Upload
xenia
View
45
Download
0
Embed Size (px)
DESCRIPTION
Preparing Melbourne’s Electrical Supply For The 2006 Commonwealth Games. Presented by Michael Farr Manager Networks – Queensland Sinclair Knight Merz. Commonwealth Games 2006. Biggest event ever staged in Victoria Held over 11 days in March 2006 71 nations 7,200 athletes - PowerPoint PPT Presentation
Citation preview
AMEU Convention 2007
Preparing Melbourne’s Electrical Supply For The 2006 Commonwealth Games
Presented by Michael Farr
Manager Networks – Queensland
Sinclair Knight Merz
AMEU Convention 2007
Commonwealth Games 2006
Biggest event ever staged in Victoria
Held over 11 days in March 2006
71 nations
7,200 athletes
3,100 media representatives
1.6m tickets sold
90,000 visitors
AMEU Convention 2007
Melbourne Statistics
Category CBD daily population
Employed in CBD **
180,000
National and International Visitors ##
90-95,000
Metropolitan and Country Victorian Visitors ##
161,000 – 200,000
Residential ## 20,000 Total Daily Population of CBD 451,000 – 495,000
Sources ** Bureau of Statistics ## Sustainable City Research Department, City of Melbourne
AMEU Convention 2007
Commonwealth Games 2006
All major venues in the inner suburbs of Melbourne (Citipower)
Venues supplied at 11kV
First time all venues operated at full capacity simultaneously
CBD was very busy at this time
AMEU Convention 2007
Orientation
AMEU Convention 2007
Orientation
AMEU Convention 2007
1998_Auckland multiple cable failure – 3 out of 4 cables ultimately failed causing extended disruption (~A$75M)
1998_New York incident approximately A$75M. 2001_Cost of the two Melbourne CBD incidents
estimated at $10M and $3M based on commercial VCR. In both events initial planned plant outages were followed
by secondary faults a number of days later that resulted in loss of supply to areas of the CBD.
2003_SKM commissioned to conduct security of supply analysis
2004_Somerville enquiry (Qld) Transmission and sub-transmission feeders: N-2 Transformers: N-1
2005/06_NSW Government mandates N-2 reliability down to the zone substations (132kV and 66kV)
Historical CBD Reliability Incidents
AMEU Convention 2007
The review findings were:
Although the network was designed and operated to an “N-1” security standard, there was little flexibility to reconfigure the 66kV network after a prior outage.
This lack of flexibility was one of the major reasons behind the two outages.
To provide improved network flexibility would require the network to be designed to a higher security standard.
Historical Melbourne CBD Development
AMEU Convention 2007
In addition, the review found thatMelbourne’s CBD security of supply was ranked very low in a comparison of equivalent major cities worldwide.
Brisbane, Sydney, Melbourne, Auckland, Wellington, Glasgow, Johannesburg, Capetown
(Based on Planning Criteria and Energy at Risk)
Historical Melbourne CBD Development
AMEU Convention 2007
What security standard should apply for the Melbourne CBD?
Term Description
N-1 The network can withstand the loss of any element and maintain supply to all customers. The network may not be in a secure state.
N-1 Secure
The network can withstand the loss of any element and maintain supply to all customers.
In addition, the network can be subsequently re-configured to withstand a further outage. During the time taken to re-configure, the network is at risk.
Modified N-2
The network can withstand the loss of a critical element together with the further loss of a non-critical element. This security standard has been applied to the Sydney CBD.
N-2 The network can withstand the loss of any 2 network elements and maintain supply to all customers. Very few networks have true N-2 security.
AMEU Convention 2007
What security standard should apply for the Melbourne CBD?
Recommended security standard is
“N-1 Secure”
Consistent with Transmission security standard;
Considers the nature and impact of the customers affected.
Cost effectiveness;
Captures most of the security benefits associated with “N-2” standard.
