Pre-Inspection Mezzanine Walkthrough Checklist Date: Station Name: Mezzanine #: Completed By: Check Task Equipment Room ID Notes Verify that electrical power design matches the field/record. Identify locations of the electrical equipment. Electrical Source Panel Name/Number: Source Breaker Name/Number: Electrical AFC Panel Name/Number: Verify if disconnect switch is connected to the AFC electrical power panel. Low or High voltage SMNT/POWR escorts requirements? Disconnect Name/Number: SMNT/POWR escorts: Check if there is a shared raceway between AFC Panel and Kiosk and identify additional source panels to be de-energized. Do AFC Panel loads feed into a shared raceway e.g. trench or trough? If Yes, specify source panels in notes. Identify the assumed pathway of duct / conduit, the location of the handholes, manholes and boxes and accessibility or special escort requirement? PLNT COMM / IT ELES RAIL CMNT Other Access/Support: Identify handhole or manhole access requirement. Required PLNT Mason for handhole/manhole access? Identified Conduit/Duct Transition to mezzanine level? Emergency Power Verification Check Task Equipment Room ID Notes Verify if AFC electrical panel is connected to an Automatic Transfer Switch (ATS). ATS Name/Number: Verification of Kiosk Emergency Panel(s) (KE, KES, KESS, etc) Source Panel Name/Number: Source Breaker Name/Number: Panel Name/Number: Notes and Discrepancies: Sign Off GFP Representative WMATA PRGM Name: Signature: Date: VerVLRQ 11/04/2014 Potomac Ave - D07 061 Tino Sahoo Panel M Breaker #20, #22, #24 Rm 301 Rm 301 1MM Rm 301 HIGH Voltage NO Power run from Kiosk to AFC Panel is approx. 156'. YES (see notes) YES Conduits/ducts on multiple levels. 2" conduit running along ceiling down to Mezzanine Floor. Overhead conduit to walker duct to handholes to Kiosk MEE Rm 301 Breaker #22, #24 Rm 301 Kiosk Panel Kiosk Panel ME serves Panel MEE breaker #10 (LOTO). Tino Sahoo 11/04/2014

Pre-Inspection Mezzanine Walkthrough Checklist · 2017. 2. 8. · SMF Rm 211 S.O.: Panel SM Breaker #2 Panel SM Breaker #8 Panel SMPO Breaker #5 Panel SME Breaker #6 HIGH and LOW

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

  • Pre-Inspection Mezzanine Walkthrough ChecklistDate: Station Name: Mezzanine #: Completed By:

    Check Task Equipment Room ID Notes

    Verify that electrical power design matches the field/record. Identify locations of theelectrical equipment.

    Electrical Source Panel Name/Number:

    Source Breaker Name/Number:

    Electrical AFC Panel Name/Number:

    Verify if disconnect switch is connected to the AFC electrical power panel. Low or High voltage SMNT/POWR escorts requirements?

    Disconnect Name/Number:

    SMNT/POWR escorts:

    Check if there is a shared raceway between AFC Panel and Kiosk and identify additional source panels to be de-energized.

    Do AFC Panel loads feed into a sharedraceway e.g. trench or trough? If Yes,specify source panels in notes.

    Identify the assumed pathway of duct / conduit, the location of the handholes, manholes and boxes and accessibility or special escort requirement?

    PLNT COMM / IT ELES

    RAIL CMNT

    Other Access/Support:

    Identify handhole or manhole access requirement.

    Required PLNT Mason forhandhole/manhole access?

    Identified Conduit/Duct Transition to mezzanine level?

    Emergency Power Verification

    Check Task Equipment Room ID Notes

    Verify if AFC electrical panel is connected to an Automatic Transfer Switch (ATS). ATS Name/Number:

    Verification of Kiosk Emergency Panel(s) (KE, KES, KESS, etc)

    Source Panel Name/Number:

    Source Breaker Name/Number:

    Panel Name/Number:

    Notes and Discrepancies:

    Sign Off GFP Representative WMATA PRGM

    Name:

    Signature:

    Date:

    Ver

    11/04/2014 Potomac Ave - D07 061 Tino Sahoo

    Panel M

    Breaker #20, #22, #24

    Rm 301

    Rm 301

    1MM Rm 301

    ✔HIGH Voltage

    ✔ NO

    ✔ Power run from Kiosk to AFC Panel is approx.156'.

