085,625 19,085,625 19,509,750 19,509,750 19,509,750Terminal Fees 71,453,298 73,006,953 80,002,407 88,227,218 97,308,195 114,712,610 117,229,310 119,651,753 122,124,981 124,650,079

Sub‐Total 89,690,673 91,668,453 98,663,907 106,888,718 116,393,820 133,798,235 136,314,935 139,161,503 141,634,731 144,159,829Value Added Taxes 12% 10,762,881 11,000,214 11,839,669 12,826,646 13,967,258 16,055,788 16,357,792 16,699,380 16,996,168 17,299,180

NET REVENUE 78,927,793 80,668,238 86,824,238 94,062,072 102,426,562 117,742,446 119,957,143 122,462,123 124,638,563 126,860,650

EXPENSESMOOE 2.5% 19,202,548      19,682,612    20,174,677    20,679,044    21,196,020    21,725,921        22,269,069    22,825,796    23,396,440    23,981,351   Depreciation 10,961,007      10,961,007    10,961,007    10,961,007    10,961,007    10,961,007        10,961,007    10,961,007    10,961,007    10,961,007   Interest Expense 18,218,803      17,019,640    15,712,552    14,287,826    12,734,875    11,042,158        9,197,097      7,185,980      4,993,863      2,604,455     

Sub‐Total Expenses 48,382,358      47,663,258    46,848,236    45,927,877    44,891,902    43,729,085        42,427,172    40,972,782    39,351,310    37,546,813   

GROSS OPERATING PROFIT 30,545,435      33,004,980    39,976,002    48,134,195    57,534,660    74,013,361        77,529,971    81,489,341    85,287,254    89,313,837   

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry TerminalsMIGEDC ‐ Special Purpose Vehicle (SPV)

Income for Parola Option 2

Annex 3.Income Option 2

Page 36: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

36

Annexes

Terminal Operations Parola Jordan Buenavista TOTAL YearlyLight & Power 54,000        44,000        44,000        142,000      1,704,000           Manpower 10,465,000        Water 10,000              5,000                5,000                20,000              240,000              Cleaning Supplies 10,000              10,000            10,000            30,000            360,000             Garbage Collection Charges 10,000              10,000            10,000            30,000            360,000             Repairs and Maintenance 52,000              52,000            52,000            156,000          1,872,000          

Total  136,000            121,000          121,000          378,000          15,001,000       

Schedule of Light & Power Parola Jordan Buenavista TOTAL RATE TOTALPower Cost 50,000 40,000 40,000 130,000 1,560,000Bulb Replacements 2,000 2,000 2,000 6,000 72,000Fixtures Replacement 2,000 2,000 2,000 6,000 72,000

Total  54,000 44,000 44,000 142,000 1,704,000

Manpower Schedule Parola Jordan Buenavista TOTAL RATE TOTALTicketing 3 2 2 7 20,000 1,820,000Building Security 5 4 4 13 15,000 2,535,000Grounds Security 6 6 6 18 15,000 3,510,000Administrative Cost 4 3 3 10 20,000 2,600,000

Total Manpower 48 10,465,000

Other Expenses Parola Jordan Buenavista TOTAL RATE TOTALWater Consumption 10,000 5,000 5,000 20,000 240,000Cleaning Supplies 10,000 10,000 10,000 30,000 360,000Garbage Collection Schedule 10,000 10,000 10,000 30,000 360,000

Repairs and Maintenance Parola Jordan Buenavista TOTAL RATE TOTALToilets 2,000 2,000 2,000 6,000 72,000Airconditioning 10,000 10,000 10,000 30,000 360,000Loading Ramps 20,000 20,000 20,000 60,000 720,000Building 20,000 20,000 20,000 60,000 720,000

Total  52,000 52,000 52,000 156,000 1,872,000

Depreciation Schedule Parola Op‐2 Jordan Buenavista TOTAL PERIOD ANNUALBuildings 85,666,000 10,200,000 26,500,000 122,366,000 25 4,894,640          Infrastructure 65,902,000 45,889,000 60,600,000 172,391,000 30 5,746,367          Equipment 2,100,000 1,500,000 1,200,000 4,800,000 15 320,000             Total Annual Depreciation 10,961,007       

Schedule of Operating Expenses

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry TerminalsMIGEDC ‐ Special Purpose Vehicle (SPV)

Income for Parola Option 2 (cont’d)

Annex 4.Income Option 2

Page 37: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

37

Annexes

Income for Parola Option 3 

Projected Income Statement1 2 3 4 5 6 7 8 9 10

Year 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018GROSS REVENUE

Building Leases 2.5% 16,965,000 16,965,000 17,389,125 17,389,125 17,389,125 17,813,250 17,813,250 17,813,250 18,237,375 18,237,375Terminal Fees 44,422,360 46,037,076 47,632,474 49,211,410 50,819,039 64,955,994 66,358,937 67,722,454 69,114,332 70,535,170

Sub‐Total 61,387,360 63,002,076 65,021,599 66,600,535 68,208,164 82,769,244 84,172,187 85,535,704 87,351,707 88,772,545Value Added Taxes 12% 7,366,483 7,560,249 7,802,592 7,992,064 8,184,980 9,932,309 10,100,662 10,264,285 10,482,205 10,652,705

NET REVENUE 54,020,877 55,441,826 57,219,007 58,608,471 60,023,185 72,836,935 74,071,525 75,271,420 76,869,502 78,119,839

EXPENSESMOOE 2.5% 13,621,000      13,961,525      14,310,563      14,668,327      15,035,035      15,410,911         15,796,184      16,191,089      16,595,866      17,010,763     Depreciation 12,712,633      12,712,633      12,712,633      12,712,633      12,712,633      12,712,633         12,712,633      12,712,633      12,712,633      12,712,633     Interest Expense 27,888,660      27,888,660      27,888,660      27,888,660      27,888,660      27,888,660         26,938,803      25,903,460      24,774,935      23,544,843     

Sub‐Total Expenses 54,222,293      54,562,818      54,911,856      55,269,621      55,636,329      56,012,205         55,447,621      54,807,182      54,083,434      53,268,239     

GROSS OPERATING PROFIT (201,417)          879,008          2,307,150      3,338,851      4,386,856      16,824,730        18,623,904    20,464,238    22,786,068    24,851,600   

11 12 13 14 15 16 17 18 19 20Year 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028

GROSS REVENUEBuilding Leases 2.5% 18,237,375 18,661,500 18,661,500 18,661,500 19,085,625 19,085,625 19,085,625 19,509,750 19,509,750 19,509,750Terminal Fees 78,931,116 80,634,327 88,392,519 97,456,340 107,460,230 126,634,572 129,389,712 132,055,363 134,776,663 137,554,795

Sub‐Total 97,168,491 99,295,827 107,054,019 116,117,840 126,545,855 145,720,197 148,475,337 151,565,113 154,286,413 157,064,545Value Added Taxes 12% 11,660,219 11,915,499 12,846,482 13,934,141 15,185,503 17,486,424 17,817,040 18,187,814 18,514,370 18,847,745

NET REVENUE 85,508,272 87,380,328 94,207,536 102,183,700 111,360,353 128,233,773 130,658,296 133,377,299 135,772,043 138,216,799