Accepted by ESC ESC allocates A$250M for refurbishment and
security of supply works
AMEU Convention 2007
Commonwealth Games 2006
Key Risk Areaso Opening and closing ceremonies
• Greatest loads, crowd volumes, dignitaries, media attention
o Damage to underground assets• Pegs from temporary facilities eg tents
o Overall system load• Co-incident with previous years system peak load period
• All loads continuously monitored
o Asset failure• All venue feeder maintenance and vegetation management brought
forward
o Access to assets • Accreditation for staff and vehicles
• Most challenging
AMEU Convention 2007
Risks and Assessment
Key Focus Areaso Assetso Imageo Incident managemento Peopleo Serviceo Stakeholders
AMEU Convention 2007
Commonwealth Games Specific Infrastructure Impact
Augmentation projectso Increase security of supply to major venues
o Increase available capacity at the main venues
AMEU Convention 2007
Infrastructure Impact
Citipower HV CBD networko Cables are run to maximum capacityo Feeders arranged into groupso Each group can consist of up to 10 feederso Each group has a dedicated standby feeder
AMEU Convention 2007
Infrastructure Impact
Standby arrangements reviewedo Second standby feeder to the MCG from a separate zone substation
Load projections provided by games officials did not consider harmonic componentso Significant amount of extra lighting and computers/laptops would add
min 10% additional load due to harmonics
Installation of 2 x 1.5MVA kiosk substations along the bank of the Yarra River
AMEU Convention 2007
MCG Supply Arrangements
Figure 2a. Existing MCG lights arrangement
Figure 2b. . Altered MCG lights arrangement
L1
L2
L3
L4
L5
L6
Zone Sub station 1
Zone Sub station 2
Standby Feeder 1
L1
L2
L3
L4
L5
L6
Zone Sub station 1
Zone Sub station 2
Standby Feeder 1 Standby Feeder 2
AMEU Convention 2007
Infrastructure Impact Cont’d
Inspection and Maintenanceo High priorityo Confirmed inspections policyo Additional substation, public lighting and reliability patrols – dailyo Corona (UV) and infrared surveys of all key assets o All planned maintenance of key assets undertaken early incl zone
substation equipment, HV insulator washing and vegetation management
o Distribution substation audit regime• RMU types• HV and LV switchgear installed• Fuse condition, ventilation• Mobile phone reception
o Confirmed each venue substation had suitable alternate LV inter-connector
AMEU Convention 2007
Infrastructure Impact Cont’d
Work Restrictionso Many Games venues were “locked down” 1 month before the start of
the Games
o Self imposed restrictions• Rescheduling works outside of the Games period
• Not working on feeders or zone substations supplying key venues
• Restricting all planned work near major venues or the CBD
• Work on sub-transmission and transmission lines supplying zone substations supplying Games events restricted (H&S excluded)
AMEU Convention 2007
Infrastructure Impact Cont’d
Enhanced Field Responseo Roster of site field technicians
• Additional to system normal • Minimise switching times • Avoid access issues• Reported current, voltage, transformer temperatures – hourly to control
room– Load monitoring model– Self updating graph – load profile
o Additional (dedicated) fault response units (flying squads)o Ensure spare equipment placed at strategic siteso Standby generators
• Quicker response than immediate repairs (access constraints)• Strategically located
o Daily patrols of public lighting and general assets
AMEU Convention 2007
Infrastructure Impact Cont’d
Other Considerationso Ban on changes to systems
• IT
• Telecommunications
• Call centre
o Protection operating points recorded• Fuse size, condition, stocks
o System stress tests undertaken twice before the Games period
o Incident management• Network contingency and escalation plans enacted (min level 3 of 5)
AMEU Convention 2007
Outcome
Demand – 116.8 MW more than same period last year
Energy – 13,000 MWHr more than same period last year
Capacity – 16.4 MVA installed and 10MVA portable
Assets – 140 maintenance activities brought forward
Reliability (fortnight) customers off supply 4,451 (average 7011)
Staff 68 directly involved (fortnight) + additional 115 indirectly involved in the lead up
No outages at any of the Commonwealth Games Venues
AMEU Convention 2007
Legacy
Enhanced infrastructure to the major venues and open space areas
Minimal outages
Significantly enhanced reputation with stakeholders
Whole of business support
Increased revenue for the period
AMEU Convention 2007
Thank you for your time