    YES (see notes)

    YES

    Conduits/ducts on multiple levels.2" conduit running along ceiling down toMezzanine Floor. Overhead conduit to walker ductto handholes to Kiosk

    MEE Rm 301

    Breaker #22, #24 Rm 301

    Kiosk Panel Kiosk

    Panel ME serves Panel MEE breaker #10 (LOTO).

    Tino Sahoo

    11/04/2014

  • Picture 1: D07 Potomac Ave – Handholes & manhole in Mezzanine

  • Picture 2: D07 Potomac Ave – Conduit run from Electrical room to Mezzanine

  • Picture 3: D07 Potomac Ave – Conduit run from Electrical room to Mezzanine

  • Picture 4: D07 Potomac Ave – Conduit run from Electrical room to Mezzanine

  • Picture 5: D07 Potomac Ave – Conduit run from Electrical room to Mezzanine

  • Picture 6: D07 Potomac Ave – Conduit run from Electrical room to Mezzanine

  • Picture 7: D07 Potomac Ave – Conduit run from Electrical room to Mezzanine

  • Picture 8: D07 Potomac Ave – Emergency panel in Kiosk

  • Picture 9: D07 Potomac Ave – Emergency panel in Kiosk

  • Picture 10: D07 Potomac Ave – Emergency panel in Kiosk

  • Picture 11: D07 Potomac Ave – Emergency panel in Kiosk

  • Picture 12: D07 Potomac Ave – AFC Panel IMM in Room 301

  • Picture 13: D07 Potomac Ave – AFC Panel IMM in Room 301

  • Picture 14: D07 Potomac Ave – AFC Panel IMM in Room 301 – Bottom of panel

  • Picture 15: D07 Potomac Ave – Panel M in Room 301

  • Picture 16: D07 Potomac Ave – Panel M in Room 301

  • Picture 17: D07 Potomac Ave – Emergency Panel MEE in Room 301

  • Picture 18: D07 Potomac Ave – Emergency Panel MEE in Room 301 – Panel schedule

  • Pre-Inspection FieldVerification 11/04/2014

  • Pre-Inspection FieldVerification 11/04/2014

  • 1&2

    1

    Pre-Inspection FieldVerification 11/04/2014

    Breaker

  • Pre-Inspection FieldVerification 11/04/2014

  • Pre-Inspection Mezzanine Walkthrough ChecklistDate: Station Name: Mezzanine #: Completed By:

    Check Task Equipment Room ID Notes

    Verify that electrical power design matches the field/record. Identify locations of theelectrical equipment.

    Electrical Source Panel Name/Number:

    Source Breaker Name/Number:

    Electrical AFC Panel Name/Number:

    Verify if disconnect switch is connected to the AFC electrical power panel. Low or High voltage SMNT/POWR escorts requirements?

    Disconnect Name/Number:

    SMNT/POWR escorts:

    Check if there is a shared raceway between AFC Panel and Kiosk and identify additional source panels to be de-energized.

    Do AFC Panel loads feed into a sharedraceway e.g. trench or trough? If Yes,specify source panels in notes.

    Identify the assumed pathway of duct / conduit, the location of the handholes, manholes and boxes and accessibility or special escort requirement?

    PLNT COMM / IT ELES

    RAIL CMNT

    Other Access/Support:

    Identify handhole or manhole access requirement.

    Required PLNT Mason forhandhole/manhole access?

    Identified Conduit/Duct Transition to mezzanine level?