EXPENSESMOOE 2.5% 17,436,032      17,871,932    18,318,731    18,776,699    19,246,116    19,727,269        20,220,451    20,725,962    21,244,111    21,775,214   Depreciation 12,712,633      12,712,633    12,712,633    12,712,633    12,712,633    12,712,633        12,712,633    12,712,633    12,712,633    12,712,633   Interest Expense 22,204,043      20,742,571    19,149,566    17,413,191    15,520,543    13,457,555        11,208,899    8,757,864      6,086,236      3,174,161     

Sub‐Total Expenses 52,352,708      51,327,137    50,180,930    48,902,524    47,479,292    45,897,458        44,141,984    42,196,460    40,042,981    37,662,009   

GROSS OPERATING PROFIT 33,155,564      36,053,191    44,026,606    53,281,176    63,881,060    82,336,315        86,516,313    91,180,839    95,729,062    100,554,790 

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry TerminalsMIGEDC ‐ Special Purpose Vehicle (SPV)

Annex 5. Income Option 3

Page 38: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

38

Annexes

Income for Parola Option 3 (cont’d)

Terminal Operations Parola Jordan Buenavista TOTAL YearlyLight & Power 19,000        19,000        19,000        57,000        684,000              Manpower 10,465,000        Water 10,000              5,000                5,000                20,000              240,000              Cleaning Supplies 10,000              10,000            10,000            30,000            360,000             Garbage Collection Charges 10,000              10,000            10,000            30,000            360,000             Repairs and Maintenance 42,000              42,000            42,000            126,000          1,512,000          

Total  91,000              86,000            86,000            263,000          13,621,000       

Schedule of Light & Power Parola Jordan Buenavista TOTAL RATE TOTALPower Cost 15,000 15,000 15,000 45,000 540,000Bulb Replacements 2,000 2,000 2,000 6,000 72,000Fixtures Replacement 2,000 2,000 2,000 6,000 72,000

Total  19,000 19,000 19,000 57,000 684,000

Manpower Schedule Parola Jordan Buenavista TOTAL RATE TOTALTicketing 3 2 2 7 20,000 1,820,000Building Security 5 4 4 13 15,000 2,535,000Grounds Security 6 6 6 18 15,000 3,510,000Administrative Cost 4 3 3 10 20,000 2,600,000

Total Manpower 10,465,000

Other Expenses Parola Jordan Buenavista TOTAL RATE TOTALWater Consumption 10,000 5,000 5,000 20,000 240,000Cleaning Supplies 10,000 10,000 10,000 30,000 360,000Garbage Collection Schedule 10,000 10,000 10,000 30,000 360,000

Repairs and Maintenance Parola Jordan Buenavista TOTAL RATE TOTALToilets 2,000 2,000 2,000 6,000 72,000Airconditioning 0 0Loading Ramps 20,000 20,000 20,000 60,000 720,000Building 20,000 20,000 20,000 60,000 720,000

Total  42,000 42,000 42,000 126,000 1,512,000

Depreciation Schedule Parola Op‐3 Jordan Buenavista TOTAL PERIOD ANNUALBuildings 70,325,000 10,200,000 26,500,000 107,025,000 25 4,281,000          Infrastructure 136,860,000 45,889,000 60,600,000 243,349,000 30 8,111,633          Equipment 2,100,000 1,500,000 1,200,000 4,800,000 15 320,000             Total Annual Depreciation 12,712,633       

Schedule of Operating Expenses

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry TerminalsMIGEDC ‐ Special Purpose Vehicle (SPV)

Annex 6.Income Option 3

Page 39: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

39

Annexes

Areas & Costs

PAROLA OPTION 1

Details

Total

a 400 sqm 10,600,000b 1,590 sqm 27,825,000

38,425,000

a 570 sqm 15,105,000b 570 sqm 15,105,000

30,210,000

a Ecopark lawn area including boardwalks 5,329 sqm 10,658,000b 1,047 sqm 2,617,500c 811 sqm 2,433,000d 452 sqm 1,356,000

17,064,500

1,400 sqm 6,300,000

a 260 lm 20,800,000b 114 lm 9,120,000

29,920,000

a 7 units 2,100,000

a 1 lot 1,500,000

125,519,500

Sub‐Total

4  Roads and Parking

1 Specialty Building Structure

Sub‐Total

Sub‐Total

Ground Floor (Shops/Flea Market)Second Floor (Restaurant)

Sub‐TotalPPA wharf side

6  Equipment Number of imported boarding ramps

7  Miscellaneous

Commercial Site (Restaurant and Shops)

Total

Clearing, Grubbing, Demolition

Pier side

Terminal AreaPier Arcade

Ecopark LagoonTerminal Site

5 Repair/Enhancement of Shore Protection

3  Landscaping and Related Site Works

2 Commercial Building Structure

Annex 7. Areas & Costs

Page 40: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

40

Annexes

Areas & Costs (cont’d)

PAROLA OPTION 2

Details

Total

a 488 sqm 12,932,000b 1,460 sqm 25,550,000c 200 sqm 4,700,000

43,182,0002 Commercial Building Structurea 552 sqm 9,660,000b 1,416 sqm 37,524,000

47,184,000

a 4,300 sqm 8,600,000b 1,000 sqm 2,500,000c 202 sqm 606,000d 354 sqm 1,062,000e Commercial Area (Flea Market site) 138 sqm 414,000

13,182,000

a 1,220 sqm 5,490,000b 1,300 sqm 5,850,000

11,340,000

a 370 lm 29,600,000b 116 lm 9,280,000

38,880,000

a 7 units 2,100,000

a 1 lot 2,500,000

158,368,000

Terminal Site

Parking

Pier side

Driveway4  Roads and Parking

5  Repair/Enhancement of Shore Protection

1 Specialty Building StructureTerminal AreaPier ArcadeCoast Guard (Office)

Shops/Flea MarketRestaurant

Ecopark lawn area including boardwalksEcopark Lagoon

Sub‐Total

Sub‐Total

Sub‐Total

Sub‐Total

Sub‐Total

Restaurant

PPA wharf side

Total

Clearing, grubbing, demolition

3  Landscaping and Related Site Works

6  Equipment Number of imported boarding ramps

7  Miscellaneous

Annex 8. Areas & Costs

Page 41: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

41

Annexes

Areas & Costs (cont’d)

PAROLA OPTION 3

Details

Total1 Specialty Building Structurea 1,300 sqm 34,450,000b 1,600 sqm 28,000,000c 200 sqm 4,700,000

67,150,000450 sqm 7,875,000

a 3,800 sqm 7,600,000b 200 sqm 600,000c Driveway and Parking Landscape 100 sqm 300,000d 240 sqm 720,000

9,220,000

a 800 sqm 3,600,000b 600 sqm 2,700,000

6,300,000

a 160 lm 12,800,000b 164 lm 13,120,000

25,920,000

a 62,400 cum 49,920,000b 130 lm 45,500,000

95,420,000

a 7 units 2,100,000

213,985,000

Earthworks (20m depth, for big vessels)Retaining structure and Shore Protection

7  Equipment Number of imported boarding ramps

Sub‐Total

DrivewayParking

5  Repair/Enhancement of Shore ProtectionPier side

Sub‐Total

PPA wharf side

6  Land cut for additional harbor

3  Landscaping and Related Site WorksEcopark lawn area including boardwalksTerminal and Restaurant Site Landscape

Commercial Site Landscape

4  Roads and ParkingSub‐Total

Terminal Area

Sub‐Total

Pier Arcade (Piers 1 and 2)Coast Guard (Office)

