Productivity Improvement On Development

Embed Size (px)

Citation preview

  • 7/24/2019 Productivity Improvement On Development

    1/40

    Productivity Improvement onProductivity Improvement onDevelopmentDevelopment

    Kevin Whipkey, Norwest CorporationKevin Whipkey, Norwest CorporationThe Rocky Mountain Coal Mining InstituteThe Rocky Mountain Coal Mining Institute

    101101stst

    Convention & Annual MeetingConvention & Annual Meeting

  • 7/24/2019 Productivity Improvement On Development

    2/40

    How is ImprovementHow is ImprovementBeing Achieved?Being Achieved?

    Section EquipmentMine Layout/ProjectionsWork ScheduleMaintenanceManagement

  • 7/24/2019 Productivity Improvement On Development

    3/40

    Section EquipmentSection Equipment

    Full-face CM/roof bolting machinesIn-place mining vs. place-change mining

    Adequate numbers of equipmentHaulage carsRoof bolters

  • 7/24/2019 Productivity Improvement On Development

    4/40

    Joy 14CM15 Miner/Bolter Joy 14CM15 Miner/Bolter

  • 7/24/2019 Productivity Improvement On Development

    5/40

    VoestVoest -- Alpine ABM 14 Miner/Bolter Alpine ABM 14 Miner/Bolter

  • 7/24/2019 Productivity Improvement On Development

    6/40

    Typical Cut SequencesTypical Cut Sequences

    ** FullFull --facefaceCM/bolter CM/bolter

  • 7/24/2019 Productivity Improvement On Development

    7/40

    Adequate Numbers of Adequate Numbers ofEquipmentEquipment

    Haulage carsOptimize for particular section set-up

    Roof boltersTypically 2 machines to minimizewait-on-bolter time

  • 7/24/2019 Productivity Improvement On Development

    8/40

    Mine Layout/ProjectionsMine Layout/Projections

    Number of Entries

    Pillar Sizing

    Ratio: Total Development/Panel Length

  • 7/24/2019 Productivity Improvement On Development

    9/40

    NumberNumberofof

    EntriesEntries

  • 7/24/2019 Productivity Improvement On Development

    10/40

    Number of EntriesNumber of Entries

    Three-entry gate developmentMost common

    Two-entry gate development

    Safety considerationsWestern U.S.

  • 7/24/2019 Productivity Improvement On Development

    11/40

    PillarPillarSizingSizing

  • 7/24/2019 Productivity Improvement On Development

    12/40

    Pillar SizingPillar Sizing

    Increase pillar lengthImproves roof controlReduces cross-cuts

    Restricted by regulations (ventilation)Point of diminishing return

    Safety is determining factor Adequate roof & rib control

  • 7/24/2019 Productivity Improvement On Development

    13/40

    Ratio of Gate Entry DevelopmentRatio of Gate Entry Development(total linear feet) to Panel Length(total linear feet) to Panel Length

    (feet)(feet)

    Ratio of 4 or less is optimal

  • 7/24/2019 Productivity Improvement On Development

    14/40

    Work ScheduleWork Schedule

    Alternative schedule

    Traditional schedule

  • 7/24/2019 Productivity Improvement On Development

    15/40

    Weekend Warrior 7Weekend Warrior 7 --Day WorkDay WorkScheduleSchedule

  • 7/24/2019 Productivity Improvement On Development

    16/40

    Alternative Schedule Alternative Schedule -- ProsPros

    Increase utilization of capitalinvestment

    Reduce number of hours worked byeach employee (theoretical)

    Improve attitude of workforce

  • 7/24/2019 Productivity Improvement On Development

    17/40

    Alternative Schedule Alternative Schedule -- ConsCons

    Requires additional manpower

    Mixed resultsProduction

    Overtime hoursCost

  • 7/24/2019 Productivity Improvement On Development

    18/40

    Idle/Preparation ShiftsIdle/Preparation Shifts

    Belt and power advancementscompleted within allocated time frame

    Production equipment serviced andready for operation

    Time to first coal is critical

  • 7/24/2019 Productivity Improvement On Development

    19/40

    Example of Schedule ChangeExample of Schedule ChangeSend in a few personnel just prior to shiftstarting time to perform requiredregulatory checks on section &

    equipmentImprovement of 15 to 30 minutes for timeto dump 1 st car

  • 7/24/2019 Productivity Improvement On Development

    20/40

    MaintenanceMaintenance

    Preventive Maintenance

    Predictive Maintenance

  • 7/24/2019 Productivity Improvement On Development

    21/40

    Preventive MaintenancePreventive Maintenance

    Enhanced by computer softwarepackages

    Reduce unscheduled downtimeConsistent servicing

    Component replacement prior to failureImprove availability

  • 7/24/2019 Productivity Improvement On Development

    22/40

    Predictive MaintenancePredictive Maintenance

    Increased emphasis as technologyhas become more accurate, practical,and affordable