    Emergency Power Verification

    Check Task Equipment Room ID Notes

    Verify if AFC electrical panel is connected to an Automatic Transfer Switch (ATS). ATS Name/Number:

    Verification of Kiosk Emergency Panel(s) (KE, KES, KESS, etc)

    Source Panel Name/Number:

    Source Breaker Name/Number:

    Panel Name/Number:

    Notes and Discrepancies:

    Sign Off GFP Representative WMATA PRGM

    Name:

    Signature:

    Date:

    Ver

    11/04/2014 Stadium-Armory (South) - D08 062 Tino Sahoo

    SM

    Breaker #8

    Rm 211

    Rm 211

    SMF Rm 211

    S.O.:Panel SM Breaker #2Panel SM Breaker #8Panel SMPO Breaker #5Panel SME Breaker #6

    ✔HIGH and LOW Voltage

    ✔ YES (see notes)Panels SMF, SML, and SMM share a trough.

    NO

    YES

    All conduit/duct on one level.No handholes in mezzanine.

    Kiosk

    Kiosk

    KE

    Breaker #7

    Emergency Power to Faregates

    Tino Sahoo

    11/04/2014

    REVISION 1

  • Pictures 1&2: D08 Stadium-Armory (South) – Emergency panels in Kiosk

  • Picture 3: D08 Stadium-Armory (South) – AFC Panel SMF in Room 211

  • Picture 4: D08 Stadium-Armory (South) – AFC Panel SMF in Room 211

  • Pictures 5&6: D08 Stadium-Armory (South) – AFC Panel SMF in Room 211 – Bottom ducts & common trough

  • Pictures 7&8: D08 Stadium-Armory (South) – Panel SM & circuits 2&8 in Room 211

  • Picture 9: D08 Stadium-Armory (South) – Panel SM in Room 211 – Panel schedule

  • Picture 10: D08 Stadium-Armory (South) – Panel SME in Room 211

  • Picture 11: D08 Stadium-Armory (South) – Panel SME in Room 211 – Panel schedule

  • Picture 12: D08 Stadium-Armory (South) – Panel SML in Room 211

  • Picture 13&14: D08 Stadium-Armory (South) – Panel SMM in Room 211

  • Picture 15: D08 Stadium-Armory (South) – Panel SMPO in Room 211

  • Picture 16: D08 Stadium-Armory (South) – Panel SMPO in Room 211 – Panel schedule

  • Pre-Inspection FieldVerification 11/04/2014

  • Pre-Inspection FieldVerification 11/04/2014

  • Pre-Inspection FieldVerification 11/04/2014

  • Pre-Inspection FieldVerification 11/04/2014

  • Pre-Inspection Mezzanine Walkthrough ChecklistDate: Station Name: Mezzanine #: Completed By:

    Check Task Equipment Room ID Notes

    Verify that electrical power design matches the field/record. Identify locations of the electrical equipment.

    Electrical Source Panel Name/Number:

    Source Breaker Name/Number:

    Electrical AFC Panel Name/Number:

    Verify if disconnect switch is connected to the AFC electrical power panel. Low or High voltage SMNT/POWR escorts requirements?

    Disconnect Name/Number:

    SMNT/POWR escorts:

    Check if there is a shared raceway between AFC Panel and Kiosk and identify additional source panels to be de-energized.

    Do AFC Panel loads feed into a shared raceway e.g. trench or trough? If Yes, specify source panels in notes.

    Identify the assumed pathway of duct / conduit, the location of the handholes, manholes and boxes and accessibility or special escort requirement?

    PLNT COMM / IT ELES

    RAIL CMNT

    Other Access/Support:

    Identify handhole or manhole access requirement.

    Required PLNT Mason for handhole/manhole access?

    Identified Conduit/Duct Transition to mezzanine level?

    Emergency Power Verification

    Check Task Equipment Room ID Notes

    Verify if AFC electrical panel is connected to an Automatic Transfer Switch (ATS). ATS Name/Number:

    Verification of Kiosk Emergency Panel(s) (KE, KES, KESS, etc)

    Source Panel Name/Number:

    Source Breaker Name/Number:

    Panel Name/Number:

    Notes and Discrepancies:

    Sign Off GFP Representative WMATA PRGM

    Name:

    Signature:

    Date:

    Ver

    11/04/2014 Stadium-Armory (North) - D08 063 Tino Sahoo

    NM

    Breaker #8

    Rm 212

    Rm 212

    NMF Rm 212

    S.O.:SWBD NGB, Breaker #1SWBD NSB1, Breaker #6Panel NEL, Breaker #2

    HIGH and LOW Voltage

    ✔ YES (see notes)Panels NMF Sect I and II, NMM, NML, NME, NM,NMPO share a common trough.