2 Commercial Building Structure (Flea Market)

Sub‐Total

Total

Annex 9. Areas & Costs

Page 42: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

42

Annexes

Areas & Costs (cont’d)

JORDAN

Details

Total

a  75          sqm 1,987,500b  280        sqm 4,900,000

6,887,500

a  125        sqm 3,312,500

a  115        sqm 345,000b 270        sqm 810,000c  55          sqm 110,000d  50          sqm 100,000

1,365,000

730        sqm 3,285,000

a 2,989     cum 2,989,000b 95          lm 33,250,000

36,239,000

6  Repair of existing shore protection 30          lm 3,000,000

1            lot 2,000,000a b c  Chairs, fans, etc. for waiting area

57,589,000

Dredging, sand piling

Pier AreaRestaurant AreaParking

4  Roads and Parking

Retaining structure and shore protection

Terminal Area

Total

Sub‐Total

Signages

5  Reclamation (dredging, sand piling)

units

8  MiscellaneousRailings

a  5           

Pier Arcade

2 Commercial Building Structure Restaurant  

3  Landscaping and Related Site Works (inclusive of fencing)

Sub‐Total

1,500,000

7  Equipment Number of boarding ramps (cable assisted reaction systems)

Terminal Area1 Specialty Building Structure

Sub‐Total

Annex 10. Areas  & Costs

Page 43: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

43

Annexes

Areas & Costs (cont’d)

BUENAVISTA

Details

Total

a 120 sqm 3,180,000b 30 sqm 795,000c 40 sqm 1,060,000d 190 sqm 5,035,000e 200 sqm 5,300,000f 420 sqm 11,130,000

26,500,000

430 sqm 27,950,000

a  500 sqm 2,250,000

a 80 lm 6,400,000b 105 lm 21,000,000

27,400,000

a 4 units 1,200,000

1 lot 3,000,000abc

88,300,000Total

Repair/enhancement of ExistingNew

Number of imported boarding ramps

Chairs, fans, etc.

5  Equipment

1 Specialty Building StructureTerminal AreaStairwayToilets

RailingsSignages

3  Roads and Parking

6  Miscellaneous

4  Shore Protection

Sub‐Total

Sub‐Total

2  Pier Widening (including waiting sheds)

2/F Restaurant

Parking

PNP Outpost1/F shops

Annex 11. Areas  & Costs

Page 44: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

44

Annexes

Loan

PROJECT COST ESTIMATES LAND, ETC. OPTION 1 OPTION 2 OPTION 3GUIMARAS PROVINCE (CASH) 50,000,000           

50,000,000            125,519,500 158,368,000 213,985,00050,000,000            57,589,000 57,589,000 57,589,00050,000,000           88,300,000 88,300,000 88,300,000

200,000,000 271,408,500 304,257,000 359,874,000

FINANCIAL PLAN OPTION 1 OPTION 2 OPTION 3Equity 47% 200,000,000        44% 200,000,000    39% 200,000,000   Debt 53% 221,408,500        56% 254,257,000    61% 309,874,000   

TOTAL PROJECT COST 100% 421,408,500     100% 454,257,000 100% 509,874,000

LOAN TERMSPeriod (Years) 20Grace Period (Years) 5Principal Repayment (Years) 15Interest (per Year) 9%Annual Amortization at year end

TOTAL TERMINAL SYSTEM

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry TerminalsSchedule of Loans & Interest24 July, 2008

PAROLA  (inclusive of Relocation Action Plan)

JORDANBUENAVISTA

Annex 12. Loan

Page 45: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

45

Annexes

Loan (cont’d)

1 2 3 4 5 6 7 8 9 102009 2010 2011 2012 2013 2014 2015 2016 2017 2018

BEGINNING LOAN BALANCE 221,408,500         221,408,500  221,408,500    221,408,500  221,408,500    221,408,500    213,867,574  205,647,964  196,688,590  186,922,872 INTEREST EXPENSE 19,926,765            19,926,765    19,926,765       19,926,765    19,926,765       19,926,765      19,248,082    18,508,317    17,701,973    16,823,058   AMORTIZATION 0 0 0 0 0 27,467,691      27,467,691    27,467,691    27,467,691    27,467,691   PRINCIPAL REPAYMENT 0 0 0 0 0 7,540,926         8,219,609      8,959,374      9,765,718      10,644,633   ENDING BALANCE 221,408,500         221,408,500  221,408,500    221,408,500  221,408,500    213,867,574    205,647,964  196,688,590  186,922,872  176,278,239 

11 12 13 14 15 16 17 18 19 202019 2020 2021 2022 2023 2024 2025 2026 2027 2028

BEGINNING LOAN BALANCE 176,278,239         164,675,590  152,028,702    138,243,594  123,217,826    106,839,739    88,987,625    69,528,820    48,318,723    25,199,717   INTEREST EXPENSE 15,865,042            14,820,803    13,682,583       12,441,923    11,089,604       9,615,577         8,008,886      6,257,594      4,348,685      2,267,974     AMORTIZATION 27,467,691            27,467,691    27,467,691       27,467,691    27,467,691       27,467,691      27,467,691    27,467,691    27,467,691    27,467,691   PRINCIPAL REPAYMENT 11,602,650            12,646,888    13,785,108       15,025,768    16,378,087       17,852,115      19,458,805    21,210,097    23,119,006    25,199,717   ENDING BALANCE 164,675,590         152,028,702  138,243,594    123,217,826  106,839,739    88,987,625      69,528,820    48,318,723    25,199,717    0                     

Schedule of Loans & Interest24 July, 2008

LOAN SCHEDULE OPTION 1

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry Terminals

LOAN SCHEDULE OPTION 1

Annex 13. Loan

Page 46: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

46

Annexes

Loan (cont’d)

1 2 3 4 5 6 7 8 9 102009 2010 2011 2012 2013 2014 2015 2016 2017 2018

BEGINNING LOAN BALANCE 254,257,000         254,257,000  254,257,000    254,257,000  254,257,000    254,257,000    245,597,291  236,158,208  225,869,607  214,655,032 INTEREST EXPENSE 22,883,130            22,883,130    22,883,130       22,883,130    22,883,130       22,883,130      22,103,756    21,254,239    20,328,265    19,318,953   AMORTIZATION 0 0 0 0 0 31,542,839      31,542,839    31,542,839    31,542,839    31,542,839   PRINCIPAL REPAYMENT 0 0 0 0 0 8,659,709         9,439,083      10,288,601    11,214,575    12,223,886   ENDING BALANCE 254,257,000         254,257,000  254,257,000    254,257,000  254,257,000    245,597,291    236,158,208  225,869,607  214,655,032  202,431,146 

