6
Click the below link to access the answer PROJ 592 Proj Cost and Schedule Control Week 6 Quiz Set 1 and set 2 Complete A+ Answer PROJ 592 Proj Cost and Schedule Control Week 6 Quiz Set 1 and set 2 A+ Answer PROJ 592 Week 6 Quiz Set 1 1. Question : (TCO B) Crashing Problem Using the network below and the additional information provided, find: (a) The crash cost per day per activity? (b) Which activities should be crashed to meet a project deadline of 12 days at minimum cost? (c) What is the extra cost to crash the project? Activity | Normal Time | Crash Time | Normal Cost | Crash Cost | A | 5 | 3 | $300 | $600 | B | 3 | 2 | $250 | $450 | C | 6 | 4 | $400 | $500 | D | 5 | 3 | $150 | $400 | 2. Question : (TCO F) We have discussed at length the Earned Value Management process. I am sure all of you have used the traditional process of assessing projects where we compare actual dollars spent to the amount we had planned to spend. This was quick and easy, but it has its shortcomings, and the Earned Value Management process is said to be better. (a) Why is this traditional approach different from using earned value when assessing project performance?

PROJ 592 Proj Cost and Schedule Control Week 6 Quiz Set 1 and Set 2

Embed Size (px)

DESCRIPTION

PROJ 592 Proj Cost and Schedule Control Week 6 Quiz Set 1 and set 2

Citation preview

Click the below link to access the answer

PROJ 592 Proj Cost and Schedule Control Week 6 Quiz Set 1 and set 2 Complete A+ Answer

PROJ 592 Proj Cost and Schedule Control Week 6 Quiz Set 1 and set 2 A+ AnswerPROJ 592 Week 6 QuizSet 1

1. Question : (TCO B) Crashing Problem

Using the network below and the additional information provided, find:(a) The crash cost per day per activity?(b) Which activities should be crashed to meet a project deadline of 12 days at minimum cost?(c) What is the extra cost to crash the project?Activity | Normal Time | Crash Time | Normal Cost | Crash Cost |A | 5 | 3 | $300 | $600 |B | 3 | 2 | $250 | $450 |C | 6 | 4 | $400 | $500 |D | 5 | 3 | $150 | $400 |

2. Question : (TCO F) We have discussed at length the Earned Value Management process. I am sure all of you have used the traditional process of assessing projects where we compare actual dollars spent to the amount we had planned to spend. This was quick and easy, but it has its shortcomings, and the Earned Value Management process is said to be better.

(a) Why is this traditional approach different from using earned value when assessing project performance?(b) Describe the EVM process used to determine how far our project is ahead of or behind schedule.

3. Question : (TCO E) The following information is extracted from a project to develop a state of the art alternative power energy storage device:Activity Duration Predecessors ResourcesA 4 days 1 Research EngineerB 3 days A 1 Marketing SpecialistC 5 days A 1 Design EngineerD 3 days A 1 Design EngineerE 3 days B 1 Prototype BuilderF 2 days D 1 Test EngineerThe Owner has stipulated that in order to provide continuity throughout the project, the same individual must handle all activities under his or her discipline. Activities on this project cannot be split.

(a) Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), which resources(s) are involved, and the quantity required.(b) Given the owners stipulation regarding project continuity, and the need to minimize project duration, how can this conflict be resolved? What will be the effect on the project duration?

4. Question : (TCO F) The following data were obtained from an Information Systems project to upgrade and expand a Local Area Network:Activity Duration Predecessors Task BudgetA 3 Days $4,920B 6 Days $7,680C 3 Days A $15,140D 2 Days B $4,980E 3 Days B $5,630F 2 Days C, D $2,270

At the end of Day 7, the status of the project is as follows:Activity % Complete Actual CostA 100% $4,200B 100% $8,740C 100% $18,250D 55% $2,600E 10% $560F 0% $0

(a) Calculate the Cost and Schedule Variances and Indexes for tasks A, B, C, D, and E.(b) As project manager, write a brief summary of the status of the project at this time

5. Question : (TCO E) We have all been associated with projects with resource problems. As a project manager, you will be responsible for resolving these problems. Remember, resources are human and otherwise. If you can name it, it may be a resource.