    YES (see notes)

    YES

    All conduit/duct on one level. Run is approx. 55'from Kiosk to AFC Panel.

    NME Rm 212

    Breaker #7 Rm 212

    Kiosk Emergency Panel Kiosk

    Panel KE located in Kiosk, Breaker #6 willde-energize emergency power to the faregates.

    Tino Sahoo

    11/04/2014

  • Picture 1: D08 Stadium-Armory (North) – No handholes in Mezzanine

  • Picture 2: D08 Stadium-Armory (North) – Manhole on floor of electrical Room 212

  • Pictures 3&4: D08 Stadium-Armory (North) – Emergency panel in Kiosk

  • Picture 5: D08 Stadium-Armory (North) – AFC Panel NMF Sect II in Room 212

  • Picture 6: D08 Stadium-Armory (North) – AFC Panel NMF Sect II in Room 212

  • Picture 7: D08 Stadium-Armory (North) – AFC Panel NMF Sect II in Room 212 – Bottom ducts & conduits

  • Picture 8: D08 Stadium-Armory (North) – AFC Panel NMF Sect II in Room 212 – Panel schedule

  • Picture 9: D08 Stadium-Armory (North) – Common trough for multiple panels in Room 212

  • Pictures 10&11: D08 Stadium-Armory (North) – Switchboard and Panel M-85 in Room 212

  • Pictures 12&13: D08 Stadium-Armory (North) – Panels NM & NME in Room 212

  • Pictures 14&15: D08 Stadium-Armory (North) – Panels NMF Sect I & NML in Room 212

  • Pictures 16&17: D08 Stadium-Armory (North) – Panels NMM & NMPO in Room 212

  • Pre-Inspection FieldVerification 11/04/2014

    One handhole

  • Pre-Inspection FieldVerification 11/04/2014

  • Pre-Inspection FieldVerification 11/04/2014

    Breaker #8

  • Pre-Inspection FieldVerification 11/04/2014

  • Pre-Inspection Mezzanine Walkthrough ChecklistDate: Station Name: Mezzanine #: Completed By:

    Check Task Equipment Room ID Notes

    Verify that electrical power design matches the field/record. Identify locations of theelectrical equipment.

    Electrical Source Panel Name/Number:

    Source Breaker Name/Number:

    Electrical AFC Panel Name/Number:

    Verify if disconnect switch is connected to the AFC electrical power panel. Low or High voltage SMNT/POWR escorts requirements?

    Disconnect Name/Number:

    SMNT/POWR escorts:

    Check if there is a shared raceway between AFC Panel and Kiosk and identify additional source panels to be de-energized.

    Do AFC Panel loads feed into a sharedraceway e.g. trench or trough? If Yes,specify source panels in notes.

    Identify the assumed pathway of duct / conduit, the location of the handholes, manholes and boxes and accessibility or special escort requirement?

    PLNT COMM / IT ELES

    RAIL CMNT

    Other Access/Support:

    Identify handhole or manhole access requirement.

    Required PLNT Mason forhandhole/manhole access?

    Identified Conduit/Duct Transition to mezzanine level?

    Emergency Power Verification

    Check Task Equipment Room ID Notes

    Verify if AFC electrical panel is connected to an Automatic Transfer Switch (ATS). ATS Name/Number:

    Verification of Kiosk Emergency Panel(s) (KE, KES, KESS, etc)

    Source Panel Name/Number:

    Source Breaker Name/Number:

    Panel Name/Number:

    Notes and Discrepancies:

    Sign Off GFP Representative WMATA PRGM

    Name:

    Signature:

    Date:

    Ver

    10/30/2014 Minnesota Ave. - D09 064 Meghan Powell

    Essential Panel - SSI

    Transformer 'T4' - (Mezzanine)

    Rm 211

    Rm 211

    F Rm C107

    Rm 211 Wayside of Track 2

    Transformer T4

    LOW Voltage

    Rm C107

    ✔ YES (see notes) Rm C107M, MMIShut off via transformer T4 (DS)

    None

    NO

    UNDETERMINED

    All on mezzanine level.No manholes.Assuming single conduit/duct run between Kioskand panel.