11 12 13 14 15 16 17 18 19 202019 2020 2021 2022 2023 2024 2025 2026 2027 2028

BEGINNING LOAN BALANCE 202,431,146         189,107,110  174,583,910    158,753,623  141,498,609    122,690,645    102,189,964  79,844,221    55,487,361    28,938,385   INTEREST EXPENSE 18,218,803            17,019,640    15,712,552       14,287,826    12,734,875       11,042,158      9,197,097      7,185,980      4,993,863      2,604,455     AMORTIZATION 31,542,839            31,542,839    31,542,839       31,542,839    31,542,839       31,542,839      31,542,839    31,542,839    31,542,839    31,542,839   PRINCIPAL REPAYMENT 13,324,036            14,523,199    15,830,287       17,255,013    18,807,964       20,500,681      22,345,743    24,356,859    26,548,977    28,938,385   ENDING BALANCE 189,107,110         174,583,910  158,753,623    141,498,609  122,690,645    102,189,964    79,844,221    55,487,361    28,938,385    0                     

1 2 3 4 5 6 7 8 9 102009 2010 2011 2012 2013 2014 2015 2016 2017 2018

BEGINNING LOAN BALANCE 309,874,000         309,874,000  309,874,000    309,874,000  309,874,000    309,874,000    299,320,038  287,816,219  275,277,057  261,609,369 INTEREST EXPENSE 27,888,660            27,888,660    27,888,660       27,888,660    27,888,660       27,888,660      26,938,803    25,903,460    24,774,935    23,544,843   AMORTIZATION 0 0 0 0 0 38,442,622      38,442,622    38,442,622    38,442,622    38,442,622   PRINCIPAL REPAYMENT 0 0 0 0 0 10,553,962      11,503,819    12,539,162    13,667,687    14,897,779   ENDING BALANCE 309,874,000         309,874,000  309,874,000    309,874,000  309,874,000    299,320,038    287,816,219  275,277,057  261,609,369  246,711,590 

11 12 13 14 15 16 17 18 19 202019 2020 2021 2022 2023 2024 2025 2026 2027 2028

BEGINNING LOAN BALANCE 246,711,590         230,473,011  212,772,960    193,479,904  172,450,474    149,528,394    124,543,327  97,309,605    67,624,847    35,268,461   INTEREST EXPENSE 22,204,043            20,742,571    19,149,566       17,413,191    15,520,543       13,457,555      11,208,899    8,757,864      6,086,236      3,174,161     AMORTIZATION 38,442,622            38,442,622    38,442,622       38,442,622    38,442,622       38,442,622      38,442,622    38,442,622    38,442,622    38,442,622   PRINCIPAL REPAYMENT 16,238,579            17,700,051    19,293,056       21,029,431    22,922,080       24,985,067      27,233,723    29,684,758    32,356,386    35,268,461   ENDING BALANCE 230,473,011         212,772,960  193,479,904    172,450,474  149,528,394    124,543,327    97,309,605    67,624,847    35,268,461    0                     

LOAN SCHEDULE OPTION 2

LOAN SCHEDULE OPTION 3

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry TerminalsSchedule of Loans & Interest24 July, 2008

LOAN SCHEDULE OPTION 3

LOAN SCHEDULE OPTION 2

Annex 14. Loan

Page 47: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

47

Annexes

Revenue Sources

ASSUMPTIONSLand Appraisal 6,000COA Floor  4%

COMMUTER TRAFFIC* Daily Yearly Daily YearlyBuenavista 4,800              1,728,000Jordan 6,870              2,473,200

TOTAL 11,670           4,201,200 139 50,000

PAROLA OPTION 1 Land Area Bldg Area Lease Rate Month Year PAROLA OPTION 2 Land Area Bldg Area Lease Rate Month YearRestaurants 1,022 570 750 427,500 5,130,000 Restaurants 1,770 1,416 750 1,062,000 12,744,000Flea Market 570 570 500 285,000 3,420,000 Flea Market 690 552 500 276,000 3,312,000

Total on Lease  712,500 8,550,000 Total on Lease  1,338,000 16,056,000

PAROLA OPTION 3 Land Area Bldg Area Lease Rate Month YearRestaurants 1,110 1,040 750 780,000 9,360,000Flea Market 690 450 500 225,000 2,700,000

Total on Lease  1,005,000 12,060,000

JORDAN Land Area Bldg Area Lease Rate Month YearRestaurants 180 125 750 93,750 1,125,000Flea Market 0 0 500 0 0

Total on Lease  93,750 1,125,000

BUENAVISTA Land Area Bldg Area Lease Rate Month YearRestaurants 420 420 750 315,000 3,780,000Flea Market 200 200 500 100,000 1,200,000

Total on Lease  415,000 4,980,000

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry Terminals

* Source: Buenavista/Jordan Boat Operators Association

Domestic Tourist

Annex 15. Revenue Sources

Page 48: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

48

Annexes

Revenue Sources (cont’d)

TOTAL AREA LEASED Parola Op‐1 Jordan BuenavRestaurants 570 125 420Flea Market 570 0 200

BUILDING LEASE INCOME Parola Op‐1 Jordan BuenavRestaurants, etc. 427,500 93,750 315,000Flea Market 285,000 0 0Gross Monthly Income 712,500 93,750 315,000Gross Annual Lease Income 8,550,000 1,125,000 3,780,000

TOTAL AREA LEASED Parola Op‐2 Jordan BuenavRestaurants 1,416 125 420Flea Market 552 0 200

BUILDING LEASE INCOME Parola Op‐2 Jordan BuenavRestaurants, etc. 1,062,000 93,750 315,000Flea Market 276,000 0 100,000Gross Monthly Income 1,338,000 93,750 415,000Gross Annual Lease Income 16,056,000 1,125,000 3,780,000

TOTAL AREA LEASED Parola Op‐3 Jordan BuenavRestaurants 1,040 125 420Flea Market 450 0 200

BUILDING LEASE INCOME Parola Op‐3 Jordan Buenav Total SystemRestaurants, etc. 780,000 93,750 315,000 1,188,750     Flea Market 225,000 0 0 225,000         Gross Monthly Income 1,005,000 93,750 315,000 1,413,750     Gross Annual Lease Income 12,060,000 1,125,000 3,780,000 16,965,000   

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry Terminals

Annex 16.Revenue Sources

Page 49: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

49

Annexes

Parola Option 1 Terminal Fees

Projected Commuter & Tourist Traffic, 5‐Year Periods

BASE YEAR COMPUTATIONCOMMUTER TRAFFIC* Daily Yearly

Buenavista 4,800 1,728,000Jordan 6,870 2,473,200

TOTAL 11,670 4,201,200

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year Data 4,201,200           50,000            Assumed Annual % Growth Rate 3.0% 15.0% 3.2% 20.0% 2.8% 25.0% 2.5% 25.0% 2.5% 20.0%Annual Commuter Traffic 4,327,236          57,500           4,465,708          69,000           4,590,747           86,250           4,705,516          107,813         4,823,154      129,375      Daily Commuter Traffic 12,020                160                 12,405                192                 12,752                 240                 13,071                299                 13,398           359              

Average Fares 12.59 20.00Annual Fare Increase vs Base Year 5% 100% 5% 0% 5% 10% 5% 0% 5% 10%One Way Fare  13.22 40.00 13.88 40.00 14.57 44.00 15.30 44.00 16.07 48.40Total Fares Generation 57,197,939        2,300,000      61,979,687        2,760,000      66,900,874         3,795,000      72,002,066        4,743,750      77,492,223   6,261,750   