(a) When there are not enough resources available to fill all the needs in the project plan, what are some specific remedies a project manager can take to complete the project. How does each of these affect the project plan and performance?(b) Describe 5 of the many benefits to resource leveling.

Set 2

Week 6 : Time and Cost Monitoring and Control Part 2 Quiz

Question 1. 1. (TCO B) Using the network below and the additional information provided, find(a) the crash cost per day per activity;(b) which activities should be crashed to meet a project deadline of 12 days at minimum cost; and(c) what the extra cost is to crash the project.Activity Normal Time Crash Time Normal Cost Crash CostA 5 3 $300 $350B 3 2 $250 $325C 6 4 $400 $700D 5 3 $150 $200

(Points : 20)

Question 2. 2. (TCO E) The following information is extracted from a project to develop a state-of-the-art alternative power energy storage device.Activity Duration Predecessors ResourcesA 4 days 1 research engineerB 3 days A 1 marketing specialistC 5 days A 1 design engineerD 3 days A 1 marketing specialistE 3 days B 1 prototype builderF 2 days D 1 test engineer

The owner has stipulated that in order to provide continuity throughout the project, the same individual must handle all activities under his or her discipline. Activities on this project cannot be split.

(a) Identify any resource conflicts in the above project. State the activities involved, the days that have conflict(s), which resources are involved, and the quantity required.(b) Given the owners stipulation regarding project continuity and the need to minimize project duration, how can this conflict be resolved? What will be the effect on the project duration? (Points : 20)

Question 3. 3. (TCO F) The following data were obtained from an information systems project to upgrade and expand a local area network.Activity Duration Predecessors Task BudgetA 3 days $4,920B 6 days $7,680C 3 days A $15,140D 2 days B $3,980E 3 days B $5,630F 2 days C and D $2,270

At the end of Day 7, the status of the project is as follows.Activity % Complete Actual CostA 100% $4,200B 100% $8,740C 100% $18,250D 75% $2,600E 10% $560F 0% $0

(a) Calculate the cost and schedule variances and indexes for Tasks A, B, C, D, and E.(b) As project manager, write a brief summary of the status of the project at this time. (Points : 20)

Question 4. 4. (TCO B) You are project manager for three different projects.

Project A: This project is behind schedule by 12 weeks. It was to have been completed in 3 months. The sponsor has additional funds to help complete the project on time if needed but does not want to increase risk to the project.Project B: This project is scheduled to take 28 weeks to complete. You are in the planning stage of the project. You need to reduce the schedule for this project by 9 weeks. This project has a number of predecessors that were created by the project teams preference. The sponsor insists on having all the work done on time without unduly increasing risk or costs to the project.Project C: This project is in the execution stage of the project. It is behind schedule by 8 weeks; it was scheduled to be completed in 10 weeks. The sponsor is desperate to accomplish something on this project. The budget is limited to the original amount, and all soft predecessors have already been removed.

For each of the project above, choose an appropriate schedule compression technique. Explain your choice. (Points : 20)

Question 5. 5. (TCO F) Given the following information, calculate the CV, SV, CPI, and SPI for this project. Also provide recommendations to improve the projects performance if needed.Activity A: This activity is complete. It was completed in 6 weeks; it was supposed to be completed in 5 weeks. The original budget for this activity was $400,000; in the end, it cost $450,000.

Activity B: This activity is 50% complete. Its original budget was $100,000. The costs to date are $55,000. The original project plan had this activity scheduled for 5 weeks; currently it is entering its third week.

Activity C: This activity is 75% complete. Its costs so far are $100,000. It is entering Week 4 of 5. It was planned to cost $100,000 when completed.

Activity D: This activity is not started yet; it will start in 2 weeks. It is planned to cost $400,000. Its costs to date are $0. (Points : 20)

PROJ 592 Proj Cost and Schedule Control Week 6 Quiz Set 1 and set 2 Complete A+ Answer