    E3 Rm C107

    Breaker #5, #7 Rm C107

    No name on panel Kiosk

    Mini-mezzanine (1 faregate) on mezzanine level.

  • Picture 1: D09 Minnesota Ave. – No handholes in Mezzanine

  • Picture 2: D09 Minnesota Ave. – Emergency Panel (Unnamed) in Kiosk

  • Picture 3: D09 Minnesota Ave. – Emergency Panel E3 in Room C107

  • Picture 4: D09 Minnesota Ave. – Emergency Panel E3 Schedule in Room C107

  • Picture 5: D09 Minnesota Ave. – AFC Panel F in Room C107

  • Picture 6: D09 Minnesota Ave. – AFC Panel F in Room C107

  • Picture 7: D09 Minnesota Ave. – AFC Panel F Schedule in Room C107

  • Picture 8: D09 Minnesota Ave. – Panel M in Room C107

  • Picture 9: D09 Minnesota Ave. – Panel M Schedule in Room C107

  • Picture 10: D09 Minnesota Ave. – Panel MMI in Room C107

  • Picture 11: D09 Minnesota Ave. – Panel MMI Schedule in Room C107

  • Picture 12: D09 Minnesota Ave. – Transformer ‘T4’ Disconnect Switch in Room C107

  • Pre-Inspection FieldVerification 10/30/2014

  • "T4"

    Pre-Inspection FieldVerification 10/30/2014

  • Pre-Inspection FieldVerification 10/30/2014

  • Pre-Inspection Mezzanine Walkthrough ChecklistDate: Station Name: Mezzanine #: Completed By:

    Check Task Equipment Room ID Notes

    Verify that electrical power design matches the field/record. Identify locations of theelectrical equipment.

    Electrical Source Panel Name/Number:

    Source Breaker Name/Number:

    Electrical AFC Panel Name/Number:

    Verify if disconnect switch is connected to the AFC electrical power panel. Low or High voltage SMNT/POWR escorts requirements?

    Disconnect Name/Number:

    SMNT/POWR escorts:

    Check if there is a shared raceway between AFC Panel and Kiosk and identify additional source panels to be de-energized.

    Do AFC Panel loads feed into a sharedraceway e.g. trench or trough? If Yes,specify source panels in notes.

    Identify the assumed pathway of duct / conduit, the location of the handholes, manholes and boxes and accessibility or special escort requirement?

    PLNT COMM / IT ELES

    RAIL CMNT

    Other Access/Support:

    Identify handhole or manhole access requirement.

    Required PLNT Mason forhandhole/manhole access?

    Identified Conduit/Duct Transition to mezzanine level?

    Emergency Power Verification

    Check Task Equipment Room ID Notes

    Verify if AFC electrical panel is connected to an Automatic Transfer Switch (ATS). ATS Name/Number:

    Verification of Kiosk Emergency Panel(s) (KE, KES, KESS, etc)

    Source Panel Name/Number:

    Source Breaker Name/Number:

    Panel Name/Number:

    Notes and Discrepancies:

    Sign Off GFP Representative WMATA PRGM

    Name:

    Signature:

    Date:

    Ver

    10/30/2014 Deanwood - D10 065 Meghan Powell

    Essential Panel - 'SS-1'

    Transformer 'T-4'

    Rm 215

    Rm 215

    Panel F Rm C104

    Rm 215 Wayside of Track 2Rm C104 is inside of Rm C100

    Transformer T-4

    LOW Voltage

    Rm C104

    ✔ YES (see notes)Panel M, Panel MMI

    All shut down w/ transformer T-4

    YES (see notes)

    UNDETERMINED

    All conduit is on one level.100+ ft of conduit.All in one run between kiosk & panel.Manhole is for mini-mezzanine