Terminal Fee (Passenger Cost) 7.50 20.00 32,454,270        1,150,000      33,492,807        1,380,000      34,430,605         1,725,000      35,291,370        2,156,250      36,173,655   2,587,500   Total Terminal Fee

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year DataAssumed Annual % Growth Rate 2.0% 7.0% 2.0% 5.0% 2.0% 3.0% 2.0% 3.0% 2.0% 3.0%Annual Commuter Traffic 4,919,617           138,431           5,018,009            145,353           5,118,370            149,713           5,220,737            154,205           5,325,152            158,831          Daily Commuter Traffic 13,666                 385                   13,939                  404                   14,218                  416                   14,502                  428                   14,792                  441                  

Average FaresAnnual Fare Increase vs Base Year 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%One Way Fare  20.08 60.50 25.10 75.63 31.38 94.53 39.23 118.16 49.03 147.71Total Fares Generation 98,802,585         8,375,091        125,973,296     10,992,306   160,615,952     14,152,595   204,785,339     18,221,465   261,101,307     23,460,137  

Terminal Fee (Passenger Cost) 46,121,410         3,460,781        47,043,838          3,633,820        47,984,715          3,742,835        48,944,409          3,855,120        49,923,297          3,970,774       Total Terminal Fee 49,582,191                                     50,677,658                                      51,727,550                                     

34,872,807                                     

2013

2018

53,894,071                                     

2011

38,761,155                               

2012

52,799,529                                     

2017

36,155,605                                      37,447,620                                     

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry Terminals

* Source: Buenavista/Jordan Boat Operators Association

33,604,270                                     

2014

2008 2009 2010

2015 2016

Annex 17.Option 1 Terminal Fees

Page 50: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

50

Annexes

Parola Option 1 Terminal Fees (cont’d)

Projected Commuter & Tourist Traffic, 5‐Year Periods

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year DataAssumed Annual % Growth Rate 2.0% 7.0% 2.0% 5.0% 2.0% 3.0% 2.0% 3.0% 2.0% 3.0%Annual Commuter Traffic 4,919,617           138,431         5,018,009          145,353         5,519,810          149,713          6,071,791          172,170         6,678,970          197,996        Daily Commuter Traffic 13,666                 385                 13,939                404                 15,333                416                  16,866                478                 18,553                550                

Average FaresAnnual Fare Increase vs Base Year 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%One Way Fare  61.29 184.63 76.61 230.79 95.77 288.49 119.71 360.61 149.63 450.76Total Fares Generation 301,521,561      25,558,748     384,439,990       33,545,857     528,604,986       43,190,291     726,831,855       62,086,043     999,393,801       89,248,687    

Terminal Fee (Passenger Cost) 56,083,634         4,152,938        57,205,307          4,360,584        62,925,837          4,491,402        69,218,421          5,165,112        76,140,263          5,939,879       Total Terminal Fee

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year DataAssumed Annual % Growth Rate 2.0% 7.0% 2.0% 5.0% 2.0% 3.0% 2.0% 3.0% 2.0% 3.0%Annual Commuter Traffic 6,812,550           211,856         6,948,801          222,448         7,087,777          229,122          7,229,532          235,996         7,374,123          243,075        Daily Commuter Traffic 18,924                 588                 19,302                618                 19,688                636                  20,082                656                 20,484                675                

Average FaresAnnual Fare Increase vs Base Year 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%One Way Fare  187.04 563.45 233.80 704.31 292.25 880.39 365.31 1,100.49 456.64 1,375.61Total Fares Generation 1,274,227,097   119,370,119 1,624,639,548  156,673,281 2,071,415,424  201,716,850 2,641,054,665  259,710,444 3,367,344,698  334,377,197

Terminal Fee (Passenger Cost) 89,414,717         7,414,949      91,203,011        7,785,696      93,027,072        8,019,267       94,887,613        8,259,845      96,785,365        8,507,641     Total Terminal Fee

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry Terminals

67,417,239                                     

2027

103,147,459                                   

2028

74,383,533                                      82,080,142                                     

105,293,006                                   

2024

96,829,666                                     98,988,708                                     

2026

101,046,339                                   

2025

2019 2020

60,236,572                                     61,565,891                                     

2022 20232021

Annex 18. Option 1 Terminal Fees

Page 51: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

51

Annexes

Parola Option 2 Terminal Fees

Projected Commuter & Tourist Traffic, 5‐Year Periods

BASE YEAR COMPUTATIONCOMMUTER TRAFFIC* Daily Yearly

Buenavista 4,800 1,728,000Jordan 6,870 2,473,200

TOTAL 11,670 4,201,200

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year Data 4,201,200           50,000           Assumed Annual % Growth Rate 3.0% 15.0% 3.2% 20.0% 2.8% 25.0% 2.5% 25.0% 2.5% 20.0%Annual Commuter Traffic 4,327,236            57,500             4,465,708            69,000             4,590,747            86,250             4,705,516            107,813           4,823,154        129,375        Daily Commuter Traffic 12,020                  160                   12,405                  192                   12,752                  240                   13,071                  299                   13,398             359                

Average Fares 12.59 20.00Annual Fare Increase vs Base Year 5% 100% 5% 0% 5% 10% 5% 0% 5% 10%One Way Fare  13.22 40.00 13.88 40.00 14.57 44.00 15.30 44.00 16.07 48.40Total Fares Generation 57,197,939        2,300,000      61,979,687        2,760,000      66,900,874         3,795,000      72,002,066        4,743,750      77,492,223   6,261,750   

Terminal Fee (Passenger Cost) 9.00 20.00 38,945,124          1,150,000        40,191,368          1,380,000        41,316,726          1,725,000        42,349,644          2,156,250        43,408,386     2,587,500     Total Terminal Fee

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year DataAssumed Annual % Growth Rate 2.0% 7.0% 2.0% 5.0% 2.0% 3.0% 2.0% 3.0% 2.0% 3.0%Annual Commuter Traffic 4,919,617           138,431          5,018,009          145,353         5,118,370          149,713         5,220,737           154,205         5,325,152          158,831        Daily Commuter Traffic 13,666                 385                   13,939                  404                   14,218                  416                   14,502                  428                   14,792                  441                  

Average FaresAnnual Fare Increase vs Base Year 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%One Way Fare  20.08 60.50 25.10 75.63 31.38 94.53 39.23 118.16 49.03 147.71Total Fares Generation 98,802,585         8,375,091        125,973,296     10,992,306   160,615,952     14,152,595   204,785,339     18,221,465   261,101,307     23,460,137  

Terminal Fee (Passenger Cost) 55,345,692         3,460,781        56,452,605          3,633,820        57,581,658          3,742,835        58,733,291          3,855,120        59,907,956          3,970,774       Total Terminal Fee

2013

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry Terminals

* Source: Buenavista/Jordan Boat Operators Association

2008 2009

43,041,726                                      44,505,894                                     

2010 2011 2012

61,324,492                                      62,588,411                                     

45,995,886                               

2014 2015 2016 2017 2018

40,095,124                                      41,571,368                                     

63,878,730                                     58,806,473                                     60,086,426                                     

Annex 19. Option 2 Terminal Fees

Page 52: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

52

Annexes

Parola Option 2 Terminal Fees (cont’d)