    Predictive maintenance engineers

  • 7/24/2019 Productivity Improvement On Development

    23/40

    Examples of Predictive MaintenanceExamples of Predictive Maintenance

    ApplicationsElectrical motors

    Conveyor beltsystems

    TypeVibration

    analysisThermographyNon-destructivetesting

  • 7/24/2019 Productivity Improvement On Development

    24/40

    FLIR Systems Infrared CameraFLIR Systems Infrared Camera

  • 7/24/2019 Productivity Improvement On Development

    25/40

    ManagementManagement

    Emphasis on CM development

    Back to basics

  • 7/24/2019 Productivity Improvement On Development

    26/40

    Average Delivered Price of Total Average Delivered Price of Total

    U.S. Coal ProductionU.S. Coal Production

    0

    10

    2030

    40

    50

    60

    $/Ton

    1980 1985 1990 1995 2000

    Year

    Bituminous

    All Coal Types

  • 7/24/2019 Productivity Improvement On Development

    27/40

    Management ItemsManagement ItemsCoordinatorsMine modeling

    AccountabilityIndustrial engineeringProblem solving

  • 7/24/2019 Productivity Improvement On Development

    28/40

    CoordinatorsCoordinators

    Longwall coordinators

    CM coordinators

  • 7/24/2019 Productivity Improvement On Development

    29/40

    CM Coordinator OrganizationCM Coordinator Organization

    ChartChart

  • 7/24/2019 Productivity Improvement On Development

    30/40

    Mine ModelingMine Modeling

    Improved forecasting of CMdevelopment

    Allows What if analysis

    Future timing problems identifiedearly

  • 7/24/2019 Productivity Improvement On Development

    31/40

    TT

    IIMM

    IINN

    GG

    MM A APP

  • 7/24/2019 Productivity Improvement On Development

    32/40

    Accountability Accountability

    Stressed at all levels, from equipmentoperator to upper management

    Projected and actual performancedata for safety, cost, and productivitynow being shared

    Production Crew A Production Crew B Production Crew C Production Crew D Preparation Crew

  • 7/24/2019 Productivity Improvement On Development

    33/40

    June Target Actual Diff. Target Actual Diff. Target Actual Diff. Target Actual Diff. Target Actual Diff.1 150 100 (50) 150 165 15 15 10 5

    2 150 155 5 150 160 10 15 15 03 180 200 20 180 180 0 15 25 (10)4 180 175 (5) 180 190 105 150 145 (5) 150 155 56 150 160 10 150 170 20 15 20 (5)7 150 165 15 150 175 25 15 5 108 150 140 (10) 150 110 (40) 15 10 59 150 150 0 150 145 (5) 15 10 5

    10 180 180 0 180 165 (15) 15 20 (5)11 180 185 5 180 175 (5)12 150 135 (15) 150 140 (10)13 150 125 (25) 150 150 0 15 30 (15)14 150 145 (5) 150 150 0 15 10 515 150 170 20 150 160 10 15 15 016 150 155 5 150 135 (15) 15 5 10

    17 180 185 5 180 205 25 15 15 018 180 185 5 180 190 1019 150 140 (10) 150 150 020 150 90 (60) 150 180 30 15 20 (5)21 150 165 15 150 120 (30) 15 15 022 150 170 20 150 140 (10) 15 15 023 150 150 0 150 165 15 15 10 524 180 195 15 180 185 5 15 20 (5)

    25 180 150 (30) 180 185 526 150 160 10 150 135 (15)27 150 140 (10) 150 130 (20) 15 15 028 150 135 (15) 150 135 (15) 15 10 529 150 170 20 150 125 (25) 15 5 1030 150 155 5 150 170 20 15 10 5

    Total 2,700 2,640 (60) 2,700 2,685 (15) 2,040 2,035 (5) 2,040 2,055 15 330 310 20

    Footage Mined Footage Mined Footage MinedForeman: B. ReadyCrew B - Foreman: Jones Crew C - Foreman: Doe Crew D - Foreman: Buck