    E3 Rm C104

    Breaker #7 Rm C104

    Panel KE Kiosk

    Meghan Powell

  • Picture 1: D10 Deanwood – Mezzanine

  • Picture 2: D10 Deanwood – Mezzanine

  • Picture 3: D10 Deanwood – Emergency Panel KE in Kiosk

  • Picture 4: D10 Deanwood – Emergency Panel E3 in Room C104

  • Picture 5: D10 Deanwood – Emergency Panel E3 schedule in Room C104

  • Picture 6: D10 Deanwood – AFC Panel F in Room C104

  • Picture 7: D10 Deanwood – AFC Panel F in Room C104

  • Picture 8: D10 Deanwood – AFC Panel F bottom conduits in Room C104

  • Picture 9: D10 Deanwood – Panel M in Room C104

  • Picture 10: D10 Deanwood – Panel MMI in Room C104

  • Picture 11: D10 Deanwood – Panel MMI bottom conduits in Room C104

  • Picture 12: D10 Deanwood – Shared trough for Panel M,MMI,F in Room C104

  • Picture 13: D10 Deanwood – Transformer Disconnect Switch T4 in Room C104

  • Pre-Inspection FieldVerification 10/30/2014

  • Pre-Inspection FieldVerification 10/30/2014

    T-4

  • Pre-Inspection FieldVerification 10/30/2014

    E-3 feeds Kiosk PanelCircuits #7

  • Pre-Inspection Mezzanine Walkthrough ChecklistDate: Station Name: Mezzanine #: Completed By:

    Check Task Equipment Room ID Notes

    Verify that electrical power design matches the field/record. Identify locations of theelectrical equipment.

    Electrical Source Panel Name/Number:

    Source Breaker Name/Number:

    Electrical AFC Panel Name/Number:

    Verify if disconnect switch is connected to the AFC electrical power panel. Low or High voltage SMNT/POWR escorts requirements?

    Disconnect Name/Number:

    SMNT/POWR escorts:

    Check if there is a shared raceway between AFC Panel and Kiosk and identify additional source panels to be de-energized.

    Do AFC Panel loads feed into a sharedraceway e.g. trench or trough? If Yes,specify source panels in notes.

    Identify the assumed pathway of duct / conduit, the location of the handholes, manholes and boxes and accessibility or special escort requirement?

    PLNT COMM / IT ELES

    RAIL CMNT

    Other Access/Support:

    Identify handhole or manhole access requirement.

    Required PLNT Mason forhandhole/manhole access?

    Identified Conduit/Duct Transition to mezzanine level?

    Emergency Power Verification

    Check Task Equipment Room ID Notes

    Verify if AFC electrical panel is connected to an Automatic Transfer Switch (ATS). ATS Name/Number:

    Verification of Kiosk Emergency Panel(s) (KE, KES, KESS, etc)

    Source Panel Name/Number:

    Source Breaker Name/Number:

    Panel Name/Number:

    Notes and Discrepancies:

    Sign Off GFP Representative WMATA PRGM

    Name:

    Signature:

    Date:

    Ver

    10/30/2014 Cheverly - D11 066 Meghan Powell

    Panel M

    Main breaker

    RmC205

    Panel F Rm C205

    Rm C205 is inside of Rm C200

    DS

    LOW Voltage

    Rm C205 No name on DS - Panel; next to Panel F.

    ✔ YES (see notes)Panel - P2, (taken out from main on Panel - M),Panel - M (main breaker).Panel - P2, Panel - M are connected to DS

    YES (see notes)

    YES

    All conduit/duct is on one level.Layout: Panel to shared trough, to duct.