Projected Commuter & Tourist Traffic, 5‐Year Periods

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year DataAssumed Annual % Growth Rate 2.0% 7.0% 2.0% 5.0% 2.0% 3.0% 2.0% 3.0% 2.0% 3.0%Annual Commuter Traffic 4,919,617           138,431         5,018,009          145,353         5,519,810          149,713          6,071,791          172,170         6,678,970          197,996        Daily Commuter Traffic 13,666                 385                 13,939                404                 15,333                416                  16,866                478                 18,553                550                

Average FaresAnnual Fare Increase vs Base Year 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%One Way Fare  61.29 184.63 76.61 230.79 95.77 288.49 119.71 360.61 149.63 450.76Total Fares Generation 301,521,561      25,558,748     384,439,990       33,545,857     528,604,986       43,190,291     726,831,855       62,086,043     999,393,801       89,248,687    

Terminal Fee (Passenger Cost) 67,300,361         4,152,938        68,646,368          4,360,584        75,511,005          4,491,402        83,062,105          5,165,112        91,368,316          5,939,879       Total Terminal Fee

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year DataAssumed Annual % Growth Rate 2.0% 7.0% 2.0% 5.0% 2.0% 3.0% 2.0% 3.0% 2.0% 3.0%Annual Commuter Traffic 6,812,550           211,856         6,948,801          222,448         7,087,777          229,122          7,229,532          235,996         7,374,123          243,075        Daily Commuter Traffic 18,924                 588                 19,302                618                 19,688                636                  20,082                656                 20,484                675                

Average FaresAnnual Fare Increase vs Base Year 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%One Way Fare  187.04 563.45 233.80 704.31 292.25 880.39 365.31 1,100.49 456.64 1,375.61Total Fares Generation 1,274,227,097   119,370,119 1,624,639,548  156,673,281 2,071,415,424  201,716,850 2,641,054,665  259,710,444 3,367,344,698  334,377,197

Terminal Fee (Passenger Cost) 107,297,661      7,414,949      109,443,614     7,785,696      111,632,486     8,019,267       113,865,136     8,259,845      116,142,439     8,507,641     Total Terminal Fee

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry Terminals

80,002,407                                      88,227,218                                     

2019 2020 2021 2022 2023

119,651,753                                    122,124,981                                   

97,308,195                                     

2024 2025 2026 2027 2028

71,453,298                                     73,006,953                                     

124,650,079                                   114,712,610                                   117,229,310                                   

Annex 20. Option 2 Terminal Fees

Page 53: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

53

Annexes

Parola Option 3 Terminal Fees

Projected Commuter & Tourist Traffic, 5‐Year Periods

BASE YEAR COMPUTATIONCOMMUTER TRAFFIC* Daily Yearly

Buenavista 4,800 1,728,000Jordan 6,870 2,473,200

TOTAL 11,670 4,201,200

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year Data 4,201,200           50,000            Assumed Annual % Growth Rate 3.0% 15.0% 3.2% 20.0% 2.8% 25.0% 2.5% 25.0% 2.5% 20.0%Annual Commuter Traffic 4,327,236          57,500           4,465,708          69,000           4,590,747           86,250           4,705,516          107,813         4,823,154      129,375      Daily Commuter Traffic 12,020                160                 12,405                192                 12,752                 240                 13,071                299                 13,398           359              

Average Fares 12.59 20.00Annual Fare Increase vs Base Year 5% 100% 5% 0% 5% 10% 5% 0% 5% 10%One Way Fare  13.22 40.00 13.88 40.00 14.57 44.00 15.30 44.00 16.07 48.40Total Fares Generation 57,197,939        2,300,000      61,979,687        2,760,000      66,900,874         3,795,000      72,002,066        4,743,750      77,492,223   6,261,750   

Terminal Fee (Passenger Cost) 10.00 20.00 43,272,360        1,150,000      44,657,076        1,380,000      45,907,474         1,725,000      47,055,160        2,156,250      48,231,539   2,587,500   Total Terminal Fee

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year DataAssumed Annual % Growth Rate 2.0% 7.0% 2.0% 5.0% 2.0% 3.0% 2.0% 3.0% 2.0% 3.0%Annual Commuter Traffic 4,919,617           138,431           5,018,009            145,353           5,118,370            149,713           5,220,737            154,205           5,325,152            158,831          Daily Commuter Traffic 13,666                 385                   13,939                  404                   14,218                  416                   14,502                  428                   14,792                  441                  

Average FaresAnnual Fare Increase vs Base Year 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%One Way Fare  20.08 60.50 25.10 75.63 31.38 94.53 39.23 118.16 49.03 147.71Total Fares Generation 98,802,585         8,375,091        125,973,296     10,992,306   160,615,952     14,152,595   204,785,339     18,221,465   261,101,307     23,460,137  

Terminal Fee (Passenger Cost) 61,495,213         3,460,781        62,725,117          3,633,820        63,979,619          3,742,835        65,259,212          3,855,120        66,564,396          3,970,774       Total Terminal Fee

2013

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry Terminals

* Source: Buenavista/Jordan Boat Operators Association

2008 2009

47,632,474                                      49,211,410                                     

2010 2011 2012

67,722,454                                      69,114,332                                     

50,819,039                               

2014 2015 2016 2017 2018

44,422,360                                      46,037,076                                     

70,535,170                                     64,955,994                                     66,358,937                                     

Annex 21. Option 3 Terminal Fees

Page 54: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

54

Annexes

Parola Option 3 Terminal Fees (cont’d)

Projected Commuter & Tourist Traffic, 5‐Year Periods

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year DataAssumed Annual % Growth Rate 2.0% 7.0% 2.0% 5.0% 2.0% 3.0% 2.0% 3.0% 2.0% 3.0%Annual Commuter Traffic 4,919,617           138,431         5,018,009          145,353         5,519,810          149,713          6,071,791          172,170         6,678,970          197,996        Daily Commuter Traffic 13,666                 385                 13,939                404                 15,333                416                  16,866                478                 18,553                550                

Average FaresAnnual Fare Increase vs Base Year 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%One Way Fare  61.29 184.63 76.61 230.79 95.77 288.49 119.71 360.61 149.63 450.76Total Fares Generation 301,521,561      25,558,748     384,439,990       33,545,857     528,604,986       43,190,291     726,831,855       62,086,043     999,393,801       89,248,687    

Terminal Fee (Passenger Cost) 74,778,179         4,152,938        76,273,742          4,360,584        83,901,117          4,491,402        92,291,228          5,165,112        101,520,351       5,939,879       Total Terminal Fee

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year DataAssumed Annual % Growth Rate 2.0% 7.0% 2.0% 5.0% 2.0% 3.0% 2.0% 3.0% 2.0% 3.0%Annual Commuter Traffic 6,812,550           211,856         6,948,801          222,448         7,087,777          229,122          7,229,532          235,996         7,374,123          243,075        Daily Commuter Traffic 18,924                 588                 19,302                618                 19,688                636                  20,082                656                 20,484                675                

Average FaresAnnual Fare Increase vs Base Year 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%One Way Fare  187.04 563.45 233.80 704.31 292.25 880.39 365.31 1,100.49 456.64 1,375.61Total Fares Generation 1,274,227,097   119,370,119 1,624,639,548  156,673,281 2,071,415,424  201,716,850 2,641,054,665  259,710,444 3,367,344,698  334,377,197