    Time to First Coal (min.)Month Foreman: Smith

    Footage MinedWW

    A ALL

    LL

    CCHH

    A ARRTT

  • 7/24/2019 Productivity Improvement On Development

    34/40

    Industrial EngineeringIndustrial Engineering

    Time study/productivityimprovement analysis

    In-house and independent

    technical review of CM operatingpractices

    Company - Mine DelayDate - Shift CodeTravel, LunchCycle

    ElementsTime O'day Delays

    KeyWords

  • 7/24/2019 Productivity Improvement On Development

    35/40

    TT

    IIMM

    EESSTTUUDDYY

    Activity/Event H o u r s

    M i n u t e s

    S e c o n d s

    C a r

    E l a p s e d

    L o a

    d

    T i m e

    C h a n g e

    T i m e

    R e s e t

    T i m e

    E x t e n

    d

    T u b e

    M o v e

    T i m e

    M a i n t .

    D e l a y

    N o n -

    M a i n t .

    O v e r l a p

    T r a v e

    l I n

    T r a v e

    l

    O u t

    L u n c h

    Start Portal Meeting 19 49 0 Mine Foreman/Shift Coord.

    Depart Surface 19 52 52 3.87 3.87 Overlap Section ForemanTravel In 20 17 7 24.25 24.25 Travel In Miner Operator

    Safety Meeting 20 19 6 1.98 1.98 Non Maint Crew: 8 + 2 mechanicsWalk to Miner 20 24 5 4.98 4.98 Non Maint

    Totals 35.08 0.00 0.00 0.00 0.00 0.00 0.00 6.97 3.87 24.25 0.00 0.00Place 1 start of cutMOVE 1 23 25 4.32 4.32 Back in #2 entry to 31 break

    Wait on Bolter 1 56 31 33.10 33.10 Maint Bolter down for hydraulic oilMOVE 2 5 2 8.52 8.52 From #2 to #3 entry

    Load 2 5 47 20 0.75 0.75 Push Push carChange 2 10 1 4.23 4.23 Bolts 2 feet from faceLoad 2 10 56 18 0.92 0.92

    Change 2 12 10 1.23 1.23Load 2 12 45 20 0.58 0.58

    Change 2 17 35 4.83 4.83Load 2 18 16 18 0.68 0.68

    Change 2 19 49 1.55 1.55Load 2 20 45 20 0.93 0.93

    Change 2 24 53 4.13 4.13Load 2 25 36 18 0.72 0.72Change 2 27 24 1.80 1.80Load 2 28 0 20 0.60 0.60

    Change 2 32 23 4.38 4.38Load 2 32 58 18 0.58 0.58

    Change 2 34 38 1.67 1.67Load 2 35 33 20 0.92 0.92

    Change 2 39 50 4.28 4.28 Miner set over to right sideLoad 2 41 4 18 1.23 1.23

    Change 2 42 32 1.47 1.47Load 2 43 17 20 0.75 0.75

    Change 2 45 16 1.98 1.98Load 2 45 52 9 0.60 0.60Load 2 45 52 9 0.00 0.00 Clean-up Clean-upReset 2 49 3 3.18 3.18 Move to left sideLoad 2 49 58 18 0.92 0.92 Clean-up Clean-up

    Place 1 Totals 90.87 10.18 31.57 3.18 0.00 12.84 33.10 0.00 0.00 0.00 0.00 0.00Place 1 Averages 0.44 1.37 0.14 Total Cars Loaded: 14

    Cut Dimensions: 37.0' x 18.5' x 10.0'

    Comments

  • 7/24/2019 Productivity Improvement On Development

    36/40

    P bl S l iP bl S l i

  • 7/24/2019 Productivity Improvement On Development

    37/40

    Problem SolvingProblem Solving

    Team concept incorporatingemployee input

    Reward system

    Team discussions may identify otherproblem areas

    Empowering employees improvesattitude and performance

    SS

  • 7/24/2019 Productivity Improvement On Development

    38/40

    SummarySummary

    Management focus on CM

    development critical to productivityincreases

    Technological advances continue todrive improvement, but are not primaryfactor

    Maintenance programs have evolvedinto important tools

  • 7/24/2019 Productivity Improvement On Development

    39/40

    Summary (cont.)Summary (cont.)

    Mine layout limited by specificconditions

    More critical aspect of sectionequipment selection is havingadequate numbers

    Correct work schedule for eachoperation

  • 7/24/2019 Productivity Improvement On Development

    40/40

    Acknowledgments AcknowledgmentsThe operating companies that respondedto requests for information, and providedfeedback for this paper

    Wayne Thomas @ Joy Mining MachineryFrank Hyden @ Voest-Alpine

    Mike Rotigliano @ FLIR Systems