    Panel - E-2 Rm C205

    Breaker #10

    No name on panel in the kiosk Kiosk

  • Picture 1: D11 Cheverly – Handholes in Mezzanine

  • Picture 2: D11 Cheverly – Manhole in Room C200

  • Picture 3: D11 Cheverly – Emergency Panel (Unnamed) in Kiosk

  • Picture 4: D11 Cheverly – Emergency Panel-E-2 in Room C205

  • Picture 5: D11 Cheverly – Emergency Panel-E-2 Schedule in Room C205

  • Picture 6: D11 Cheverly – Panel F in Room C205

  • Picture 7: D11 Cheverly – Panel F (without cover) in Room C205

  • Picture 8: D11 Cheverly – Panel F (bottom conduits) in Room C205

  • Picture 9: D11 Cheverly – Panel M in Room C205

  • Picture 10: D11 Cheverly – Panel F & M common trough in Room C205

  • Picture 11: D11 Cheverly – Panel F & M common trough in Room C205

  • Picture 12: D11 Cheverly – Panel P2 in Room C205

  • Picture 13: D11 Cheverly – Panel P2 schedule in Room C205

  • Picture 14: D11 Cheverly – Disconnect Switch in Room C205

  • Pre-Inspection FieldVerification 10/30/2014

    Rm 205

  • Pre-Inspection FieldVerification 10/30/2014

    M

  • Pre-Inspection FieldVerification 10/30/2014

  • Pre-Inspection Mezzanine Walkthrough ChecklistDate: Station Name: Mezzanine #: Completed By:

    Check Task Equipment Room ID Notes

    Verify that electrical power design matches the field/record. Identify locations of theelectrical equipment.

    Electrical Source Panel Name/Number:

    Source Breaker Name/Number:

    Electrical AFC Panel Name/Number:

    Verify if disconnect switch is connected to the AFC electrical power panel. Low or High voltage SMNT/POWR escorts requirements?

    Disconnect Name/Number:

    SMNT/POWR escorts:

    Check if there is a shared raceway between AFC Panel and Kiosk and identify additional source panels to be de-energized.

    Do AFC Panel loads feed into a sharedraceway e.g. trench or trough? If Yes,specify source panels in notes.

    Identify the assumed pathway of duct / conduit, the location of the handholes, manholes and boxes and accessibility or special escort requirement?

    PLNT COMM / IT ELES

    RAIL CMNT

    Other Access/Support:

    Identify handhole or manhole access requirement.

    Required PLNT Mason forhandhole/manhole access?

    Identified Conduit/Duct Transition to mezzanine level?

    Emergency Power Verification

    Check Task Equipment Room ID Notes

    Verify if AFC electrical panel is connected to an Automatic Transfer Switch (ATS). ATS Name/Number:

    Verification of Kiosk Emergency Panel(s) (KE, KES, KESS, etc)

    Source Panel Name/Number:

    Source Breaker Name/Number:

    Panel Name/Number:

    Notes and Discrepancies:

    Sign Off GFP Representative WMATA PRGM

    Name:

    Signature:

    Date:

    Ver

    10/30/2014 Landover - D12 067 Meghan Powell

    Panel M

    Breaker #23

    RmC108

    Rm C108

    Panel F Rm C108

    Rm C108 is inside of Rm C100

    No

    LOW Voltage

    ✔ NO

    YES (see notes)

    YES

    All conduit/duct is on mezzanine level.Layout: Assume freeside straight run back to panelfrom HH at kiosk (120+ ft.).

    Panel - E-2 Rm C108

    Breaker #9 Rm C108

    Panel KE Kiosk

  • Picture 1: D12 Landover – Handholes in Mezzanine

  • Picture 2: D12 Landover – Manholes in Mezzanine (not part of duct run)

  • Picture 3: D12 Landover – Manholes in Mezzanine (not part of duct run)

  • Picture 4: D12 Landover – No handhole in passageway of Room C100

  • Picture 5: D12 Landover – Panel F in Room C108

  • Picture 6: D12 Landover – Panel F in Room C108

  • Picture 7: D12 Landover – Panel F bottom conduits in Room C108

  • Picture 8: D12 Landover – Panel F Schedule in Room C108

  • Picture 9: D12 Landover – Panel M in Room C108

  • Picture 10: D12 Landover – Panel M in Room C108 (breaker #23 is at bottom of panel)

  • Picture 11: D12 Landover – Panel M Schedule in Room C108

  • Picture 12: D12 Landover – Kiosk Emergency Panel-E2 in Room C108

  • Picture 13: D12 Landover – Kiosk Emergency Panel-E2 Schedule Room C108

  • Pre-Inspection FieldVerification 10/30/2014

  • Pre-Inspection FieldVerification 10/30/2014

  • Pre-Inspection FieldVerification 10/30/2014