Terminal Fee (Passenger Cost) 119,219,623      7,414,949      121,604,015     7,785,696      124,036,096     8,019,267       126,516,818     8,259,845      129,047,154     8,507,641     Total Terminal Fee

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry Terminals

88,392,519                                      97,456,340                                     

2019 2020 2021 2022 2023

132,055,363                                    134,776,663                                   

107,460,230                                   

2024 2025 2026 2027 2028

78,931,116                                     80,634,327                                     

137,554,795                                   126,634,572                                   129,389,712                                   

Annex 22. Option 3 Terminal Fees

Page 55: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

55

Annexes

Carrying Capacity

ASSUMPTIONSCOMMUTER TRAFFIC* Daily Yearly

Buenavista 4,800 1,728,000Jordan 6,870 2,473,200

TOTAL 11,670 4,201,200* Source: Buenavista/Jordan Boat Operators Association

Commuter Tourist Commuter Tourist Commuter Tourist Commuter Tourist Commuter Tourist Commuter Tourist ARRIVAL DEPARTUREPAROLA

Jordan 1,236,600     25,000         1,236,600   25,000     2,473,200   50,000     6,870          139 50 80 137 2 23 23Buenavista 864,000        ‐               864,000      ‐           1,728,000   ‐           4,800          0 50 80 96 0 16 16

TOTAL 2,100,600     25,000         2,100,600   25,000     4,201,200   50,000     11,670        139 160 233 2 39 39Minutes per Boat  2 2Docking Bays 7 11 11

JORDAN 1,236,600     25,000         1,236,600   25,000     2,473,200   50,000     6,870          139 50 80 137 2 23 23Minutes per Boat  3 3Docking Bays 5 13 13

BUENAVISTA 864,000        ‐               864,000      ‐           1,728,000   ‐           4,800          0 50 80 96 0 16 16Minutes per Boat  4 4Docking Bays 4 15 15

ARRIVAL DEPARTURE SUB‐TOTAL PER DAY(360 days) LOAD DOCKING BAYS

BOAT TRIPS / DAY PEAK HOURS

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry Terminals

ANNUAL ‐ TOTAL COMMUTERS DAILY ‐ TOTAL COMMUTERS DAILY ‐ NUMBER OF BOATS CARRYING CAPACITY

CARRYING CAPACITY

Annex 23. Carrying Capacity

Page 56: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

56

Annexes

Private Sector

PAROLA ECO‐PORT PROJECTProjected Commuter & Tourist Traffic, 5‐Year PeriodsPrivate Sector 

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year Data 4,201,200        50,000             Assumed Annual % Growth Rate 3.0% 15.0% 3.2% 20.0% 2.8% 25.0% 2.5% 25.0% 2.5% 20.0%Annual Commuter Traffic 4,327,236      57,500            4,465,708      69,000            4,590,747        86,250            4,705,516      107,813          4,823,154      129,375         Daily Commuter Traffic 12,020            160                  12,405            192                  12,752              240                  13,071            299                  13,398            359                 

Catchment Potential 15% 20% 649,085          11,500            669,856          13,800            688,612            17,250            705,827          21,563            723,473          25,875           Average purchase 100.00 100.00 64,908,540    1,150,000      66,985,613    1,380,000      68,861,210      1,725,000      70,582,741    2,156,250      72,347,309    2,587,500     

Total Annual SalesGross Operating Profit %

Gross Operating ProfitLoan Retirement 

Amount Available for AmortizationInterest Years Pay

Match Amortization to Available GOP Loan Terms 12% 10Equity of Project Cost 40%Total Project Cost Potential

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year DataAssumed Annual % Growth Rate 2.0% 7.0% 2.0% 5.0% 2.0% 3.0% 2.0% 3.0%Annual Commuter Traffic 5,305,469        174,656          5,836,016      218,320          6,419,618      251,068          7,061,580        288,729         Daily Commuter Traffic 14,737              485                  16,211            606                  17,832            697                  19,615              802                 

Catchment Potential 795,820            34,931            875,402          43,664            962,943          50,214            1,059,237        57,746           Average purchase 79,582,040      3,493,125        87,540,244      4,366,406        96,294,269      5,021,367        105,923,695    5,774,572       

Total Annual SalesGross Operating Profit %

Gross Operating ProfitLoan Retirement 

Amount Available for Amortization

Match Amortization to Available GOP Loan TermsEquity of Project CostTotal Project Cost Potential

20122011

40%

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCIL

20102008 2009

5,994,785

66,058,540 68,365,61340% 40%

29,973,924

70,586,210

29,095,59620% 20%

30,000,000

2014‐2018

15,000,000 17,000,000

2019‐2023 2024‐2028

18,000,00012,000,00011,000,000

72,738,991 74,934,809

2013

20% 20% 20%

40%26,423,416 27,346,245 28,234,484

40%

5,819,119

40% 40%

10,000,000 10,666,667

83,075,165 91,906,650

28,333,33326,666,667 27,500,000

5,646,897

20% 20%44,679,30733,230,066

20%

101,315,636

36,762,660

5,284,683 5,469,249

2029‐2033

20%40,526,254

111,698,26840% 40%

16,000,000 16,500,000

(3,982,144) (4,424,604) (4,867,065)

6,646,013 7,352,532 8,105,251 8,935,861

(3,185,715)(2,920,239)

11,333,333

(2,654,762) (2,831,747) (3,008,731)

25,000,000

33,333,333 37,500,000 41,666,667 45,833,333

(3,539,683)

18,333,33327,500,000

13,333,33320,000,000 22,500,000 25,000,000

15,000,000 16,666,667

Annex 24. Private Sector

Page 57: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

57

Annexes

Boat Operators

Boat Operators 

YearPassenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year Data 4,201,200      50,000       Assumed Annual % Growth Rate 3.0% 15.0% 3.2% 20.0% 2.8% 25.0% 2.5% 25.0% 2.5% 20.0% 2.5% 20.0%

Annual Commuter Traffic 4,327,236        50,000         4,465,708     60,000         4,590,747        75,000               4,705,516        93,750              4,823,154        112,500            4,943,733        135,000           Daily Commuter Traffic 12,020             139               12,405           167               12,752              208                     13,071              260                    13,398              313                    13,733              375                   Total Number of Boats 100 1 100 1 100 1 100 1 100 2 100 2 100 2Passengers per Boat per Day 120                 139             124               167             128                  208                   131                   130                  134                  156                  137                  188                 Load per Trip 50 80 50 80 50 80 50 80 50 80 50 80Trips per Boat Daily 2.4                  1.7              2.5                2.1              2.6                   2.6                     2.6                    1.6                   2.7                   2.0                   2.7                   2.3                  Total Boat Trips per Day  240                 2                 248               2                  255                  3                         261                   3                      268                  4                      275                  5                     Average Fares 12.59 20.00Annual Fare Increase vs Base Year 5% 100% 5% 0% 5% 10% 5% 0% 5% 10% 5% 10%One Way Fare  13.22 40.00 13.88 40.00 14.57 44.00 15.30 44.00 16.07 48.40 16.87 53.24Total Fares Generation 57,197,939   2,000,000 61,979,687 2,400,000  66,900,874    3,300,000        72,002,066      4,125,000      77,492,223    5,445,000      83,401,006    7,187,400     

