    Presentation Overview Main objectives and deliverables

    Main activities based on the case study analysis

    Network diagram & Critical Path Finance

    Options to shorten the time

    Revision of the activities table

    Recommendations

  • 8/12/2019 Presentation Slides Vision Bmaf2

    3/12

    Objectives To perform the H.M.S PINAFORE, which will take place from 13thof

    January to 22ndof January 1994.

    Give students, faculty and greater community the opportunity to

    participate in the high quality theatre production at affordable prices.

    Perform the planning and all the activities involved within budget andon time.

    To create the most professional looking production within the budget.

    To make the opening night as professional as possible in order to makesure that the following performance will run smoothly.

  • 8/12/2019 Presentation Slides Vision Bmaf2

    4/12

    Deliverables Ticketing ( $14 for adults and $12 for seniors and students )

    Performance of H.M.S Pinafore

    The program printed copies

    Advertising Glossy posters, radio, television

    Set designed and built

    The place of performance -Talbot theatre ( 360 seats)

  • 8/12/2019 Presentation Slides Vision Bmaf2

    5/12

    Main Activities with PrecedenceNo. Task Name Duration Start Finish Predecessors

    1 Budget approval 1 day Tue 07/09/93 Tue 07/09/932 Hire publicity director 14 days Tue 07/09/93 Mon 20/09/93 1

    3 Advertising to hire crew and cast 7 days Tue 21/09/93 Mon 27/09/93 2

    4 Hire set designer 14 days Wed 08/09/93 Tue 21/09/93 1

    5 Set designed and built 42 days Wed 27/10/93 Fri 07/01/94 4,6

    6 Hire production crew 28 days Tue 28/09/93 Tue 26/10/93 3

    7 Train production crew 12 days Wed 27/10/93 Sun 07/11/93 4,6

    8 Hire place for auditions 7 days Tue 28/09/93 Mon 04/10/93 39 Auditions to hire cast 2 days Fri 08/10/93 Sat 09/10/93 3,8

    10 Rehearsals 12 wks Sun 10/10/93 Sun 01/02/94 12,9

    11 Hire orchestra 7 days Wed 08/09/93 Tue 14/09/93 1

    12 Music 7 days Wed 15/09/93 Tue 21/09/93 11

    13 Photograph cast and crew/ collect biographies 35 days Wed 27/10/93 Tue 30/11/93 6,11,9

    14 Enter information into computer 1 day Wed 01/12/93 Wed 01/12/93 13

    15 Printing 5 days Thu 02/12/93 Thu 06/01/94 14

    16 Publicity 28 days Tue 21/09/93 Tue 19/10/93 2

    17 Order costumes 7 days Sun 10/10/93 Sun 17/10/93 9

    18 Costume parade and alterations 5 days Sat 08/01/94 Wed 12/01/94 5,17

    19 Dress rehearsal 1 day Thu 13/01/94 Thu 13/01/94 18

    20 Performances start 1 day Thu 13/01/94 Thu 13/01/94 19,15,7,10,16

    Activities on the critical path

  • 8/12/2019 Presentation Slides Vision Bmaf2

    6/12

    Network Diagram & Critical Path

    See the MS Project for more information

  • 8/12/2019 Presentation Slides Vision Bmaf2

    7/12

    Finance Overview

    Total funds available $28,000

    Fixed Expenses $14,000

    Printing $3,500

    Advertising Space $40

    Costumes $6,500

    Builder $3,360

    Total Expenses $27,400

    Funds left $600

  • 8/12/2019 Presentation Slides Vision Bmaf2

    8/12

    Options for Francis to shorten timeActivity Extra Cost Time reduced Comments

    One additional

    Rehearsal/week$0 3 weeks and 1 day

    They need to be careful mainly

    because they are dealing with

    volunteers.

    Cut down on

    number of

    rehearsals

    $0 3 weeks and 1 day

    Due to the less rehearsals they might

    not look as professional as they wantto and the overall performance may

    be affected.

    Printing $ 750 3 daysThey do not have enough funds to

    proceed with this option.

    Costume Extra $100/day 5 days

    In terms of finance, they could affordit but it would not make much

    difference in terms of timing as the

    main problem in the plan is

    rehearsals.

    Additional builder $ 80/day 1 week

    Financially, they will not be able to

    afford additional builder.

  • 8/12/2019 Presentation Slides Vision Bmaf2

    9/12

    Revision of the precedence table

    and network diagram Auditions and hiring the cast

    Orchestra rehearsals

    Cast rehearsals

    Timing issues

    Activity 3 (Advertising to hire crew and cast) & 8 (Hireplace for audition)

  • 8/12/2019 Presentation Slides Vision Bmaf2

    10/12

    No. Task Name Duration Start Finish Predecessors

    1 Budget approval 1 day Tue 07/09/93 Tue 07/09/93

    2 Hire publicity director 14 days Tue 07/09/93 Mon 20/09/93 1

    3 Advertising to hire crew and cast 7 days Tue 21/09/93 Mon 27/09/93 2

    4 Hire set designer 14 days Wed 08/09/93 Tue 21/09/93 15 Set designed and built 42 days Wed 27/10/93 Fri 07/01/94 4,6

    6 Hire production crew 28 days Tue 28/09/93 Tue 26/10/93 3

    7 Train production crew 12 days Wed 27/10/93 Sun 07/11/93 4,6

    8 Hire place for auditions 7 days Tue 21/09/93 Mon 27/09/93 2

    9 Auditions to hire cast 2 days Fri 01/10/93 Sat 02/10/93 3,8

    10 Rehearsals 12 wks Sun 03/10/93 Sun 11/01/94 12,911 Hire orchestra 7 days Wed 08/09/93 Tue 14/09/93 1

    12 Music 7 days Wed 15/09/93 Tue 21/09/93 11

    13 Photograph cast and crew/ collect biographies 35 days Wed 27/10/93 Tue 30/11/93 6,11,9

    14 Enter information into computer 1 day Wed 01/12/93 Wed 01/12/93 13

    15 Printing 5 days Thu 02/12/93 Thu 06/01/94 14

    16 Publicity 28 days Tue 21/09/93 Tue 19/10/93 2

    17 Order costumes 7 days Sun 10/10/93 Sun 17/10/93 9

    18 Costume parade and alterations 5 days Sat 08/01/94 Wed 12/01/94 5,17

    19 Dress rehearsal 1 day Thu 13/01/94 Thu 13/01/94 18

    20 Performances start 1 day Thu 13/01/94 Thu 13/01/94 19,15,7,10,16

    Activities on the critical path

    Recommendations to Francis

    Reduce the number of planned rehearsals.

    Increase the number of rehearsals per week.

    Add one more hour to the duration of each rehearsal.

    Activity 3 (Advertising to hire crew and cast) & 8 (Hireplace for audition) starting at the same time.

  • 8/12/2019 Presentation Slides Vision Bmaf2

    11/12

    Recommendations to Francis for

    next year Earlier start of the project.

    Use some human resources from previous projects.

    No formal project plans have been set.

    Contracts with the suppliers could be considered inorder to save some money.