SE REGION PROJECT UPDATE BUREAU OF

TRAFFIC OPERATIONSPresenter:

Dewayne Johnson, P.E.

SE Region Director/Bureau of Traffic Operations Director

TRANSPORTATION IN THE FUTURE: CONNECTED VEHICLES (BTO)

ZOO INTERCHANGE

Expected completion in 2018

SCHEDULEOVERVIEW

• 2014: Watertown Plank

Road (including US 45

interchange)

• 2014: WIS 100 bridge,

UPRR bridge and 76th Street

bridge over I-94

• Fall 2014 – Summer 2016:

Core Phase 1

• Fall 2015 – Winter 2017

Core Phase 2

• 2016 Center Street Bridge

• 2017 - 2018: North Leg

NEW INTERCHANGE

Milwaukee County Zoo

State Fair

I-94 NORTH SOUTH FREEWAY

I-94 NORTH SOUTH PROJECT SCHEDULE

WIS 20 Interchange Construction of I-94 Northbound freeway and modernized entrance and exit ramps at WIS 20

WIS 142 to WIS 158:Completion of Freeway expansion and interchange improvements on I-94 southbound

WIS 50 Local RoadsCompletion of local road improvements adjoining the newly constructed interchange.

PROJECT SCOPE

9

I-43 CORRIDOR STUDY PROJECT SCHEDULE

Current (this year):•Summer 2014 – Final of Environmental Impact Statement (EIS) anticipated•Fall 2014 – Functional plans of alternative development & Record of Decision Environmental Clearance anticipated•2014 – Agency coordination completion is anticipated

I-94 EAST WEST STUDY

I-90/39 (SOUTHWEST REGION)

I-90/39 SOUTHWEST REGIONPROJECT SCHEDULE

Current 2014: WIS 73 reconstruction from I-39/90 north to US

12/18 in Dane County Reconstruct the I-39/90 southbound bridge over

Siggelkow Road, south of the US 12/18 interchange near Madison

Pavement repairs on I-39/90 northbound and southbound from Milwaukee Street in Janesville to just north of the WIS 73/US 51 interchange in Dane County

Future 2015: I-39/90 construction scheduled to start 2021 Construction expected to be completed

MADISON BELTLINE PLANNING & ENVIRONMENT LINKAGE (PEL) STUDY

(SOUTHWEST REGION)

I-90 STILLWATER BRIDGE (NORTHWEST REGION)

I-90 STILLWATER BRIDGEPROJECT SCHEDULE

March 10 through Nov. 14, 2014: Complete first phase of project

Week of June 2, 2014: •Place concrete for bridge radius walls • Remove dirt at the new interchange (County E)

Fall 2016 - Full project completion