Annual Gross Revenue per Boat 571,979 2,000,000 619,797 2,400,000 669,009 3,300,000 720,021 2,062,500 774,922 2,722,500 834,010 3,593,700Daily Gross Revenue per Boat (360 days) 1,589 5,556 1,722 6,667 1,858 9,167 2,000 5,729 2,153 7,563 2,317 9,983

Year 2015 2016 2017 2018 2019 2020Passenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism

Base Year DataAssumed Annual % Growth Rate 2.5% 20.0% 2.5% 20.0% 2.5% 20.0% 2.5% 20.0% 2.5% 20.0% 2.5% 20.0% 2.5% 20.0%

Annual Commuter Traffic 5,067,326      162,000     5,194,009      194,400     5,323,860   233,280     5,456,956      279,936           5,593,380        335,923          5,733,214      403,108          5,876,545      483,729         Daily Commuter Traffic 14,076            450             14,428           540             14,788         648             15,158            778                   15,537              933                  15,926            1,120              16,324            1,344             Total Number of Boats 100 2 100 2 100 2 100 2 100 2 100 2 100 2Passengers per Boat per Day 141                  225             144                 270             148               324             152                  389                   155                   467                  159                  560                  163                  672                 Load per Trip 50 80 50 80 50 80 50 80 50 80 50 80 50 80Trips per Boat Daily 2.8                   2.8              2.9                    3.4                3.0                  4.1                3.0                     4.9                      3.1                     5.8                     3.2                     7.0                     3.3                     8.4                    Total Boat Trips per Day  282                  6                  289                   7                   296                 8                    303                    10                       311                    12                      319                    14                      326                    17                     Average FaresAnnual Fare Increase vs Base Year 5% 10% 5% 10% 5% 10% 5% 10% 5% 10% 5% 10% 5% 10%One Way Fare  17.71 58.56 18.60 64.42 19.53 70.86 20.51 77.95 21.53 85.74 22.61 94.32 23.74 103.75Total Fares Generation 89,760,332    9,487,368  96,604,558     ######## ######### ######### 111,898,417    21,820,643       120,430,672    28,803,249      129,613,511    38,020,288      139,496,541    50,186,780     

Terminal Fee (Passenger Cost) 38,004,946    3,240,000  38,955,070     3,888,000   39,928,946   4,665,600    40,927,170      5,598,720          41,950,349      6,718,464        42,999,108      8,062,157        44,074,086      9,674,588       Total Terminal Fee ########## ########## ########## ########## # ########## # ########## #

Annual Gross Revenue per Boat 897,603 4,743,684 966,046 6,261,663 1,039,707 8,265,395 1,118,984 10,910,321 1,204,307 14,401,624 1,296,135 19,010,144 1,394,965 25,093,390Daily Gross Revenue per Boat (360 days) 2,493 13,177 2,683 17,394 2,888 22,959 3,108 30,306 3,345 40,005 3,600 52,806 3,875 69,704

20132011 2012

2021

53,748,674

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry Terminals

2014

Projected Commuter & Tourist Traffic, 5‐Year Periods

2008 Base Year 2009 2010

Annex 25. Boat Operators

Page 58: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

PRE-

FEA

SIB

ILIT

Y S

TUD

YGuimaras‐Iloilo Ferry Terminals System

 Project

58

Annexes

Boat Operators (cont’d)

Annex 26. Boat Operators

Boat Operators 

Year 2022 2023 2024 2025 2026Passenger Type Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter Tourism Commuter TourismBase Year DataAssumed Annual %  2.5% 20.0% 2.5% 20.0% 2.5% 20.0% 2.5% 20.0% 2.5% 20.0% 2.5% 20.0% 2.5% 20.0%

Annual Commuter Tr 6,023,458                  580,475                     6,174,045                  696,570                     6,328,396                  835,884                     6,486,606                  1,003,061                  6,648,771                  1,203,674                  6,814,990                  1,444,408                  6,985,365                  1,733,290                 Daily Commuter Traf 16,732                       1,612                         17,150                       1,935                         17,579                       2,322                         18,018                       2,786                         18,469                       3,344                         18,931                       4,012                         19,404                       4,815                        Total Number of Boa 100 2 100 2 100 2 100 2 100 2 100 2 100 2Passengers per Boat  167                           806                            172                             967                           176                           1,161                       180                           1,393                       185                            1,672                       189                           2,006                       194                           2,407                      Load per Trip 50 80 50 80 50 80 50 80 50 80 50 80 50 80Trips per Boat Daily 3.3                              10.1                            3.4                              12.1                            3.5                              14.5                            3.6                              17.4                            3.7                              20.9                            3.8                              25.1                            3.9                              30.1                           Total Boat Trips per D 335                             20                               343                             24                               352                             29                               360                             35                               369                             42                               379                             50                               388                             60                              Average FaresAnnual Fare Increase 5% 10% 5% 10% 5% 10% 5% 10% 5% 10% 5% 10% 5% 10%One Way Fare  24.92 114.12 26.17 125.54 27.48 138.09 28.85 151.90 30.30 167.09 31.81 183.80 33.40 202.18Total Fares Generatio 150,133,152             66,246,550               161,580,805             87,445,446               173,901,341             115,427,988             187,161,318             152,364,945             201,432,369             201,121,727             216,791,587             265,480,680             233,321,946             350,434,497            

Terminal Fee (Passen 45,175,938               11,609,506               46,305,336               13,931,407               47,462,970               16,717,688               48,649,544               20,061,226               49,865,782               24,073,471               51,112,427               28,888,165               52,390,238               34,665,799              Total Terminal Fee 56,785,444 60,236,743 64,180,658 68,710,770 73,939,254

Annual Gross Revenu 1,501,332 33,123,275 1,615,808 43,722,723 1,739,013 57,713,994 1,871,613 76,182,472 2,014,324 100,560,864 2,167,916 132,740,340 2,333,219 175,217,249Daily Gross Revenue 4,170 92,009 4,488 121,452 4,831 160,317 5,199 211,618 5,595 279,336 6,022 368,723 6,481 486,715

2028

87,056,036

2027

80,000,592

METRO ILOILO ‐ GUIMARAS ECONOMIC DEVELOPMENT COUNCILMIG Commuter Ferry TerminalsProjected Commuter & Tourist Traffic, 5‐Y

Page 59: Pre-feasibility Study of the Guimaras-Iloilo Ferry Terminals System Project

CDIA-MIG Team

Team Leader: DR. NATHANIEL VON EINSIEDEL  

PRE‐FEASIBILITYSub‐Team Leader:

 MR. LEON MAYO 

Investment Planning Specialist: MR. ELPIDIO DAMASO Costing Engineer: MS. MIRIAM TAMAYO 

Architectural Designer: MS. DEANNA SANTOSMR. NICASIO ESPINA MR. JULIUS GARRIDO MS. JAYCEE GOPEZ MR. WILFREDO SY 

INVESTMENT PLANNINGSub‐Team Leader:

 MR. JOSE ANTONIO LEAGUE 

Business Development Specialist:

MS. ELIRINE SIWA 

CAPACITY BUILDINGSub‐Team Leader: MS. VICTORIA DE VILLA 

Local Development Specialist: MS. RASHEL PARDO 

LOCAL COUNTERPARTBusiness Development Advisor:

 MR. ANGEL DE LEON