Process Management & Monitoring WG. Quarterly Report January 25, 2005. Components. Process Management Process Manager Checkpoint Manager Monitoring Job Monitor System/Node Monitors Meta Monitoring. Component Progress. Checkpoint Manager (LBNL) BLCR Process Manager (ANL) MPDPM - PowerPoint PPT Presentation
Citation preview
Process Management & Monitoring WG
Quarterly Report
January 25, 2005
January 25, 2005 PMWG Quarterly Report 2
Components Process Management
Process Manager Checkpoint Manager
Monitoring Job Monitor System/Node Monitors Meta Monitoring
January 25, 2005 PMWG Quarterly Report 3
Component Progress
Checkpoint Manager (LBNL) BLCR
Process Manager (ANL) MPDPM
Monitoring (NCSA) Warehouse
January 25, 2005 PMWG Quarterly Report 4
Checkpoint Manager:BLCR Status
Full save and restore of CPU registers Memory Signals (handlers & pending signals) PID, PGID, etc Files (w/ limitations) Communication (via MPI)
January 25, 2005 PMWG Quarterly Report 5
Checkpoint Manager:BLCR Status (Files)
Files Files unmodified between checkpoint
and restart Files appended to between
checkpoint and restart Pipes between processes
January 25, 2005 PMWG Quarterly Report 6
Checkpoint Manager:BLCR Status (Comms)
LAM/MPI 7.x over TCP and GM Handles in-flight data (drains) Linear scaling of time w/ job size Migratable
OpenMPI Will inherit LAM/MPI’s support
ChaMPIon/Pro (Verari)
January 25, 2005 PMWG Quarterly Report 7
Checkpoint Manager:BLCR Status (Ports)
Linux only “Stock” 2.4.X RedHat 7.2 – 9 SuSE 7.2 – 9.0 RHEL3/CentOS 3.1 2.6.x port in progress (FC2 & SuSE 9.2)
x86 (IA32) only today x86_64 (Opteron) will follow 2.6.x port Alpha, PPC and PPC64 may be trivial No IA64 (Itanium) plans
January 25, 2005 PMWG Quarterly Report 8
Checkpoint Manager:BLCR Future Work
Additional coverage Process groups and Sessions (next priority)
Terminal characteristics Interval timers Queued RT signals
More on files Mutable files Directories
January 25, 2005 PMWG Quarterly Report 9
Checkpoint Manager:SSS Integration
Rudimentary Checkpoint Manager Works with Bamboo, Maui and MPDPM Long delayed plans for “next gen”
Upgraded interface spec (using LRS) Management of “context files”
lampd mpirun replacement for running LAM/MPI
jobs under MPD
January 25, 2005 PMWG Quarterly Report 10
Checkpoint Manager:Non-SSS Integration
Grid Engine DONE by 3rd party (online howto)
Verari Command Center In testing
PBS family Torque: Cluster Resources interested PBSPro: Altair Engineering interested (if funded)
SLURM Mo Jette of LLNL interested (if funded)
LoadLeveler IBM may publish our URL in support documents
January 25, 2005 PMWG Quarterly Report 11
Process ManagerProgress (ANL)
Continued daily use on Chiba City, along with other components
Miscellaneous hardening of MPD implementation of PM, particularly with respect to error conditions, prompted by Intel use and Chiba experience
Conversion to LRS, in preparation for presentation of interface at this meeting
Preparation for BG/L
January 25, 2005 PMWG Quarterly Report 12
Monitoring at NCSAWarehouse Status
Network code has been revamped; that code is in cvs in oscar sss
Connections are now retried Starting to monitor does not wait for all connections to
finish Connection and monitoring thread pools are independent No full reset (if lots of nodes are down, continues blindly) Any component can be restarted. Restart no longer
depends on start order. Features intended for sss-oscar 1.0 (SC2004), didn't
make it, made it into 1.01
January 25, 2005 PMWG Quarterly Report 13
Monitoring at NCSAWarehouse Testing
Warehouse run on former Platinum cluster at NCSA
Node count kept dropping 400 nodes originally 200 nodes in post-cluster configuration 120 available for testing
Ran on 120 nodes with no problems Have head node, but cannot have whole
cluster So didn't try sss-oscar
January 25, 2005 PMWG Quarterly Report 14
Monitoring at NCSAWarehouse Testing (2)
"Infinite" Itanium cluster (Infiniband development machine)
Have root access Will run warehouse for sure, for long range testing Might try whole suite (semi-production)
T2 cluster (Dell Xeon 500+ nodes) May run warehouse across (Mike Showerman says)
Anecdote: Went to test new warehouse_monitor on xtorc. Installed and
started new warehouse_monitors on nodes. Called up warehouse_System_Monitor to make sure it wasn't running. The already running System Monitor had connected to all the new warehouse_monitors and everything was running fine.
January 25, 2005 PMWG Quarterly Report 15
MonitoringWork at NCSA
David Boxer, RA, working on warehouse Craig worked bugs and fiddly things, David did
development heavy lifting Revamped network code (modularized) Developed new info storage (more on this in the afternoon) New info store and logistics
info store: redesigned and updated: DONE protocol re-designed: DONE send protocol: DONE receive protocol: still to do
IBM offered him real money - he's off to work for them.
January 25, 2005 PMWG Quarterly Report 16
MonitoringWork at NCSA
Wire Protocol: I (Craig) need to have working knowledge of
signature/hash functions. When I do, I'll be back to coding on this
Perilously close to being able to do useful stuff
Documentation: Have most of a web site written with
philosophy of warehouse, and debugging tools.
January 25, 2005 PMWG Quarterly Report 17
Monitoring at NCSAFuture Work
New interaction (to come): Node Build and Config Manager On start-up, will talk to Node State Manager and get
list of up nodes Subscribe to Node State Manager events for updates For now, can continue to store node state, transition to
Scheduler obtaining state information itself. Also to come:
Intelligent error handling (target-based vs. severity based)
Command line debugging/control?